Method Statement of Heavy Schedule Piping Fabrication
Method Statement of Heavy Schedule Piping Fabrication
FABRICATION
METHOD STATEMENT OF FABRICATION OF HEAVY SCH. PIPING
INDEX
1.0 OBJECTIVE.
2.0 EXECUTION OF WORK.
4.0 RELEVANT STANDARD.
5.0 MATERIALS.
6.0 FILLER WIRE.
7.0 CONSUMABLE.
9.0 EDGE PREPARATION.
11.0 HEAT TREATMENT.
1.0 OBJECTIVE
CLIENT’S REQUIREMENT
2.0 EXECUTION OF WORK:-
2.1 WORK SHOP
THE SITE SHALL BE MOBILIZED WITHIN STIPULATED PERIOD THE AWARD OF
LOI / WORK ORDER.
4.0 RELEVANT STANDRAD
ASME 31.3
5.0 MATERIALS
6.0 FILLER WIRE
7.0 CONSUMABLES:-
9.0 EDGE PREPARATION
5. ALL TACK WELDER DEPLOYED SHALL BE TESTED AND QUALIFIED. ALL TACK
WELD SHALL BE DONE UTMOST CARE SINCE THIS WORLD FORM A PART IF
FINAL WELDING.
7. ALL DEFECTIVE FIT UP OF TACK WELDS WHICH ARE REJECTED BY THE CLIENT
SHALL BE REDONE.
12.0 NON DESTRUCTIVE TESTING
12.1 RELEVANT STANDARD
1.0 ASME SECTION V
12.2 VISUAL EXAMINATION
12.3 HARDNESS TEST EXAMINATION
12.4 RADIOGRAPHIC EXAMINATION
12.4.2 CONTRACTOR SHALL FURNISH THE NAMES AND BIO DATA OF THE RADIO
GRAPHIC CONTRACTOR. NO AGENCY OR CONTRACTOR SHALL BE DEPLOYED
WITHOUT THE APPROVAL OF CONSULTANT. RADIOGRAPHER SHOULD HAVE
MINIMUM LEVEL II QUALIFICATION.
13.2 BARE PIPES RECEIVED FROM CLIENT WILL BE BLASTED AND PRIMED USING
COPPER SLAG OR SAND AND ZINC PHOSPHATE PRIMER (RED OXIDE) TO THE
REQUIRED DFT OF 30 MICRON PRIOR TO WELDING OF FLANGES.