Concrete Construction Article PDF - Construction Procedures For Tilt-Up Buildings

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

Construction procedures

for tilt-up buildings


Editor’s note: The floor slab must be level and tively simple examples of form
Readers with specific questions on smoothly troweled. If the floor con- work, should be securely bolted or
tilt-up construction are referred to the tains openings for pipes or other weighted down to the casting sur-
PROBLEM CLINIC section of this is- utilities, a 3⁄4-inch skin coat over sand face. Top and bottom edge form
sue where detailed question and an-
swer material if presented. fill can be used to close up the open- sections need to be braced and
ings temporarily. Smoothness is im- squared. If side forms contain holes
portant in preventing mechanical for rebars, these forms usually are
bond and is necessary for clean split 2 by 6’s to facilitate stripping.
ood planning is an impor-

G tant part of all successful


construction work, but it is
especially critical in tilt-up
construction if the many inherent
economics of this technique are to
cleavage when lifting. A properly
constructed floor slab should have a
thoroughly compacted subgrade
with adequate strength and thick-
ness to carry material trucks and the
heavy mobile cranes that may be
(See Figure 9)
Window and door openings in
panels are rarely a problem to form.
The easiest way to include windows
in a tilt-up panel is to cast directly
against the steel sash. A wood-form
be realized. A carefully worked out
needed in the tilting process. Floor buck should be sanded and primed
schedule of operations is essential
jointing should be located between to prevent swelling, or allowance for
to ensure that the proper sequence
panels whenever possible. swelling can be made with diagonal
of panels is ready for the tilt-up
Curing of the concrete floor slab cuts through the bucks. All opening
process. A casting layout should be
is important to obtain a uniform forms should be held down on the
drawn prior to construction to de-
surface and prevent dusting and casting platform with weights. Ex-
termine proper use of space and ac-
plastic shrinkage cracks. A good posed surfaces of sash and wood
cess for material and equipment.
bond-breaking agent is also essen- surrounds should be given a coat of
Where crane capacity is marginal,
tial in tilt-up construction to obtain bond-breaking compound.
extra safety can often be achieved
a clean, trouble-free lift from the
by improving crane access and Reinforcement
floor slab. Because curing and bond
t h e re by shortening the boom
breaking are critical to successful The usual building code require-
length.
tilt-up work, materials and tech- ment for wall reinforcement calls
The panels should be cast as close
niques are discussed in detail later for a steel area 0.0015 to 0.0025
to their final position as possible. times the area of the concrete in
in this report.
Recommended practices for quality cross-section. Number 4 deformed
concrete should be followed to en- Edge forms bars 16 inches on center for a 6-inch
sure that panels attain a minimum panel are common. Around open-
One of the obvious advantages of
strength of 3,000 psi within 28 days.
tilt-up wall construction is the sav-
A helpful device for preplanning a Charts and diagrams on insert place-
ings in form material and labor.
large tilt-up building is the critical ment, rigging and bracing were pro-
Panel edge forms, which are rela- vided by the Engineering Department
path method of scheduling. Provi-
of Burke Concrete Accessories, Inc.
sion for an efficient casting layout
can be coordinated with the activi- figure 9
ty-time schedule.

Casting surface
The concrete floor slab of the
building is usually the most conve-
nient place for casting tilt-up pan-
els. Other casting platforms or cast-
ing beds may be necessary when
panels are prepared outside of the
building. The following are impor-
tant considerations in the construc-
tion of an industrial floor to be used
as a casting platform.
posed, a curing compound should
be used that will not stain or discol-
or the surface. If the panel is to be
painted, care must be taken to select
a bond breaker that does not trans-
fer to the concrete surface.

