Download as pdf or txt
Download as pdf or txt
You are on page 1of 28

FOR APPROVAL

C 02.10.18 G.J.PARK K.H.JUNG J.H.WOO FOR APPROVAL


B 31.05.18 G.J.PARK K.H.JUNG J.H.WOO FOR APPROVAL
A 23.02.18 G.J.PARK K.H.JUNG J.H.WOO FOR APPROVAL
Rev Date Prepared Checked Approved Details of Revision
Owner

VIETNAM ELECTRICITY
Owner’s Engineer

POWER ENGINEERING POWER ENGINEERING


CONSULTING JS COMPANY 3 CONSULTING JS COMPANY 4

Contractor

Sub-Supplier

Project Project Code


VT4E
VINH TAN 4 EXTENSION THERMAL POWER PLANT UAS Code
DN05

Date Unit Code


(DD.MM.YYYY)
Name Title P3
KKS Code
Prepared 02.10.2018 G.J.PARK QU
COMMISSIONING PROCEDURE Reg. No.
Checked 02.10.2018 K.H.JUNG
FOR 830001
Approved 02.10.2018 J.H.WOO SAMPLING SYSTEM Rev.
Dept. Field Service Engineering Team C
Document No. Page-No.
VT4E-DN05-P3QU-830001 13 Pages
EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

CONTENTS

1. INTRODUCTION .......................................................................................................... 3
1.1. Purpose........................................................................................................................................ 3
1.2. Safety Knowledge in Operation ................................................................................................ 3
1.3. System Boundary ....................................................................................................................... 3
1.4. System Description..................................................................................................................... 3
1.5. Major Components .................................................................................................................... 4
1.6. Reference Document .................................................................................................................. 5
1.7. Risks Assessment And Safety Prescription .............................................................................. 5
1.8. Commissioning Sequence & Revelant Schedule...................................................................... 6

2. COMMISSIONING REQUIREMENTS ...................................................................... 7

3. COMMISSIONING........................................................................................................ 8
3.1. Loop Test ..................................................................................................................................... 8
3.2. Interlock & Trip Test ............................................................................................................... 10
3.3. Sampling system Commissioning.............................................................................................11

4. ATTACHMENT ............................................................................................................ 13
Attachment 1. Inspection and Test Plan ......................................................................................... 13
Attachment 2. Commissioning Record Sheet For Loop Test ........................................................ 13
Attachment 3. Commissioning Record Sheet For Interlock & Trip Test .................................... 13
Attachment 4. Outstanding Works ................................................................................................. 13
Attachment 5. P&ID......................................................................................................................... 13

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 2 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

1. INTRODUCTION
1.1. Purpose
The purpose of this document is to define, describe, take records, certify, and validate all the
commissioning tests that have to be carried out on the Sampling System provide by DMPP on which for
for 1 x 600 MW Vinh Tan 4 Extension Thermal Power Plant Project.

1.2. Safety Knowledge in Operation


• Before the start of any testing it should be confirmed that all power supplies to the system have been
isolated or that they are in a known condition. The Commissioning engineer is responsible for the
safety of those personnel working of the system Check for the presence of harmful electrical or
mechanical potential energy before starting work.
C
• Fire is strictly prohibited on site, no smoking there must be a warning mark in hazardous area.
• Strictly comply with the safety and environmental protection regulations of local government.
• In order to ensure the reliable operation of every part of the system, strictly obey the corresponding
procedures.
• Have a regular maintenance for the long-time standby equipment
• Obey the relevant safety regulations of the power plant during commissioning all along. Ensure the
successful commissioning work.
• All personnel directly involved with the commissioning that will attend a kickoff safety meeting to
review for the dangers. Ensure that all personnel understand the process and the operation. Any
personnel involved in the commissioning have the authority to terminate the operation at any time,
if a serious problem or safety issue develops.
• During the duration of the test, withdraw all the workers working areas. Only testing team and the
supervisors should be inside of these areas.
• Safe working clearances must be at all times maintained.
• Appoint a person looks around the test area
• Warning tape and barrier around test area
• All works must be supervised by safety person who is qualified
• Passageway have to be kept clean and clear; never block access and egress routes
• Abide all the site regulations.
• Follow manufacturer’s safety instructions given in O&M manual or similar documents.
• Test equipment should be properly grounded according to the manufacturers’ instructions.
• Test equipment, including cables and test probes, shall be inspected before each use.
• All meters and probes shall be used within their rated voltage or current limits.
• After testing, all conditions normalize

1.3. System Boundary


The system boundary of the Sampling System is from each sample point to Drain Header. Detail marked
system boundary is attached to this procedure. (attachment 8. P&ID. VT4E-XG02- P3QU-120001)

1.4. System Description


The primary purpose of the Sampling System is to allow efficient operation, monitoring and
control of sampling, analyzing and chemical feed to facilitate optimum chemistry control.
Sample pressure and temperature is reduced and controlled by the sample system to provide

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 3 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

optimum sample conditions for continuous analysis, chemical feed control and grab sample
purposes.

