Professional Documents
Culture Documents
Method Statement For Chamber Construction of TSE Line Ev Manager
Method Statement For Chamber Construction of TSE Line Ev Manager
Method Statement For Chamber Construction of TSE Line Ev Manager
C853/3
CONTRACT NO. - PA 2019 C 056 G
02 11 Oct. 2021 Third Release Okorie Primus Sayed Hamouda Bahodur Muhdi Noufal
for Approval QA/QC Engineer QA/QC Manager Safarov Project Director
Project
Manager
01 25 May 2021 Second Karthik Makam Sayed Hamouda Bahodur Muhdi Noufal
Release for Material Engineer QA/QC Manager Safarov Project Director
Approval Project
00 17 Feb 2021 Initial
Release- Hernando Bullo Bassel Orabi
Sayed Hamouda Muhdi Noufal
Revise and Re- Sr. QA/QC Technical
QA/QC Manager Project Director
Submittal Engineer Manager
1. PURPOSE
3. PRELIMINARIES
5. WORK METHODOLOGY
6. STAKE HOLDERS
12. INTERFACES
15. REFERENCES
3. PRELIMINARIES
a. License:
- All drivers, operators shall have valid driving- operating licenses/permits. Licenses/permits
should be obtained, from relevant concerned department/authorities.
- Proper sign boards and barriers will be placed as per HSE procedure & as required on site
1 and depends on the work activities.
- All permits should be secured ahead of time as per PW A/Concerned Department
rules &Regulations.
d. Disconnection/Reconnection of Service:
- UCC-INFRAROAD JV will seek permission from the AUTHORITY or asset owner for
disconnection / reconnection of service as applicable prior to initiate the job and during the
course of completion come across if any. No job will proceed without prior approval from
e. Permits to work:
- The contractor to ensure collecting all the needed permits from all the concerned Authorities
prior of any activity such as, valid RO, approved TDPs, excavation permit, valid SIS for MV/LV
1 & HV/EHV, cold permit, …etc.
- Permit To Dig - Excavation Works
- KAHRAMAA Permit (SIS or Cold Permit) - Work in the vicinity of existing KAHRAMAA
services
- Hot Work Permit
- Approved Traffic Diversion Plan.
- Ensure obtaining and maintaining valid work permits from all Authorized work permit holders.
-Valid Environmental Permits
DEFINITIONS/ACRONYMNS
Client PWA(Ashghal)
Supervision Consultant Parsons
Contractor UCC-Infraroad-JV
QCR Quality Control Records
ITP Inspection & Test Plan
QA/QC Quality Assurance & Quality Control
HSE Health, Safety & Environment
HS Health & Safety
RA Risk Assessment
QCS Qatar Construction Specifications
SRC Sulfur Resistant Cement
OPC Ordinary Portland Cement
1 HP Hold Point
WP Witness Point
SP Surveillance Point
R Record Review
N/A Not Applicable
SIS Service Information Sheet
RAMS Risk Assessment & Method Statement
LOA Limitation Of Access
RO Road Opening
TDP Tunnel Diversion Plan
TSE Treated Sewage Effluent
STARRT Safety Task & Risk Reduction Talks
CAT Computer Aided Testing
LOTO Lock Out Tag Out
PWA Public Works Authorithy
MV Medium Voltage
LV Low Voltage
PTW Permit To Work
A. Personel
1. Project Dırector/ Manager- Oversee the project to ensure the desired result is achieved, the
most efficient resources are used and the different interests involved are satisfied. Review the
quality of the work within the project team on a regular basis to ensure that it meets the
project standards and are completed as per the program. Monitor safety to ensure that the
requirements are enforced and implemented at all times on site.
Project/ Site Engineer – Work directly at site with the foreman to ensure that all the required
information has been provided to proceed with the work, and that the works comply with
project specification, method statement and shop drawings. He liaises with client’s staff with
respect to inspection and approvals. He reports to project/construction manager.
QA/QC Manager- Coordinate with Project Manager and his team about QA/QC related
activities of the Project, Following up continuous improvement for the quality within the
project. Evaluating the project quality program.
QA/QC Engineer – He will be monitor all activities and make sure that all required inspection
& test are carried out and all work shall be operated and recorded in accordance with the
contract quality plan.
Land Surveyor- The surveyor will supervise all the surveying activities on site and has full
control over the use of the chainmen and equipment. He ensures for achieving timely and
proper setting out of the works, responsible for accuracy of survey and testing of equipment
and will coordinate to the Site Engineers for any work that ready for inspection.
HSE Manager – He will monitor and provide full technical support for the implementation of
this procedure. Ensuring that the requirements of these procedures are consistently met to
adhered to. Preparing the HSE required documents and submissions, securing the approval
1
of top management for their implementation and for making all necessary needed
arrangements.
