Professional Documents
Culture Documents
Quantity Take Off Sheet Earhtworks
Quantity Take Off Sheet Earhtworks
Quantity Take Off Sheet Earhtworks
Dimension Est.
Item DESCRIPTION no. Length width height Qty Total Unit TOTAL
COLUMN FOOTING
F1
ALONG X 6 1.4 7 42 pcs
ALONG Y 6 1.4 7 42 pcs
total 84
using 6.00 m 84x1.4/5.6 21.00 pcs
16mm diax6.0m rsb
6
1.4
4.28571
waste 0.39998 21 pcs , 16mm dia x 0.40 m
F2
ALONG X 6 2.3 12 72
ALONG Y 6 2.3 12 72
144 pcs 2.3 m length
using 6 m 72
6
2.3
2.6087 2 72 pcs
16mm diax 6 m RSB
4.6 .
excess 1.4 72 pcs 1.4 m rsb
F3
ALONG X 6 2.1 11 66
ALONG Y 6 2.1 11 66
132 pcs 16mmx2.1 m
using 6 m rsb 66 pcs 16mmx6m Rsb
6
2.85714 66
4.2
excess 1.8 66 pcs16mmx1.8 m RSB
COLUMN
C-1 16mmx5.8 m RSB
LEVEL 1-2 8 5 6 48 pcs USE 6MRSB
Level 2-deck 8 3 6 48 PCS 16mmx3.2m RSB
0
ARCH
1 8.2 0.3 1.5 3.69 3.69 3.69
PCCP
1 50 7 0.15 52.5
sub.base 1 50 7 0.1 35 43.75
gravel base 1 50 7 0.1 35 43.75
87.5
Computation
Using Class B mixture
Materials
portland cement 8 0 0 240.00 -
screened sand 0.5 - -
screened gravel 1 - -
Labor
Mason
Common laborer
iii. REBARS
FOOTING
F1 - 34 UNITS 6 1.2 7.2 244.8
7 1 7 238 16 mm rebars
482.8
6 80.4667
ALLOWANCE FOR WASTE 5
4.02333333
ORDER 84.49
f3 6 2 4 48
12 1 4 48
96 16
36 16 mm rebars
COLUMN
Main post 16 6 2 32 32 16 mm rebars
ties 27 4 2 37.2414 37.241
arch 7 8 1 7 20 mm rebars
14 8 1 18.6667 16 mm rebars
stirrups 44 3.5 1 25.6667 10 mm rebars
C2 4 4.8 10 40 16 mm rebars
4 4.8 10 40 12 MM REBARS
TIES 25 1.2 10 51.7241
C3 4 4.8 8 32 16 mm rebars
4 4.8 8 32 12 MM REBARS
TIES 25 1.2 8 41.3793 10 MM rebars
SUMMMARY
20 MM 12
16 MM 396.67
12 MM 72
10 MM 67.046
arch
formworks
1/2 ord. plywood 12
column
c1 2 6 12
c2 18 1 18
web member
diagonal 2.15
4.72
4.24
6.2
6.5
7.87
31.68
two sides 2 31.68 63.36 63.36
king post 1 7.96 7.96 7.96
168.72 29.526 30
double 60 5.5mmx50mmx50mm < ba
JASON P. PENEYRA ESTRELLA L. PONCE DE LEON
Administrative Officer SUC VP & VP for Administration
Est. TOTAL
DESCRIPTION Unit Qty Price
I. Masonry works
CHB using 6" pcs 230 8
CHB using 4" pcs 560 8
Cement bags 83.00 150.00 12,450.00
Sand cu.m 1.00 400.00 400.00
Gravel cu.m 2.00 400.00 800.00
13,650.00
Laborer
TOTAL COST
Est. TOTAL
DESCRIPTION Unit Qty Price
BILL OF MATERIALS:
Labor cost
2.3 m length
m diax 6 m RSB
6mmx2.1 m
6mmx6m Rsb
mmx1.8 m RSB
16mmx5.8 m RSB
USE 6MRSB
16mmx3.2m RSB
Est.
