Productivity Rate (Site Development Works)

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 33

A Road Marking(Sign) M2 200

B Daily Output M2 150

C A/B Duration, Days (8 Hrs/Day) Day 1.33

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.02 Mday

E2 Skilled Labor 2.000 8 0.33 Mday

E3 Equipment Operator (light) 0.500 8 0.08 Mday

E4 Labor 3.000 8 0.50 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.01 8 0.05 Mday

H G*A Total Manhours 1.33 8 0.17 Mday

OD 3

Manpower/day 0.06

I Equipment: @ Hrs

11 Gradall 3.0 m.ton 0.500 8 0.08 Mday

12 Tool Set 1.000 8 0.17 Mday

J Sum "I" Total Equip 0.500

K J*D/B EquipHour 0.027 8 0.21 Eday

L K*A Total Equiphours 5.33 8 0.67 Eday

OD 3.00

Equipment/day 0.22
A Exterior Plants Nos. 1000

B Daily Output Nos. 65

C A/B Duration, Days (8 Hrs/Day) Day 15.38

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.24 Mday

E2 Labor 2.000 8 3.85 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.02 8 0.12 Mday

H G*A Total Manhours 15.38 8 1.92 Mday

OD 3

Manpower/day 0.64

I Equipment: @ Hrs

11 Tool Set 2.000 8 3.85 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.246 8 1.97 Eday

L K*A Total Equiphours 246.15 8 30.77 Eday

OD 3.00

Equipment/day 10.26
A Lawn & Grasses M2 1000

B Daily Output M2 600

C A/B Duration, Days (8 Hrs/Day) Day 1.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.03 Mday

E2 Equipment Operator 1.000 8 0.21 Mday

E3 Labor 4.000 8 0.83 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.00 8 0.01 Mday

H G*A Total Manhours 1.67 8 0.21 Mday

OD 3

Manpower/day 0.07

I Equipment: @ Hrs

11 Wheel Loader 1.000 8 0.21 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.013 8 0.11 Eday

L K*A Total Equiphours 13.33 8 1.67 Eday

OD 3.00

Equipment/day 0.56
A Irrigation Pipes & Accessories Nos. 500

B Daily Output Nos. 5

C A/B Duration, Days (8 Hrs/Day) Day 100.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Mechanical Foreman 0.125 8 1.56 Mday

E2 Skilled Labor 1.000 8 12.50 Mday

E3 Labor 3.000 8 37.50 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.20 8 1.60 Mday

H G*A Total Manhours 100.00 8 12.50 Mday

OD 3

Manpower/day 4.17

I Equipment: @ Hrs

11 Tool Set 0.500 8 6.25 Mday

J Sum "I" Total Equip 0.500

K J*D/B EquipHour 0.800 8 6.40 Eday

L K*A Total Equiphours 400.00 8 50.00 Eday

OD 3.00

Equipment/day 16.67
A Benches Lm. 500

B Daily Output Lm. 36

C A/B Duration, Days (8 Hrs/Day) Day 13.89

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Foreman 0.125 8 0.22 Mday

E2 Skilled Labor 1.000 8 1.74 Mday

E3 Labor 1.000 8 1.74 Mday

E4 Equipment Operator 0.500 8 0.87 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.03 8 0.22 Mday

H G*A Total Manhours 13.89 8 1.74 Mday

OD 3

Manpower/day 0.58

I Equipment: @ Hrs

11 Crane 0.500 8 0.87 Mday

12 Tool Set 1.000 8 1.74 Mday

J Sum "I" Total Equip 0.500

K J*D/B EquipHour 0.111 8 0.89 Eday

L K*A Total Equiphours 55.56 8 6.94 Eday

OD 3.00

Equipment/day 2.31
A Trash Receptacles Nos. 500

B Daily Output Nos. 30

C A/B Duration, Days (8 Hrs/Day) Day 16.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Skilled Labor 1.000 8 2.08 Mday

E2 Labor 1.000 8 2.08 Mday

E3 Equipment Operator 1.000 8 2.08 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.27 8 2.13 Mday

