GABON ROAD PROJECT SATURDAY


MAR 2021

27

REHABILITATION & UPGRADATION OF 2 LANE NATIONAL ROAD RN1 FROM PK24+000 TO PK


105+000 ON EPC BASIS IN GABON
WEEKLY PROGRESS REPORT 09

 NAVIGATOR
Page 2 of 22

58
DAY
OF
547
DURATION
SATURDAY
MAR 2021

27

SAFETY QUALITY STATUS SCHEDULE LOOK AHEAD KEY HIGHLIGHTS

1. SAFETY 4. SCHEDULE
2. QUALITY 5. LOOK AHEAD
3. PROJECT STATUS 6. KEY HIGHLIGHTS

 NAVIGATOR
Page 3 of 22

WEEKLY UPDATE GABON ROAD PROJECT LAYOUT 

Building
B

Building
A

 NAVIGATOR
Page 4 of 22

WEEKLY UPDATE SAFETY STATISTICS 


88818 NCR ISSUED : 00
NCR OPEN : 00
ACCIDENT FREE MAN HOURS
OBSERVATION ISSUED : 00
OBSERVATION OPEN : 00
TOTAL SAFE MANHOURS SAFETY
Achieved on Project AVERAGE NUMBER OF MANDAYS DURING WEEK:175 NOS

88,818 HRS NUMBER OF LOST TIME INJURIES : NIL


NUMBER OF ACCIDENTS : NIL
WORKMEN INDUCTION STATISTICS :175 NOS
SAFETY BULLETIN/ TOPICS ISSUED : NIL

 NAVIGATOR
Page 5 of 22

WEEKLY UPDATE PROJECT STATUS 


START
Monday SURVEY WORKS GEO TECHNICAL MOBILISATION
FINISH
Monday

COMPLETED FOR PK50- INVESTIGATION FOR


JAN 2021 PK75. PK50-PK75. JUL 2022

22 100 % 100 % 40 % 22

STATUS

COMPLETION FOR
NTP FOR SEGMENT 4
PROJECT NTP FOR NTP FOR
CONSTRUCTION 22 FEB 2022
COMMENCEMENT CONSTRUCTION CONSTRUCTION
FOR SEGMENT 4 FOR SEGMENT 5 &6 FOR SEGMENT 1 &3
DATE- 22 JAN OVERALL PROJECT
22 MAR 2021 22 JUN 2021 22 SEP 2021
2021 COMPLETION DATE-
22 JUL 2022
NTP FOR
NTP FOR
DETAILED
DETAILED
DESIGN FOR
DESIGN FOR
SEGMENT 4,5 & 6
SEGMENT 1, 2 & 3
- 22 JAN 2021
22 APR 2021

2021 2022
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18

 NAVIGATOR
Page 6 of 22

WEEKLY UPDATE AFCONS OFFICE COMPLETED, INTERNAL


PARTITION WORK IS IN PROGRESS 

STATUS

 NAVIGATOR
Page 7 of 22

WEEKLY UPDATE ENGINEER’S MESS ROOFING WORK IS IN PROGRESS 

STATUS

 NAVIGATOR
Page 8 of 22

WEEKLY UPDATE CONTAINER FOR ACCOMODATION & INTERNAL


ROAD WORKS IS IN PROGRESS 

STATUS

 NAVIGATOR
Page 9 of 22

WEEKLY UPDATE STORE, SUPERVISOR MESS, DDU


TRANSFORMER ROOM WORKS IS IN PROGRESS

STATUS

 NAVIGATOR
Page 10 of 22

WEEKLY UPDATE 100MT WEGHBRIDGE INSTALLATION IS


IN PROGRESS

STATUS

 NAVIGATOR
Page 11 of 22

WEEKLY UPDATE ROAD SAFETY PROTOCOL FOLLOWS AT SITE 

STATUS

 NAVIGATOR
Page 12 of 22

WEEKLY UPDATE KEY STAFF STATUS 


1.Key staffs of environment and safety mobilized 45 days ahead of schedule

Sujit Kumar Jha


Project Manager

STATUS

Aneesh Kumar Ange Francois M. Subbanna Santhosh George C.


Rajeshwar Sao
HSE Manager Environmental Pavement Manager Planning Manager
QA/QC Manager
Manager

Sisir Kumar Kailash C. S.


