BALANCE MANHOUR REQUIREMENT FOR PLUMBING

Productivity Rate in MH
Total
Balance Time Needed Balance

19-Oct
Floor Activity Balance Qty as on 04.20.21 Referance Number Installed Unit Time Needed for 1 Total MH Required Balance MH Remarks Clearance Status No: of
Qty = A No: of People
qty Nos/Mtr (mins) Unit MH required Required start date finish date comments Balance People for 1 Nos/Mtr MH
(mins) Required

Rigid Support installation 41 41 0 Nos 2 25 0.83 34.17 0.00 0 2 25 0


floor trap (vip lift) installtion 4 0 4 Rmt 2 45 1.50 6.00 6.00
civil clearence a 3hours after clearence 4 2 45 6

GF plainted drain cover 24 14 10 Rmt 2 10 0.33 8.00 3.33


civil clearence a 2 hours after clearence 10 2 10 3.3333333
sanitary ware (WC ) 18 0 18 Nos 2 40 1.33 24.00 24.00
NO CLEARENCE A 2 days after clearence 18 2 40 24
sanitary ware (WB ) 21 0 21 Nos 2 40 1.33 28.00 0.00
NO CLEARENCE A 2 days after clearence 21 2 0
sanitary ware (WC ) 19 9 10 Nos 2 30 1.00 19.00 10.00 NO CLEARENCE A 1 day after clearence 10 2 30 10
1F
sanitary ware (WB ) 27 27 0 Nos 2 30 1.00 27.00 0.00 2-Oct 5-Oct 0 2 30 0
sanitary ware (WC ) 17 15 2 Nos 2 30 1.00 17.00 2.00 Matertial not available (airolink) A 2 hours after clearence 2 2 30 2
2nd Sanitary ware ( accessories) 89 76 13 Nos 2 20 0.67 59.33 8.67 Matertial not available (airolink) a 1 day after clearence 13 2 20 8.6666667
sanitary ware (WB ) 19 16 3 Nos 2 30 1.00 19.00 3.00 (no clearence) a 2 hours after clearence 3 2 30 3
sanitary ware (WC ) 19 14 5 Nos 2 30 1.00 19.00 5.00 NO CLEARENCE a 2 hours after clearence
3rd Sanitary ware ( accessories) 89 57 32 Nos 2 30 1.00 89.00 32.00 no material a 5 days after clearence
sanitary ware (WB ) 19 0 19 Nos 2 30 1.00 19.00 19.00 (no clearence) a 1 day after clearence 19 2 30 19
sanitary ware (WC ) 17 12 5 Nos 2 30 1.00 17.00 5.00 (no clearence) a 9-Oct 11-Oct 5 2 30 5
4th
sanitary ware (WB ) 19 14 5 Nos 2 30 1.00 19.00 5.00 c 6-Oct 7-Oct 5 2 30 5

Total MH Required for Plumbing 1547.13


115.8

balance MH Required 142.80

clearence area Days required to no clearence Days required to complete the


manpower available man power complete the manpower Balance Activities (no clearence
Balance Activities area)
32 16 2 123 7.6875

6.5
BALANCE MANHOUR REQUIREMENT FOR DRAINAGE PIPING
Productivity Rate in MH

Balance Time
Floor Activity Qty as on Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Total Balance Unit Time Needed for 1 Total MH Required No: of Needed Balance
19.12.20 qty qty qty qty qty qty qty qty qty qty qty Installed No: of People Unit MH required Balance for 1 MH
-Dec20 -Dec21 -Dec22 -Dec23 -Dec24 -Dec26 -Dec27 -Dec28 -Dec29 -Dec30 -Dec31 qty -Jan1 qty -Jan2 qty -Jan3 qty -Jan4 qty -Jan5 qty -Jan6 qty -Jan7 qty -Jan8 qty -Jan9 qty -Jan10 qty Qty = A Nos/Mtr (mins) People Nos/Mtr Required
(mins)

GF 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16 -15 LS 60.00
Gravity Testing of UPVC Pipe -15 0 60 60

Total Available Total MH Required -


0
Total MH Required for Plumbing 0.00
Date No of people in PL No of people in DR No of people in FF Hours Manhour Remarks

20.04.2021 3 3 7 42
21.04.2021 3 3 7 42
22.04.2021 4 2 7 42
24.04.2021 3 3 7 42
25.04.2021 3 5 8 64
26.04.2021 3 3 7 42
27.04.2021 3 3 7 42
28.04.2021 3 3 7 42
Diesel Filling
29.04.2021 3 3 7 42

Fire Fighting 3rd Flr FHC cleaning and


1.05.2021 3 3 7 42 painting.Consultant Comments Addressed

Consultant Comments Addressed for Sprinkler


02.05.2021 3 5 7 56
Dropping Points

03.05.2021 3 5 8 64 Foam System Cylinder Material Shifting .


