Download as pdf or txt
Download as pdf or txt
You are on page 1of 53

BBU3900 V200

Installation Guide

Issue: 05
Part Number: 31504449
Date: 2009-03-05

HUAWEI TECHNOLOGIES CO., LTD.


Content

Safety Information 2
1. Information About the Installation 3
2. Installing the BBU in the APM30 8
3. Installing the BBU in the APM30H 15
4. Installing the BBU in the APM30 (+24 V) 17
5. Installing the BBU in the 19-Inch Cabinet 19
6. Installing the BBU on the Wall 23
7. Installing the BBU in the PS4890 Cabinet 28
8. Installing the BBU in the OMB Cabinet 33
9. Installing the BBU in the TMC 39
10. Installing the BBU in the TMC11H 41
11. Checking the Power-On Status of the BBU 42
12. Reference 43

1
Safety Information
Following All Safety Precautions
Before any operation, read the instructions and precautions in this document carefully to minimize the possibility
of accidents.
The Danger, Caution, and Note items in the documents do not cover all the safety precautions that must be
followed. They only provide the generic safety precautions for operations.

When operating Huawei products and equipment, you must comply with safety precautions and special safety
instructions related to corresponding equipment provided by Huawei. The safety precautions in the document
are related to only Huawei products. Huawei is not liable for any consequence that results from the violation of
universal regulations for safety operations and safety codes on design, production, and equipment use.

Complying with the Local Safety Regulations


When operating the device, comply with the local safety regulations. The safety precautions provided in the
documents are supplementary. You must comply with the local safety regulations.

Qualified Personnel Only


The personnel in charge of installation and maintenance must be trained and master the correct operating
methods and safety precautions before beginning work.

Symbols

This symbol indicates that casualty or serious accident may occur if you ignore
the safety instruction.

This symbol indicates that serious or major injury may occur if you ignore the
safety instruction.

This symbol indicates that the operation may be easier if you pay attention to the
safety instruction.

Safety of Personnel
• The high voltage power supply provides power for running the system. Direct contact with the high voltage
power supply or contact through damp objects may result in fatal danger.
• Non-standard and improper high voltage operations may result in fire and electric shock.
• In a thunderstorm, do not perform operations on high voltage and AC power supply facilities or on a steel
tower and mast.
• Ground the device before powering on the device. Otherwise, the personnel and device are in danger.
• Power off the device before performing operations on the power supply equipment.
• High power radio-frequency signals are harmful to human body. Before installing or maintaining an antenna
on a steel tower or mast with a large number of transmitter antennas, the operator should coordinate with all
parties to ensure that the transmitter antennas are shut down.
• When handling optical fibers, do not stand close to, or look into the optical fiber outlet with unaided eyes.
• Protect yourself when drilling holes. Flying dust may hurt your eyes or you may inhale the dust.
• Power off the batteries before connecting the cables to the batteries. Otherwise, casualties may occur.
• When working at a height, be cautious about falling objects.

Device Safety
• Check the electrical connection of the device before operation and ensure that the device is reliably grounded.
• The static electricity generated by the human body may damage the electrostatic sensitive components on
the circuit board, such as the large-scale integrated circuit (LIC). Wear an ESD wrist strap or ESD gloves when
performing the operation.
• When working on batteries, take measures to prevent short circuits in the batteries and electrolyte spill/loss.
The electrolyte may erode metal and boards, or even cause rust of the equipment or short circuits in the boards.
• The NodeB must be powered on within one week after installation.

2
1 Information About the Installation
a Installation Tools

Insulated screwdriver Cross screwdriver Straight screwdriver

Adjustable wrench Socket wrench Torque wrench

Power cable crimping


pliers RJ-45 crimping pliers Wire cutter

Rubber hammer Claw hammer Cable peeler

Percussion drill Heat gun Level bar

Multimeter Long measuring tape Vacuum cleaner

3
1 Information About the Installation
b Installation Scenarios

1.APM30 2.APM30H

BBU BBU

3.TMC 4.TMC11H

BBU BBU

4
1 Information About the Installation
b Installation Scenarios

5.APM30 (+24V) 6.PS4890

BBU

BBU

7. In OMB cabinet 8. In other 19-inch cabinet 9. On the Wall

BBU
BBU

BBU

5
1 Information About the Installation
c BBU Hardware and Cables
1. Appearance of the BBU (Unit: mm)

2. Configuration Principles of the BBU Boards

Board Mandatory/Op Full Installation Slot Remarks


tional Configuration

WMPT Mandatory 2 S6 and S7 Preferentially configured in Slot 7.

