Professional Documents
Culture Documents
Risk Calculation Formula of The Bay in Switchyard To Determine The Main Priority of Maintenance at PLN Uit JBTB
Risk Calculation Formula of The Bay in Switchyard To Determine The Main Priority of Maintenance at PLN Uit JBTB
Risk Calculation Formula of The Bay in Switchyard To Determine The Main Priority of Maintenance at PLN Uit JBTB
Abstract—Currently PLN Unit Induk Transmisi Jawa TABLE I. TOTAL EXSISTING BAY IN PLN UIT JBTB
Bagian Timur dan Bali (PLN UIT JBTB) planned the
TOTAL
maintenance of an HV equipment installed in Substation both TYPE BAY
150 kV 70 kV 30 kV 20 kV ALL VOLTAGE
preventive and corrective maintenance carefully, because it’s so
BUS SECTION 17 10 0 0 27
so difficult to offline the bay maintained and limited budgeted BUSBAR 162 69 4 0 243
of maintenance costs. Therefore, a risk calculation formula in CAPASITOR/SVC/MSC 29 7 0 1 37
one bay in Substation is made to determine the priority of COUPLE 70 19 0 0 89
maintenance. DIAMETER 35 0 0 0 88
MOBILE TRANSFORMER/SUBSTATION 8 0 0 3 11
Keywords—HV Equipment, risk, the priority of maintenance. POWER PLANT & CONSUMERS 63 21 6 1 94
REACTOR 0 1 0 0 5
I. INTRODUCTION BAY LINE 387 156 10 0 571
BAY TRANSFORMER 226 57 0 0 294
PLN UIT JTBT has total 2125 existing conventional bays BAY TRANSFORMER (LOW VOLTAGE) 34 33 1 232 300
without GIS (see Table.I). PLN has several maintenance TOTAL 1031 373 21 237 1759
strategies including preventive and correction maintenance. In
2013, PLN established refreshment regulation of high In this paper, the authors makes a calculation by
voltage (HV) equipment [1]. The refreshment criteria are calculaiing likelihood including assesment condition, age and
based on technical, age, and risk consideration. However, failure occurrence on all HV equipment in one bay and impact
Equipement replacement justification is only based on age citeria on the bay.
and technical condition in practically. Also PLN has no
regulation to determine the maintenance priorities of the bay II. ASSESSMENT PARAMETERS
in Switchyard. Good planning in determining maintenance Assessment parameters of HV Equipment used for
priorities reduces the chance of equipment failure and the consideration the maintenance priority of the bay, consist of
impact of the risk, so that in the future PLN UIT JBTB will Inpection Level-1, .Inpection level-2, and inpection level-3.
not be doing the routine maintenance or the corrective Inpection Level-1 is In service Inspection that detected
maintenance to other HV equipment at the same bay in the abnormalities or anomaly in HV equipment then initiated
same year. further inspections, this Inspection using the senses (vision,
hearing, smell, etc). For example, gas leakage by looking at
gas pressure, cracks on the insulator, etc. Inpection Level-2 is
online inspection with a measuring instrument that aims to
determine the condition of the HV equipment (condition
assessment) such as leakage current monitor. Inpection Level-
3 is shutdown measurement that aims to understand the
Secondary Junction
min min
wf = 0.03 wf = 0.17
Dielectric Grading
min
wf = 0.24 Ring min
wf = 0.04
Driving
Mechanism min
Grounding
wf = 0.21 min
wf = 0.1
Grounding
min
wf = 0.05
Calculate the range to determine lower limit and upper
limit.
