Professional Documents
Culture Documents
Manpower For Plumbing and Fire Fighting
Manpower For Plumbing and Fire Fighting
Productivity Rate in MH
Total
Balance Time Needed Balance
19-Oct
Floor Activity Balance Qty as on 04.20.21 Referance Number Installed Unit Time Needed for 1 Total MH Required Balance MH Remarks Clearance Status No: of
Qty = A No: of People
qty Nos/Mtr (mins) Unit MH required Required start date finish date comments Balance People for 1 Nos/Mtr MH
(mins) Required
6.5
BALANCE MANHOUR REQUIREMENT FOR DRAINAGE PIPING
Productivity Rate in MH
Balance Time
Floor Activity Qty as on Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Installed Total Balance Unit Time Needed for 1 Total MH Required No: of Needed Balance
19.12.20 qty qty qty qty qty qty qty qty qty qty qty Installed No: of People Unit MH required Balance for 1 MH
-Dec20 -Dec21 -Dec22 -Dec23 -Dec24 -Dec26 -Dec27 -Dec28 -Dec29 -Dec30 -Dec31 qty -Jan1 qty -Jan2 qty -Jan3 qty -Jan4 qty -Jan5 qty -Jan6 qty -Jan7 qty -Jan8 qty -Jan9 qty -Jan10 qty Qty = A Nos/Mtr (mins) People Nos/Mtr Required
(mins)
GF 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 16 -15 LS 60.00
Gravity Testing of UPVC Pipe -15 0 60 60
20.04.2021 3 3 7 42
21.04.2021 3 3 7 42
22.04.2021 4 2 7 42
24.04.2021 3 3 7 42
25.04.2021 3 5 8 64
26.04.2021 3 3 7 42
27.04.2021 3 3 7 42
28.04.2021 3 3 7 42
Diesel Filling
29.04.2021 3 3 7 42
9/28/2021 2 2 8
32
9/29/2021 2 2 8 32
9/30/2021 2 2 8 classes change all droping as per RCP
32
10/2/2021 2 2 8 4TH ALIIGNMENT SPRINKLER
32
10/3/2021 2 2 8 MARKING CORRIDOR
32
10/4/2021 1 2 8 AC drain and shifting material + FCU shifting
32
AC drain at hair dresser room + sanitary shifting
10/5/2021 2 2 8 for 4th floor (FF Marking balance at 3rd floor+
32 final fixing elec)
valve package relecote at gym area + prv fixing
10/6/2021 2 2 8 32 (dewa comments ) + FF( pressurized B3 all line )
10/7/2021 2 2 8
32
10/9/2021 2 2 8 32 filter cleaning @ 2nd & 3rd (FF team )
10-Oct
Floor Activity Total Unit Time (mins) Needed Balance MH Remarks target
04/19/2021 Balance Qty = A No: of People Unit MH required Required Status start date comments
Installed qty for 1 Nos/Mtr Required date
Fire extingusher CO2 7.00 5.00 2.00 Nos. 2 10 0.33 2.33 0.67 civil work ballence a 1 hour after clearence
B1
Fire extingusher DCP 7.00 5.00 2.00 Nos. 2 10 0.33 2.33 0.67 dewa lock room a 1 hour after clearence
final fix sprinkler cap 149.00 - 149.00 Nos. 2 7 0.23 34.77 34.77 NO CLEARENCE A 2 days after clearence
Sprinkler Installation 149.00 149.00 - Nos. 2 10 0.33 49.67 -
GF Fire extingusher DCP 11.00 5.00 6.00 Nos. 2 10 0.33 3.67 2.00 wall not complete a 1 hour after clearence
Fire extingusher DRY 2.00 - 2.00 Nos. 2 10 0.33 0.67 0.67 wall not complete a 1 hour after clearence
Fire extingusher CO2 10.00 5.00 5.00 Nos. 2 10 0.33 3.33 1.67 wall not complete a 1 hour after clearence
final fix sprinkler cap 229.00 105.00 124.00 Nos. 2 5 0.17 38.17 20.67 FINAL PAINT NOT DONE a 2 days after clearence
Fire extingusher DCP 13.00 8.00 5.00 Nos. 2 10 0.33 4.33 1.67 wall not complete a 1 hour after clearence
1F
Fire extingusher CO2 13.00 8.00 5.00 Nos. 2 10 0.33 4.33 1.67 wall not complete a 1 hour after clearence
Fire extingusher DRY 2.00 - 2.00 Nos. 2 10 0.33 0.67 0.67 wall not complete a 1 hour after clearence
final fix sprinkler cap 259.00 207.00 52.00 Nos. 2 5 0.17 43.17 8.67 FINAL PAINT NOT DONE a 4 hoursn after clearence
2f Fire extingusher DRY 4.00 - 4.00 Nos. 2 10 0.33 1.33 1.33 wall not complete a 1 hour after clearence
final fix sprinkler cap 259.00 197.00 62.00 Nos. 2 5 0.17 43.17 10.33 FINAL PAINT NOT DONE a 1 day after clearence
3F
Fire extingusher DRY 4.00 - 4.00 Nos. 2 10 0.33 1.33 1.33 wall not complete a 1 hour after clearence
final fix sprinkler cap 239.00 40.00 130.00 109.00 Nos. 2 5 0.17 39.83 18.17 FINAL PAINT NOT DONE a 2 days after clearence
4F
Fire extingusher DRY 3.00 - 3.00 Nos. 2 10 0.33 1.00 1.00 wall not complete a 1 hour after clearence
clearence area manhour available man power Days required to complete the Balance no clearence Days required to complete the Balance Activities (no
required Activities manhour required clearence area)
16 0 112 7
MANPOWER MANAGEMENT -( D
Total Manhour Total Manhour
Required to complete Required to
Activity Total Manhour
the Works as on 20- complete the Works
Consumed till
04-21 as on
Sat, May 15, 2021 Sat, May 15, 2021
WATER SUPPLY 1547.13 115.80
DRAINAGE - 2,706.00
FIRE FIGHTING 1304.43 110.93
Total 2851.57 226.73 2,706.00
MANPOWER MANAGEMENT -( DHPP0016) MOHRE - WS+DR+FF
Available Daily Manpower
Manhour worth work (AEM + Supply + Sub Contr.) Working
Productivity as on Total MH
done as on (without hours
Supervisor/Foreman)
Sat, May 15, 2021 Sat, May 15, 2021
7.00 8.00 56.00
2,624.83 97%
4.05
4.05
50
FF balance work for clearence area
Sprinkler Installation
( Side Wall+Upright)
Basment 1 8/14/2021
piping instalation
1st and 4th floor Pu foam for all MEP services 8/16/2021