HAIL2CC-00-BF-EDC-AT-0104 (Rev 01) Warranty Inspection Procedure For Transformer
HAIL2CC-00-BF-EDC-AT-0104 (Rev 01) Warranty Inspection Procedure For Transformer
HAIL2CC-00-BF-EDC-AT-0104 (Rev 01) Warranty Inspection Procedure For Transformer
CONT.
HAIL2CC-00-BF-EDC-AT-0104 01
TRANSMITTAL No.:
Document No. Date
CONVERSION OF HAIL- SIMPLE CYCLE
TO COMBINED CYCLE POWER PLANT HAIL2CC-00-BF-EDC-AT- 25/10/2021
0104
WARRANTY INSPECTION PROCEDURE FOR GSU TRANSFORMER Page: 01
AND MV/LV TRANSFORMER
Rev.: 01
1. OBJECT
1.1. DESCRIPTION OF WORK
The purpose of this document is to provide guideline for the checks to be performed
for warranty inspection for GSU Transformer and MV/LV Transformer in accordance
with SEC specification reference Schedule C, Attachment BF-X-A.
1.2. ABBREVIATIONS
1.3. STANDARDS
For applicable codes and standards see document:
2. METHOD STATEMENT:
The following steps to be Carried Out During Warranty Inspection for GSU Transformer
and MV/LV Transformers:
1) Visual Inspection of GSUT for any physical damage or defect.
2) Visual inspection of HV bushing and expansion tank.
3) Visual inspection of LV bushing and NSBD connection.
4) Visual inspection for link box.
5) Visual inspection of all gauges for oil level and temperature.
6) Visual inspection of Marshaling panel.
7) Visual inspection of AVR cabinet and manual operation.
8) Tap changer operation from DCS or AVR panel.
9) Check the color of Silica gel in the breather
10) Check and inspection of the cooling fans for both group.
11) Visual Inspection of Cooling system radiators
3. RISK ASSESMENT:
Document No. Date
CONVERSION OF HAIL- SIMPLE CYCLE
TO COMBINED CYCLE POWER PLANT HAIL2CC-00-BF-EDC-AT- 25/10/2021
0104
Page: 03
WARRANTY INSPECTION PROCEDURE FOR GSU TRANSFORMER
AND MV/LV TRANSFORMER Rev.: 01
4. CHECK LIST