H G*A Total Manhours 133.33 8 16.67 Mday

OD 3

Manpower/day 5.56

I Equipment: @ Hrs

11 Crane 1.000 8 2.08 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.267 8 2.13 Eday

L K*A Total Equiphours 133.33 8 16.67 Eday

OD 3.00

Equipment/day 5.56
A Curbstone Lm 500

B Daily Output Lm 30

C A/B Duration, Days (8 Hrs/Day) Day 16.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 2.08 Mday

E2 Skilled Labor 1.000 8 2.08 Mday

E3 Labor 2.000 8 4.17 Mday

E4 Equipment Operator 2.000 8 4.17 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.27 8 2.13 Mday

H G*A Total Manhours 133.33 8 16.67 Mday

OD 3

Manpower/day 5.56

I Equipment: @ Hrs

11 Crane 2.000 8 4.17 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.533 8 4.27 Eday

L K*A Total Equiphours 266.67 8 33.33 Eday

OD 3.00

Equipment/day 11.11
A Wall Cladding Stone Coping m2 500

B Daily Output m2 55

C A/B Duration, Days (8 Hrs/Day) Day 9.09

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 1.14 Mday

E2 Skilled Labor 1.000 8 1.14 Mday

E3 Labor 2.000 8 2.27 Mday

E4 Equipment Operator 2.000 8 2.27 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.15 8 1.16 Mday

H G*A Total Manhours 72.73 8 9.09 Mday

OD 3

Manpower/day 3.03

I Equipment: @ Hrs

11 Crane 2.000 8 2.27 Mday

J Sum "I" Total Equip 2.000

K J*D/B EquipHour 0.291 8 2.33 Eday

L K*A Total Equiphours 145.45 8 18.18 Eday

OD 3.00

Equipment/day 6.06
A Aggregate Concrete around the b m2 500

B Daily Output m2 67

C A/B Duration, Days (8 Hrs/Day) Day 7.46

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 0.93 Mday

E2 Skilled Labor 6.000 8 5.60 Mday

E3 Labor 2.000 8 1.87 Mday

E4 Equipment Operator 1.000 8 0.93 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.12 8 0.96 Mday

H G*A Total Manhours 59.70 8 7.46 Mday

OD 3

Manpower/day 2.49

I Equipment: @ Hrs

11 Truck Crane 0.125 8 0.12 Mday

12 Tool Set 1.000 8 0.93 Mday

J Sum "I" Total Equip 0.125

K J*D/B EquipHour 0.015 8 0.12 Eday

L K*A Total Equiphours 7.46 8 0.93 Eday

OD 3.00

Equipment/day 0.31
A Reinforce Blockworks m2 500

B Daily Output m2 18

C A/B Duration, Days (8 Hrs/Day) Day 27.78

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.125 8 0.43 Mday

E2 Mason 1.000 8 3.47 Mday

E3 Labor 1.000 8 3.47 Mday

E4 Equipment Operator 0.250 8 0.87 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.06 8 0.44 Mday

H G*A Total Manhours 27.78 8 3.47 Mday

OD 3

Manpower/day 1.16

I Equipment: @ Hrs

I1 Mixer .25 m3 0.125 8 0.43 Mday

I2 Crane 0.250 8 0.87 Mday

I3 Tool Set 1.000 8 3.47 Mday

I4 Forklift 0.125 8 0.43 Mday

I5 Truck 0.125 8 0.43 Mday

J Sum "I" Total Equip 0.125

K J*D/B EquipHour 0.056 8 0.44 Eday

L K*A Total Equiphours 27.78 8 3.47 Eday

OD 3.00

Equipment/day 1.16
A Precast Concrete Steps Lm 500

B Daily Output Lm 11

C A/B Duration, Days (8 Hrs/Day) Day 45.45

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 1.000 8 5.68 Mday

E2 Skilled Labor 1.000 8 5.68 Mday

E3 Labor 2.000 8 11.36 Mday

E4 Equip Operator ( Light ) 1.000 8 5.68 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.73 8 5.82 Mday

