WELCOME!

This live event will begin shortly...

M A R K E T O C TAV I A
LIVING ALLEYS
Workshop 1 | June 24th, 2020 | 6-7p

sfpublicworks.org/living-alleys

MARKET OCTAVIA LIVING ALLEYS


1
Workshop 1 | June 24, 2020
M A R K E T O C TAV I A
LIVING ALLEYS Workshop 1 | June 24th, 2020
WORKSHOP 1
OBJECTIVE //

• Provide an update on the Living Alleys


program, including budget and timeline for
implementation

• Obtain feedback to prioritize alley(s) to receive


living alley improvements within a constrained
budget

MARKET OCTAVIA LIVING ALLEYS


3
Workshop 1 | June 24, 2020
WORKSHOP 1 AGENDA
INTRODUCTION //
BACKGROUND //
PROJECT INFORMATION //
NEXT STEPS //

LIVE QUESTIONS, SUGGESTIONS,


STORIES //
Throughout the presentation, please share your questions,
suggestions, and stories through Microsoft Team’s Q&A
chat function. At the end of the presentation, a facilitator
will respond to some of the most common questions

MARKET OCTAVIA LIVING ALLEYS


4
Workshop 1 | June 24, 2020
A LIVING ALLEY is a narrow, pedestrian-
oriented street that is designed to focus on livability,
instead of parking and traffic. Typically, this means creating
a street primarily for pedestrians and bicyclists, as well as
space for social uses. It can be considered an “urban living
room”.

MARKET OCTAVIA LIVING ALLEYS


5
Workshop 1 | June 24, 2020
POTENTIAL LIVING ALLEYS
Living Alleys within the Market Octavia Plan
Elm St area //

Van Ness A
• Belcher • Germania • Pearl

ve
Birch St • Birch • Henry • Pierce
Ivy St
• Brady • Hickory • Plum
Linden St
• Brosnan • Hidalgo • Potomac
Octavia Blv

t
Hickory S
Stevenson
Lily St Colusa Pl
Chas e C t
nn
a St
• Carmelita • Ivy • Ramona
d

Rose St La Mi
• Chase • Jessie • Rose
fay
Stevenson
Br

South
ett
a

Colton
dy

e
St

t
Laussat S Van N
Carmelita

• Clinton Park • Lafayette • Rosemont


Potomac S
Pierce St

Stevenson
Jessie Woodward
Elgin Park
Webster S

St Plum St
ss Ave
Pearl St

Germania
• Colton • Landers • Sharon
St
Fillmore elcher St

t
St

ke
t

ar
M
t

Clinton Park
• Colusa • Laussat • Stevenson
B
Walter St

Rosemont Brosnan
Pl
Hid go
al Stevenson LEGEND
• Elgin Park • Lily • Walter
Ramona Ave

Terrace St
Alleys considered for
Henry St
Landers St

Living Alley improvements


• Elm • Linden • Webster
Church St

Dolores St

Hub Area
Sharon St

• Fillmore • Minna • Woodward


Market Octavia Area
Green/Open Space

MARKET OCTAVIA LIVING ALLEYS


6
Workshop 1 | June 24, 2020
FUNDING AND IMPLEMENTATION

• Living Alleys Program Transition //


The Living Alleys Program is now under the direction of San Francisco Public Works
who will provide the design and implementation of a community supported vision for
living alley improvements within the Market Octavia Plan area

• $4M from Market Octavia Impact Fees //


CAC approved allocation of these funds for Living Alleys public realm improvements

• Full funding to come on line through Fiscal Year 2023-2024 //


Funds are dependent on projected developments within the Market Octavia Area
Plan and Market Octavia Plan Amendment boundaries and will be apportioned each
fiscal year

MARKET OCTAVIA LIVING ALLEYS


7
Workshop 1 | June 24, 2020
IMPLEMENTATION TIMELINE

Phase I Remaining Funding


Concept Design Design Drawings Construction Appropriated Phase II Construction

2020 2021 2022 2023 2024 2025 2026

Workshop 1 - Project Kick Off - June


Workshop 2 - Draft Concept Designs - August
Workshop 3 - Final Concept Design - October

MARKET OCTAVIA LIVING ALLEYS


8
Workshop 1 | June 24, 2020
THE ORIGIN OF LIVING ALLEYS
WOONERF //

A Dutch term for a “living street”,


where the street is seen as a social
space rather than a space just for
vehicles. The living alleys concept
borrows this ethos, creating a
vibrant and engaging public space.