Item DESCRIPTION no. Length width height Qty Total Unit price
I. FOOTINEXCAVATION
COLUMN FOOTING
F1 17 1 1 1.1 18.7
18.7
WALL FOOTING
WF1 1 28.3 0.3 0.6 5.094
WF-2 1 52.85 0.4 0.6 12.684
17.778
TOTAL FOOTING 63.6285
LABOR COST
1.72 Mhrs/cu.m 63.6285 1.72
2 laborer
no. of days
Labor cost
CONCRETE WORKS
FOOTING
F1 2 2.2 2.2 0.4 3.872
F2 10 1 1 0.25 2.5
F3 4 2 1 0.25 2
8.372
COLUMN
C1 2 1 1 4.5
less 2 0.6 0.6 0.72
3.78
C2 10 0.3 0.3 4.5 4.05
C3 8 0.3 0.3 4.5 3.24
11.07
ARCH
1 8.2 0.3 1.5 3.69 3.69 23.13
PCCP
1 50 7 0.15 52.5
sub.base 1 50 7 0.1 35 43.75
gravel base 1 50 7 0.1 35 43.75
87.5
Computation
Using Class B mixture
Materials
portland cement 8 63.6285 509.028 240.00
screened sand 0.5 63.63 31.81
screened gravel 1 63.63 63.63
Labor
Mason
Common laborer
iii. REBARS
FOOTING
F1 - 34 UNITS 6 1.2 7.2 244.8
7 1 7 238 16 mm rebars
482.8
6 80.466667
ALLOWANCE FOR WASTE
ORDER
6 2.2 2 26.4 4.551724 20 mm rebars
F2 12 1 10 120 20
f3 6 2 4 48
12 1 4 48
96 16
36 16 mm rebars
COLUMN
Main post 16 6 2 32 32 16 mm rebars
ties 27 4 2 37.2414 37.24138
arch 7 8 1 7 20 mm rebars
14 8 1 18.6667 16 mm rebars
stirrups 44 3.5 1 25.6667 10 mm rebars
C2 4 4.8 10 40 16 mm rebars
4 4.8 10 40 12 MM REBARS
TIES 25 1.2 10 51.7241
C3 4 4.8 8 32 16 mm rebars
4 4.8 8 32 12 MM REBARS
TIES 25 1.2 8 41.3793 10 MM rebars
SUMMMARY
20 MM 12
16 MM 396.6667
12 MM 72
10 MM 67.04598
arch
formworks
1/2 ord. plywood 12
column
c1 2 6 12
c2 18 1 18
Est.
DESCRIPTION Unit Qty Price
I. Excavation
2 Laborers days 12.00 170.00
II. Concreting
Cement bags 24.00 150.00
Sand cu.m 1.50 400.00
Gravel cu.m 3.00 400.00
TOTAL COST
Est.
DESCRIPTION Unit Qty Price
I. Masonry works
CHB using 6" pcs 230 8
CHB using 4" pcs 560 8
Cement bags 83.00 150.00
Sand cu.m 1.00 400.00
Gravel cu.m 2.00 400.00
Laborer
TOTAL COST
Est.
DESCRIPTION Unit Qty Price
BILL OF MATERIALS:
Labor cost
Labor cost
TOTAL COST
26-Jul-11
TOTAL
0.90
109.44
54.72
7.82
1.10
###
34
5 1.2 34 40.8 6.8 7
16 mm rebars 6 1 34 34 5.666667 6
81
5
4.02333333
84.49
20 mm rebars
16 mm rebars
16 mm rebars
20 mm rebars
16 mm rebars
10 mm rebars
16 mm rebars
12 MM REBARS
16 mm rebars
12 MM REBARS
10 MM rebars
Estimate No.
SHEET NO:
DATE :
TOTAL
2,040.00
2,040.00
3,600.00
600.00
1,200.00
5,400.00
780.00
630.00
1,080.00
360.00
300.00
405.00
405.00
180.00
400.05
750.00
5,290.05
10,140.00
3,240.00
330.00
13,710.00
504.00
504.00
450.00
330.00
252.00
300.00
2,340.00
28,780.05
11,219.9
40,000.0
. QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
Estimate No.
SHEET NO:
DATE :
TOTAL
12,450.00
400.00
800.00
13,650.00
80.00
960.00
1,050.00
2,090.00
270.00
360.00
410.00
20.00
180.00
270.00
660.00
810.00
3,120.00
6,100.00
21,840.00
. QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
Estimate No.