WBBP Mandatory 4 S0 to S3 Preferentially configured in Slot 3,


then Slot 2, at last Slot 0,1.

UPEU Mandatory 2 PWR1 and WR2 Preferentially configured in PWR2.

UBFA Mandatory 1 FAN Only in the FAN slot.

UTRP Optional 5 S0 to S5 Preferentially configured in Slot 4,


5.

UELP Optional 2 S0 and S4 Preferentially configured in Slot 4.

UFLP Optional 2 S0 and S4 Preferentially configured in Slot 4.

UEIU Optional 1 PWR1 Preferentially configured in PWR1.

6
1 Information About the Installation
d Cable connections of the BBU

Alarm Monitoring
Equipment Equipment

Power System

BBU Power Cable Alarm Cable


E1 surge protection transfer cable CPRI Optical
E1 Cable FE cable
Monitoring Cable FE surge protection transfer cable

e Procedure

7
2 Installing the BBU in the APM30
a Cable connections

NO. Cable Installation Position

From... To ...

1 BBU power cable LOAD3 on PDU PWR on BBU

2 E1 transfer cable E1/T1 on WMPT INSIDE on UELP

3 E1cable OUTSIDE on UELP Transmission equipment

4 Monitoring cable TX/RX on APMI MON1on BBU

5 CPRI CPRI on BBU CPRI on RRU

8
2 Installing the BBU in the APM30
b Installing BBU
1 Install the mounting ears at both sides of
the BBU reversely.

PDU

BBU
M6 bolt

2 Slide the BBU case into the cabinet.


3 Check the DIP switches (see appendix).

c Installing cables
1. Install power cable.
Connect the OT terminal of the power cable to the LOAD3
terminal of the PDU, and then fix the 3V3 connector of the
power cable to the PWR port on the BBU.

LOAD3

NEG(-)

RNT(+)

PWR

The power cable is to be made


depending on field requirements.

9
2 Installing the BBU in the APM30
b Installing the BBU cables

2. Install optical cables.


Connect one end of the optical cable to CPRI0, CPRI1, or CPRI2 on the WBBP. Then,
connect the other end to the RRU.
Insert the optical module into CPRI0, CPRI1,
or CPRI2.
Turn outwards the puller on the optical
module.

Optical module

Puller

Remove the dustproof caps from the


optical connectors.
Insert the optical connector at one end of the
CPRI optical cable into the optical module. lead
the CPRI optical cable out of the cabinet along
the left side of the cabinet.

Wrap the fiber tail with the winding pipe till the
first cable tie.

• Connect the fiber tails labeled 1A and


1B to the CPRI_W port on the RRU.
• Connect the fiber tails labeled 2A and Optical cable
2B to one of the CPRI0 to CPRI5 ports connector
on the WMPT.

Winding pipe

10
2 Installing the BBU in the APM30
b Installing the BBU cables
3. Install the E1 transfer cable.
Fix the DB25 connector of the E1 transfer cable to the INSIDE port on the UELP and the DB26 connector to the
E1/T1 port on the WMPT.

4. Install the E1 cable.


Cabling the E1 cable.

Fix the DB26 connector of the E1 cable to the


OUTSIDE port on the UELP.

Strip the jacket off the E1 cable near the


grounding point at the lower right corner of the
cabinet to expose the shielding layer E1 cable

25mm

E1 transfer cable

Thread the E1 cable through the grounding clip.


Then, tighten the screw on the grounding clip to
make the shielding layer of the E1 cable in full
contact with the grounding clip. Finally, connect INSIDE OUTSIDE
the PGND cable on the grounding clip to the
grounding bolt of the APM30.

Shielding layer
of the E1 cable

E1/T1

11
2 Installing the BBU in the APM30
b Installing the BBU Cables
5. Install the FE transfer cable (FE transmission
mode).

Connect one end of the FE transfer cable to the


FE0 port near the INSIDE label on the UFLP and
the other end to the FE0 port on the WMPT.