Credit: Clarence Eckerson Jr. - Streetfilms

MARKET OCTAVIA LIVING ALLEYS


9
Workshop 1 | June 24, 2020
THE ORIGIN OF LIVING ALLEYS
MARKET OCTAVIA AREA PLAN (2008) // Identifies
alleys as places for open space and calm pedestrian environments and
MARKET & calls for process by which residents can participate in the design and
OCTAVIA implementation of improvements to their alleys
AN AREA PLAN OF THE GENERAL PLAN
OF THE CITY AND COUNTY OF SAN FRANCISCO

LIVING ALLEYS TOOLKIT (2015) // A resource to develop and


TOOLKIT

SAN FRANCISCO PLANNING DEPARTMENT


implement living alleys including design tools and example prototypes

MARKET OCTAVIA PLAN AMENDMENT (formerly


A

EE T
SOU T H

STR

known as The Hub) (2019) // Builds on the Market Octavia Area


ET

PUBLIC
ARK
VAN N

M
E
S S AV

REALM
ENUE

PLAN Plan with updated design recommendations for living alleys and outlines a
public benefits package for implementation
DECEMBER 2019

MARKET OCTAVIA LIVING ALLEYS


10
Workshop 1 | June 24, 2020
POTENTIAL DESIGN ELEMENTS FROM PLANS
MARKET OCTAVIA MARKET OCTAVIA
LIVING ALLEYS TOOLKIT (2015)
AREA PLAN (2008) PLAN AMENDMENT (2019)

• Street Trees • Above Ground • Bike Racks • Pedestrian-Only Street


• Pedestrian-Scaled Lighting Planters • Temporary Closures • Raised Intersection
• Concentrate parking along • Living Walls for Street Events • Special Street/Sidewalk Paving
curbside with fewest driveways • Bollards • Active Frontages • Gateway Features
• Corner Plazas • Chicanes • Street-Scaled • Art on Empty Facades
• Seating • Shared Alleys Lighting

• Play Areas • Living Zones • Minimize and


• Raised Coordinate Building
Crosswalk Service Functions
• Public Art • Sidewalk Gardens
• Street Signage • Sidewalk Extensions
• Light Strings • Mid-Block Crossing

MARKET OCTAVIA LIVING ALLEYS


11
Workshop 1 | June 24, 2020
COMPLETED LIVING ALLEYS
Linden Alley

Van Ness A
ve
2018
Linden St
2019
Octavia Blv

t 2018
Hickory S

Between Octavia St and Gough St (2018)


d

South Hickory Alley


Van N
e
ss Ave
Stt
ke
ar
M

LEGEND
Completed Living Alleys
Alleys considered for
Living Alley improvements
Church St

Dolores St

Hub Area

Market Octavia Area


Green/Open Space

Between Octavia St and Laguna St (2018) Between Franklin St and Van Ness Ave (2019)

MARKET OCTAVIA LIVING ALLEYS


12
Workshop 1 | June 24, 2020
PRECEDENTS

MARKET OCTAVIA LIVING ALLEYS


13

LINDEN ALLEY, SF
Workshop 1 | June 24, 2020
HICKORY ALLEY, SF
MARKET OCTAVIA LIVING ALLEYS
Workshop 1 | June 24, 2020
14

(VAN NESS TO FRANKLIN)


HICKORY ALLEY, SF
MARKET OCTAVIA LIVING ALLEYS
Workshop 1 | June 24, 2020
15

(OCTAVIA TO LAGUNA)
MARKET OCTAVIA LIVING ALLEYS
16

FERN ALLEY, SF
Workshop 1 | June 24, 2020
MARKET OCTAVIA LIVING ALLEYS
17

ANNIE ALLEY, SF
Workshop 1 | June 24, 2020
MARKET OCTAVIA LIVING ALLEYS
18

RINGOLD ALLEY, SF
Workshop 1 | June 24, 2020
MARKET OCTAVIA LIVING ALLEYS
19

BELDEN PLACE, SF
Workshop 1 | June 24, 2020
MARKET OCTAVIA LIVING ALLEYS
20

TEMESCAL ALLEY, OAKLAND


Workshop 1 | June 24, 2020
NEIGHBORHOOD CONTEXT
B. Margaret Hayward Playground (2020) D. Patricia’s Green F. Buchanan Street Mall
B
F A