SHEET NO:
DATE :
TOTAL
-
-
4,600.00
350.00
1,050.00
300.00
1,100.00
1,100.00
8,500.00
1,155.00
1,155.00
5,900.00
150.00
616.00
6,666.00
462.00
462.00
16,783.0
. QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
QUANTITY TAKE OFF SHEET
Est.
Item DESCRIPTION no. Length width height Qty Total Unit TOTAL
FRONT 4"CHB 1 6 3 18
LESS w-1 1 1.8 1.4 2.52
w-2 1 1.2 1.4 1.68
net area 13.8 13.8
REAR
ALONG 4 M 6
0.6
10 4.00 40.00
7.02
SAY 8.00
TOTAL 16.00
rebars for beams
COLUMN REBARS
MAIN REBARS
C1 - 12 UNITS 6 4.85 72
USE 16MM x 6.0 m rebars 1.15 WASTE
LAT TIES
10 MX 6.0 M REBARS 1 50
4 100
REST 200
350 2 700
4300
18 3600
OUTER TIES -12 UNITS 28 1 28
STRAIGHT TIES 28 0.25 7
35
5.8333
12
70 10-MM REBRS
CIRCULAR COLUMN
C3 - 2 UNITS
Computation
Using Class B mixture
Materials
portland cement 8 0 0 240.00 -
screened sand 0.5 - -
screened gravel 1 - -
Labor
Mason
Common laborer
Est. TOTAL
DESCRIPTION Unit Qty Price
I. Excavation
2 Laborers days 12.00 170.00 2,040.00
2,040.00
II. Concreting
Cement bags 24.00 150.00 3,600.00
Sand cu.m 1.50 400.00 600.00
Gravel cu.m 3.00 400.00 1,200.00
5,400.00
Est. TOTAL
DESCRIPTION Unit Qty Price
I. Masonry works
CHB using 6" pcs 230 8
CHB using 4" pcs 560 8
Cement bags 83.00 150.00 ###
Sand cu.m 1.00 400.00 400.00
Gravel cu.m 2.00 400.00 800.00
###
Laborer
TOTAL COST
Project: Repair of SAKA building Estimator :ENGR.JOHNA LUANNE NAKPIL Estimate No.
LOCATION:SPCP Main campus, Aborlan SHEET NO:
ENGINEER:JOHN F. QUILLOPE Checked ENGR. JOHN QUILLOPE DATE :
CLASSIFICATION : Construction works
Est. TOTAL
DESCRIPTION Unit Qty Price
BILL OF MATERIALS:
Labor cost
The following features in this workbook are not supported by earlier versions of
Excel. These features may be lost or degraded when you save this workbook in
an earlier file format.
Some cells or styles in this workbook contain formatting that is not supported 3
by the selected file format. These formats will be converted to the closest format
available.
Republic of the Philippines
WESTERN PHILIPPINES UNIVERSITY
PHYSICAL PLANT OFFICE
Aborlan, Palawan
2.00 SITEWORKS
1.1 Removal of Existing Fence and other structures
Labor Cost
2 Carpenter days 4.00 300.00 2,400.00
4 Common laborers days 4.00 200.00 3,200.00
SUB-TOTAL (labor ) 5,600.00
1.5 Backfilling
4 common laborer days 5.00 220.00 4,400.00
Labor Cost
2 mason days 2.00 300.00 1,200.00
8 common laborer days 2.00 200.00 3,200.00
SUB-TOTAL (Labor ) 4,400.00
Equipment
transit mixer trip 1.48 6,000 8,895.00
concrete vibrator days 2.00 300 600.00
SUB-TOTAL (Equipment ) 9,495.00
SUB-TOTAL ( Concrete Pavement) 42,154.88
2.2 Gate columns , Arch and Fence post qty 25.50 cu.m
wall footing tie beam
2.2.1 Cast In-place concrete
Materials
Portland cement bags 229.50 240 55,080.00
G1 Gravel cu.m 25.50 1,000 25,500.00
screened sand cu.m 13.77 1,200 16,524.00
SUB-TOTAL (Materials) 97,104.00
Labor cost
2 Mason days 10.00 300.00 6,000.00
8 common laborer days 10.00 200.00 16,000.00
22,000.00
2.2.1 Steel Reinforcement