The HSE Manager shall carry out the inital review of the method statement,prepare risk
assessement and conduct RAMS breefing as soon as method statement and risk
assessement are approved by the consultant.
The HSE Manager shall ensure that work carried out in strict compliance with project
approved H & S plan, QCS 2014 requirements,contract documents and BS 6164 requirement.
To lead the entire HSS team, maintaining HSS awareness and to create safe culture and
working environment through innovative ideas.
Environmental Manager - He will ensure that the required environmental permit and approval
is in place before the commencement of work, ensure that conditions and requirements (i.e.
Noise Pollution, Dust Control, Waste Management etc.) of the permit and CEMP are
effectively implemented in the site and will also ensure the environmental impacts from this
Issue necessary directives to Project Safety Officer / Departmental Managers and render
advice to the Project Manager as required.
Prepare and submit HSS report to project Manager whenever so required.
Visit construction site during on-going activities and interact with Consultant and Sub-
contractors on HSS matters, whenever necessary.
Reporting internally and externally as required in consultation with the Supervision Consultant,
safety incidents, including near miss events and injuries
Investigating incidents, ensuring root cause/s are identified, and corrective actions address
root cause/s, managers are assigned responsibility for actions and that lessons learnt are
communicated and implemented to prevent recurrence
Actively promote hazard identification, reporting and elimination or control by all project
personnel
Monitoring and reviewing the HS performance of the project HS team and taking appropriate
action to correct poor performance
Ensure security arrangement for the project is in place
Monitor and report effectiveness of security arrangements.
HSE Officer – He will be responsible for ensuring implementation of safe working
procedures. Keeping hazard/incident/unsafe practices reports and ensuring that corrective
actions are undertaken as per HSE plan. Evaluate and record all relevant documentation,
shall be current and valid.
Civil Foreman – The civil foreman will supervise all the activities on site and has full control
over the use of the labor, plant and equipment. He ensures that the work is carried out in full
compliance with the specification, and in manner that conforms to the safety requirements
and will coordinate to the Project/ Site Engineer for any work is complete and ready for
inspection.
Lifting Supervisor-
- Conduct daily pre-task briefing prior to starting the activity and that all lifting activities are
in accordance with the lifting plan.
- Make sure a valid lift plan is available for the critical lift.
5. WORK METHODOLOGY
Typical section for DN 1400DI & twin DN1200 TSE mains combined washout chamber
structural details
a) Setting-out
UIJV will prepare shop drawings showing survey information and levels based on
issued for construction/ as per approved shop drawing and approved survey drawing of
design longitudinal profile. Such levels shall be related to the temporary bench marks;
Setting of the lines, levels and grades as per drawings is carried out prior to
commencement of works. In addition, offset reference will be established for easy counter
checking as the work progresses.
UIJV will provide measuring and recording equipment for the supervision consultant
and will be properly maintained in a good working order at all times.
b) Dewatering
(if needed) will be provided depending on the location of ground water and subsequent
procedure will be submitted separately for this item of works.
c) Excavation Works
Prior to start for excavation works, all utilities shall be located and marked ahead of the
excavator. UIJV shall be responsible for locating all services crossing or closely paralleling the
line of structure by consultation with the relevant services department.
Curing of concrete to comply as per QCS 2014, Section 05, Part 10. Water curing with
hessian cloth covering the surface with a saturated absorptive and keeping it continuously wet
.
De- shuttering after concrete curing;
The formwork shall be carefully stripped as per specification to avoid sudden shocks from the
removal of sections or vibration which might cause damage to the concrete.
1 Methodology of crack mitigation and crack repairs(minimum and maximum size)works has
submitted to GEC separately for the review and approval(C853-P03-PIL-CI-MST-SRF-0007-
02)
h) Preparation of Construction joints
All Laitance shall be treated to expose the aggregate over the full depth to leave for
irregularities surface for the shear key.
Fittings assemble installation
Wall Steel reinforcement
Shuttering
k) Ladder Installation
The fixing/Installation detail of ladder will be followed accordiang to shop drawing approved
and as per manufacturer recommendation.
Mark the holes then drill and clean theme.
The recommended stainless steel through bolt for use for a Ladder to anchor shall be as per
manufacturer recommendation from approved source of the vendor from the PIL and material
submission shall be submitted to PIL for the approval in due time.
The embedment depths increase the flexibility concerning the thickness of the fastener
element and the depth of the drill hole.
When setting the through bolt at least until the thread end, hereby causing the expanded
portion of the bolt to bite into the concrete wall.
A request for inspection INR will be submitted for checking if approved the ladder is ready to
be used.
m) Construction of Plinth
Setting of the lines, levels and grades as per drawings is carried out prior to commencement
of works
Installation of reinforcement steel as per approved Bar Bending Schedule will be done by
approved nominated sub-contractor.
