Professional Documents
Culture Documents
PPC Loading and Scheduling
PPC Loading and Scheduling
Chapter VIII
Loading and Scheduling
Learning Objectives:
Reading this chapter would enable you to understand:
• Different types of loading and scheduling
• Advantages of loading and scheduling
• Units of loading and scheduling
Contents
8.1 Introduction: Why Scheduling?
8.2 Inputs of Scheduling
8.3 Loading and Scheduling Devices
8.4 Gantt Charts
8.5 Techniques of Scheduling
Summing Up
Self-assessment
Scheduling has yet another objective to fulfil to confirm or revise the tentative
delivery date promised in the original quotation. At times while scheduling a
work order, it is discovered that delivery date originally and tentatively
promised cannot be met. This may be due to materials not being available
immediately or due to increased plant loading while the customer was deciding
whether or not to award the quoted job to this company. Determination of
the realistic delivery date can only be made after detailed and firm scheduling.
73/MITSDE
Production Planning and Control
(a) Performance standard is the first and the foremost requirement of good
scheduling. Performance standards enable the scheduler to determine
the machine capacity in order to assign required machine hours and
man-hours for the various operations. Good scheduling is always
possible if the time study or industrial engineering department exists
in the plant. The performance standards for repetitive jobs in such plants
are available and for new jobs they can be estimated from tables of
synthetic standards prepared by the department.
Should this not be the case, the approximate time estimates can be
prepared by breaking the task into elements and then estimating time
for each manual and machine element. Simple arithmetic formulae may
be made use of to compute time for each of the machine elements
considering tool travel, speed, feed per revolution, number of cuts, etc.
Again if this is not possible the scheduler can make use of past records
of the same or similar jobs.
(b) Unit of measurement refers to the unit in which the loading and
scheduling is to be extended. This unit of measurement is usually
different for different industries. Industries such as sugar, cement,
fertilizers, foundries, steel mill etc. generally use weight (kg/ton) as a
unit of measurement while in textile mills; it is in length (meters). The
most common unit of measurement in engineering firms is “man-hours’’
or “machine-hours”.
(c) Unit of loading and scheduling refers to the duration for which loading
and scheduling should be done. The unit of loading and scheduling -
scheduled start and finishing timings - depends on the company’s
scheduling needs and the operating cycles. This implies that scheduling
should be done on daily basis if the company makes promises in days
and it should be done on daily or weekly basis if promises are
made in weeks.
74/MITSDE
Loading and Scheduling
(d) Effective capacity per work centre implies effective hours available for
production on a machine or on a work centre in a week, or in a month.
Theoretical capacity equals number of normal working hours of that
machine. Usually there are Interruptions. A few examples of these
interruptions are Power failure
• Preventive maintenance
• Waiting for inspection
• Operators engaged in other than production activities (functions
or celebrations)
• Machine engaged for technical studies
• Tool tryouts, jigs and fixture tryouts.
• Operator left work place for official discussion
• Machine breakdown electrical or mechanical)
• Waiting for transport.
• Operator absence
• Tool breakage
• Defective materials (hard material requiring reduced speeds and
feeds) or materials of incorrect specification (e.g. excess stock
removal).
• Operator training time.
• Rework
• Late start and early close.
• Overtime or incentive payment collection
• Operatives trade test.
75/MITSDE
Production Planning and Control
Case Study
Solution
76/MITSDE
Loading and Scheduling
Time needed for rush orders depends on the frequency of rush orders.
Each firm should work out its own average time spent on processing
rush orders.
77/MITSDE
Production Planning and Control
The principle tool used in scheduling and loading is the Gantt Chart.
78/MITSDE
Loading and Scheduling
The chart consists of a simple grid formed by a series of horizontal and vertical
lines. The vertical lines divide horizontal lines into small squares representing
units of measurement which may be days, weeks or months. The horizontal
lines divide vertical lines into sections which are used to represent either
operations (job schedule) or to represent work centres (load chart).
The former is known as the job schedule (Fig. 10.1) while the later is called
load chart (Fig. 10.2)
Symbols used
The symbols used on the chart vary from company to company. The following
are more commonly used (Fig. 10.3)
79/MITSDE
Production Planning and Control
SYMBOLS DESCRIPTION
Time when work started
Time when work completed
Time required for scheduled production
Setup time
Actual production or progress of work shown by thick
line between the legs
(1080) Identification symbol written in brackets
Y Date of updating of the chart
To prepare load charts, the Gantt Chart in the industry has been used with
lot of variations. One of the methods is to indicate the load by numerals.
(Fig. 10.4)
The load chart in Figure 10.4 indicates that there are eight capstan lathes, each
having a capacity of 94.5 hours per week (total work centre capacity of 94, 5 x 8
= 756 hours per week). The chart shows machine loading for different weeks.
Another form of load chart is the one that utilises the graphical approach (Fig.
10.5). The amount of work assigned in a particular week is indicated by suitable
line against the machine on which it is intended to be processed. Thin lines are
used to represent load on individual days while heavy lines are used to represent
cumulative work load. The period of loading is split up into percentage for
clarity. Figure 10.5 shows a typical master load chart based on this concept.
Besides Gantt Chart, there are many other types of scheduling devices which
are in vogue in the industry, Some firms make use of sliding tapes, sonic use
strings, others use pegs in board, and still others use track boards. The
scheduling devices may differ but the principles underlying them are same.
Once the readers grasp these principles, it is not difficult to adopt any one of
the above mentioned devices.
80/MITSDE
Loading and Scheduling
81/MITSDE
Production Planning and Control
Summing Up
Self-assessment
3. What are load charts? Why are they required? How are they prepared
and used in scheduling of work in [‘PC department?
82/MITSDE
Loading and Scheduling
83/MITSDE