Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Chevron Specification TAM-MU-8

RELEVELING TANKS

SPECIFICATION TAM-MU-8
RELEVELING TANKS

June 1989 Page 1 of 5


Chevron Specification TAM-MU-8

RELEVELING TANKS

CONTENTS

1.0 SCOPE .................................................................................................................................3

2.0 PRELIMINARY MEASUREMENTS ...................................................................................3

3.0 GROUTING MATERIAL ....................................................................................................3

4.0 TANK RELEVELING BY PRESSURE GROUTING ..........................................................4

5.0 FILLING VOIDS AND REDUCING BOTTOM DEPRESSIONS .......................................4

6.0 TANK RELEVELING BY JACKING .................................................................................4

7.0 HYDROTEST.......................................................................................................................5

8.0 SUBMITTALS......................................................................................................................5

Page 2 of 5 June 1989


Chevron Specification TAM-MU-8

RELEVELING TANKS

1.0 SCOPE

This specification covers the work necessary to relevel tanks and to fill in voids under tank
bottoms.

2.0 PRELIMINARY MEASUREMENTS

2.1 The Company will provide the following measurements:

2.1.1 Elevations of the tank bottom at the shell. A minimum of 8 measurements will be
taken on the tank with intervals not greater than every 30 feet.

2.1.2 Tank diameters taken at the same location as the elevations in Subsection 2.1.1,
above. One diameter measurement will be taken 1 foot above the tank bottom and
another at the top of the tank shell.

2.1.3 Eight annular space measurements between the floating roof rim and the shell with the
floating roof resting on its supports. If additional measurements are to be provided, it
will be specified in the Agreement.

2.2 The Contractor shall use the same locations as the Company for taking measurements and
elevations upon completion of the work.

3.0 GROUTING MATERIAL

3.1 Grout pumped underground to raise the tank shell and roof supports shall be sand or a sand-
cement low slump-type mixture. The mixing ratio shall be a minimum of 12% or more cement
to 88% or less sand by volume. The sand gradation shall be within the following range:

Sieve Size Percent by Weight Passing

#4 95-100
#8 80-100
#16 55-90
#30 40-85
#50 30-70
#100 20-50
#200 10-20
#400 5-15
20 microns 0-10
10 microns 0-3

3.2 Grout pumped between the tank bottom and soil shall be a fly ash-cement (Pozzolanic-
cement) grout. The mixing ratio shall be 1 cubic foot cement to 3 cubic feet Pozzolanic sand.

June 1989 Page 3 of 5


Chevron Specification TAM-MU-8

RELEVELING TANKS

4.0 TANK RELEVELING BY PRESSURE GROUTING

4.1 The Contractor shall submit a step-by-step procedure to level the tank. The procedure shall
be submitted to the Company Representative for approval prior to job start.

4.2 Piping running tangent to the shell area shall be daylighted to prevent the soil from stressing
the pipes. Piping requiring daylighting will be specified in the Agreement.

4.3 The Contractor shall pump grout underground. Tank level and the annular space (on floating
roof tanks) shall be checked after each 1/4 inch of rise. On floating roof tanks, the Contractor
shall discontinue grouting if the annular space variation increases and shall notify Company
Representative.

4.4 Fixed roof support columns and floating roof legs shall be raised to the appropriate level by
pressure grouting alongside the columns or legs at the same depth that the grout was installed
under the shell. Holes through the tank bottom (or bottoms) for injecting grout shall be made
by drilling or cold cutting. Upon completion, holes shall be patched with 1/4-inch thick steel
plate. During welding, the Contractor shall nitrogen-purge the bottom.

5.0 FILLING VOIDS AND REDUCING BOTTOM DEPRESSIONS

5.1 Voids under the tank bottom shall be filled and depressions in the bottom plate shall be raised
by pumping sand or grout under the bottom between the bottom plate and the soil.

5.2 When the existing bottom is being repaired, the Contractor shall lap weld 1/4-inch thick steel
plate patches over the injection holes cut in the bottom. All patch welds shall be vacuum
tested. The Company will witness the test. No patching is required when a new bottom is to
be installed. However, any concrete protruding through the injection holes shall be ground
smooth.

6.0 TANK RELEVELING BY JACKING

6.1 The Contractor shall design, furnish and install shell-mounted brackets as necessary to raise
the tank. Each bracket installation shall be designed to support its proportionate load with a
safety factor of 4.

6.2 The Contractor shall jack up the low areas of the tank shell as necessary to level the bottom
edge of the shell to plus or minus 1/4 inch.

6.3 During leveling, the tank diameter or annular space between the floating roof rim and the tank
shell shall be measured in at least 8 equally spaced locations. If the annular space variation
increases, the Contractor shall stop the jacking and notify the Company Representative.

Page 4 of 5 June 1989


Chevron Specification TAM-MU-8

RELEVELING TANKS

6.4 Prior to, during and following the leveling process, the Contractor shall measure shell out-of-
roundness, bottom-of-shell level and shell plumbness. The Contractor shall report final
measurements to the Company Representative.

6.5 The Contractor shall install a sufficient number of steel shims between the existing bottom and
the foundation to prevent point loading on the foundation of over 3000 psi. Then the
Contractor shall lower the tank onto the shims. The maximum spacing between shims shall be
3 feet. The Contractor shall recheck the tank bottom level and shell plumbness and adjust the
level as necessary to meet the tolerances described in Subsection 3.2. The Contractor shall
trim the shims flush with the edge of the tank bottom.

6.6 The Contractor shall pump sand or grout into the area under the tank shell and between the
shims as specified in Sections 3.0 and 4.0. Sand or grout shall be pumped into the entire
space under the tank, occupying any gap greater than 1/8 inch high.

6.7 The Contractor shall remove shell-mounted lifting brackets upon job completion and grind the
shell smooth.

7.0 HYDROTEST

7.1 After releveling work is complete, the Contractor shall do all the necessary mechanical work
to apply a full hydrotest.

7.2 The Contractor shall check foundation elevations and annular space measurements at ten-foot
intervals during the hydrotest.

8.0 SUBMITTALS

The Contractor shall submit a detailed grouting procedure to the Company for review.

June 1989 Page 5 of 5

You might also like