Lift and brace inserts


The size and placement of lifting
inserts will depend on the size and
shape of the panel, the surface de-
The supporting feet of the lifting and bracing in- When lifting with exposed aggregate up it is im-
serts must rest on top of the rock to insure portant to obtain a firm even bearing for the lift sign and the casting method (face
proper imbedment and prevent rust. The insert plate. One manner this may be done is as fol- up or face down). Figure 10 illus-
supplied should be for a slab thickness of the lows: 1. Place the proper length lifting bolt
dimension “C.” The insert should be securely through a 5⁄8-inch plywood doughnut and the lift trates the proper insert placement
wired to the reinforcing steel to prevent move- plate and start it into the insert. 2. Raise the ply- for various situations.
ment when the insert feet are placed on the un- wood and shovel pea gravel onto the exposed
even aggregate. The standard 1⁄4 -inch to 1⁄2-inch rock to fill the voids. 3. As the bolt is tightened, Lift and brace inserts must be
clearance below the top surface of the slab rotate the plywood to screed off the pea gravel carefully positioned in the slab at
should be maintained, and the usual slotted lag until the plywood is firmly against the highest
stud used for setting. rocks. proper distances from edges and
openings and must be kept upright
during the casting operation. A
guide to the correct number and po-
sition of inserts is given in Figure 11.
Setting bolts should be the correct
length and not so long as to leave a
void in the slab beneath the insert
after removal. Plastic-capped in-
serts are now available which sim-
plify this procedure.

The insert supplied should be for a slab thick-


Rigging for the lift
When an exposed aggregate panel is cast face ness of the dimension “A.” The insert should Cables for lifting slings need to be
up a lifting bolt should be used for setting in- then be 1⁄4 inch to 1⁄2 inch below the surface. The
stead of the slotted lag stud. Since the top sur- proper length lifting bolt will have the threaded long enough to provide at least a
portion of the bolt protruding 1⁄2 inch to 1 inch
face need not be troweled the bolt can protrude
below the coil. Make sure the lift plate is cor-
60-degree angle from the plane of
well above the surface of the exposed archi-
tectural aggregate. The threaded portion of the rectly oriented and bearing firmly on the con- the panel, and the rigging design
crete before lifting. The bolts should be firmly
bolt should protrude 1⁄2 inch to 1 inch below the
tightened. D=2-3⁄4 inches for single swivel lift
should provide approximately
coil. The insert supplied should be for a slab
thickness of the dimension “C.” plate. D=3/4 inch for double angle lift plate. equal stress on all inserts. Three-
point lifts are not recommended ex-
cept when a modified M or other
automatic equalizing system is be-
figure 10 ing used. A turnbuckle is not usual-
proper bolt, insert size and placement ly adequate to balance stresses. Var-
ious rigging arrangements are
illustrated in Figure 12. In general
the location of pick-up points and
ings, number 5 bars are added to Concrete placement and curing
the design of strongbacks should be
strengthen the corners and edges. The concrete is placed the same carried out under supervision of a
When wire fabric is the principal re- way as in a floor slab. Care must be
inforcement, dowel bars are provid- licensed engineer.
taken to prevent rock pockets along
ed where panels and columns are Tilting procedures
the bottom of the edge forms and to
tied together.
p re vent damage to the bond-break- The method of erection will de-
Mats of reinforcement assembled
on a jig are lowered onto stainless ing material. Screeding, compacting pend largely upon two factors:
steel, galvanized or plastic-coated and floating are also the same as for
floors. Techniques for finishing de- 1. Whether the crane can operate on
chairs to hold them near the center the floor slab or must stay outside
of the panels. Except for unusual pend on the texture desired.
the perimeter of the building;
conditions the center position pro- Curing is started as soon after fin-
vides the greatest strength for the ishing as possible without surface 2. Whether the panel is to be cast
panel. marring. If the panel is to be left ex- face up or face down.
O rd i n a rily a crane on the floor
slab is preferable, especially where a
smooth roadway is required for
walking the panel into position. The
suicide pick, where the crane opera-
tor is under the panel during lifting
and the attach points on the panel
are hidden from view, should be
avoided.
Casting and erection layouts
should be carefully prepared with
thought given to crane size, clear-
ances for the lifting sequence, and
placing of the concrete from the
transit mixer. Because of edge re-
bars, setting a panel between two
sections that have already been
erected should be avoided if possi-
ble. Braces may be attached to the
panels before lifting.
Exterior surface treatments, such
as a pebble finish, should be cast
with the outside face up. This gives
the contractor better control of the
treatment and enables him to clean
and seal the surface before erection.
This involves filling the pick-up and
bracing insert holes from the ve rt i-
cal position.
Vacuum lifters have been used in Alternative crane positions formed beside each other in rows to
some areas instead of pick-up in- permit a substantial amount of cast-
When the wall panels are to be
serts. Vacuum equipment is particu- erected before construction of the ing at one time.
larly efficient for picking up irregu- building frame, the crane can oper- In the tilting process an eight
lar shaped panels and those having ate easily on the floor slab. Gi ve n wheel truck crane operating on the
door and window openings. this approach, wall panels can be floor slab uses a horizontal lifting
bar with cables threaded over pul-
knee brace and cross lacing details leys to produce two eight-hook
points as needed. The arrangement
equalizes the lifting force on all
points simultaneously and allows
the slab to tilt to a vertical position
as it is suspended in the air. It is then
placed on the foundation and tem-
p o ra rily braced. This method pro-
vides good visual control.
If the structural frame is erected
first, the crane must operate outside
the building; this usually re q u i re s
that wall panels be cast on the floor
slab adjacent to their final positions
in the wall. When the panel is tilted
and rotated into place the underside
becomes the inside face of the wall.
Wall panels are tilted and positioned
Knee brace must have positive connection at each end and connect at mid-span with an adjustable strongback that
of brace. Cross lacing must be continuous and have positive connection at each is mounted on the panel’s upper
brace and at the end of each line. face and hooked to a crane. The
Maximum control
and safety is
possible when the
crane is able to
operate on the floor
slab within the
building, tilting the
panel in the manner
shown here.