H G

C
E

G. Koshland Community Park

E. Duboce Park
A. City Hall 56 M A R K E T a n d o c tav i a a r e a p l a n : H U B P U B L I C R E A L M P L A N

C. Stevenson Alley

H. Page & Laguna Mini Park

MARKET OCTAVIA LIVING ALLEYS


21
Workshop 1 | June 24, 2020
NEIGHBORHOOD CONTEXT
Van Ness looking south towards Market (Proposed)

Over 4,900 new housing units have


been built or are under construction in
the Market Octavia Plan Amendment 1500
Mission
10 South
Van Ness
1 Oak

Area. Additional units are expected as


part of the Plan Amendment.

Market & Van Ness (Proposed)

30 Van Ness (Proposed) 1500 Mission (2020)

10 South 1 Oak 30
Van Ness Van Ness

1500
Mission Market & Van Ness (Existing)

MARKET OCTAVIA LIVING ALLEYS


22
Workshop 1 | June 24, 2020
CRITERIA FOR SELECTION
CURRENT INFRASTRUCTURE CURRENT DEVELOPMENT
STAKEHOLDER INPUT PROJECTS & CONDITION OF PROJECTS ($)
ROADWAY ($)

Community-vetted ideas for Road repaving, sewer Potential synergies with


living alley improvements replacement, current paving required public realm
and prioritization of condition and other roadway improvements
elements within a and sidewalk projects
constrained budget

ADJACENT LAND USE & POTENTIAL FOR


GROUND FLOOR PROGRAMMING & SITE EXISTING CONCEPT PLANS
CONDITION STEWARDSHIP

Active ground floor uses Partners and proper Living alley concepts and
that support robust configuration for anticipated applications that have
programming and use + care partners and already been developed and
activation stewards to clean and vetted with the community
maintain the space

MARKET OCTAVIA LIVING ALLEYS


23
Workshop 1 | June 24, 2020
CRITERIA FOR SELECTION
Upcoming Sewer/Paving Project //
• Hickory St, Lily St, Rose St

Van Ness A
ve
Upcoming infrastructure projects may be
opportunities to pair living alley treatments
with repaving work. Alleys with low PCI scores
Octavia Blv

t
Hickory S
Stevenson
Lily St Colusa Pl
t
Chase C inn
a St are not conducive to stamping/decorative inlay
d

La M
Rose St
Stevenson
fay
and should wait until repaving.
Br

South
ett
a

Colton
dy

e
St

t
Laussat S Van N
Carmelita

Potomac S
Pierce St

Stevenson
Jessie Woodward
Elgin Park
Webster S

St Plum St
ss Ave
Pearl St

Germania
St
Fillmore elcher St

t
ke
St

ar
M
t

Clinton Park
B
Walter St

Rosemont Brosnan
Pl
Hidalgo Stevenson
Ramona Ave

Terrace St LEGEND
Henry St
Landers St

Upcoming Sewer/Paving
Church St

Dolores St

Hub Area
Sharon St

Market Octavia Area


Green/Open Space

MARKET OCTAVIA LIVING ALLEYS


24
Workshop 1 | June 24, 2020
CRITERIA FOR SELECTION
Recently Repaved Alleys //
Elm St
• Elm St, Ivy St, Linden St, Hickory St, Lily St

Van Ness A
ve
Recently repaved alleys or those with a
Ivy St
Pavement Condition Index (PCI) score of
Linden St
75 or greater, will have asphalt that may be
Octavia Blv

t
Hickory S
Stevenson
Lily St Colusa Pl
t
Chase C inn
a St suitable for stamping/decorative inlay.
d