Ravindra Raut Muneesh Thakur Shrikant B. P.
Shadangi Procurement
Structure Manager F & A Manager Logistics Manager
P&A Manager Manager

 NAVIGATOR
Page 13 of 22

WEEKLY UPDATE WORKMEN STATUS 


SR.
MANPOWER UNIT MOBILISED
NO
1 NATIONAL WORKFORCE NOS 175

2 EXPATS WORKFORCE NOS 48

Workmen Mandays till After Commencement


Months STATUS
Skilled Unskilled Skilled Unskilled
Sep-20 12 4
Oct-20 265 250
Nov-20 286 546
Dec-20 666 469
Jan-21 994 881 368 472
Feb-21 1,356 1,692 1,356 1,692
Mar-21 2,220 1,890 2,220 1,890
Total 5,799 5,732 3,944 4,054

 NAVIGATOR
Page 14 of 22

WEEKLY UPDATE EXPATS MOBILISATION STATUS 

SCHEDULE

 NAVIGATOR
Page 15 of 22

WEEKLY UPDATE
PLANT AND MACHINERY MOBILISATION STATUS
AND SCHEDULE 

May-21

May-22
Aug-21

Nov-21
Sep-21

Dec-21

Mar-22
Jun-21

Feb-22

Jun-22
Jan-22
Oct-21
Apr-21

Apr-22
Jul-21

Jul-22
Description of Assets Cap. Plan. Avl.

Excavator 20/30T 9 4 6 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Crawler Bull Dozer D6 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Motor Grader 120 k 5 2 4 5 5 5 5 5 5 5 5 5 5 5 5 5 5 4
Soil Compactors 10T 6 2 5 6 6 6 6 6 6 6 6 6 6 6 6 5 5 4
Tractor Dozer 75 HP 4 1 2 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Dumpers 25/40T 66 18 58 66 66 66 66 66 66 66 66 66 66 66 66 66 66 66
Wheel Loader 2.1 Cum 7 3 3 7 7 7 7 7 7 7 7 7 7 7 7 7 7 7
Backhoe Loader 0.3 Cum 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
Water Tanker 10 KLit 8 0 1 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
Trailer 50 TON 3 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3 3
SCHEDULE
Generator 82.5 to 500 KVA 8 8 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9 9
Weigh Bridge 100 TON 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Concrete Batching Plant 30 cum/Hr 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Transit Mixer 6 Cum 10 0 1 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
HOT Mix Plant 260 / 160 TPH 2 1 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2
9/10m
Asphalt Paver 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Width
Tandem Rollers 14T 3 2 2 3 3 3 3 3 3 3 3 3 3 3 3 3 3 2
PTR 24T 2 1 1 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2
Cement Bulker 30T 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Stone Crusher 250TPH 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Total 144 53 107 145 146 146 146 146 146 146 146 146 146 146 146 145 145 142

 NAVIGATOR
Page 16 of 22

WEEKLY UPDATE WEATHER REPORT 

STATUS

 NAVIGATOR
Page 17 of 22

WEEKLY UPDATE LOOK AHEAD PLAN 

LOOK AHEAD

 NAVIGATOR
Page 18 of 22

WEEKLY UPDATE LOOK AHEAD PLAN 

LOOK AHEAD

 NAVIGATOR
Page 19 of 22

WEEKLY UPDATE LOOK AHEAD PLAN 

LOOK AHEAD

 NAVIGATOR
Page 20 of 22

WEEKLY UPDATE KEY HIGHLIGHTS 


KEY HIGHLIGHT :

 ROW Marking Completed.


 Temporary Benchmarks from PK 50 to 55 is in progress
 Engineer’s Mess Truss & Roofing Work is in Progress.
 Road Maintenance, Container placing is in Progress.
 Afcons office completed, only internal partition work is in progress.
 100MT Weighbridge installed on pedestal, Calibration & other works is in progress
 Other Activities i.e. DDU excavation, LT panel room, Sewer Chamber, Transformer room,
works is in progress
KEY HIGHLIGHTS
 Custom’s clearance for temporary lab equipment's received on 27th Mar 2021, Equipment
hopefully received by 29th March 2021

 NAVIGATOR
Page 21 of 22

WEEKLY UPDATE SUPPORT REQUIRED 


SUPPORT REQUIRED:

 Intervention in expediting resolution of issues for PK95 secondary camp


location.
 Expediting for Design and Drawing Clearance
 Permission from administration for operation in curfew hours/other received
through Laissez passer letter dated 12.03.2021, But few passes still pending.
 Expediting of Euro payments against 2nd and 3rd Payment Milestone.
 Intervention in expediting VISA process for expats.
 Custom clearance received on 27th March 2021 for temporary import of Lab
items.
 Facilitation for royalty exemption for the earth, laterite and sand being project
of national importance as per taxation rules of Gabon and precedence of earlier KEY HIGHLIGHTS
projects executed in Gabon.

 NAVIGATOR
Page 22 of 22

Thank You

www.afcons.com