6. Install the FE cable (FE transmission).


Connect one end of the FE cable to the FE0 port
near the OUTSIDE label on the UFLP. Then, lead
the other end out of the cabinet along the right side
of the cabinet.

FE transfer cable
Strip the jacket off the FE cable near the
grounding point at the lower right corner of the
FE cable cabinet to expose the shielding layer

25mm

INSIDE FE0

OUTSIDE FE0

Thread the FE cable through the grounding


clip. Then, tighten the screw on the grounding
FE0 clip to make the shielding layer of the FE
cable in full contact with the grounding clip.
Finally, connect the PGND cable on the
grounding clip to the grounding bolt of the
APM30.

Shielding layer
of the FE cable

12
2 Installing the BBU in the APM30
b Installing the BBU Cables

7. Install the monitoring signal cable


between the APMI and the BBU.

Fix the RJ45 connector at one end of the cable to the


MON1 port on the UPEU.

Monitoring signal cable between the MON1


APMI and the BBU

EXT-ALM1 8. Install the external alarm cable.


Connect one end of the alarm cable to the EXT-ALM port
External alarm on the UPEU, and the other end to the associated alarm
cable device.
The port on the external alarm device is added depending
on field requirements.

9. Install the EMUA monitoring signal cable.


When the MON0 port on the BBU is available, fix the RJ45 connector of the EMUA
monitoring signal cable to the MON0 port on the UPEU, and the DB9 connector to the
corresponding port on the EMUA.

MON0

RS485

13
2 Installing the BBU in the APM30
b Installing the BBU Cables

b. When the MON0 port on the BBU is unavailable, cut off the RJ45 connector of the
EMUA monitoring signal cable, and then connect the four exposed bare wires to the
RX+, RX-, TX+, and TX- ports on the APMI. For the relationship between the ports and
wires. Fix the DB9 connector to the corresponding port on the EMUA.

EMUA monitoring signal cable

Pin on the RJ45 Pin on the DB9 Male Color Type Port on the APMI
Connector Connector

X1.1 X2.3 White Twisted pair TX+

X1.2 X2.7 Orange TX-

X1.4 X2.2 Blue Twisted pair RX+

X1.5 X2.6 White RX-

14
3 Installing the BBU in the APM30H
a BBU Cable Connections

The procedure for installing the BBU case in the APM30H is the same as that in the APM30.
For details, see pages 9–14. The following figure shows the cable connections of the BBU.
Page 15 shows how to install the monitoring signal cable between the HEUA and the BBU
in the APM30H.

No. Cable Installation Position

One end is connected to... The other end is connected


to...

1 BBU power cable LOAD3 terminal of the PDU PWR port on the BBU

2 E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

3 E1 cable OUTSIDE port on the UELP External transmission device

4 Monitoring signal COM IN port on the HEUA MON1 port on the BBU
cable

5 CPRI optical CPRI port on the BBU CPRI port on the RRU
cable

15
3 Installing the BBU in the APM30H
b Installing the Monitoring Signal Cable between the HEUA and the BBU

HEUA
COM IN
MON1

UPEU on the
BBU

16
4 Installing the BBU in the APM30 (+24 V)
a BBU Cable Connections

The procedure for installing the BBU in the APM30 (+24 V) is the same as that in the APM30. For
details, see pages 9–14. The following figure shows the cable connections of the BBU. Page 17
shows how to install the monitoring signal cable of the cabinet.

No. Cable Installation Position

One end is connected to... The other end is connected


to...

1 BBU power cable LOAD3 terminal of the PDU PWR port on the BBU

2 E1 surge protection E1/T1 port on the WMPT INSIDE port on the UELP
transfer cable

3 E1 cable OUTSIDE port on the UELP External transmission device

4 Monitoring signal COM IN port on the HEUA MON1 port on the BBU
cable

5 CPRI optical cable CPRI port on the BBU CPRI port on the RRU

17
4 Installing the BBU in the APM30 (+24 V)
b Installing the Monitoring Signal Cable of the Cabinet

Pin assignment of the monitoring signal cable of the cabinet

Pin on the RJ45 Pin on the RJ45 Wire Color Wire Type
Connector Connector

X1.1 X2.1 White/orange Twisted pair

X1.2 X2.2 Orange

X1.3 X2.3 White/green Twisted pair

X1.6 X2.6 Green

X1.5 X2.5 White/blue Twisted pair

X1.4 X2.4 Blue

X1.7 X2.7 White/brown Twisted pair

X1.8 X2.8 Brown

18
5 Installing the BBU in the 19-Inch Cabinet
a BBU Cable Connections

No. Cable Installation Position

From... To...

