Professional Documents
Culture Documents
Productivity Rate (Site Development Works)
Productivity Rate (Site Development Works)
Productivity Rate (Site Development Works)
OD 3
Manpower/day 0.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.22
A Exterior Plants Nos. 1000
OD 3
Manpower/day 0.64
I Equipment: @ Hrs
OD 3.00
Equipment/day 10.26
A Lawn & Grasses M2 1000
OD 3
Manpower/day 0.07
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.56
A Irrigation Pipes & Accessories Nos. 500
OD 3
Manpower/day 4.17
I Equipment: @ Hrs
OD 3.00
Equipment/day 16.67
A Benches Lm. 500
OD 3
Manpower/day 0.58
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.31
A Trash Receptacles Nos. 500
OD 3
Manpower/day 5.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 5.56
A Curbstone Lm 500
B Daily Output Lm 30
OD 3
Manpower/day 5.56
I Equipment: @ Hrs
OD 3.00
Equipment/day 11.11
A Wall Cladding Stone Coping m2 500
B Daily Output m2 55
OD 3
Manpower/day 3.03
I Equipment: @ Hrs
OD 3.00
Equipment/day 6.06
A Aggregate Concrete around the b m2 500
B Daily Output m2 67
OD 3
Manpower/day 2.49
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.31
A Reinforce Blockworks m2 500
B Daily Output m2 18
OD 3
Manpower/day 1.16
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.16
A Precast Concrete Steps Lm 500
B Daily Output Lm 11
OD 3
Manpower/day 15.15
I Equipment: @ Hrs
OD 3.00
Equipment/day 15.15
A Asphalt M2 500
OD 3
Manpower/day 0.01
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.04
A Concrete paving M2 500
B Daily Output M2 24
OD 3
Manpower/day 2.60
I Equipment: @ Hrs
OD 3.00
Equipment/day 6.94
A Granite Pavers M2 500
B Daily Output M2 12
OD 3
Manpower/day 5.21
I Equipment: @ Hrs
OD 3.00
Equipment/day 13.89
A Sandstone Paving M2 500
OD 3
Manpower/day 3.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 24.51
A Quarry Stone Paving M2 500
OD 3
Manpower/day 1.81
I Equipment: @ Hrs
OD 3.00
Equipment/day 14.49
A Terra Cotta Paving M2 500
OD 3
Manpower/day 3.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 24.51
A Unit Pavers M2 500
OD 3
Manpower/day 3.06
I Equipment: @ Hrs
OD 3.00
Equipment/day 24.51
A Backfilling & Compaction m3 5000
OD 3
Manpower/day 16.67
I Equipment: @ Hrs
OD 3.00
Equipment/day 16.67
A Remove Disposable Materials m3 300
OD 3
Manpower/day 0.77
I Equipment: @ Hrs
OD 3.00
Equipment/day 0.77
A Common Earth (Excavation) m3 1000
OD 3
Manpower/day 2.30
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.15
A Heavy Soil (Excavation) m3 1000
OD 3
Manpower/day 3.33
I Equipment: @ Hrs
OD 3.00
Equipment/day 1.67
A Site Clearing (Stripping) m3 5000
OD 3
Manpower/day 4.76
I Equipment: @ Hrs
OD 3.00
Equipment/day 2.38
Item Activity Activity SUB Unit
ID Description ACTIVITY
SITEWORKS
SUBSTRUCTURE
For Disposal M3
Formworks M2
Rebars kg
Deshuttering M2
QTY Prod. Rate Days (H) Tot. Man Crew Tot. Mdays
53,280.00 250 213.12 2.056 1 Steel Fixer, 1 Helper, .056 Operator 438.17
1,184.00 35 33.83 3.056 2 Carpenter, 1 Helper, .056 Operator 103.38
OD (O) Manpower MAN-DAYS
/day
(N/O) Carpenter Mason Steel Fixer Helper Operator Driver Technician Painter
1 42.76
Desc. (H x X)
0 0 0 0 0
EQMT-DAYS
0.08
0.55
1.19
0.19
0 0 0 1.93 0.08 0 0