METHOD STATEMENT OF HEAVY SCHEDULE PIPING

FABRICATION
 METHOD STATEMENT OF FABRICATION OF HEAVY SCH. PIPING

INDEX

1.0           OBJECTIVE.

2.0           EXECUTION OF WORK.

3.0           WPS AND PRQ.

4.0           RELEVANT STANDARD.

5.0           MATERIALS.

6.0           FILLER WIRE.

7.0           CONSUMABLE.

8.0           TOOLS AND TACKLES.

9.0           EDGE PREPARATION.

10.0        FIT UP, ALINGMENT AND WELDING.

11.0        HEAT TREATMENT.

12.0        NON DESTRUCTIVE TESTING.

13.0        BLASTING AND PAINTING.

14.0        FINAL INSPECTION AND DISPATCH.


-------------------------------------------------------------------------------------------------------------------
------------

1.0      OBJECTIVE

     TO EXECUTE THE WORK AND PROVIDE SAFE, COMPETENT, PROFESSIONAL


AND QUALITY SERVICE WITHIN THE TIME SCHEDULE.

CLIENT’S REQUIREMENT

      TO CARRY FABRICATION, STRESS RELIVING, RADIOGRAPHY AND BLASTING &


PAINTING OF HEAVEY SCHEDULE PRESSURE PIPING.

-          SAFETY OF PERSONNEL & SAFE WORK PRACTICE.


-          GOOD ENGINEERING PRACTICE
-          ENSURE QUALITY OF WORK
-          ADHERE TO TIME SCHEDULE
-          MOBILIZATION OF RESOURCES ON TIME

         
2.0      EXECUTION OF WORK:-

2.1      WORK SHOP
THE SITE SHALL BE MOBILIZED WITHIN STIPULATED PERIOD THE AWARD OF
LOI / WORK ORDER.

3.0      WPS & PQR

3.1       THE WELDING PROCEDURE SPECIFICATION (WPS) FOR PIPING SHALL BE


SUBMITTED TO CLIENT FOR REVIEW AND APPROVAL.

3.2       ON APPROVAL OF WPS, THE WELDING PROCEDURE QUALIFICATION (PQR) AND


SUBSEQUENTLY WELDER’S QUALIFICATION SHALL BE CARRIED OUT AT WORK
SHOP.

4.0      RELEVANT STANDRAD

ASME 31.3

5.0      MATERIALS

5.1       CONTRACTOR SHALL ARRANGE TO RECEIVED AND STORE ALL FREE ISSUE


MATERIALS.

5.2       PIPES AND FITTINGS USED IN THIS PARTICULAR PIPING SHALL BE AS SPECIFIED


IN PIPING SPECIFICATION.

5.3       CONTRACTOR SHALL VISUALLY INSPECT MATERIALS BEING COLLECTED AND


IMMEDIATELY BRING IN TO THE NOTICE CLIENT ANY DISCREPANCY OR SHORT
FALL NOTICED

5.4       CONTRACTOR WILL DEPLOY ONE MOBILE CRANE WITH SUFFICIENT MAN


POWER AND LIFTING TOOLS FOR SAFE HANDLING OF MATERIALS AS
ILLUSTRATED IN SKETCH.
 

6.0      FILLER WIRE

1. CONTRACTOR SHALL ARRANGE TO SUPPLY FILLER WIRE REQUIRED FOR


THE JOB.
2. CONTRACTOR SHALL ENSURE THAT APPROVED BRAND OF FILLER WIRE
IS USED.

3. CONTRACTOR SHALL PRODUCE THE BATCH CERTIFICATE FOR EVERY


BATCH OF FILLER WIRE.

7.0      CONSUMABLES:-

1. CONTRACTOR SHALL ARRANGE AND SUPPLY ALL CONSUMABLE

2. CONTRACTOR SHALL ENSURE THAT ALL REGULATOR, HOSES ETC. USED


ARE REPUTED BRAND.
 
3. PURITY OF ARGON SHALL BE 99.995% WHEN USED FOR SHIELDING AND
PURGING.
4. FLOW RATE OF PURGING GAS SHOULD BE ESTABLISH DURING
PROCEDURE QUALIFICATION RECORD TEST.

8.0      TOOLS AND TACKLES.

1. CONTRACTOR SHALL PROVIDE ALL NECESSARY TOOLS AND TACKLES


REQUIRED FOR THE JOB. LIST OF TOOLS AND TACKLES ARE MAILED TO
CLIENT.

2. ALL GAUGES USED ARE TO BE TESTED SHALL BE CALIBRATED AND


TEST CERTIFICATES MADE AVAILABLE FOR VERIFICATION.