1 BBU power External power supply PWR port on the BBU


cable

2 E1 cable External transmission device E1/T1 port on the WMPT

3 FE cable External transmission device FE0 port on the WMPT


(optional)

4 Monitoring External monitoring device MON/ALM on the BBU


signal cable

5 CPRI optical CPRI port on the RUU CPRI port on the BBU
cable

19
5 Installing the BBU in the 19-Inch Cabinet
b Space Requirements

1. 25 mm on the left of the BBU for ventilation


2. 25 mm on the right of the BBU for ventilation
3. 70 mm in front of the BBU for cabling

c Installing the BBU Case


Slide the BBU case into the cabinet. Then, tighten the four M6 screws.

20
5 Installing the BBU in the 19-Inch Cabinet
d Installing BBU Cables

1 Install the PGND cable.

Grounding bolt
on the right side
of the BBU

PGND cable

2 Install the power cable.

PWR

3 Install the signal cable.

EXT-ALM0 MON1

21
5 Installing the BBU in the 19-Inch Cabinet
d Installing the BBU Cables

4 Install the CPRI optical cable and the E1 cable.

E1/T1
E1/T1

Insert the optical module into the CPRI0, CPRI1, or CPRI2 port.
Turn outwards the puller on the optical module.

Optical module

Puller

Remove the dustproof caps from the optical connectors.


Insert the optical connector at one end of the CPRI optical cable into the
optical module. Lead the CPRI optical cable out of the cabinet along the
left side of the cabinet.

CPRI optical cable

Winding pipe

22
6 Installing the BBU on the Wall
a BBU Cable Connections

External
grounding bar

External power
equipment

External
External transmission grounding bar
equipment

External monitoring
equipment

SN Cable Installation Position

One End Connected to... The Other End


Connected to...
1 RRU power cable LOAD0 to LOAD5 on the DCDU-03 Power supply socket on the
RRU

2 CPRI optical cable CPRI port on the BBU CPRI port on the RRU

3 E1 cable E1/T1 port on the WMPT External transmission


equipment

4 Monitoring signal MON/ALM port on the BBU External monitoring equipment


cable

5 BBU power cable PWR port on the BBU LOAD6 on the DCDU-03

6 DCDU power cable DC input port on the DCDU-03 External power equipment

7 PGND cable Grounding bolt on the equipment External grounding bar

23
6 Installing the BBU on the Wall
b Space Requirements

A single BBU BBU+DCDU-03C

DCDU-03C

BBU

The DCDU is installed near the BBU.

c Installing the BBU Case

1. Install the mounting ears for wall installation.

Mounting ear on
the BBU case

Mounting ear
for wall installation

24
6 Installing the BBU on the Wall
c Installing the BBU Case
2. Place the BBU against the wall, and then use the marking pen to mark
the holes of the mounting ears for wall installation.

wall

BBU

3. Install the expansion bolts.

Bolt M10×80
Nut
Spring washer 10
Flat washer 10

Expansion tube

55mm~60mm

20mm

25
6 Installing the BBU on the Wall
c Installing the BBU Case

4. Mount the BBU on the wall.

Flat washer

Spring washer

d Installing the DCDU-03C Case


1. Turn the mounting ears on the 2. Place the DCDU-03C against the wall,
DCDU-03C by 90 degrees. and then use the marking pen to mark the
anchor points of the mounting ears for
wall installation.

wall

26
6 Installing the BBU on the Wall
d Installing the DCDU-03C Case
3. Install the expansion bolts.

