Professional Documents
Culture Documents
Project Selection: Pre Study Phase of The VE Job Plan
Project Selection: Pre Study Phase of The VE Job Plan
Project Selection: Pre Study Phase of The VE Job Plan
Project Selection
Pre Study Phase of the VE job plan:
The pre study phase is the first stage of the eight phase Job Plan discussed in the previous lecture. The
project selection stage falls under this phase of the overall VE process. In general the pre study phase of
the Job plan in VE analysis consists of the following steps:
Select project
Select VE team
Establish budget
Set agenda
Select location
Gather documents
Determine requirements
Any project with significant money inflow and outflow can afford to have a VE study performed.
Normally, the larger and more complex the project, the more opportunity there is for a greater return
on investment. For example, if the owner selected a $50 million construction project to be studied and
the VE team cost to study the project was $50,000, and their findings were $10,000,000 in potential
savings (value improvement), the potential return on investment could be 200 to 1. If the owner's actual
implemented savings were $5,000,000, the actual return on investment is 100 to 1.
A VE team could review projects that are large and complex at two design stages without affecting the
design process as much. Those stages are normally 35% and 65%. If we wait until 90-100% complete
design to study and offer value improvement solutions, the redesign costs may exceed the potential
initial savings. VE at a later stage should not be ruled out. VE change proposals (VECPs) are often
1
Value Engineering SSM College of Engineering
B.E 8th Semester
submitted on a project to offer (or share savings with the owner) savings to the client even though the
design had reached final completion. Savings realized on one project can be multiplied when applied to
every other similar project component under design.
VE is one of the most effective problem-solving methodologies used in projects today to improve:
Design standards
Design Procedures
Constructability
Performance
Operation and maintenance
Processes
Time
Value
Worth
Function
Number of steps involved
Market strength
Future vision
Company healthiness (project wise)
Profits
Relationships
As such central part of the project selection process is evaluation and prioritization of identified
projects. There methods available are:
These methods require a certain minimum level of "planning" for each one of the projects to be
evaluated. We need to know
2
Value Engineering SSM College of Engineering
B.E 8th Semester
Usually, we do this whole evaluation in definition or early planning phase. Then, we only have estimates
of those values and should make sure that the estimation accuracies are comparable.
The Net Present Value (NPV) of a project is defined as the difference between present value of cash
inflow (revenue, PV in) and present value of cash outflow (cost, PV out) of that project over the project
life cycle time. Here is the formula to calculate the present value (PV) for given future value (FV),
interest rate (r), and number of accounting periods (n):
Investment project "Blue": development of a new version of product "Blue Dolphin". The cost for
development is $100,000.-- this year. Next year, we will be able to sell the first batch for $70,000.--, in
two years the second batch for $50,000.--. Given an interest rate of 10%, what is the net present value
of that project?
Investment project "Red": development of a new version of product "Red Shark". The cost for
development is $150,000.-- this year. Next year, we will be able to sell the first batch for $90,000.--, in
two years the second batch for $85,000.--. Given an interest rate of 10%, what is the net present value
of that project?
3
Value Engineering SSM College of Engineering
B.E 8th Semester
If we would have to choose between project "Blue" and project "Red" we would choose the one with
the higher NPV, i.e. project "Blue".
Another evaluation method uses the concept of Internal Rate of Return (IRR). The internal rate of return
of a project is defined as the interest rate at which the net present value of that project equals zero.
Again, we choose project "Blue", the one with the higher IRR.
In project selection, we usually account for an overall view of benefits and costs of proposed projects,
trying to express all benefits and all costs in monetary terms of present values at given interest rates.
This is the concept of the benefit cost ratio (BCR). Here is the formula:
4
Value Engineering SSM College of Engineering
B.E 8th Semester
If we only consider cash inflow as benefits and cash outflow as costs we end up with our familiar
decision to choose project "Blue".
With the concept of opportunity cost (OC) we consider that choosing one option means to give up other
options we might have. In our example, we choose project "Blue" (because of the higher NPV or IRR or
BCR) and give up project "Red", at an opportunity cost of NPV = $2,066.
Using the method of payback period (PP) gives us the simplest approach. We have the following
formula.
We decide in favor of the project with the shorter payback period, and our choice would be project
"Blue". Notice that we do not apply present values explicitly.
In general, we emphasize that the methods using Net Present Value (NPV), Internal Rate of Return (IRR),
Benefit / Cost Ratio (BCR), or Opportunity Cost (OC), are all based upon the calculation of present values
of estimated future cash inflows and outflows. In a mathematical sense, they usually lead us to the same
project selection results. Typically, application of one of these methods is enough.
If available, we can take initial risk assessments into consideration of the evaluation of project
proposals. The following chart shows an example of this comparative analysis.
5
Value Engineering SSM College of Engineering
B.E 8th Semester
We represent each project by a bubble with the size of the bubble indicating the project volume. Those
with high NPV and low risk value we should choose, those with low NPV and high risk value avoid. For
the others we need to consider other criteria like estimated profit, payback period, etc. We find our two
projects, "Blue" and "Red", but now, the picture does not immediately lead to the selection of "Blue"
since it seems to have a much higher risk value than "Red".