IN FOCUS:

Pipe Wraps Issue 2, Summer 2013

Contents

WRAP IT UP WITH It’s a Wrap! 1

BELZONA Base material, reinforcement


sheet…

A major battle faced by asset owners and Composite repairs have gained greater
operators is to maintain the integrity of pipework. acceptance because they provide an
As main conduits of processed fluids, pipework engineered, durable and affordable solution
is susceptible to suffer corrosion, erosion which is easy to apply thus saving time.
or mechanical damage. (see Fig 1) If these Recognising these issues, Belzona Polymerics
problems are not addressed in time, there is a Ltd., a manufacturer of high performance
high probability that environmental and safety composites and industrial coatings, has
hazards, incidents and high costs can occur. developed cold curing wrap systems designed
The question of how to reduce the likelihood of for pipework repair.
these events in the long term represents a major
challenge for the industry. Cold curing composite wraps
Composite repair systems are composed of
International Standards
Historically, damaged pipework was repaired by a polymer binder and fibrous reinforcement.
cutting out the affected section and replacing it with The fibrous reinforcement provides structural Compliance 2
a new welded section. This requires production to strength to the polymer, which itself provides
be stopped and involves hot work which can lead corrosion resistance and adhesion to the The Italian Job 3
to metallurgical problems, hazards to the safety substrate.
of applicators and serious environmental issues if Oil and hydrocarbon transfer
risks are not carefully managed. (see Fig 2) Epoxies are convenient materials to be used as pipes repaired in service…
they have outstanding adhesion and excellent
Hence, coating and composites manufacturers mechanical properties compared to other
worldwide have been developing new non-metallic systems such as polyurethane,
repair technologies that avoid hot work and methacrylate, alkyd, vinyl and polyester-based
shutdowns, improve safety and protect assets polymers.
against corrosion for the long term.

Some like it cold 4


No hot work, no replacement, no
shutdown required…
Fig 1: Erosion, corrosion and pitting damage Fig 2: Stress cracking on a weld
Through wall damage resulting in leaks

CONTACT 1
www.belzona.com/wraps
BELZONA
IN FOCUS: Pipe Wraps
Application Procedure pipe defect that it is to be repaired. They also
The reinforcement sheet provides strength to the include applicator training and validation by the
INTERNATIONAL repair after being embedded within the polymer. manufacturer of the composite system.
STANDARDS Reinforcement sheet is usually made out of
COMPLIANCE carbon or glass fibres. It is important to point out
that glass fibres are less rigid, less costly and
easier to cut, design and apply in comparison to
ASME PCC-2 standard, “Repair of
carbon fibres.
Pressure Equipment and Piping”
Risks associated with welded repairs
This Standard provides methods
Welding would need to be carried out in a
for repair of equipment and
more controlled environment ensuring that the
piping within the scope of
atmosphere is free from hydrocarbons due to
ASME Pressure Technology
the explosion risk associated with hot work.
Codes and Standards after it has
Additionally, welding can lead to metallurgical
been placed in service. These Polymer binder
problems, such as stress cracking on a weld and
repair methods include relevant
localised corrosion.
design, fabrication, examination,
and testing practices and may
Benefits of wraps
be temporary or permanent,
Compared to that, wraps can be applied in situ
depending on the circumstances.
and online, they are cold curing and the pipework
The methods provided in this
will not require stress relieving. In addition, a
Standard address the repair
typical repair takes only a few hours to complete.
of components when repair is
deemed necessary based on
Finally, composite repairs can be considered as
appropriate inspection and flaw
a permanent type of repair system, international
assessment.
standards enable a design life of up to 20 years
with some systems, which, if there is no natural
Fibrous reinforcement
degradation mechanism, can be extended
following a suitable review.

System selection
Depending on the application situation different
base materials can be specified. Belzona 1831
(Super UW-Metal) is recommended when the
substrate is contaminated with water or oil.
Where chemical resistance is required, Belzona
4301 (Magma CR1 Hi-Build) offers outstanding
protection to a wide range and concentration of
chemicals. Depending on the size of repair area,
cure time may be extended with Belzona 1121
Completed application
(Super XL-Metal) or shortened with Belzona
1221 (Super E-Metal). Application to a hot
pipe (70°C – 150°C) requires a heat activated
material – Belzona 1251 (HA-Metal). Finally,
Belzona 1111 (Super Metal) may be suitable for
general applications where time, temperature,
contaminants and pipe contents are not an issue.

Compliant composite technologies


Compliant composite repairs differ from other
ISO/TS 24817 Standard,
traditional non-compliant repair systems mainly
“Petroleum, petrochemical and
in that they rely on a pre-qualified material,
natural gas industries-composite
pre-defined mathematical design and require Hot work is not necessary
repairs for pipework-qualification
validated application craftsmanship. These
and design, installation, testing
technologies experienced growth and acceptance
and inspection”
of use in the industrial sector after the publication
of two international standards in 2007. These are:
This Standard gives requirements
and recommendations for
• ISO/TS 24817 –Composite repairs for
the qualification and design, Hot work is not necessary
pipework – qualification and design,
installation, testing and inspection
installation, testing and inspection; and,
for the external application of
• ASME PCC-2 Article 4.1 –Non-metallic
composite repairs to corroded or
composite repair systems for pipelines and
damaged pipework used in the
pipework: high risk applications.
petroleum, petrochemical and
natural gas industries.
These govern all aspects related to composite Three-component composite repair after completion
repairs, from the pre-qualification of materials
and repair systems, to the design of a repair,
specific and ‘fit for purpose’ for the individual

