Bidder'S Work Plan: Al-Janadriyah Exhibition Facility, Ar-Riyadh
Bidder'S Work Plan: Al-Janadriyah Exhibition Facility, Ar-Riyadh
:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 1of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
This document or /and his attachments are subjected to revisions / modifications. Before using this document, please
verify to have the updated document.
Whoever comes in possession of this edition, is obliged to cancel or destroy any previous copies in his hands or
duplicates submitted of with he must have evidence tracking
SAUDI ARAMCO Southern Area Projects Department Doc. No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 2of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
Revision Summary
TABLE OF CONTENTS
1 INTRODUCTION 4
2 PROJECT OVERVIEW 5
4 MOBILIZATION 6
7 SECURITY FACILITIES 15
9 WORK SCHEDULE 16
SAUDI ARAMCO Southern Area Projects Department Doc. No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 4of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
1 INTRODUCTION
1.1. Purpose
The purpose of this Work Plan is to present the general sequence of pre-construction and
construction activities which shall be carried out by the BIDDER/CONTRACTOR for the Al
Janadriyah Exhibition Facility, Ar Riyadh, KSA.
1.2. Objectives
1.3. Definitions
2 PROJECT OVERVIEW
Saudi Aramco solicits the assistance of selected competent Contractors to Bid on a Lump-Sum
Procure Built (LSPB) Contract for the procurement & construction of AL JANADRIYAH
EXHIBITION FACILITY, AR RIYADH. This shall be an exhibition facility for the use by Ministry
and its main companies including Saudi Aramco in presenting related functions as well as wide
range of services to the public during the yearly Al Janadriyah Festival. With the minimum
capacity of 1000 guests per hour, the proposed facility will be in two levels with multi-function
spaces to be constructed inside the Al Janadriyah Zone in Riyadh.
3.7 CONTRACTOR shall obtain necessary construction permits such as, Personnel &
Vehicle Gate Pass, Work Permits, etc. within the local authorities and National Guard
with the assistance of the CLIENT.
3.8 Approvals of CONTRACTOR documents, i.e. HSE Plan, Project Execution Plan, Quality
Plan, etc.
4 MOBILIZATION
Upon the award of the Contract and Notice to Proceed, mobilization shall commence in
accordance with the CONTRACTOR Project Schedule. See Attachment 01. Work Schedule.
A thorough and logical mobilization plan is essential to ensure the successful start up of
construction. This plan covers all preparation and pre-construction activities necessary to
ensure the timely arrival on Site of CONTRACTOR personnel, construction equipment, temporary
facilities and materials as required facilitating a timely start and continuous support of
construction efforts.
The mobilization plan will be closely coordinated with the overall Construction Execution Plan in
order to ensure that the mobilization activities properly lead into and provide a smooth transition
into initial construction activities.
The mobilization will be executed in two phases as described here below:
4.1 Mobilization – Initial Phase
Initial Mobilization Phase will be initiated from the CONTRACTOR Home Office in Eastern
Province to the Project Site in Riyadh. The following main activities will be executed in this
Phase:
a. The CONTRACTOR project management shall conduct a project kick-off meeting with the
project mobilization team and will initiate the start of the project with clear and defined
responsibilities. This team will be headed by the Site Manager and Construction
Manager.
b. During the kick-off meeting, mobilization plans established during the bidding stage and
all project information will be handed over to the mobilization team in accordance with
the “Mobilization Check List”, and action for each item will be assigned to the various
members of the mobilization team.
c. Various support departments at the Home Office will assist in the execution of the project
requirements under the direction of the members of the mobilization team involved in
executing the following:
(1) Prepare/update a master list of contractual requirements/submittals and distribute to
the various departments responsible for providing the necessary information such as
Legal, Insurance, Financial, QA/QC, Technical etc.
(2) Update and detail the master schedule.
(3) Start the program monitoring system.
(4) Initiate the purchase of the initial consumables and temporary facilities.
d. The mobilization plans for staff, labor; the temporary facilities established during the bid
stage will be examined in detail and re-evaluated in light of any changes that may have
occurred since the date of their initial preparation. All necessary corrective measures will
be implemented.
SAUDI ARAMCO Southern Area Projects Department Doc. No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 7of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
e. Additional Site visits will be conducted promptly to confirm data collected during the
bidding stage and to establish any additional information required to permit mobilization.
