This document outlines a footbridge construction project in Brgy. Basa, Trento, Agusan del Sur that was completed within 120 calendar days with a budget of Php 1.2 million funded partially by the 2017 Local Development Fund. The project involved constructing 157.8 meters of footbridge through a contract mode of implementation and achieved 100% physical accomplishment.
This document outlines a footbridge construction project in Brgy. Basa, Trento, Agusan del Sur that was completed within 120 calendar days with a budget of Php 1.2 million funded partially by the 2017 Local Development Fund. The project involved constructing 157.8 meters of footbridge through a contract mode of implementation and achieved 100% physical accomplishment.
This document outlines a footbridge construction project in Brgy. Basa, Trento, Agusan del Sur that was completed within 120 calendar days with a budget of Php 1.2 million funded partially by the 2017 Local Development Fund. The project involved constructing 157.8 meters of footbridge through a contract mode of implementation and achieved 100% physical accomplishment.
PROJECT TITLE :Construction of Footbridge ( Phase 2 and 3 )
LOCATION :Brgy. Basa, Trento, Agusandel Sur
PROJECT DESCRIPTION :Construction of 157.8mts. footbridge DURATION :120 CALENDAR DAYS PROJECT COST :Php 1,200,000.00 SOURCE OF FUND :20% 2017 LDF MODE OF IMPLEMENTATION :BY CONTRACT STATUS OF PROJECT :COMPLETED PHYSICAL ACCOMPLISHMENT :100%