Materials
20 mm x 9 m dia rebars pcs 12.00 610 7,320.00
16 mm dia Rebars pcs 185.00 380 70,300.00
12 mm dia rebars pcs 92.00 230 21,160.00
10 mm dia rebars pcs 80.00 150 12,000.00
tie wire ga 16 ks 45.00 70 3,150.00
SUB-TOTAL (Materials) 113,930.00
Equipment Cost
1 bagger concrete mixer days 10.00 1,000 10,000.00
concrete vibrator days 10.00 300 3,000.00
sub-total (Equipment Cost) 13,000.00
4.3.3 Doors and window Jambs, base boards and fascia boards
QDE paint gal 2.00 520 1,040.00
oil tinting colors
8.4.5. Panel doors and built-in cabinets
Paint thinner gal 4.00 200 800.00
lacquer thinner gal 2.00 250 500.00
sanding sealer gal 1.00 550 550.00
assorted paint brush pcs 3.00 50 150.00
paint roller pcs 6.00 80 480.00
other necessary materials ls 1.00 3,000.00
SUB-TOTAL (Materials) 37,070.00
2.1.2. Contingency
15,000 3,000.00
5,000 2,000.00
3,000 500.00
5,600.00
10,000.00
2,325.00
300.00
8,748.92
4,400.00
43,887.50
5,000.00
5,000.00 10,000.00
80,261
37,754.88
4,400.00
9,495.00
97,104.00
22,000.00
113,930.00
28,482.50
37,710.00
7,542.00
10,000.00
3,000.00 13,000.00
50,390.00
24,000.00
1,760.00
5,000.00
5,960.00
2,384.00
63,200.00
6,320.00
1.00 SITEWORKS
1.1 Removal of Defective Corr. GI Roofing
Labor Cost
2 Carpenter days 2 300.00
2 Common laborers days 2 200.00
SUB-TOTAL (labor )
1.2 Removal of Defective Roofing Frames, ceiling frames, and other defective members
Labor Cost
2 Carpenter days 3 300.00
4 Common laborers days 3 200.00
SUB-TOTAL (labor )
Labor cost
2 common laborers days 4 200.00
SUB-TOTAL (Soil Poisoning and wood treatment)
TOTAL (SITEWORKS )
labor Cost
4 Carpenter days 12 300.00
Labor Cost
2 Carpenter days 3 300.00
SUB-TOTAL (Labor)
SUB-TOTAL (Partition )
4.3.3 Doors and window Jambs, base boards and fascia boards
QDE paint gal 2 520
oil tinting colors
8.4.5. Panel doors and built-in cabinets
Paint thinner gal 4 200
lacquer thinner gal 2 250
sanding sealer gal 1 550
assorted paint brush pcs 3 50
paint roller pcs 6 80
other necessary materials ls 1
SUB-TOTAL (Materials)
Labor Cost ls 1
Sub-total (Repainting )
1,200.00
800.00
2,000.00
members
1,800.00
2,400.00
4,200.00
10,500.00
800.00
11,300.00
17,500.00
9,600.00
300.00
2,250.00
1,000.00
1,200.00
3,000.00
17,350.00
1,800.00
1,200.00
3,000.00
20,350.00
37,700.00
14,370.00
7,200.00
7,200.00
1,500.00
30,270.00
14,400.00
44,670.00
29,400.00 12.5
330.00 6
29,730.00 12
7
10
12,000.00 4
12,000.00 4
41,730.00 55.5
4,750.00
75.00
4,825.00
1,800.00
1,800.00
6,625.00
4,400.00
4,400.00
300.00
8,800.00 257.64
12,000.00
350.00
300.00
1,040.00
800.00
500.00
550.00
150.00
480.00
3,000.00
37,070.00
12,974.50
50,044.50
98,399.50
4,200.00
975.00
780.00
975.00
700.00
700.00
8,330.00
2,500.00
10,830.00
3,200.00
800.00
700.00
1,000.00
2,200.00
160.00
1,000.00
9,060.00
2,000.00
2,000.00
11,060.00
11,060.00
4,320.00
1,600.00
320.00
1,320.00
1,000.00
4,240.00
1,200.00
1,200.00
5,440.00
5,440.00
225,599.50
22,559.95
22,559.95
248,159.5
QUANTITY TAKE- OFF SHEET
Dimension Est.