04.05.2021 3 5 8 64
05.05.2021 3 5 8 64
Diesel Filling,Pump Room Pressure
06.05.2021 3 3 8 48 Testing.1st,2nd and 3rd Floor Consultant
Comment Addressed.

08.05.2021 3 3 8 48 Diesel Filling.Rigid Support Prepared.Consultant


comments Addressed.
09.05.2021 3 5 8 64
10.05.2021 3 5 8 64 Multimedia Filter Chemical Filling.
11.05.2021 3 5 8 64 Sumpump Testing and commissioning
15.05.2021 3 5 8 64
16.05.2021 3 5 8 64
17.05.2021 3 5 8 64 Diesel pump testing and commissioning
18.05.2021 3 5 8 64 Sumpump and gatevalve leak fixing
22.05.2021 4 4 8 64
23.05.2021 4 3 8 56
24.05.2021 4 3 8 56
25.5.2021 3 2 8 40
26.5.2021 3 2 8 40
27.5.2021 3 2 8 40
28.5.2021 3 2 8 40
29.5.2021
30.5.2021 3 2 8 40
31.5.2021 3 2 8 40
1.6.2021 3 2 8 40
2.6.2021 3 2 8 40
3.6.2021 3 2 8 40
4.6.2021
5.6.2021 3 2 8 40
6.6.2021 3 2 8 40
7.6.2021 3 2 8 40
8.6.2021 3 2 8 40
12.6.2021 2 8 16
13.6.2021 2 2 8 32
14.6.2021 2 2 8 32
15.6.2021 2 2 8 32
16.6.2021 2 2 8 32
17.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
19.6.2021 3 8 24 24 HOURS WORK FOR FLUSHING
20.6.2021 3 8 24 24 HOURS WORK FOR FLUSHING
21.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
22.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
23.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
24.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
26.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
27.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
28.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
29.6.2021 2 8 16 24 HOURS WORK FOR FLUSHING
30.6.2021 2 8 16 ff WORK WITH CHW PIPES
1.7.2021 2 8 16 ff WORK WITH CHW PIPES
3.7.2021 2 8 16 ff WORK WITH CHW PIPES
4.7.2021 2 2 8 32
5.7.2021 2 2 8 32
6.7.2021 2 2 8 16 pb WORK BACK FLASHING
7.7.2021 2 2 8 16 pb WORK BACK FLASHING
8.7.2021 2 2 8 16 pb WORK BACK FLASHING
9.7.2021 2 2 8 16 pb WORK BACK FLASHING
10.7.2021 2 2 8 16 pb WORK BACK FLASHING
11.7.2021 2 1 8 24
12.7.2021 2 1 8 16 SANITARY FITTING
13.7.2021 2 1 8 16 SANITARY FITTING
14.7.2021 2 1 8 24
15.7.2021 2 1 8 24
17.7.2021 2 1 8 16 ff WORK WITH CHW PIPES
18.7.2021 2 1 8 16 ff WORK WITH CHW PIPES
24.7.2021 2 1 8 24
25.7.2021 2 1 8 24
26.7.2021 2 2 8 32
27.7.2021 2 2 8 32
28.7.2021 2 2 8 working on AHU with CHW
29.7.2021 2 2 8 working on AHU with CHW
31.7.2021 2 2 8 working on AHU with CHW
01.8.2021 2 2 8 working on AHU with CHW
02.8.2021 2 2 8 working on AHU with CHW
03.8.2021 2 2 8 working on AHU with CHW
04.8.2021 2 2 8 working on AHU with CHW
05.8.2021 2 2 8 working on AHU with CHW
07.8.2021 1 8 working on AHU with CHW
08.8.2021 2 1 8 working on AHU with CHW
8/9/2021 2 1 8 working on AHU with CHW
8/10/2021 2 1 8 working on AHU with CHW
8/11/2021 2 2 8 16 pb working on AHU with CHW
8/14/2021 2 2 8 32
8/15/2021 2 2 8 32
8/16/2021 2 2 8 32
8/17/2021 2 2 8 32 pb marking for counter bar
8/18/2021 2 2 8 32
8/19/2021 2 2 8 16 FF working strainer cleaning
8/21/2021 2 2 8 16 pb marking for counter bar 2ND FLOOR
8/22/2021 1 3 8 32 ff WORK WITH CHW PIPES
8/23/2021 2 3 8 40 ff WORK WITH CHW PIPES
8/24/2021 2 3 8 40
8/25/2021 2 3 8 ff worrk for firestop with electric + sunp pump
32 work
8/26/2021 2 4 8 32 FF ( nafco comments)+ pb marking 3rd floor
8/28/2021 2 4 8 32 FF ( insultion roof floor)
8/29/2021 2 4 8 32 FF ( insultion roof floor)+ Pb FD cutting
8/30/2021 2 4 8 32 FF ( insultion roof floor)+ Pb FD cutting
FF ( insultion roof floor)+ Pb FD cutting+testing
8/31/2021 2 4 8 32 cdp line
9/1/2021 2 4 8 32 FF ( insultion roof floor)+ Pb FD cutting
9/2/2021 2 4 8 32 floor trap cutting at 1st floor + utrap checking
9/4/2021 2 4 8 32 FF roof floor insulation
9/5/2021 2 4 8 32 FF roof floor insulation
9/6/2021 2 4 8 32 FF CHW work balancing work
9/7/2021 2 4 8 32 FF CHW
9/8/2021 2 4 8 32 FF pressure test for fm 200
9/9/2021 2 8 32 FF pressurize basment 3 to basment 1
9/11/2021 2 3 8 32
Utrap rectification at 2nd + FF charging riser and
9/12/2021 2 3 8
32 b2
Utrap rectification at 3rd+floor drain pipe
9/13/2021 2 4 8
32 cutting (23) GF+ rectification at 4th
9/14/2021 2 4 8 Utrap rectification at 4th
32
9/15/2021 2 2 8 FF preusize line
32
9/16/2021 2 2 8 32 FF ( strainer cleaning)+