H G*A Total Manhours 363.64 8 45.45 Mday

OD 3

Manpower/day 15.15

I Equipment: @ Hrs

11 Truck Crane 1.000 8 5.68 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.727 8 5.82 Eday

L K*A Total Equiphours 363.64 8 45.45 Eday

OD 3.00

Equipment/day 15.15
A Asphalt M2 500

B Daily Output M2 4220

C A/B Duration, Days (8 Hrs/Day) Day 0.12

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Surveyor 0.375 8 0.01 Mday

E2 Labor 7.000 8 0.10 Mday

E3 Equip Operator ( Light ) 1.000 8 0.01 Mday

E4 Asphalt Paver 1.000 8 0.01 Mday

E5 Skilled Labor 2.000 8 0.03 Mday

F Sum "E" Total Man 0.375

G F*D/B Manhour 0.00 8 0.01 Mday

H G*A Total Manhours 0.36 8 0.04 Mday

OD 3

Manpower/day 0.01

I Equipment: @ Hrs

I2 Tandem Roller 1.000 8 0.01 Mday

13 Roller, Pneumatic Wheel 1.000 8 0.01 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.002 8 0.02 Eday

L K*A Total Equiphours 0.95 8 0.12 Eday

OD 3.00

Equipment/day 0.04
A Concrete paving M2 500

B Daily Output M2 24

C A/B Duration, Days (8 Hrs/Day) Day 20.83

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.375 8 0.98 Mday

E2 Labor 2.000 8 5.21 Mday

E3 Equipt.Operator 1.000 8 2.60 Mday

E4 Skilled Labor 2.000 8 5.21 Mday

F Sum "E" Total Man 0.375

G F*D/B Manhour 0.13 8 1.00 Mday

H G*A Total Manhours 62.50 8 7.81 Mday

OD 3

Manpower/day 2.60

I Equipment: @ Hrs

I2 Tandem Roller 1.000 8 2.60 Mday

13 Sheep Roller 300 HP 1.000 8 2.60 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.333 8 2.67 Eday

L K*A Total Equiphours 166.67 8 20.83 Eday

OD 3.00

Equipment/day 6.94
A Granite Pavers M2 500

B Daily Output M2 12

C A/B Duration, Days (8 Hrs/Day) Day 41.67

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Foreman 0.375 8 1.95 Mday

E2 Tile Layer 2.000 8 10.42 Mday

E3 Labor 3.000 8 15.63 Mday

E4 Equipt.Operator 1.000 8 5.21 Mday

E5 Labor 1.000 8 5.21 Mday

F Sum "E" Total Man 0.375

G F*D/B Manhour 0.25 8 2.00 Mday

H G*A Total Manhours 125.00 8 15.63 Mday

OD 3

Manpower/day 5.21

I Equipment: @ Hrs

I2 Crane 11 ton 1.000 8 5.21 Mday

13 Power Tool Set 1.000 8 5.21 Mday

14 Grinding Machine 0.500 8 2.60 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.667 8 5.33 Eday

L K*A Total Equiphours 333.33 8 41.67 Eday

OD 3.00

Equipment/day 13.89
A Sandstone Paving M2 500

B Daily Output M2 6.8

C A/B Duration, Days (8 Hrs/Day) Day 73.53

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 1.15 Mday

E2 Brick Layer 1.000 8 9.19 Mday

E3 Labor 1.000 8 9.19 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.15 8 1.18 Mday

H G*A Total Manhours 73.53 8 9.19 Mday

OD 3

Manpower/day 3.06

I Equipment: @ Hrs

11 Tool Set 1.000 8 9.19 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.176 8 9.41 Eday

L K*A Total Equiphours 588.24 8 73.53 Eday

OD 3.00

Equipment/day 24.51
A Quarry Stone Paving M2 500

B Daily Output M2 11.5

C A/B Duration, Days (8 Hrs/Day) Day 43.48

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 0.68 Mday

E2 Brick Layer 1.000 8 5.43 Mday

E3 Labor 1.000 8 5.43 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.09 8 0.70 Mday

