(Package-2-Mech Works) : Clean Fuels Project
(Package-2-Mech Works) : Clean Fuels Project
METHOD OF STATEMENT
FOR
TIE-IN NO. 054-061
(EGE-TR-MS-061)
Revision Number 1 Reference EGE-TR-MS-061
Number
Amendment 0 Date 23-Oct-2018
Document Title METHOD STATEMENT OF PIPING TIE-IN NO. 054-061 AT UNIT
054 FOR RASTANURA REFINERY CLEAN FUELS PROJECT
RECOD OF REVISION
REVISION DESCRIPTION DATE
0 ISSUED FOR REVIEW & APPROVAL 13-Sep-18
1 ISSUED FOR REVIEW & APPROVAL 23-Oct-18
METHOD STATEMENT OF PIPING TIE-IN NO. 054-061 AT UNIT 054
RASTANURA REFINERY CLEAN FUELS PROJECT
Table of Contents
5.0 MANPOWER.......................................................................................................... 4
7.2 WORK to be executed before Shutdown Time for TIE-IN 054-061 ......................................................... 6
7.3 Work to be executed during the shutdown time for Tie-In Work for 054-061.................................. 8
1.0 SCOPE
This Method Statement covers the methodology of Tie-In No. 054-061 pipe spool at unit
054 for Rastanura Refinery Clean Fuel project. The work consists of furnishing of all
supervision, labor, materials, tools and equipment necessary for all Tie-in works.
2.0 PURPOSE
The purpose of this Method Statement is to show the methodology and describe the
sequential steps for execution of Tie-In No. 054-061. It is the intention of this document to
ensure that safe practices are being imposed on the tie-in works considering the protection
and safety of personnel & utilities from hazards that might occur during execution of works.
TERM DESCRIPTION
A written document that explains the planned execution method
Method Statement to control the work at various stages and to assure quality, and
delivery on time of the work.
Company Saudi Aramco
Contractor TR (Tecnicas Reunidas)
Sub-Contractor EVERGREEN CONTRACTING CO. (EGE)
WPS Welding Procedure Specification
PQR Procedure Qualification Record
ITP Inspection & Test Plan
Work to be performed with piping or equipment out of service,
Cold Tap
depressurized and vented.
4.0 RESPONSIBILITIES
Piping Foremen Direct execution of the Responsible for the direct execution at site
work. Instruct working and ensure that the work is performed in
accordance with latest approved Tie-In IFC
personnel. drawing and Proper usage of tools,
equipment, wearing of PPE and daily
housekeeping of the work area.
Welding Supervisor Site Supervision Directly in-charge and supervise all welding
work activities. Responsible for the daily
work progress, work quality and safety.
Welding Foremen Take the lead on Directly execute, lead and give instruction to
welders about the assigned work, work
assigned work.
procedure.
5.0 MANPOWER
The Piping Supervisor will control the activities at the site and he will be directly reporting to
the Project Engineer. The basic manpower under him will consist of the following:
Tools and equipment needed should be in good condition and must be checked by
Supervisor prior to use in the Tie-In area. These includes but not limited to:
Tie-In Information
NOTE; REFER TO ATTACHED P&ID MARKED-UP HYDRO TEST LIMIT FOR REFERENCE
P&ID DWG. No: NA-641518 Sht.011 Rev. 9A1 & Isometric Dwg, no.CD-363071 Sht.001
rev. 01B.
7.2.3 Pre-Tie-in/Site Activities:
7.2.3.1 Ensure that tie-in site verification has been carried out and tag the tie-in
location.
7.2.3.2 Initial Survey- UT thickness Survey and defect checks
After final cleaning and purging line will be handover to Contractor/Sub-
Contractor for Execution. Activities to carry out to conduct UT that
will be determine the thickness at Tie in location.
Submit and get the approval for Hot WP from company and follow
Operations Safety’s Instructions.
Mark exact tie-in using approved marking method.
External paint material shall be removed carefully from the run pipe
using power buffing in the proposed area.
The pipe surface shall be visually examined to confirm that there is no
circumferential weld with 150mm distance of propose pipe location by
Subcontractor and Contractor QA/QC.
The positive confirmation of wall thickness shall be obtained over the
circumference of existing pipe as per UT scanning procedure.
7.2.3.3 Storage and handling of Tie-ins spools and material
7.3.1 Before any works is done, Work permit must be secured from Saudi
Aramco Operation Department.
7.3.2 Prior to cutting, check that tie-in location is gas free by following HOT
WORK PERMIT pr ocedur e and Operations instructions .
Precaution shall be taken care to prevent ignition of flammable or
combustible materials. Existing pipe will be cut with Cold cutting machine and
mobilized using crane as per approved lifting plan.
7.3.3 Perform PT test on existing pipe bevel at both ends to check for crack
indications or any other material defect.
7.3.4 Lift Reducer 24x36 of CD-363071 Sht.001 in proper position using crane as
per approved lifting plan.
7.3.5 EGE QC will raise and issue fit-up inspection request to TR prior to
commencement any welding works for joints 01 (for CD-363071 Sht.001 rev.
01B.
7.3.6 Hydro test will be conduct after erection of continue drawing’s spools.
7.3.7 RT needs to be performed of field joint 01.
7.4.1 Clean the area of construction debris, waste materials, tools and equipment.
7.4. 2 EGE shall close all related work permits.
8.0 RFI for Layup & Reinstatement
8.1 EGE assigned site QC/QA Inspector will perform quality inspection of tie-in
activities as per approved ITP.
8.2 QC acceptance criteria shall be in accordance to the approved ITP as described in the
project specifications, Saudi Aramco QC Standard.
8.3 EGE assigned QC Inspector shall carry out all the inspection works related to
Tie-In activities and coordinate with TRS-QC representative on daily basis.
EGE assigned Site Safety Officer will implement safety program and policies at site in
accordance to Saudi Aramco Safety Standards. A Job Safety Analysis will be prepared by
EGE site safety representative for submission to TRS and for review and approval by Saudi
Aramco Ras Tanura Refinery Safety Department before start of tie-in works.
12.0 APPENDICES