Item DESCRIPTION no. Length width height Qty Total
800 SITE CLEARING/EARTHWORKS
0
ARCH
1 8.2 0.3 1.5 3.69 3.69
PCCP
1 50 7 0.15 52.5
sub.base 1 50 7 0.1 35 43.75
gravel base 1 50 7 0.1 35 43.75
87.5
Computation
Using Class B mixture
Materials
portland cement 8 0 0
screened sand 0.5 - -
screened gravel 1 - -
Labor
Mason
Common laborer
iii. REBARS
FOOTING
F1 - 34 UNITS 6 1.2 7.2 244.8
7 1 7 238
482.8
6
ALLOWANCE FOR WASTE
ORDER
f3 6 2 4 48
12 1 4 48
96 16
36
COLUMN
Main post 16 6 2 32 32
ties 27 4 2 37.2414 37.241
arch 7 8 1 7
14 8 1 18.6667
stirrups 44 3.5 1 25.6667
C2 4 4.8 10 40
4 4.8 10 40
TIES 25 1.2 10 51.7241
C3 4 4.8 8 32
4 4.8 8 32
TIES 25 1.2 8 41.3793
SUMMMARY
20 MM 12
16 MM 396.67
12 MM 72
10 MM 67.046
arch
formworks
1/2 ord. plywood 12
column
c1 2 6 12
c2 18 1 18
Est.
DESCRIPTION Unit Qty
I. Excavation
2 Laborers days 12.00
II. Concreting
Cement bags 24.00
Sand cu.m 1.50
Gravel cu.m 3.00
Labor Cost
TOTAL COST
Est.
DESCRIPTION Unit Qty
I. Masonry works
CHB using 6" pcs 230
CHB using 4" pcs 560
Cement bags 83.00
Sand cu.m 1.00
Gravel cu.m 2.00
Laborer
TOTAL COST
Est.
DESCRIPTION Unit Qty
BILL OF MATERIALS:
Labor cost
Labor cost
Unit TOTAL
ls
l.m
l.m
isolated
combined
matt footing
cu.m
cu.m
cu.m 750.00
cu.m 1,200.00
3.69
240.00 -
34
5 1.2 34 40.8 6.8 7
16 mm rebars 6 1 34 34 5.666667 6
81
80.4667
5
4.02333333
ORDER 84.49
20 mm rebars
16 mm rebars
16 mm rebars
20 mm rebars
16 mm rebars
10 mm rebars
16 mm rebars
12 MM REBARS
16 mm rebars
12 MM REBARS
10 MM rebars
LUANNE NAKPIL Estimate No.
SHEET NO:
DATE :
TOTAL
Price
170.00 2,040.00
2,040.00
150.00 3,600.00
400.00 600.00
400.00 1,200.00
5,400.00
5.00 780.00
5.00 630.00
5.00 1,080.00
5.00 360.00
5.00 300.00
5.00 405.00
5.00 405.00
5.00 180.00
5.00 400.05
5.00 750.00
5,290.05
260.00 10,140.00
120.00 3,240.00
55.00 330.00
13,710.00
28.00 504.00
28.00 504.00
30.00 450.00
55.00 330.00
7.00 252.00
50.00 300.00
2,340.00
28,780.05
11,219.9
40,000.0
JOHN F. QUILLOPE
Physical Plant supervisor
TOTAL
Price
8
8
150.00 12,450.00
400.00 400.00
400.00 800.00
13,650.00
80.00 80.00
320.00 960.00
350.00 1,050.00
2,090.00
5.00 270.00
5.00 360.00
5.00 410.00
5.00 20.00
5.00 180.00
5.00 270.00
5.00 660.00
5.00 810.00
260.00 3,120.00
6,100.00
21,840.00
JOHN F. QUILLOPE
Physical Plant supervisor
TOTAL
Price
-
-
230.00 4,600.00
1.75 350.00
350.00 1,050.00
30.00 300.00
275.00 1,100.00
275.00 1,100.00
8,500.00
231.00 1,155.00
1,155.00
295.00 5,900.00
30.00 150.00
308.00 616.00
6,666.00
231.00 462.00
462.00
16,783.0
JOHN F. QUILLOPE
Physical Plant supervisor
Est.