Bolt M10×80
Nut
Spring washer 10
Flat washer 10

Expansion tube

55mm~60mm

20mm

4. Mount the DCDU-03C on the wall.

27
7 Installing the BBU in the PS4890 Cabinet
a BBU Cable Connections

No. Cable Installation Position

From... To...
1 BBU power cable LOAD6 terminal on the PWR port on the BBU
DCDU

2 E1 cable External transmission E1/T1 port on the WMPT


device

3 BBU alarm cable (optional) External transmission ALM port on the UPEU
device

4 Monitoring signal cable RS232/RS422 port on the MON0 port on the BBU
between the PMU and the PMU
BBU

5 CPRI optical cable CPRI port on the RRU CPRI port on the BBU

28
7 Installing the BBU in the PS4890 Cabinet
b Installing the BBU

Slide the BBU case into the PS4890 cabinet. Then, tighten the four M6 screws.

29
7 Installing the BBU in the PS4890 Cabinet
c Installing the BBU Cables

1 Install the power cable.

LOAD 6

PWR

30
7 Installing the BBU in the PS4890 Cabinet
c Installing the BBU Cables
2 Install the signal cable.

Install the BBU alarm cable (optional).


Install the monitoring signal cable between the PMU and the BBU.

RS232/RS422 MON0

EXT ALM1

31
7 Installing the BBU in the PS4890 Cabinet
c Installing the BBU Cables
3 Installing the CPRI optical Insert the optical module into the CPRI0, CPRI1,
or CPRI2 port.
cable and the E1 cable.
Turn outwards the puller on the optical module.

Optical
module

Puller

Remove the dustproof caps from the optical


connectors.

Insert the optical connector at one end of the


CPRI optical cable into the optical module. lead
the CPRI optical cable out of the cabinet along
the left side of the cabinet.

E1/T1

CPRI optical cable

Winding pipe

32
8 Installing the BBU in the OMB Cabinet
a BBU Cable Connections

No. Cable Installation Position

From... To...
1 PGND cable External grounding bar Grounding bar of the OMB
cabinet

2 Input power cable External DC power supply DC input terminal of the DCDU
of the OMB

3 BBU power cable LOAD6 output terminal on the PWR port on the BBU
DCDU

4 E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

5 E1 cable OUTSIDE port on the UELP External transmission device

6 CPRI optical cable CPRI port on the BBU CPRI port on the RRU

33
8 Installing the BBU in the OMB Cabinet
b Installing the brackets on the metal pole and mounting plate
a.1 Install the brackets on the metal pole.
Use a level bar to adjust the levelness of the brackets to ensure that the front and back brackets are
on the same plane.

Flat washer Spring washer

Bolt M10×110

Inner hexagon
spanner
255~306kgf·cm

a.2 Install the mounting plate.

Inner hexagon
spanner
255~306kgf·cm

Bolt M10×110
Flat Spring
washer washer

appearance of the mounting plate

34
8 Installing the BBU in the OMB Cabinet
c Installing the OMB Cabinet
Slide the BBU case into the OMB
cabinet gently. Then, tighten the four
M6 screws.

d Installing the BBU Cables


1. Install the PGND cable of OMB Cabinet.

35
8 Installing the BBU in the OMB Cabinet
d Installing the BBU Cables
2 Install the input power cable.

NEG(-)

RNT(+)

LOAD6
3. Install the BBU power cable.

36
8 Installing the BBU in the OMB Cabinet
d Installing the BBU Cables

4 Install the E1 cable (E1 transmission).

OUTSIDE

E1/T1

INSIDE

Shielding layer

37
8 Installing the BBU in the OMB Cabinet
d Installing the BBU Cables

5. Install the FE cable (FE transmission).

6. Install the CPRI optical cable.


1. Insert the optical module into the CPRI0, CPRI1, or
CPRI2 port.
2. Turn outwards the puller on the optical
module.

Optical module

Puller

3. Remove the dustproof caps from the


optical connectors.
4. Insert the optical connector at one end
of the CPRI optical cable into the optical
module. lead the CPRI optical cable out of
the cabinet along the left side of the
cabinet.

38
9 Installing the BBU in the TMC
a BBU Cable Connections
The procedure for installing the BBU in the TMC is the same as that in the APM30. For details,
see pages 9–14. Page 39 shows how to install the TMC alarm cable in the TMC.