Then formworks will be formed in position and well supported by timber brace properly to
avoid movement.
The plinth constructed shall be approved by the supervision consultant, prior to proceed
subsequent work.
Once approved, proceed for the concreting. (concrete grade 40 SRC as per QCS 2014, Sec.
08, Part 04, Cl. 4.5.1.3 and/ or as per contract requirements). (Material Ref for concrete:C853-
P03-UIV-CE-MAT-0028)
1 The quality checks and test of concrete shall be as per QCS 2014, Section 05, Part 06,
Clause 6.8.2. Care should be observed during the depositing of concrete to prevent
segregations.
Concrete will be compacted using mechanical vibrators and let it set and cured.
Concreting during hot weather condition shall not be placed if the shade temperature exceeds
400C and; Maximum fresh concrete temperature shall not exceed 32°C unless construction
testing to verify a proposed concrete mixture will function satisfactorily at a concrete
temperature greater than 32°C. No concrete shall be placed if the concrete temperature is
above 35°C.
Curing of concrete to comply as per QCS 2014, Section 05, Part 10. Water curing with
hessian cloth covering the surface with a saturated absorptive and keeping it continuously wet
.
De- shuttering after concrete curing;
o The formwork shall be carefully stripped as per specification to avoid sudden shocks from
the removal of sections or vibration which might cause damage to the concrete.
p) Backfilling Works
Upon completion of the placement and light compaction of pipe surround, check will be carried
out thru an inspection request and approval by supervision consultant prior to backfilling.
Backfilling will be carried out according to contract requirements and QCS 2014, Section 8,
Part 2, Clause 2.3.
Stockpile shall be tested and approved suitable materials prior to use in backfilling trench
excavation.;
Once the stockpiled materials have been properly separated (numbered and flagged) and
tested, no further material shall be placed on the same tested materials. Another stockpiling
should be made and to be tested separately.
As soon as the work in manhole/ chambers has been accepted, approved and the places
around shall be cleared all debris, bricks and mortar droppings, backfilling procedure as
follow:
Fill with approved soil in layers not exceeding 150 mm compacted thickness.
The first layer which should be visually inspected and the second to the last layer shall be
inspected and tested using Nuclear Gauge Machine by the approved Third Party Laboratory.
Compaction test (FDT) will be carried out for the backfilling to obtain a minimum of 95% of the
Standard Proctor Maximum Dry Density of the materials (QCS 2014, Section 08, Part 02,
Clause 2.3.4).
No backfill layer shall be covered by the next layer of construction until it has been inspected,
tested approved by supervision consultant.
Each layer shall be levelled and rolled to achieve uniform compaction free from undulations,
soft spots and depressions.
Field Density Test (FDT) shall be one test per backfill layer for each structure (such as
manholes, chambers, and thrust blocks) unless otherwise directed and approved by
supervision consultant for 3 to 4 test in one manhole/chamber.
Any failure for the Test (FDT) which is not passing 95% MDD, the contractor shall do a
compaction again until achieve and fulfilled the required test.
q) Completed Work
When work is completed ensure that appropriate clean up and disposal measures have
been undertaken.
The Project/ Site/ Safety Engineers are responsible for ensuring dust control measures are
maintained throughout all stages of the site activity.
6 STAKE HOLDERS
Stake Holder Engineer will submit all required documents to authority to get the approval prior
to start the work on site.
Impact Assessment
With various site activities on site, relevant aspect and corresponding impacts to the environment
follows, such as:
Additional
Environmental Relevant Relevant control
Source/Activity mitigation
aspect permits procedure
measures
Air Emissions Field equipmentMME permit CEMP Generator sets
operation and vehicular Implementation will also be
traffic Regular secured by using
Stockpiles maintenance of the covered
Earthmoving and equipment’s and hoardings both
Construction associated vehicles. top and sides.
activities Speed Limit Regular dust
Cover the suppression
Stockpiles with through water
Green mesh or any tankers
suitable material. Speed Limit for
Vehicular traffic
Monitoring
Awareness
Training
Noise and Field equipment’sMME permit CEMP
Vibration operation Implementation Monitoring
Acoustic enclosure Awareness
for DG sets and Training
regular
maintenance of the
equipment’s and
vehicles.
Noise Monitoring
Will be ensured by
using sound level
meter and records
will be maintained
as and when noise
monitoring
conducted.
a. In accordance with the H&S Plan requirements; trained first aiders with First Aid Kits and,
trained fire wardens with available firefighting equipment will be provided and mobilized. A
List of trained first aider and fire warden will be displayed on site and regularly updated.
b. In the event of an emergency, a verbal alarm will be raised to notify any nearby personnel.
