Retaining Wall

Abstract of Estimate - Retaining wall


Item
No. Description of Items Qty Rate Unit Amount

Earth work

1 Earth work in excavation by mechanical

means (Hydraulic excavator) / manual means

over areas (exceeding 30 cm in depth,1.5m

in width as well as - 10 sqm on plan)

including disposal of excavated earth, lead

upto 50 m and lift upto 1.5m, disposed

earth to be levelled and neatly dressed.

Ordinary rock 15.00 400.00 cum 6,000

cum

Concrete work

2 Providing and laying in position cement

concrete of specified grade excluding the


cost of centering and shuttering.- All work

upto plinth level -1:5:10 (1 cement:5coarse

sand : 10 graded stone aggregate 40mm

nominal size) 1.60 5000.00 cum 8,000

cum

R.C.C work

3 Providing and laying in position


specified grade of reinforced

cement concrete excluding the cost

of centering,shuttering,finishing

and reinforcement -All work upto

plinth level : 1:1.5:3 (1 cement :

1 .5 coarse sand : 3 graded stone

aggregate 20mm nominal size) 11.00 7500.00 cum 82,500

cum

4 Centring and shuttering including

strutting, propping etc. and

removal of form for:

columns,pillars,piers,abutments,posts

1/5
Item
No. Description of Items Qty Rate Unit Amount
and struts.- Using steel sheet

with M.S.frames 23.00 500.00 sqm 11,500

sqm

5 Reinforcement for R.C.C work

including straightening , cutting

bending , placing in position

and binding all complete - Thermo


- Mechanically treated bars(ISI

BRAND OF APPROVED MAKE) including

placing the M30 grade Athees make

cover block @ 60cm centre to centre 650 75.00 Kg 48,750

Kg

6 Plastering with CM 1:5 - 12 mm thk

(1 cement : 5 Psand) 14.00 450.00 sqm 6,300


Sqm

Total 163,050

7 GST @ 18% 29,349

8 Sundries 101

Grand Total 192,500

Rupees One Lakh Ninety Two Thousand Five hundred Only

2/5
Retaining Wall
Item
Description of Items No Length Breadth Depth Quantity Units
No.

Earth work

1 Earth work excavation …

Retaining wall 1 x 1 9.00 0.95 1.65 14.11


Sundries 0.89

Total 15.00 cum

Concrete work

2 Providing and laying PCC 1:5:10

Retaining wall 1 x 1 9.00 0.95 0.15 1.28

sundries 0.32
Total 1.60 cum

R.C.C work

3 Providing and laying RCC 1:1.5:3 -


All works upto Plinth Beam
Retaining wall

Bottom 1 x 1 9.00 0.90 0.45 3.65


vertical 1 x 1 9.00 0.45 1.75 7.09

Sundries 0.27

Total 11.00 cum

4 Centring and shuttring - columns

Retaining wall
Foundation

Side in length 1 x 1 9.00 0.45 4.05

At Ends 1 x 2 0.45 1.75 1.58

1 x 2 0.90 0.45 0.81

Vertical side 1 x 1 9.00 1.75 15.75

sundries 0.81

Total 23.00 sqm


Item
Description of Items No Length Breadth Depth Quantity Units
No.

5 Reinforcement for RCC work..


TMT…
Retaining wall kg/m

Vertical Bar 1 (#12) 1 x 90 3.10 0.89 248.31


Vertical Bar 2 (#10) 1 x 60 2.35 0.62 87.42

Horizontal Bar (#10) both side 2 x 12 9.00 0.62 130.20

Retaining Wall Bottom

Top Horizontal 1 x 60 1.20 0.62 44.64

Horizontal Bar (#10) both side 2 x 6 9.00 0.62 66.96

sundries & wastage 72.47

Total 650.00 kg
length of the RW 9.00

Height of the RW 2.35

C/S of the RW
A 0.45
B 0.45
Heght 2.35
Foundation
E/w
breadth 0.95
Depth 1.65

concrete
Breadth 0.95
Depth 0.15

Pile Depth
Depth 0.00

Rate per runing meter 21388.89