The following items especially will be reviewed and confirmed:
1) Access at the job Site.
2) Requirements for block visas, permits and licenses.
3) Locations for temporary facilities.
4) CLIENT requirements for properly validated licenses and certificates to be held by
construction personnel.
5) Transportation plans.
6) Loss prevention and safety requirements.
7) Plans for medical facilities.
8) Arrangements for drinking and construction water.
9) Arrangements for supply of electricity.
10) Arrangements for storage of fuel & lubricants.
11) Arrangements of site sanitary facilities.
9) Plant
10) Site Facilities
11) Method Statements
12) Subcontractors
13) Submittals and Approvals
14) Budgets
15) Reporting
16) QA/QC Plan
17) Safety Plan
4.2.2 ACCOMMODATION
The CONTRACTOR will provide accommodation for all its personnel employed on
the Project. The construction camp/housing complex will be located in the area
around or at reasonable distance from the Site as allocated by CLIENT. The
transportation means to the work-site will be provided for all personnel to and from
the camp/housing complex, as necessary.
However, to cater the plan for immediate mobilization required for this project,
CONTRACTOR is planning to rent an existing camp or building for labor
accommodation near or within the proximity of the Job Site during initial stage until
the completion of his permanent camp.
Construction and set-up of CONTRACTOR’s Temporary Camp Facilities (TCF) &
Laydown Yard which shall be the primary support/staging area for the project.
The TCF with an approx. Area = 60,098 m2 and can accommodate up to 790 persons
at peak, shall consist of the following:
Accomodation (33,834 m2)
a. Senior Cabin: 10 units @ 2 rooms; 1/room = 20 persons
b. Junior Cabin: 20 units @ 2 rooms; 2/room = 80 persons
c. Skilled & Labor: 35 units @ 3 rooms; 4/room = 420 persons
Camp Office, Messhall & Utilities (9,731 m2)
Recreation (4,420 m2)
Laydown Yard (2,500 m2)
The Laydown Yard shall be established inside the TCF and constitutes the following:
1) Non Air Conditioned Warehouse/Containers
2) Air-conditioned Warehouse/Containers
3) Lay down Yard
4) General Workshop (Mechanical works, Rebar, Carpentry, etc.).
SAUDI ARAMCO Southern Area Projects Department Doc. No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 9of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
CONTRACTOR shall submit detail design drawings for construction of camp to the
CLIENT and ensure the adequate standard of living, dining, medical, fire fighting,
recreation facilities, cleaning & laundry services for its staff, work force, specialist,
vendors and subcontractor. CONTRACTOR will comply with CLIENT’s sanitary code
and requirement of Schedule B.
CONTRACTOR will fence the camp area & provide security access gate to ensure
the safety & security of the camp accommodation.
driving along with speed limits, and monitoring road conditions for any maintenance
or repair work.
4.2.6 WATER
CONTRACTOR shall be responsible for the provision, transportation, storage and
distribution of potable water for its own use and for the TCF and for the permanent
WORK.
CONTRACTOR shall make necessary arrangements for the supply of the potable
water. As noted during the site visit, CONTRACTOR shall make tie-in to an existing
water supply inside the project site.
The CONTRACTOR will evaluate their water requirements for the Project and will
develop a specific Construction Water Plan that explains in detail arrangements for:
(a) Adequate water storage facilities
(b) Methods of water collection transport storage and distribution
(c) Drinking water
(d) Personnel waste flushing
(e) Testing of and flushing piping, vessels and tanks
(f) Aggregate materials washing
(g) Compaction
(h) Dust control
CONTRACTOR will be responsible for the water line distribution system and supply of
piping within the TCF area.
The raw and portable water required for construction and drinking for the
Construction Sit e will be supplied by CONTRACTOR. The quality of water will be
monitored regularly on Site to assure it is safe always.
4.2.7 FUEL/MAINTENANCE
Fuel servicing of construction plant and equipment will be carried out using a truck
mounted fuel/servicing unit, which will be replenished from our on-site maintenance
facilities.
It is intended repair that all routine maintenance and minor works to our construction
plant and equipment will be carried out using our on-site facilities and a truck
mounted fuel / servicing unit. These facilities will be established at an early stage
during the mobilization to site and will remain on site until the end of the project.