9/18/2021 2 2 8 Pb charging riser staircase2 +FF strainer cleaning


32
Pb charging riser staircase2 +FF rectification
9/19/2021 2 2 8
32 comments + acces door marking 2nd
Pb charging line in toiler 1f to 4f +FF
9/20/2021 2 2 8
32 rectification comments + acces door marking
3rd
9/21/2021 2 2 8 Pb charging riser staircase3+FF rectification
32 comments 4th
Pb charging riser staircase3 +FF rectification
9/22/2021 2 2 8
32 comments + electric work
9/23/2021 2 2 8
32
9/25/2021 2 2 8 charging b1 sprinkler line
32
9/26/2021 2 2 8 32 allignment dropping at GF

9/27/2021 2 2 8 32 GF Rectfication drain line

9/28/2021 2 2 8
32
9/29/2021 2 2 8 32
9/30/2021 2 2 8 classes change all droping as per RCP
32
10/2/2021 2 2 8 4TH ALIIGNMENT SPRINKLER
32
10/3/2021 2 2 8 MARKING CORRIDOR
32
10/4/2021 1 2 8 AC drain and shifting material + FCU shifting
32
AC drain at hair dresser room + sanitary shifting
10/5/2021 2 2 8 for 4th floor (FF Marking balance at 3rd floor+
32 final fixing elec)
valve package relecote at gym area + prv fixing
10/6/2021 2 2 8 32 (dewa comments ) + FF( pressurized B3 all line )
10/7/2021 2 2 8
32
10/9/2021 2 2 8 32 filter cleaning @ 2nd & 3rd (FF team )

10/10/2021 2 2 8 32 FF Acces pannel Marking

10/11/2021 2 2 8 FF acces panel Marking + dainkin AHU @ 1F


32
marking counter GF+ sanitary sensor +FF Ahu
10/12/2021 2 2 8
32 remove with chw
10/13/2021 2 2 8 valve package relecote at 3rd & 4th +
32 FF( working with chw shifting FCU )
Total 2706
BALANCE MANHOUR REQUIREMENT FOR FIRE FIGHTING PIPING
Productivity Rate in MH

Balance Qty as on Total MH Clearance

10-Oct
Floor Activity Total Unit Time (mins) Needed Balance MH Remarks target
04/19/2021 Balance Qty = A No: of People Unit MH required Required Status start date comments
Installed qty for 1 Nos/Mtr Required date