With the roof already in place, the crane must operate


from outside the building. Strongbacks are used on
the panel which is raised, turned 180 degrees and
bolted to the roof structure.

strongback carries two removable


jacks with wheels located beyond
the lower edge of the panel allowing
the panel to roll outward as it is lift-
ed. Once the panel clears the roof,
the jack wheels are removed and the
These rock-faced panels panel is lifted and turned 180 de-
were cast face down. grees; then it is attached to the roof
With the crane operating
or frame. In this method the crane
outside the building, the
result is that the operator operates completely outside the
cannot observe the building.
bracing crew or At times the crane must operate
attachment points. If the outside the building even before the
panel fell it would fall frame is erected. Under this circum-
toward the crane. stance panels may be cast on the
floor slab or on a waste slab, wood
platform or even hard-packed earth.
Panels may also be cast in a stack in
the reverse order of their use. Cast-
ing panels face down permits place-
ment of pick-up points and bracing
an example of the use of the above chart left of 27’ in the “H” column. The 27’ line intersects the
curve at 3’ and 12’, indicating a safe bracing of 3’ of pan-
el width or 12’ of panel width if cross lacing and knee
The brace points required for a panel 27 feet above finished bracing are used.
floor are found as follows:
1. Enter the “H” column of the table at 27’. Summary
2. Read to the right to “0.667H” column for the distance up H=27’
the panel of 17’-4”.
0.667H=17’-4”
3. Read further right to “0.385H” column for the distance
out on the floor of 10’-0”. 0.385H=10’-0”
4. Read to the extreme right to “0.770H” column for the ap- 0.770H=20’-0”
proximate brace length of 20’-0”. 3’ of panel width per brace
5. To determine the number of braces required read to the 12’ with cross lace & knee brace
inserts on the back side, but this velocity of 50 to 60 miles per hour zontal and vertical forces. The angle
leaves the crane operator out of vi- produces a horizontal force of ap- between brace and floor should be
sual contact with the bracing crew. proximately 10 pounds per square between 45 degrees and 60 degrees,
foot. The addition of a driving rain and all connecting bolts must be
Bracing the panels can increase the pressure to about checked to ensure tightness and
After tilt up, the panels must of 12 pounds per square foot. prevent flutter of the braces.
course be temporarily braced until Adjustable tilt-up braces that are
the joints are secure, columns are knee-braced and cross-laced are
cast, and other steps taken to estab- recommended in most instances.
lish the structural integrity of the The braces should be positively an- PUBLICATION#C710428
building. Wind loads on exposed chored to imbedded inserts of suffi- Copyright © 1971, The Aberdeen Group
vertical panels can be severe. A wind cient strength to resist both hori- All rights reserved

You might also like