La M
fay
Stevenson
Br

South
ett
a

Colton
dy

e
St

t
Laussat S Van N
Carmelita

Potomac S
Pierce St

Stevenson
Jessie Woodward
Elgin Park
Webster S

St Plum St
ss Ave
Pearl St

Germania
St
Fillmore elcher St

t
ke
St

ar
M
t

Clinton Park
B
Walter St

Rosemont Brosnan
Pl
Hidalgo Stevenson
Ramona Ave

Terrace St LEGEND
Henry St
Landers St

Recently Repaved
Church St

Dolores St

Hub Area
Sharon St

Market Octavia Area


Green/Open Space

MARKET OCTAVIA LIVING ALLEYS


25
Workshop 1 | June 24, 2020
CRITERIA FOR SELECTION
Development & Existing Concept Plans //

Van Ness A
Upcoming development projects that are

ve
currently entitled or under review may be
Ivy St
opportunities to pair living alley treatments
with their required streetscape improvements.
Octavia Blv

Stevenson
Lily St Colusa Pl St
t a
Chase C inn
d

La M
Rose St
Stevenson
fay
Some alleys already have concept designs
Br

South
ett
a

Colton
dy

e
St

Van N
via past planning efforts and community
Stevenson
Jessie

e
Plum St
ss Ave
Pearl St

applications.
St
t
ke
ar
M

LEGEND
Alleys with Concept Designs
Church St

Dolores St

Potential Development
Market Octavia Area
Green/Open Space

MARKET OCTAVIA LIVING ALLEYS


26
Workshop 1 | June 24, 2020
LEVELS OF IMPROVEMENTS

LIGHT MEDIUM EXTENSIVE

• Sidewalk planters • Above ground planters • Extensive planting


• New trees • Pedestrian and street-scale • Extensive pedestrian lighting
• Simple pedestrian-scale lighting • Extensive decorative paving
lighting • Decorative paving • Partial raised roadway
• Removeable bollards • Raised crossings • Gateway features
• Mural* • Sidewalk extensions at corners • Mid-block crossing
or mid-block • Seating elements

* Improvements on private property would require alternative funding source & coordination

MARKET OCTAVIA LIVING ALLEYS


27
Workshop 1 | June 24, 2020
LEVELS OF IMPROVEMENTS
HICKORY ALLEY, SF
LIGHT

• Facade mural spanning 5


buildings
• Pedestrian-scale string lighting
• Programming & Events

MARKET OCTAVIA LIVING ALLEYS


28
Workshop 1 | June 24, 2020
LEVELS OF IMPROVEMENTS
FERN ALLEY, SF
MEDIUM

• Sidewalk planters
• New street trees
• Decorative roadway inlay*
• Pedestrian and street-scale
lighting

*does not include cost of asphalt


repaving

MARKET OCTAVIA LIVING ALLEYS


29
Workshop 1 | June 24, 2020
LEVELS OF IMPROVEMENTS
LINDEN ALLEY, SF
EXTENSIVE

• Raised crossing
• Partial raised roadway
• Pedestrian and street-scale
lighting
• New street trees
• Sidewalk planters
• Seating

MARKET OCTAVIA LIVING ALLEYS


30
Workshop 1 | June 24, 2020
SO WHAT DOES ALL THIS MEAN?

• The Living Alleys program has a limited amount of implementation


funding

• Therefore, a limited number of alleys will be able to receive


improvements

• We need your help in prioritizing alley(s) to receive these


improvements within this constrained budget

MARKET OCTAVIA LIVING ALLEYS


31
Workshop 1 | June 24, 2020
NEXT STEPS
FEEDBACK //
We need your help addressing alleys within a limited budget.
Take our online survey!
sfpublicworks.org/living-alleys

UPCOMING OUTREACH //
On-site, Neighborhood, and Community Group outreach
Dates TBD

Workshop 2 - Draft Concept Designs


August 2020

Workshop 3 - Final Concept Design


October 2020
MARKET OCTAVIA LIVING ALLEYS
32
Workshop 1 | June 24, 2020
THANK YOU!
M A R K E T O C TAV I A
LIVING ALLEYS
sfpublicworks.org/living-alleys
Survey QR Code
Let us hear from you!
Contact Information
Arun Bhatia, Project Manager