No. Cable Installation Position

From... To...
1 BBU power cable LOAD6 terminal of the PDU PWR port on the BBU

2 E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

3 E1 cable OUTSIDE port on the UELP External transmission device

4 Monitoring signal cable Wiring terminal of cabinet ALM1 port on the BBU
monitoring

5 CPRI optical cable CPRI port on the BBU CPRI port on the RRU

39
9 Installing the BBU in the TMC
b Installing the BBU

Slide the BBU case into the


TMC cabinet. Then, tighten
the four M6 screws.

c Installing the BBU Cables


APMI
Installing the TMC alarm cable Door status sensor

a. Fix the RJ45 connector Wiring terminal of


DCDU surge protection
at one end of the alarm
cable to the EXT_ALM1
port on the BBU.

b. Connect the two bare


terminals X1.4 (blue) and
X1.5 (white) to the alarm
wiring terminals on the
door status sensor.
c. Connect the two bare
terminals X1.1 (white)
and X1.2 (orange) to the
OUT+ and OUT- alarm
wiring terminals on the
APMI.

d. Connect the two bare


terminals X1.3 (white)
and X1.6 (green) to the
alarm wiring terminals on
the DCDU.

40
10 Installing the BBU in the TMC11H
a BBU Cable Connections

The procedure for installing the BBU in the TMC11H is the same as that in the APM30. For
details, see pages 9–14.

No. Cable Installation Position

From... To...
1 CPRI optical cable CPRI port on the BBU CPRI port on the RRU

2 E1 transfer cable E1/T1 port on the WMPT INSIDE port on the UELP

3 E1 cable OUTSIDE port on the UELP External transmission device

4 BBU power cable LOAD6 terminal on the PDU PWR port on the BBU

5 Monitoring signal Wiring terminal of cabinet monitoring MON1 port on the BBU
cable

41
11 Checking the Power-On Status of the BBU

Procedure for checking the power-on status of the BBU:

Start

Powering on the BBU3900 Clearing the fault

a Powering off the


BBU3900

No
Checking whether all LEDs on the
BBU are normal?

Yes

End

a
The normal status of LED on the
WMPT is as follows:
• RUN LED: 1s ON, 1s OFF
(blinking at 0.5 Hz)
• ALM LED: OFF
• ACT LED: ON
The normal status of LED on the
UBFA is as follows:
• STATE LED: Green
1s ON, 1s OFF (blinking at 0.5 Hz)
The normal status of LED on the
UPEU is as follows:
• RUN LED: ON
The normal status of LED on the
WBBP is as follows:
• RUN LED: 1s ON, 1s OFF
(blinking at 0.5 Hz)
• ALM LED: OFF

42
12 Reference
c
a Cable List
Cable Connector Connects to…

PGND cable OT terminal Grounding bolt of the BBU3900


OT terminal Protection grounding bar

BBU power cable 3V3 connector PWR port on the UPEU


Bare wire. The connector needs External power supply
to be made on site according to
the field requirements. (The
following figure shows the BBU
power cable by taking OT
terminals as an example.)

CPRI optical cable DLC connector Connect the fiber tails labeled 1A
and 1B to the CPRI_W port on the
RRU
DLC connector Connect the fiber tails labeled 2A
and 2B to one of the CPRI0 to
CPRI3 ports on the WBBP

E1 cable DB26 male connector E1/T1 port on the WMPT, or


OUTSIDE port on the UELP
The connector needs to be made Peer device
on site according to the field
requirements.

43
12 Reference
c
a Cable List

Cable Connector Connects to…

E1 transfer DB26 male connector PWR port on the UPEU


cable
DB25 male connector E1/T1 port on the WMPT

FE cable RJ45 connector FE0 port on the WMPT

RJ45 connector Routing equipment

FE transfer RJ45 connector FE0 port on the WMPT


cable
RJ45 connector FE0 port near the INSIDE label on
the UFLP

Monitoring RJ45 connector RS232/RS422 port on the PMU


signal cable
RJ45 connector MON port on the BBU
between the
PMU and the
BBU

44
12 Reference
a Cable List

Cable Connector Connects to…

APMI-BBU Be connected APMI


Monitoring
RJ45 connector MON1 port on the UPEU
signal cable

EMUA Monitoring RJ45 connector MON0 or MON1 port on the


signal cable UPEU

DB9 male connector RS485 port on the EMUA

Alarm cable RJ45 connector EXT-ALM0 or EXT-ALM1 port on


the MON0 or MON1 port on the
UPEU

RJ45 connector External alarm device

45
12 Reference
b Engineering Specifications of the BBU

Item Specification

Dimensions 86 mm (height) x 442 mm (width) x 310 mm (length)

Weight Typical configuration: 7 kg; full configuration: 11 kg

Input voltage –48 V DC or +24 V DC

c Checking the DIP Switches of the BBU

Wear an ESD wrist strap or a pair of ESD gloves when performing


operations related to the boards, as shown in the figure below.

