Interview Preparaton: 1. Question: Tell Me About A Time When You Disagreed With Your Supervisor and How You Handled It?
Interview Preparaton: 1. Question: Tell Me About A Time When You Disagreed With Your Supervisor and How You Handled It?
Interview Preparaton: 1. Question: Tell Me About A Time When You Disagreed With Your Supervisor and How You Handled It?
Task: To convince the Manager that I was doing the right thing.
Actions: I researched the internet and checked the bearings and seals for
the pump at the SKF website where the life span of the pumps were average
5 years. Longer so I printed this results and spoke with my supervisor that
the problem was the quality of materials and parts we ordered not the
procedure of work by the technicians.
Task: The following tasks were allocated to materials and spare parts
management. Developing work procedure for work request on rotating and
static equipments. Project control and monitoring
Actions: first I recognized that I had 8 hrs a day. Take a walk around the
Plant. The first thing I did is to prioritize the jobs, based on time, safety and
high production risk areas. Take a walk around the Plant. Determining who
will do the job, based on individual schedule. Controlling and managing
schedule/cost per month.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low, Grouping
the plant layout into high risk zones and putting emphasis on the plant areas
with very important equipments such as boilers.
Actions: switch off the generator, Coolant water and check the vanes/tanks
to be sure
Result: I learnt to be very thorough even though everything sounds and
looks good I should take a look around and not jump into assumptions until
personally verified.
Actions: I had to work with them gave very good suggestions to them but
whenever we went to the professor He was always commenting on my
suggestions and my decisions
Result: Most solution ended up with me and the professor kept referring to
my work and with time they agreed with my expertise. We are still friends
today. I learned sometimes it might take time to get the level of co-operation
to make a project work effectively especially when there are personal
differences.
Actions: I talked with each people involved personally and heard heir views
and after we reached a better way individually .I now called everyone
together to explain to everybody so everybody felt very comfortable.
Result: better working relationships, better productivity, better
communication and understanding.
Task: To convince the manager that what I was doing was right to make
sure we were ahead.
Task: I had to look for ways of given him rest with his family
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Result: Saved company money for maintenance, faster way /method of
performing work client satisfaction, my manager was very happy.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.
Actions: I reorganized the system, by using the primavera (P6), I was able
to re aligning organizational breakdown structure, project structure,
resources (Positions) and roles (tasks to do). Analysis with wrench time
(feedback with respect to when a job was completed and basic personal
experiences from technicians), work breakdown structure of jobs and
projects. Records of time to be able to evaluate performance and
productivity with respect to work. Prioritizing jobs from high to low.