4.2.8 POWER
The power for all facilities will be provided by CONTRACTOR through the connection
to an existing substation inside the project site. Also, if necessary, Generator sets shall
be provided to carry out particular activties like welding works. CONTRACTOR shall be
responsible f or installation of electrical network & lighting system to all the temporary
SAUDI ARAMCO Southern Area Projects Department Doc. No.:
AL JANADRIYAH EXHIBITION FACILITY, AJEF-DOC-003/BWP
AR-RIYADH Rev.No.01 Page: 11of16
EASTERN TRADING & CONT. EST. Date: 18/05/2015
BIDDER’S WORK PLAN
Req. No. 3000613310
construction facility area. Contractor will ensure the regular inspection, routine
maintenance and repair or replacement of the electrical distribution systems at the
TCF area.
The information that follows illustrates the Contractors intimate understanding of CLIENT
requirements.
7 SECURITY FACILITIES
All the Temporary Facilities will be fenced and regular and random security patrols will be
carried out, particularly at night. CONTRACTORS will bear the responsibility for the security
of its resources and temporary construction facility areas that shall include to the following:
Personnel security
Materials of construction, from port lay down to erection including transport of oversize
equipment
Personnel Transport
Temporary Facilities
Work Site
Any Equipment / Material provided by CLIENT
Contractor will coordinate with the CLIENT to discuss ongoing security activities/issues.
After award the contract, CONTRACTOR will apply & obtain CLIENT Identification Cards to
start the construction of the temporary facilities.
In addition, on the grounds of safety and security, CONTRACTOR will install type V
fencing to all the temporary construction facilities areas that’s include camp Accommodation
Area, Fabrication shop, Ware house & lay down yard and offices.
CONTRACTOR will also provide lighting coverage to all CONTRACTORS’s a n d CLIENT
temporary Site facilities and camp areas.
9 WORK SCHEDULE
WORK SCHEDULE shall be carried out in one shift per day, six days a week, in conformance to
Bid Addendum 01 & modified Milestone Schedule, issued by the CLIENT as follows:
Day Shift:
6:00 AM to 12:00 NN
Break: 12:00 NN to 1:00 PM
1:00 PM to 5:00 PM
Work shall be at 10 hours/day and from Saturday – Thursday. Above schedule shall be adjusted
as neccessary in accordance with the site condition and approved by the CLIENT.
CONTRACTOR assures the CLIENT that the project will be competently and comprehensively
planned and scheduled, and that continuous progress control will be achieved at all times. To
this end CONTRACTOR shall develop and supply formal planning, scheduling, progress control,
and reporting procedures appropriate to a project of this size and complexity, and in as much
detail as is necessary in order to remove any doubts concerning validity and accuracy.
The Construction Schedule will be in the form of a time-scaled CPM depicting the major
activities and milestones required to successfully complete the project, and the Project
Milestone Schedule will be in the form of a bar chart summarizing the major Project activities
and project milestones.
The Project Control and Construction Tracking systems consists of a suite of In-house
developed interactive programs which automatically pass information to each other after
updating is carried out on any component.
The l o g i c network shall b e d e v e l o p e d in p r e c e d e n c e format utilizing Primavera
Computer Scheduling software (P6 or latest version), critical activities shall be identified, together
with optimum resource requirements. Initially certain construction activities shall be included as
hammocks. Such activities shall be further expanded by sub networks as the work progresses
and more information becomes available. All subsequent schedules and bar charts shall be
derived from this logic diagram network.
CONTRACTOR will undertake a l l construction-related activities on a dedicated project team
basis. The CONTRACTOR’s Project Manager and other key personnel will be located at site in
order to achieve the project goals.
CONTRACTOR recognizes the importance of using the project expertise that CONTRACTOR
management has gained o n his previous & present projects with Saudi Aramco.
Immediately upon award of the project, the CONTRACTOR w i l l mobilize the key personnel
and arrange with CLIENT kick off meetings to carry out site surveys.
The p r o j e c t team w i l l b e s t a f f e d with p e r s o n n e l w i t h v a l u a b l e experienced in
m a n a g e m e n t , HSE, field engineering, procurement, quality control and construction of
infrastructure facilities in the Middle East and Saudi Arabia. Organization support will be
provided to the project by the CONTRACTOR’s functional managers and their staff.
10 ATTACHMENTS
10.1 Attachment 01 Work Schedule
10.2 Attachment 02 CONTRACTOR Proposed TCF Lay-out Plan