9.0      EDGE PREPARATION

1. EDGE SHALL BE PREPARED BY BEVELING MACHINE.

2. EDGE SHALL BE CLEANED TO REMOVE ANY DUST, DIRT OR RUST


WHICH MAY BE PRESENT PRIOR TO FIT UP.

10.0   FIT UP,ALINGMENT AND WELDING

1.     ALIGNMENT AND FIT UP OF INDIVIDUAL PIPING COMPONENT IS ESSENTIAL TO


OBTAIN A GOOD JOINT THERE FOR LOT OF CARE MUST BE TAKEN DURING FIT
UP.

2.     CONTRACTOR SHALL BE RESPONSIBLE FOR ACCURACY OF FABRICATION.


CONTRACTOR SHALL REVIEW THE DRAWING AND IN CASE ANY ARROW OR
OMISSION IS IDENTIFIED THE SAME SHALL BE BROUGHT INTO THE NOTICE OF
CLIENT

3.     COMPONENTS TO BE ALIGNED SHALL BE SPACED AS PER APPLICABLE CODE.

4.     WIRE SPACERS SHALL BE USED TO OBTAIN PROPER ROOT GAP, HOWEVER


AFTER TACK WELDING THERE SHALL BE REMOVED.

5.     ALL TACK WELDER DEPLOYED SHALL BE TESTED AND QUALIFIED. ALL TACK
WELD SHALL BE DONE UTMOST CARE SINCE THIS WORLD FORM A PART IF
FINAL WELDING.

6.     TACKS SHALL BE EQUALLY SPACED. THE MINIMUM NUMBER OF TRACKS FOR


VARIOUS SIZE OF PIPES SHALL BE AS FOLLOWS
    6.1              PIPE SIZE                                                     No. OF TACKS

a) 3’’ DIAMETER AND BELOW                                                2

b) BETWEEN 3 AND 12’’ DIAMETER                                         4

c) ABOVE 12’’ DIAMETER                                                        6

7.     ALL DEFECTIVE FIT UP OF TACK WELDS WHICH ARE REJECTED BY THE CLIENT
SHALL BE REDONE.

8.     PRIOR TO WELDING FIT UP SHALL BE JOINTLY INSPECTED BY CONTRACTOR,


CLIENT AND CONSULTANT AND RELEASE FOR WELDING
9.     WELDER QUALIFICATION AS PER THE SPECIFICATION SHALL BE CARRIED OUT
PRIOR TO COMMENCEMENT OF WELDING.

10.  ONLY QUALIFIED TACK WELDERS OR WELDERS ARE ALLOWED TO WORK ON


THE JOB

11.  CONTRACTOR SHALL MAINTAIN THE FOLLOWING DOCUMENTS FOR THE


WELDERS.

a)    WELDING PROCEDURE SPECIFICATION.

b)    PROCEDURE QUALIFICATION RECORD.

c)     WELDER IDENTIFICATION CARD.

12.  ALL DOCUMENTS SUCH AS DAILY FIT UP AND WELDING REPORT SHALL BE


MAINTAINED BY THE CONTRACTOR. CLIENT OF CONSULTANT SHALL BE FREE
TO INSPECT AND RECORD HIS OBSERVATION ON THESE DOCUMENTS

13.  ABOVE ACTIVITIES IS FURTHER ILLUSTRATED IN THE SKETCH.

11.0    HEAT TREATMENT (STRESS RELIVING)

11.1    HEAT TREATMENT OF CARBON STEEL IS NOT REQUIRED, UNLESS


SPECIFICALLY STATED IN THE DRAWINGS

11.2    CARBON STEEL MATERIALS HAVING CARBON CONTENT 0.35% MAXIMUM AND


WALL THICKNESS LESS THEN 19 MM DO NOT REQUIRE TO BE HEAT TREATED.

11.3    CARBON STEEL MATERIALS HAVING CARBON CONTENT 0.35% MAXIMUM AND


WALL THICKNESS 19 MM OR ABOVE NEED TO BE STRESS RELIVED.

11.4    CARBON STEEL MATERIALS HAVING CARBON CONTENT ABOVE 0.35%


MAXIMUM IRRESPECTIVE OF WALL THICKNESS REQUIRED TO BE HEAT
TREATED.

11.5    THE JOINT SHALL BE WRAPPED IN ASBESTOS OR MINERAL WOOL TO A


DISTANCE OF 150 MM ON BOTH SIDE OF WELD JOINT DURING HEATING OR
COOLING.

11.6    STRESS RELIVING CAN BE DONE BY DEPLOYING A FURNACE OR BY USING


ELECTRIC RESISTANCE OR INDUCTION HEATING EQUIPMENT.