CONTACT
2 Issue 2
BELZONA
IN FOCUS: Pipe Wraps

THE ITALIAN JOB BELZONA SUPERWRAP


Oil and hydrocarbon transfer pipes back to service
Permanent solution - engineered
Oil and hydrocarbon transfer pipes repaired and designed for conditions that
while in service. the repair in the pipework will
encounter throughout its 20-
Oil and hydrocarbon transfer pipes at a fuel storage year design life.
point company were suffering from external
corrosion, which lead to thin wall with minimum A downtime saving alternative to
thickness in some places reaching 1.4mm, welding. The cold curing ability
whereas the original wall thickness was 9.52mm. enables corrosion damaged
components to be repaired
The client required a composite repair compliant online within 24 hours.
to ISO/TS 24817 that could be completed
on both pipes within a limited timeframe and
without the need for shutdown. Applying polymer base

Belzona’s fully compliant SuperWrap system


was chosen and designed to Belzona’s most
stringent standards. The hydrocarbon pipe
required two layers of material, whereas the
oil transfer pipe was encapsulated using five
layers. Application took place in June 2013 and
the client was so satisfied with the outcome,
they ordered for similar repairs to be carried
out on the rest of the exposed pipework in the Compliant with ISO/TS 24817
following months. and ASME PCC-2 Standards
Applied in situ to pipes and
The expected service life of this application is a vessels, even in cases where
minimum of 10 years, which could be extended operating pressures are up to
Reinforcing with resin soaked wrap
250 bar.
during a 2023 inspection.
Allows applications to any
geometry of pipework, including
bends, tees and complex
geometry, and resists a wide
range of chemicals, oils and
process fluids.

Wetting out the substrate Smoothing out with a polymer base

SUPERWRAP
VALIDATED TRAINING
Belzona SuperWrap has been
used by many Oil and Gas,
Raising application standards Petrochemical and Power clients
worldwide and has been in
Belzona has state of the art training facilities around the world in which we
service for in excess of 35,000
guarantee that our training is delivered to the highest standards. These training hours.
courses have been developed following internationally recognised Engineering
Standards. In order to be specified and
SuperWrap courses are designed to provide the experienced applicator with the applied, the system must satisfy
theoretical and practical knowledge required to effectively and consistently apply a range of requirements. The
a SuperWrap system to the required standard to repair and protect clients’ assets. repair solution must be designed
and approved by a validated
Belzona offers SuperWrap Installer, Supervisor and Designer validation, ensuring designer and application carried
high application standards. This allows us to control the quality of every out by a validated installer
application to ensure the client receives an approved cost-effective solution with and controlled by a validated
a clear design life. supervisor.

@ To find out more, email globaltraining@belzona.com

CONTACT
Summer 2013 3
BELZONA
IN FOCUS: Pipe Wraps

BELZONA COLD
SOME LIKE IT COLD
CURING WRAPS SOLVE No hot work – no problem
PIPEWORK PROBLEMS
A wrap can be specified to suit Pipework in a refinery was suffering from thin
particular application situation and and through-wall defects, caused by severe
in-service conditions. external corrosion and pitting. Due to Health &
Safety hazards blasting to prepare the surface
»» Internal corrosion was not an option, and the client required a fast
»» External erosion, corrosion solution to this problem with minimal service
»» Pitting damage disruption. After all, every day of shutdown was
»» Thin wall defects costing them £1.5 million. Temporary wrap to holed area
»» Through wall defects
»» Leak sealing An application team worked without the
»» Damage to elbows and necessity for shutdown, hence production could
T-pieces continue. Where leaks were present, a plate was
»» Sealing flanges bonded using Belzona 1221 (Super E-Metal)
»» Resist aggressive chemicals over a holed area. Temporary wrap was created
and process fluids around that area using the same material. Then
the whole pipe was wrapped using Belzona
4301 (CR1), a material known for its excellent
chemical resistance properties.

Belzona 1831 (Super UW-Metal) wrap was


applied on top and also used to encapsulate the Belzona 4301 (CR1) for chemical resistance
adjacent flange. This clever system was chosen
for a reason. In case the metal underneath the
Belzona wrap continued to deteriorate and a
through-wall defect occurred, Belzona 4301
(CR1) would resist the contents of the pipe.
Belzona 1831 (Super UW-Metal) in turn adds
mechanical strength, while at the same time
protecting the pipework from external damage.

Application took only 3 days to complete; no hot


work, no replacement, no shutdown required.

Belzona 1831 (Super UW-Metal) final infill and wrap

Belzona is not just a product


manufacturer but strives to
provide a complete supply
and apply package through its
Global Distribution network.
This network was specifically
created to provide clients with
direct access to Belzona quality
products, specialist application
services, inspection services and
supervision. It is Belzona’s mission
to meet specialist repair and Damaged pipework Belzona 1831 (Super UV-Metal) flange sealing
maintenance needs in its target
industries and markets worldwide..

For more information, please contact your local Belzona representative:


Click here to find your local
Belzona Representative

02
Issue No.

Summer 2013

4 www.belzona.com/wraps

You might also like