Item
I. DESCRIPTION
FOOTINEXCAVATION no. Length width height Qty Total Unit price
CONCRETE WORKS
CLASS B 7.5 bags /cu.m
FOOTING
F1 16 1 1 0.25 4
4.00
FOOTING BEAM
ALONG ROW 5 1 10 0.2 0.25 0.5
ALONG ROW 4 (TB1) 1 3 0.2 0.25 0.15
ALONG ROW 3 2 3 0.2 0.25 0.3
ALONG ROW 2 1 4 0.2 0.25 0.2
1 3 0.2 0.25 0.15
ALONG ROW 1 1 2.3 0.2 0.25 0.115
ALONG ROW cr 1 1.75 0.2 0.25 0.0875
0
ALONG COLM A 1 5 0.2 0.25 0.25
ALONG COLM B 1 10.9 0.2 0.25 0.545
ALONG COLM 1 8.4 0.2 0.25 0.42
ALONG COLM C 1 8.4 0.2 0.25 0.42
1 2.5 0.2 0.25 0.125
TOTAL 3.2625
GRADE BEAM 1 3 0.2 0.25 0.15
Materials Qty 7.4125 order
Portland cement 55.594 bags 55 265 14,575.00
screened sand 3.7063 cu.m 4 950 3,800.00
screened gravel 7.4125 cu.m 8 1000 8,000.00
total material cost 26,375.00
4.47
ARCH
1 8.2 0.3 1.5 3.69 3.69 12.16
PCCP
1 50 7 0.15 52.5
sub.base 1 50 7 0.1 35 43.75
gravel base 1 50 7 0.1 35 43.75
87.50
Computation
Using Class B mixture
Materials
portland cement 8 63.6285 509.03 240.00
screened sand 0.5 63.63 31.81
screened gravel 1 63.63 63.63
Labor
Mason
Common laborer
Est.
DESCRIPTION Unit Qty Price
I. Excavation
2 Laborers days 12.00 170.00
II. Concreting
Cement bags 24.00 150.00
Sand cu.m 1.50 400.00
Gravel cu.m 3.00 400.00
Labor Cost
TOTAL COST
Est.
DESCRIPTION Unit Qty Price
I. Masonry works
CHB using 6" pcs 230 8
CHB using 4" pcs 560 8
Cement bags 83.00 150.00
Sand cu.m 1.00 400.00
Gravel cu.m 2.00 400.00
Laborer
TOTAL COST
Est.
DESCRIPTION Unit Qty Price
BILL OF MATERIALS:
Labor cost
Labor cost
2 carpenter days 2.00 231.00
TOTAL COST
26-Jul-11
TOTAL
122,166.72
Estimate No.
SHEET NO:
DATE :
TOTAL
2,040.00
2,040.00
3,600.00
600.00
1,200.00
5,400.00
780.00
630.00
1,080.00
360.00
300.00
405.00
405.00
180.00
400.05
750.00
5,290.05
10,140.00
3,240.00
330.00
13,710.00
504.00
504.00
450.00
330.00
252.00
300.00
2,340.00
28,780.05
11,219.9
40,000.0
QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
Estimate No.
SHEET NO:
DATE :
TOTAL
12,450.00
400.00
800.00
13,650.00
80.00
960.00
1,050.00
2,090.00
270.00
360.00
410.00
20.00
180.00
270.00
660.00
810.00
3,120.00
6,100.00
21,840.00
QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
Estimate No.
SHEET NO:
DATE :
TOTAL
-
-
4,600.00
350.00
1,050.00
300.00
1,100.00
1,100.00
8,500.00
1,155.00
1,155.00
5,900.00
150.00
616.00
6,666.00
462.00
462.00
16,783.0
QUILLOPE
lant supervisor
PONCE DE LEON
for Administration
Page 92
92
Page 93
labor equipment
#REF! #REF!
#REF!
93
Page 94
4,960,237.38
94
Page 95
5,787,382.21
5,787,382.21 520
95