Dayly Welding Inspection Report: Client Report No Project Name JOB Item Work Location Part of Section Drawing No Date
Dayly Welding Inspection Report: Client Report No Project Name JOB Item Work Location Part of Section Drawing No Date
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 002/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :5 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 003/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :5 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 004/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :5 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 005/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :5 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 006/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :6 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 007/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :6 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 008/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :6 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 009/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :6 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 010/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :6 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 011/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :7 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 012/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :7 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 013/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :7 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 014/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :7 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 015/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :7 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 016APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 017/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 018/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 019/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 020/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 021/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :8 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 022/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :9 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 023/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :9 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 025/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :9 februari2019
Date: Date :
Client : PT.TOBA PULP LESTARI Report No : 026/APM/02/CONV
Project Name : TOBA PULP LETARI TBK . JOB Item :CONVEYOR
Work Location : PORSEA- INDONESIA
DAYLY WELDING INSPECTION REPORT Part of Section :1 of 1
Drawing No : 100-P-1010-001 Date :9 februari2019