H G*A Total Manhours 43.48 8 5.43 Mday

OD 3

Manpower/day 1.81

I Equipment: @ Hrs

11 Tool Set 1.000 8 5.43 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.696 8 5.57 Eday

L K*A Total Equiphours 347.83 8 43.48 Eday

OD 3.00

Equipment/day 14.49
A Terra Cotta Paving M2 500

B Daily Output M2 6.8

C A/B Duration, Days (8 Hrs/Day) Day 73.53

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 1.15 Mday

E2 Brick Layer 1.000 8 9.19 Mday

E3 Labor 1.000 8 9.19 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.15 8 1.18 Mday

H G*A Total Manhours 73.53 8 9.19 Mday

OD 3

Manpower/day 3.06

I Equipment: @ Hrs

11 Tool Set 1.000 8 9.19 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.176 8 9.41 Eday

L K*A Total Equiphours 588.24 8 73.53 Eday

OD 3.00

Equipment/day 24.51
A Unit Pavers M2 500

B Daily Output M2 6.8

C A/B Duration, Days (8 Hrs/Day) Day 73.53

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Labor Foreman 0.125 8 1.15 Mday

E2 Brick Layer 1.000 8 9.19 Mday

E3 Labor 1.000 8 9.19 Mday

F Sum "E" Total Man 0.125

G F*D/B Manhour 0.15 8 1.18 Mday

H G*A Total Manhours 73.53 8 9.19 Mday

OD 3

Manpower/day 3.06

I Equipment: @ Hrs

11 Tool Set 1.000 8 9.19 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 1.176 8 9.41 Eday

L K*A Total Equiphours 588.24 8 73.53 Eday

OD 3.00

Equipment/day 24.51
A Backfilling & Compaction m3 5000

B Daily Output m3/day 100

C A/B Duration, Days (8 Hrs/Day) Day 50.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Equipt.Operator 1.000 8 6.25 Mday

E2 Skilled 1.000 8 6.25 Mday

E3 Helper 1.000 8 6.25 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.08 8 0.64 Mday

H G*A Total Manhours 400.00 8 50.00 Mday

OD 3

Manpower/day 16.67

I Equipment: @ Hrs

11 Roller Compactor 1.000 8 6.25 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.080 8 0.64 Eday

L K*A Total Equiphours 400.00 8 50.00 Eday

OD 3.00

Equipment/day 16.67
A Remove Disposable Materials m3 300

B Daily Output m3/day 130

C A/B Duration, Days (8 Hrs/Day) Day 2.31

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Laborer 1.000 8 0.29 Mday

F Sum "E" Total Man 1.000

G F*D/B Manhour 0.06 8 0.49 Mday

H G*A Total Manhours 18.46 8 2.31 Mday

OD 3

Manpower/day 0.77

I Equipment: @ Hrs

11 Shovel 0.5m3 1.000 8 0.29 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.062 8 0.49 Eday

L K*A Total Equiphours 18.46 8 2.31 Eday

OD 3.00

Equipment/day 0.77
A Common Earth (Excavation) m3 1000

B Daily Output m3/day 290

C A/B Duration, Days (8 Hrs/Day) Day 3.45

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Laborer 1.000 8 0.43 Mday

E2 Equipt.Operator 1.000 8 0.43 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.06 8 0.44 Mday

H G*A Total Manhours 55.17 8 6.90 Mday

OD 3

Manpower/day 2.30

I Equipment: @ Hrs

11 Excavator 0.76m3 1.000 8 0.43 Mday

12 Shovel 0.5m3 1.000 8 0.43 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.028 8 0.22 Eday

L K*A Total Equiphours 27.59 8 3.45 Eday

OD 3.00

Equipment/day 1.15
A Heavy Soil (Excavation) m3 1000

B Daily Output m3/day 200

C A/B Duration, Days (8 Hrs/Day) Day 5.00

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Laborer 1.000 8 0.63 Mday

E2 Equipt.Operator 1.000 8 0.63 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.08 8 0.64 Mday

H G*A Total Manhours 80.00 8 10.00 Mday

OD 3

Manpower/day 3.33

I Equipment: @ Hrs

I2 Excavator 0.76m3 1.000 8 0.63 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.040 8 0.32 Eday