Tan delta measurement is the main measurement of CT,
error in measuring is one of caused why some the CT Lower limit
exploded. It is the biggest weighting factor (see Table IV). = (1 x Sub system of the biggest WF)+∑(9 x the other Sub system)
TABLE IV. WEIGHTING FACTOR OF CT SUB-SYSTEM
Upper limit
Sub Thermo Grounding Insulation Tan For = (6 x Sub system of the biggest WF)+∑(9 x the other Sub system)
Anomaly Ratio
system vision System Condition delta mula
Current
The category of index condition
Carriying min • “9” for scoring of HV equipment > upper limit
wf = 0.26 • “6” for lower limit < scoring < upper limit
Dielectric
min
• “1” for scoring of HV equipment < lower limit
wf = 0.63
One case of CB condition assesment as Table VII, was V Fail
Fai
lur
found anomaly crack on insulator and cable in the secondary ol Ma ure V Man
e
V Man
Failure
t nu Occ olt u olt u
box have chipped. Total scoring of CB condition is 7.04 (see (k fact ur (k factu
Oc
(k factu
Occur
cur rence
Table VII). Lower limit = (1 x 0.4)+ (9 x 0.6) = 5.8, Upper limit V urer renc V) rer
ren
V) rer
) e
= (6 x 0.4) + (9 x 0.6) = 7.8. So the category of index condition ce
1
is “6”. 1 5 A 1 150 A 2 150 A 1
0
TABLE VII. ONE CASE OF CB CONDITION ASSESSMENT 7
2 B 1 150 B1 2 150 B1 1
0
Sub Ano Thermov Grounding Insulation Timing Contact 1
system SF6 Formula 3 5 C 1 500 B2 2 150 B2 2
maly ision System Condition Test Resistance
0
7
4 D1 1 500 B3 2 150 C 2
Primary = 6 x 0.4 0
9 6 9 9
wf = 0.4 = 3.2 1
5 5 D2 1 500 B4 1 150 D 2
0
Secondary = 1 x 0.12
1 9 1
wf = 0.12 = 0.12
6 5 E 1 150 C1 1 150 E1 2
0
Dielectric = 6 x 0.2 1
1 9 9 9
wf = 0.2 = 1.2 7 5 F1 1 70 C2 2 150 E2 2
0
Driving 1
= 9 x 0.28
Mechanism 9 9 8 5 F2 1 150 D1 1 150 E3 2
wf = 0.28 = 2.52
0
7
9 F3 1 150 D2 1 150 E4 2
0
1
IV. AGE OF EQUIPMENT 1
0
5 G 1 150 D3 1
0
In normal ageing condition, age of HV Equipment has 1 7
H1 1 150 E1 2
influence to HV Equipment performance. HV Equipment 1 0
1 7
reliability decreases with time due to ageing process, minor 2 0
H2 1 70 E2 1
failure will occur during time operation. Age criteria of HV 1
150 E3 2
3
Equipment divided in two conditions [1] (see Table VIII).:
• “Old”, with score assessment “6”;
• “Very Old”, with score assessment “1”. PLN UIT JBTB have so many failure on CT. The failure
• And another condition has score assessment “9”, and still was dominated by manufacurer “A” (see Table X), One of
in good condition. caused is the age distribution of the manufacurer “A” and
“P” have very old criteria.
TABLE VIII. AGE CRITERIA OF HV EQUIPMENT TABLE X. WEIGHTING F FACTOR OF CT FAILURE OCCURRENCE
REFERENCES
Fig. 1. Single line diagram of “Y” Substation
The risk is likelihood multiplied by impact. Impact level [1] PT PLN (Persero) BOD Decree 149.K/DIR2013, “Replacement
that shown in Table XI, used as impact factor in risk matrix. criteria for high voltage equipment in PT PLN (Persero)”, Jakarta,
Likelihood and Impact from calculation formula are then 2013.
applied in risk matrix as shown in Table XIII to obtain the [2] PT PLN (Persero) BOD Decree 0520-2.K/DIR2014, “Maintenance
guidelines for circuit breaker”, Jakarta, 2014.
priority scale for HV Equipment Maintenance. The risk is
likelihood multiplied by impact. The result of HV [3] PT PLN (Persero) BOD Decree 0520-2.K/DIR2014, “Maintenance
guidelines for disconecting switch”, Jakarta, 2014.
equipment condition assessment and impact criteria shown in
[4] PT PLN (Persero) BOD Decree 0520-2.K/DIR2014, “Maintenance
Table XVII. guidelines for lightning arrester”, Jakarta, 2014.
[5] PT PLN (Persero) BOD Decree 0520-2.K/DIR2014, “Maintenance
guidelines for current transformer”, Jakarta, 2014.
TABLE XVII. SCORE RISK OF THE BAY
[6] PT PLN (Persero) BOD Decree 0520-2.K/DIR2014, “Maintenance
Bay Line Bay Transformer guidelines for potential transformer”, Jakarta, 2014.
arameter [7] PT PLN (Persero) P3BJB, “Practical guidelines for high voltage
DS DS DS DS
Bus 1 Bus 1
CB CT
PT 1
DS LA
Bus 1 Bus 1 CB 2 CT 2 PT 1
LA equipment”, Jakarta, 2013.
1 1 Line 1 1 1
A B A B [8] PT PLN (Persero) Trans-JBTB, “Determination guidelines for
Assess criticality of bay”, Surabaya, 2019.
0 0 3 5 3 0 0 0 0 0 0 0 0
ment [9] PT PLN (Persero) P3BJB, “Vulnerability of Java Bali subsystem”,
Age 1 1 2 2 2 2 0 2 1 2 2 2 2 Jakarta, 2015.
Failure [10] PT PLN (Persero) BOD Decree 0355.K/DIR2014, “Risk management
occur 0 0 2 2 2 1 0 0 0 2 2 2 1 implementation in PT PLN (Persero)”, Jakarta, 2014.
rence