GABON ROAD PROJECT

SATURDAY
JAN 2021

30

REHABILITATION & UPGRADATION OF 2 LANE NATIONAL ROAD RN1 FROM PK24+000 TO PK 105+000 ON EPC BASIS
IN GABON

WEEKLY CONSTRUCTION REPORT 01

NAVIGATOR
9
DAY
OF
547
DURATION
SATURDAY
JAN 2021

30

SAFETY QUALITY STATUS SCHEDULE LOOK AHEAD KEY HIGHLIGHTS

1. SAFETY 4. SCHEDULE
2. QUALITY 5. LOOK AHEAD
3. PROJECT STATUS 6. KEY HIGHLIGHTS

NAVIGATOR
WEEKLY UPDATE GABON ROAD PROJECT LAYOUT

Building
B

Building
A

NAVIGATOR
WEEKLY UPDATE SAFETY STATISTICS

10,080 NCR ISSUED : 00


NCR OPEN : 00
ACCIDENT FREE MAN HOURS
OBSERVATION ISSUED : 00
OBSERVATION OPEN : 00
TOTAL SAFE MANHOURS SAFETY
Achieved on Project AVERAGE NUMBER OF MANDAYS DURING WEEK:118 NOS

10,080 HRS NUMBER OF LOST TIME INJURIES : NIL


NUMBER OF ACCIDENTS : NIL
WORKMEN INDUCTION STATISTICS :118 NOS
SAFETY BULLETIN/ TOPICS ISSUED : NIL

NAVIGATOR
WEEKLY UPDATE QUALITY STATISTICS

NCR ISSUED : 00
NCR OPEN : 00
NRC PAST WEEK : 00
OBSERVATION PAST WEEK :00
OBSERAVATION OPEN :00 QUALITY
OBSERVATION PAST WEEK :00

NAVIGATOR
WEEKLY UPDATE PROJECT STATUS

START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION
FINISH
Monday

COMPLETED FOR PK50- INVESTIGATION FOR


JAN 2021 PK75. PK50-PK75. JUL 2022

22 100 % 100 % 40 % 22

STATUS

COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021

2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18

NAVIGATOR
WEEKLY UPDATE SURVEY WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE GEO TECHNICAL WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE TRAFFIC CENSUS AND TRAFFIC AXLE LOAD WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE TEMPORARY ROAD REPAIR WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE TEMPORARY ROAD REPAIR WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE CROSS DRAINAGE DECONGESTION WORKS

STATUS

NAVIGATOR
WEEKLY UPDATE STATUS OF MAKORA CRUSHER AREA

STATUS

NAVIGATOR
WEEKLY UPDATE SITE CAMP AREA CLEARENCE AND CAMP FACILITY

STATUS

NAVIGATOR
WEEKLY UPDATE CAMP FENCING AND FACILITY CONSTRUCTION IN
PROGRESS

STATUS

NAVIGATOR
WEEKLY UPDATE ROAD WORKS IN PROGRESS

STATUS

NAVIGATOR
WEEKLY UPDATE KEY STAFF STATUS

1.Key staffs of environment and safety mobilized 45 days ahead of schedule


2.Project related major plans like Environment Management Plan, Health & Safety Management Plan,
Quality Management Plan, Method Statement of Geotech investigation ahead of schedule.

STATUS

NAVIGATOR
WEEKLY UPDATE WORKMEN STATUS

After
Workmen Mandays till
Commencement STATUS
Months Inception
Workmen Mandays
Skilled Unskilled Skilled Unskilled
Sep-20 12 4
Oct-20 265 250
Nov-20 286 546
Dec-20 666 469
Jan-21 994 881 368 472
Total 2,223 2,150 368 472

NAVIGATOR
WEEKLY UPDATE EXPATS MOBILISATION STATUS

Sl. No. Functional Department Plan Avl.