L K*A Total Equiphours 40.00 8 5.00 Eday

OD 3.00

Equipment/day 1.67
A Site Clearing (Stripping) m3 5000

B Daily Output m3/day 700

C A/B Duration, Days (8 Hrs/Day) Day 7.14

D Day Hours Hrs/Day 8

E Crew Structure: @ Hrs

E1 Building Laborer 1.000 8 0.89 Mday

E2 Equipt.Operator 1.000 8 0.89 Mday

F Sum "E" Total Man 2.000

G F*D/B Manhour 0.02 8 0.18 Mday

H G*A Total Manhours 114.29 8 14.29 Mday

OD 3

Manpower/day 4.76

I Equipment: @ Hrs

I2 Dozer 200 HP 1.000 8 0.89 Mday

J Sum "I" Total Equip 1.000

K J*D/B EquipHour 0.011 8 0.09 Eday

L K*A Total Equiphours 57.14 8 7.14 Eday

OD 3.00

Equipment/day 2.38
Item Activity Activity SUB Unit

ID Description ACTIVITY

SITEWORKS

Z2V33-0000 Site Clearing M2

Z2V33-0010 Setting-out / Layout M

SUBSTRUCTURE

Z2V33-0020 Excavation for footings + Disposal of Materials For Excavation M3

For Disposal M3

Z2V33-0030 Formation Level & Compaction M3

Z2V33-0040 Anti-Termite Applications (Under PCC Footings)

Z2V33-0050 Backfill & Compaction upto bot. of PCC Tie-Beam

Z2V33-0060 Anti-Termite Applications (Under PCC Tie-Beam)

Z2V33-0070 Backfill & Compaction up to bot of PCC Grd. Slab

Z2V33-0080 Anti-Termite Applications (Under PCC Grade Slab)

Z2V33-0090 Shutters + 50mm Thk. PCC Under Footings

Z2V33-0100 50mm Protection Screed (Over W.P. Membrane-Ftg.)

Z2V33-0110 RCC For Footings Casting M3

Formworks M2

Rebars kg
Deshuttering M2
QTY Prod. Rate Days (H) Tot. Man Crew Tot. Mdays

(unit/day) (H) (I) Desc. (K)

(F) (G) (F/G) (H x I)

1,597.00 4,200.00 0.38 2 1 Operator, 1 Helper 0.76

163.88 76 2.16 3 2 Carpenter, 1 Helper 6.47

576 409.5 1.41

288 345.6 0.83

194 252 0.77

296 180 1.64 26 1 Carpenter, 18 Helper, 6 Mason, 1 Steel Fixer 42.76

1,184.00 12 98.67 3.056 2 Carpenter, 1 Helper, .056 Operator 301.53

53,280.00 250 213.12 2.056 1 Steel Fixer, 1 Helper, .056 Operator 438.17
1,184.00 35 33.83 3.056 2 Carpenter, 1 Helper, .056 Operator 103.38
OD (O) Manpower MAN-DAYS

/day

(N/O) Carpenter Mason Steel Fixer Helper Operator Driver Technician Painter

1 0.76 0.38 0.38

1 6.47 4.31 2.16

1 42.76

4 75.38 19.73 9.87 0.55

3 146.06 21.31 21.31 1.19


2 51.69 6.77 12.92 3.38 0.19

10 26.5 12.92 21.31 34.56 1.93 0 0 0


Tot. Eqmt. (X) Eqmt Tot. Edays (Z) E

Desc. (H x X)

Alum. Tech Waterproofer Dozer Shovel Dump T.

1 1 Dozer 0.38 0.38

0.5 .5 Vibrator 0.82

0.056 .056 M. Crane 5.53

0.056 .056 M. Crane 11.93


0.056 .056 M. Crane 1.89

0 0 0 0 0
EQMT-DAYS

B. Roller B. Cat S. Roller M. Crane Vibrator Excavator Tower Crane

0.08

0.55

1.19
0.19

0 0 0 1.93 0.08 0 0