ESD strap

ESD gloves

1. Remove the BBU boards.

46
12 Reference
c Checking the DIP Switches of the BBU
2. Set the DIP switches of the BBU.
Settings of the DIP switches on the UELP

75-ohm E1 Mode

Other Modes

Settings of the DIP switches on the WMPT

T1 Mode

75-ohm E1 Mode 120-ohm E1 Mode

3. Reinstall the boards.

47
12 Reference
ed Pin Assignment of the BBU Signal Cables
75-ohm E1 cable

Pin on the DB26 Male Wire Type Coaxial SN. Label


Connector

X1.1 Tip 1 RX1+

X1.2 Ring RX1-

X1.3 Tip 3 RX2+

X1.4 Ring RX2-

X1.5 Tip 5 RX3+

X1.6 Ring RX3-

X1.7 Tip 7 RX4+

X1.8 Ring RX4-

X1.19 Tip 2 TX1+

X1.20 Ring TX1-

X1.21 Tip 4 TX2+

X1.22 Ring TX2-

X1.23 Tip 6 TX3+

X1.24 Ring TX3-

X1.25 Tip 8 TX4+

X1.26 Ring TX4-

48
12 Reference
d Pin Assignment of the BBU Signal Cables

120-ohm E1 cable

Pin on the DB26 Male Wire Color Wire Type Label


Connector

X1.1 Blue RX1+


Twisted pair
X1.2 White RX1-

X1.3 Orange RX2+


Twisted pair
X1.4 White RX2-

X1.5 Green RX3+


Twisted pair
X1.6 White RX3-

X1.7 Brown RX4+


Twisted pair
X1.8 White RX4-

X1.19 Grey TX1+


Twisted pair
X1.20 White TX1-

X1.21 Blue TX2+


Twisted pair
X1.22 Red TX2-

X1.23 Orange TX3+


Twisted pair
X1.24 Red TX3-

X1.25 Green TX4+


Twisted pair
X1.26 Red TX4-

49
12 Reference
d Pin Assignment of the BBU Signal Cables

FE cable

Pin on the RJ45 Wire Color Wire Type Pin on the RJ45
Connector Connector

X1.2 Orange Twisted pair X2.2

X1.1 White/orange X2.1

X1.6 Green Twisted pair X2.6

X1.3 White/green X2.3

X1.4 Blue Twisted pair X2.4

X1.5 White/blue X2.5

X1.8 Brown Twisted pair X2.8

X1.7 White/brown X2.7

Monitoring signal cable between the APMI and the BBU

Pin on the RJ45 Wire Pins on the Wire Type Port on the
Connector Color X2, X3, X4, APMI
and X5

X1.1 White X2 Twisted TX+


pair

X1.2 Orange X3 Twisted TX-


pair

X1.4 Blue X4 Twisted RX+


pair

X1.5 White X5 Twisted RX-


pair

50
12 Reference
d Pin Assignment of the BBU Signal Cables

EMUA monitoring signal cable

Pin on the RJ45 Pin on the Wire Wire Port on the


Connector DB9 Male Color Type APMI
Connector

X1.1 X2.3 White Twisted TX+


pair

X1.2 X2.7 Orange Twisted TX-


pair

X1.4 X2.2 Blue Twisted RX+


pair

X1.5 X2.6 White Twisted RX-


pair

Alarm cable
Pin on the RJ45 Pin on the RJ45 Wire Color Wire Type
Connector Connector

X1.1 X2.1 White/orange Twisted pair

X1.2 X2.2 Orange

X1.3 X2.3 White/green Twisted pair

X1.6 X2.6 Green

X1.5 X2.5 White/blue Twisted pair

X1.4 X2.4 Blue

X1.7 X2.7 White/brown Twisted pair

X1.8 X2.8 Brown

51
HUAWEI TECHNOLOGIES CO., LTD.
Huawei Industrial Base Bantian Longgang
Shenzhen 518129
People’s Republic of China
www.huawei.com

You might also like