1 Project Management 2 1
2 Planning, MIS & QS 6 1
3 QAQC 3 2
4 Plant & Equipment 10 3
5 Survey 3 2
6 Execution – Road & Structure 13 8
SCHEDULE
7 Quarry & Crusher 1 0
8 Procurement & Stores 5 2
9 Administration & Accounts 7 7
10 Health Safety & Environment 1 1
11 Foreman & Supervisors 34 13
Total 85 40

NAVIGATOR
PLANT AND MACHINERY MOBILISATION STATUS
WEEKLY UPDATE
AND SCHEDULE
Description of Assets Cap. Plan. Avl. M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18

Excavator 20T 7 3 3 3 5 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Excavator 30T 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Crawler Dozer D6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 0
Motor Grader 120 k 5 2 2 2 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Soil Compactors 10T 6 2 2 2 6 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Tractor Dozer 75 HP 4 1 1 1 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Dumpers 25T 46 3 3 3 14 46 46 46 46 46 46 46 46 46 46 46 46 46 46 46
Dumpers 40T 20 15 15 15 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20 20
Wheel Loader 2.1 Cum 7 3 3 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Pick & Carry/Other Crane 16/30/80T 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Backhoe Loader 0.3 Cum 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Trailer 50 TON 3 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Generator 500 KVA 500 KVA 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Generator 250 KVA 250 KVA 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Generator 160 KVA 160 KVA 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Generator 125 Kva 125 KVA 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Generator 82.5 KVA 82.5 KVA 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
SCHEDULE
Diesel Bowser 10 KL 2 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Weigh Bridge 100 TON 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Concrete Batching Plant 30 cum/Hr 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Transit Mixer 6 Cum 10 0 0 0 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
Concrete Pump 26 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
RM800 12 cum 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
260 / 160
HOT Mix Plant 2 1 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
TPH
Asphalt Paver 9/10m Width 2 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Tandem Rollers 14T 3 2 2 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
PTR 24T 2 1 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Air compressor 300 CFM 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Tractor comp. - Mech
165 cfm 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Broom
Bitumen Bowser 10 Klts 2 0 0 0 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Cement Bulker 30T 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stone Crusher 250TPH 1 0 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 158 64 64 64 121 159 160 160 160 160 160 160 160 160 160 160 160 159 159 154

NAVIGATOR
WEEKLY UPDATE LOOK AHEAD

Location/
Activity Unit Scope Balance Completion Feb'21
Facility
Week 1 Week 2 Week 3 Week 4
Segment 4 Km 25 25 0% 25
Hydraulic Design
Segment 5 Km 20 20 0%
Report
Segment 6 Km 10 10 0%

Segment 4 Km 25 25 0% 25
Pavement Design
Segment 5 Km 20 20 0%
Report
Segment 6 Km 10 10 0%

Plan and Profile Segment 4 Km 25 25 0% 10


Drawings and Segment 5 Km 20 20 0%
Drainage Drawings Segment 6 Km 10 10 0%

Land Levelling Works Sqm 100,000 100%

Fencing Works M 1,700 600 65% 300 300


LOOK AHEAD
Batching Plant
No 100% 50% 50% 25.0% 25.0%
Installation
Camp Facility

Quality Lab No 100% 55% 45% 27.5% 27.5%

Afcons Office No 100% 78% 22% 19.5% 19.5% 19.5% 19.5%

Afcons Accomodation
Nos 50 46 8% 12 12 12 10
Containers Shifting

NAVIGATOR
WEEKLY UPDATE KEY HIGHLIGHTS

KEY HIGHLIGHT :

❑ Commencement date and NTP for detailed design received for Segment 4, 5 &6.

❑ Quality Lab Block works completed upto Lintel level.

❑ Hydraulic design report released for review with ICO.

❑ Plan and Profile Drawings expected by 15th Feb’20.

❑ Survey, Geo technical works are in Progress.

KEY HIGHLIGHTS

NAVIGATOR
WEEKLY UPDATE SUPPORT REQUIRED

SUPPORT REQUIRED:

❑ Seeking Land on Lease for Second Base Camp and Beach at PK95 near Kango
Bridge belonging to M/s. Olam.

❑ Seeking permission from administration for operation in curfew hours/other


restrictions imposed due to Covid.

KEY HIGHLIGHTS

NAVIGATOR
Thank You