Workers will be instructed to evacuate and assemble at a designated assembly area and wait
for further instructions from supervisors.
c. In the event of any emergency situation that arises, the emergency services listed below
should be contacted. The company management should also immediately be notified by
contacting one of the individuals listed on the emergency contact list below:
EMERGENCY CONTACT NUMBERS
Ambulance, Fire, Police 999
Nearest Hospital (WAKRAH HOSPITAL) 40114444
JV PROJECT MANAGEMENT CONTACTS
Muhdi Noufal – Project Director 5582 4317
Jinoy Mathew – HSE Manager 5526 1548
11 QUALITY CONTROLS
The Inspection and Test Plan (ITP) for this Method Statement summarises various
characteristics to be checked. The concerned Site Engineer or General Foreman will be
responsible to ensure compliance for these operations and the site QA / QC Engineer will carry
out quality control checks and report the inspection results. The Inspection and Test Plan (ITP)
applicable to this work is attached.
All materials shall be inspected at time of delivery for damage and for compliance with
specifications.
Any material that is found to be damaged or not in accordance with the specification shall
be immediately replaced.
All materials shall be handled and stored as recommended by the manufacturer to prevent
damage and deterioration.
During storage, handling and transporting, every precaution shall be taken to prevent
damage to material. On delivery at site, material will be checked for any damage incurred
during transport and offloading to Storage area. Storage will be done in suitable and safe
locations (e.g. store yard or near site work area).
Storing of materials near site work area has the potential of congesting the site and could
affect the Health and Safety of operatives hence suitable storage facility for materials
storage will be provided at a safe distance from the work areas.
12 INTERFACES
a. Control measures will be ensured to be in place to protect the public, workforce and assets by
providing appropriate lighting, fencing, barricades, and lockable units. Adequate levels of
security including the use of trained security guards will be required. The UCC-INFJV will also
ensure appropriate warning signage is displayed and where appropriate safe pedestrian
walkways are identified and maintained.
b. Safety and security procedures will be implemented in accordance with the Qatar Work Zone
Traffic Management Guide and as required by the Department of Civil Defense and the police.
These shall be included, as a minimum, warning signs and lights, adequate barricades,
railings, road hump for reduced & control speed and other safeguards as required by the
nature and location of the work being undertaken.
c. Access to all properties will be maintained by adequately sign posted diversions, temporary
bridges or other facilities.
d. A night safety patrol & watchman (as applicable areas) will be assigned to ensure that all
barricades, lights and other protective apparatus are maintained during the hours of darkness.
e. Designated pedestrian routes will be clearly signed and with firm even surfaces that are free
from distractions. Slopes and steps will have anti-slip surfaces. Where the edges of pedestrian
routes are raised more than 1.2m above the surrounding level solid barriers will be provided at
each raised edge to prevent people from falling.
f. Temporary pedestrian bridges with hand railings or suitable ramp will be provided to facilitate
safe access/egress for occupied and under construction villas. Temporary electrical cables,
hoses or pipes shall be routed away from pedestrian access areas. Where such equipment
crosses pedestrian areas it will be located under the pedestrian area or over it at a height of at
least 5.2 m above the surface. Supports shall be provided at span of 3 meters. Where such
equipment is routed over a pedestrian area it will be clearly marked with warning signs.
g. Method statement and risk assessment will be provided for all demolition and dismantling
activities. Everyone involved in the work needs to know what measures are to be taken to
control the risks and a pre work briefing based on the method statement and job hazard
analysis will be given and recorded by the supervisor. Workers will be closely supervised to
ensure that the control measures required are put into practice. An exclusion zone will be
created around the demolition or dismantling area to prevent persons not directly involved with
the work activity around the work area gaining access. Any materials will not be allowed to fall
into any area where people are working or passing through. Protection screens, fences or
canopies may be needed to control falling objects
h. Approved Flood Mitigation and Rainy Season Plan shall be implemented effectively to ensure
safety of the public and occupiers.
i. Public Complains if any will be attended immediately and ensuring no re-occurrence by
implementing all necessary control measures are in place.
14 RESOURCE PLANNING
2. Materials
All materials shall comply with the project specification and relevant standards of QCS 2014
and approved list of materials in accordance with manufacturer’s recommendation.
a. BS 8110 Ready Mix Concrete (Grade OPC 40)
b. Screed and Blinding (SRC 20)
c. Water proofing Membrane system
d. Reinforcement steel
e. DI Cover and Frame or Aluminum Cover
f. Ladder
g. Approved fill materials
h. Epoxy Coating
15 REFERENCES
a. Work programmed
b. Qatar Construction Specification 2014
c. Ashghal Interim Advice Note
d. Permits
e. Drawings
f. Risk Assessment
g. Coordination Procedure
h. Work Checklist
i. Supervision Responsibilities
j. Inspection and Test Plan, etc...
k. Operation Specific Quality Checklist