Professional Documents
Culture Documents
T R Fx70inst20
T R Fx70inst20
(optional — concrete
or steel piles only)
(optional — concrete
epoxy coating
or steel piles only)
FX-70-9™
coating
Pile/Column
FX-70-9™
Pile/Column
Beveled top seal of
epoxy
FX-763 trowel-grade
Beveled top seal of Spacer epoxy mixed with
Spacer FX-763 trowel-grade FX-702 silica filler
epoxy mixed with
Length
multi-purpose
marine epoxy grout
Jacket
diameter/size
Jacket
diameter/size FX-70 FX-225 non-shrink
fiberglass jacket cementitious
underwater grout
Spacer
Spacer 6" (152 mm) layer of
6" (152 mm) layer of FX-70-6MP
FX-70-6MP multi-purpose marine
multi-purpose marine epoxy grout or FX-70-6FS
epoxy grout or FX-70-6FS fast-set epoxy bottom seal
½" (13 mm) fast-set epoxy bottom seal
Pile 2" (51 mm)
annular void Pile
diameter/size annular void
diameter/size FX backer rod
FX backer rod
Table of Contents
Scope .............................................................................. 2 Filler Grout Application .................................................. 7–8
Surface Preparation ......................................................... 2 FX-70-6MP Epoxy Grout Method.................................. 7
Jacket Preparation ........................................................... 3 FX-225 Cementitious Grout Combination Method......... 8
Typical Spacer Placement ................................................ 3 Top Seal Application (FX-225 cementitious grout
Jacket Preparation (two or more jackets per pile) ............. 4 combination method only) ............................................ 9
Jacket Installation (one jacket per pile) .......................... 4–5 Epoxy Bevel Construction ................................................ 9
Jacket Installation (two or more jackets per pile) .............. 6 Completion of Work ....................................................... 10
Bottom Seal Application................................................... 6 Suggested Tool List ....................................................... 10
I. Scope
1. This guide covers the installation procedures for using the FX-70 system to repair and protect timber,
concrete, and steel piles with two different application methods:
• FX-70-6MP™ epoxy grout method: consisting of a fiberglass jacket that is placed around the
existing pile with a ½" min. annular space between the pile and the jacket. The annular space is then
filled with a marine epoxy grout and a bevel of epoxy mortar is placed at the top of the jacket.
• FX-225 cementitious grout combination method: consisting of a fiberglass jacket that is placed
around the existing pile with a 2" min. annular space between the pile and the jacket. The annular
space is initially filled with 6" of FX-70-6MP marine epoxy grout (or 6” of FX-70-6FS fast-set epoxy
bottom seal) at the bottom of the jacket, and then filled with FX-225 marine cementitious grout to
within 4" from the top of the jacket. Finally, the remaining space is filled with FX-70-6MP marine
epoxy grout (or FX-70-6FS fast-set epoxy bottom seal), and a bevel of FX-763 trowel-grade epoxy
mixed with FX-702 silica filler is placed at the top of the jacket.
2. All submerged jackets should be installed by certified professional divers.
Page 2 of 10
TECHNICAL BULLETIN
Annular
Annular void Pile/column size
void
Pile/column diameter Pile/column size
Spacer Spacer
Spacer Spacer
Page 3 of 10
TECHNICAL BULLETIN
Tongue-and-groove joint
2. “Close” the jacket by inserting the tongue into the groove of the jacket. Temporarily suspend/hold the
jacket in position so there is 18"–24" (457-610 mm) of undamaged pile inside the jacket above and below
the damaged area. Note: Use of ratchet straps may be required to pull jacket together.
Page 4 of 10
TECHNICAL BULLETIN
FX backer rod
FX backer rod
4. Install external bracing as needed to secure jacket and prevent excessive deflection and rupture. Ratchet
straps shown for bracing round piles. Other shapes will require conventional concrete bracing methods.
Ratchet straps
Ratchet straps
© 2020 Simpson Strong-Tie Company Inc. T-R-FX70INST20
5. Install a self-drilling, self-tapping FXSSST121 316 stainless-steel screw every 6" (152 mm) on center to
secure the tongue-and-groove joint. Start the screw spacing approximately 1" from the top and bottom of
the jacket.
Page 5 of 10
TECHNICAL BULLETIN
Tongue-and-groove
Tongue-and-groove
joints notshown
joints not shown
for clarity
for clarity
3"(76.2
3" (76.2mm)
mm)
Bell
Bellof
of lower jacket
lower jacket
Page 6 of 10
TECHNICAL BULLETIN
Pile columns
(optional - concrete
or steel piles only)
epoxy coating
FX-70-9TM
High-water level
18–24"
Filler grout
© 2020 Simpson Strong-Tie Company Inc. T-R-FX70INST20
Damaged region
FX-70-6MP
Length
FX-70-6MP multi-purpose
Jacket marine epoxy grout
diameter
(456-610
(456–610 mm)
mm)
FX-70-6MP or Spacer
18-24"
FX-70-6FS
18–24"
Page 7 of 10
TECHNICAL BULLETIN
6.
3. Allow filler grout to cure overnight before proceeding with repair.
Pile columns
(optional - concrete
or steel piles only)
epoxy coating
FX-70-9TM
FX-70-6MP multi-purpose
FX-70-6FS marine epoxy grout or FX-70-6FS
18-24" (456–610
High-water level
fiberglass jacket
Length
FX-225
cementitious Jacket
diameter
filler grout
mm)
(456–610 mm)
FX-225 non-shrink
18-24" (456-610
underwater grout
Spacer
18–24"
Page 8 of 10
TECHNICAL BULLETIN
IX. Top Seal Application (FX-225 cementitious grout combination method only)
1. Mix FX-70-6MP™ or FX-70-6FS per current Simpson Strong-Tie® Technical Data Sheet found at strongtie.com.
2. Pour FX-70-6MP or FX-70-6FS into the remaining 4" (100 mm) at the top of the jacket.
3. Allow the seal to cure before proceeding with the epoxy bevel.
FX-225
4" (102 mm) layer of
FX-70-6MP multi-purpose
marine epoxy grout or
FX-70-6FS fast-set epoxy
bottom seal
FX-70-6MP
or FX-70-6FS
2. Using a steel trowel, immediately construct the bevel using the mixed FX-763 trowel-grade
epoxy mortar, taking care to construct a slope which will shed water.
Epoxy bevel
Epoxy bevel Epoxy bevel
Page 9 of 10
TECHNICAL BULLETIN
Page 10 of 10