Fire extingusher CO2 7.00 5.00 2.00 Nos. 2 10 0.33 2.33 0.67 civil work ballence a 1 hour after clearence
B1
Fire extingusher DCP 7.00 5.00 2.00 Nos. 2 10 0.33 2.33 0.67 dewa lock room a 1 hour after clearence
final fix sprinkler cap 149.00 - 149.00 Nos. 2 7 0.23 34.77 34.77 NO CLEARENCE A 2 days after clearence
Sprinkler Installation 149.00 149.00 - Nos. 2 10 0.33 49.67 -

GF Fire extingusher DCP 11.00 5.00 6.00 Nos. 2 10 0.33 3.67 2.00 wall not complete a 1 hour after clearence
Fire extingusher DRY 2.00 - 2.00 Nos. 2 10 0.33 0.67 0.67 wall not complete a 1 hour after clearence
Fire extingusher CO2 10.00 5.00 5.00 Nos. 2 10 0.33 3.33 1.67 wall not complete a 1 hour after clearence
final fix sprinkler cap 229.00 105.00 124.00 Nos. 2 5 0.17 38.17 20.67 FINAL PAINT NOT DONE a 2 days after clearence
Fire extingusher DCP 13.00 8.00 5.00 Nos. 2 10 0.33 4.33 1.67 wall not complete a 1 hour after clearence
1F
Fire extingusher CO2 13.00 8.00 5.00 Nos. 2 10 0.33 4.33 1.67 wall not complete a 1 hour after clearence
Fire extingusher DRY 2.00 - 2.00 Nos. 2 10 0.33 0.67 0.67 wall not complete a 1 hour after clearence
final fix sprinkler cap 259.00 207.00 52.00 Nos. 2 5 0.17 43.17 8.67 FINAL PAINT NOT DONE a 4 hoursn after clearence
2f Fire extingusher DRY 4.00 - 4.00 Nos. 2 10 0.33 1.33 1.33 wall not complete a 1 hour after clearence
final fix sprinkler cap 259.00 197.00 62.00 Nos. 2 5 0.17 43.17 10.33 FINAL PAINT NOT DONE a 1 day after clearence
3F
Fire extingusher DRY 4.00 - 4.00 Nos. 2 10 0.33 1.33 1.33 wall not complete a 1 hour after clearence
final fix sprinkler cap 239.00 40.00 130.00 109.00 Nos. 2 5 0.17 39.83 18.17 FINAL PAINT NOT DONE a 2 days after clearence
4F
Fire extingusher DRY 3.00 - 3.00 Nos. 2 10 0.33 1.00 1.00 wall not complete a 1 hour after clearence

Total MH Required 1,304.43

Balance MH required 132.26

clearence area manhour available man power Days required to complete the Balance no clearence Days required to complete the Balance Activities (no
required Activities manhour required clearence area)

16 0 112 7
MANPOWER MANAGEMENT -( D
Total Manhour Total Manhour
Required to complete Required to
Activity Total Manhour
the Works as on 20- complete the Works
Consumed till
04-21 as on
Sat, May 15, 2021 Sat, May 15, 2021
WATER SUPPLY 1547.13 115.80
DRAINAGE - 2,706.00
FIRE FIGHTING 1304.43 110.93
Total 2851.57 226.73 2,706.00
MANPOWER MANAGEMENT -( DHPP0016) MOHRE - WS+DR+FF
Available Daily Manpower
Manhour worth work (AEM + Supply + Sub Contr.) Working
Productivity as on Total MH
done as on (without hours
Supervisor/Foreman)
Sat, May 15, 2021 Sat, May 15, 2021
7.00 8.00 56.00
2,624.83 97%

2,624.83 97% 7.00 8.00


Days required to
complete the
Remarks
Balance
Activities

4.05

4.05

50
FF balance work for clearence area

Area clearence Activity Target date

Ground floor Sprinkler Dropping 8/11/2021

Sprinkler Installation
( Side Wall+Upright)
Basment 1 8/14/2021

piping instalation

rework for droping


2nd and 3rd location as per ID and 8/15/2021
light fitting
Ground floor Sprinkler Installation 8/18/2021

Plumbing balance work for clearence area


Area clearence Activity Target date
Pu foam for all MEP
1st and 4th floor 8/16/2021
services
sanitary ware
3rd floor ( wet area) installtion ( wc + 8/21/2021
angle valve+ wash
basin)

2nd floor (wet area) wash basin installatiom 8/22/2021


Plumbing balance work for clearence area
Area clearence Activity Target date

1st and 4th floor Pu foam for all MEP services 8/16/2021

sanitary ware installtion


3rd floor ( wet area) ( wc + angle valve+ wash 8/21/2021
basin)

2nd floor (wet area) wash basin installatiom 8/22/2021