11.7    THE TEMPERATURE OF THE JOINT BEING STRESS RELIVE SHALL BE


RECORDED BY USING THERMOCOUPLES AND RECORDER. THE MINIMUM
NUMBER OF THERMOCOUPLES TO BE PROVIDED PER JOINT SHALL BE AS
STATED BELOW.
                        JOINT SIZE                             NO. OF THERMOCOUPLES

                  a) UPTO 6 ‘’                                                                  1

                  b) UPTO 10’’                                                                 2

                  c) FOR 12’’ AND ABOVE                                              3

11.8    AFTER COMPLETION OF STRESS REVELING HARDNESS TEST SHALL BE


CONDUCTED ON THE JOINTS

11.9    ALL NECESSARY DOCUMENTATION SHALL BE PREPARED AND MAINTAINED BY


THE CONTRACTOR AND THE SAME WILL BE FORWARDED TO CONSULTANT FOR
REVIEW AND APPROVAL.

12.0   NON DESTRUCTIVE TESTING

12.1   RELEVANT STANDARD

1.0   ASME SECTION V
12.2   VISUAL EXAMINATION

12.2.1   WELDS JOINTS SHALL BE VISUALLY EXAMINED AND RELEASED FOR


RADIOGRAPHY

12.3   HARDNESS TEST EXAMINATION

12.3.1   HARDNESS TEST SHALL BE CARRIED OUT AS SPECIFIED IN THE PIPING


SPECIFICATION INDEX / DRAWINGS OR AS PER THE INSTRUCTION OF
CONSULTANT ENGINEER.

12.4   RADIOGRAPHIC EXAMINATION

12.4.1   PROCEDURE FOR RADIOGRAPHY EXAMINATION TO BE ADOPTED WILL HAVE TO


BE FURNISHED BY THE CONTRACTOR TO THE CONSULTANT AND APPROVAL
OBTAINED.

12.4.2   CONTRACTOR SHALL FURNISH THE NAMES AND BIO DATA OF THE RADIO
GRAPHIC CONTRACTOR. NO AGENCY OR CONTRACTOR SHALL BE DEPLOYED
WITHOUT THE APPROVAL OF CONSULTANT. RADIOGRAPHER SHOULD HAVE
MINIMUM LEVEL II QUALIFICATION.

12.4.3   THE RADIOGRAPHIC TECHNIQUE AND PROCEDURE ADOPTED SHALL CONFIRM


TO THE REQUIREMENTS OF ASME SECTION V.

12.4.4   THE ACCEPTABLE LIMITS OF DEFECTS AND REMOVAL OF DEFECTS SHALL BE


AS THE RELEVANT CODE OF FABRICATION.

12.4.5   ALL STATUTORY, SAFETY REQUIREMENT WHILE HANDLING X-RAY SOURCE


SHALL BE FOLLOWED BY THE CONTRACTOR.

12.4.6   PERCENTAGE OF RADIOGRAPHY SHALL BE AS STATED IN THE PIPING


SPECIFICATION OR DRAWINGS.

12.4.7   CONTRACTOR SHALL RADIOGRAPHY THE JOINTS SELECTED BY THE


CONSULTANT INSPECTOR.
12.4.8   AFTER RADIOGRAPHY THE CONTRACTOR SHALL FURNISH ALL THE
RADIOGRAPHY TO THE CONSULTANT ENGINEER AFTER PROCESSING ALONG
WITH HIS OBSERVATION.

12.4.9   ALL NECESSARY DOCUMENTATION SHALL BE PREPARED AND MAINTAINED BY


THE CONTRACTOR AND THE SAME WILL BE FORWARDED TO CONSULTANT FOR
REVIEW AND APPROVAL.

13.0   BLASTING AND PAINTING

13.1    BLASTING YARD SHALL BE BUILT UP WITH MACHINERY SUCH AS AIR


COMPRESSOR, SPRAY PAINTING EQUIPMENT, HOPPER, HOSES AND COPPER
SLAG FOR BLASTING AND PRIMER APPLICATION.

13.2    BARE PIPES RECEIVED FROM CLIENT WILL BE BLASTED AND PRIMED USING
COPPER SLAG OR SAND AND ZINC PHOSPHATE PRIMER (RED OXIDE) TO THE
REQUIRED DFT OF 30 MICRON PRIOR TO WELDING OF FLANGES.

13.3    SLIP ON OR WELD NECK FLANGES WILL BE WELDED ON THE PRIMED PIPE.

13.4    FINAL EPOXY PAINT WILL BE APPLIED ON FINISH SPOOLS. 

14.0   FINAL INSPECTION AND DESPATCH OF SPOOLS

14.1    FINISH SPOOLS ARE INSPECTED AND DISPATCH TO ERECTION SITE.