1.5. Major Components


1) Chiller unit
Type Water cooled(HD-7.5W)

Manufactuer Hyundai Eng.

Heat removed 21075.6 Kcal/hr

Power consumption 7.5 kW

Refrigerant R-407C

2) Primary sample Cooler unit


Type Shell & Tube

Cooling water flow 2.3 m3/h (Each cooler)

Heat Removed 235929.5 kcal/hr

3) Secondary sample Cooler unit


Type Shell & Tube

Cooling water flow 1.2 m3/h (Each cooler)

Heat Removed 20673.7 kcal/hr

4) Hotwell sampling pump


Maker GRUNDFOS
Quantity 2
Type vertical multi-stage
Capacity 2.8 m3/hr
Total dynamic head 35 m
Power 0.55 kW

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 4 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

1.6. Reference Document


SL.
Document No. Document Title
No.
1 VT4E-XG02-P3QU-120001 P&ID for Sampling System (Attachment 5.)

2 VT4E-XS00-P3QU-120001 System Description for Sampling System

3 VT4E-YL00-P3QU-120001 Instrument List for Sampling System

4 VT4E-YL01-P3CCA-150011 DCS IO Database for Unit

5 VT4E-DN02-P3ZEN-840001 Commissioning Site Test Procedure for Motor Solo Run

6 VT4E-DD09-P3ZEN-040218 Method Statement For Loop Test

7 VT4E-DH01-P3ZEN-160218 ITP For Instrument Loop Test

8 VT4E-YT02-P3QU-120001 Instrument Data Sheet for Sampling System

1.7. Risks Assessment And Safety Prescription


The envisaged risks deriving from the operations included in this document are related to the hazards as
listed below. Before the activities, begin the Safety Manager will co-operate with the Commissioning
Manager to prepare the risk assessment. The document shall be attached to this procedure.
SL.
Activity Hazards
No.
Electrical Live Parts
3.1 Loop Test Noise
Tripping Hazards
Electrical Live Parts
Noise
3.2 Interlock Test High pressure Fluids
Hot surfaces
Tripping Hazards
Electrical Live Parts
Noise
3.3 Commissioing for Chiller Unit & SWAS High pressure Fluids
Hot surfaces
Tripping Hazards

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 5 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

1.8. Commissioning Sequence & Revelant Schedule

SWGR for
Electrical
Power Supply

MCC for Sampling System


Sampling system
Electrical Loop Test Interock Test Commissioning
Commissioing
Power Supply Completion

DCS System

Week 1 Week 2

1 2 3 4 5 6 7 1 2 3 4 5 6 7

SWGR for Electrical Power Supply

MCC for Electrical Power Supply

DCS System

3.1 Loop Test

3.2 Interlock Test


3.3 Sampling System
Commissioning
Sampling System Commissioning
Completion

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 6 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

2. COMMISSIONING REQUIREMENTS
Before start commissioning, ensure the follow activities are performed adequately.

1) Chiller Unit

SL.
Description
No.
Check all pipe and valves from the sampling point to the sample conditioning racks have been
1
connected as per the attached P&I diagram.
2 Check the chilled water inlet and outlet valves of chiller unit are opened.

3 Check the water tank level is maintained to normal by float valve.

4 Verify the refrigerant(R-407C GAS) has been charged in the chiller unit.

2) Sampling rack and analyzer

SL.
Description
No.
Check all pipe and valves from the sampling point to the sample conditioning racks have been
1
connected as per the attached P&I diagram.
2 Check the cooling water flow at outlet of sampling coolers(primary & secondary) is normal.
Adjust the control knob of each pressure regulating valve to the direction of decrease(close
3
position) until sampling steam or water flow is available.
Set all the alarm points after putting each analyzer in service and those are to be displayed
4
from the monitor.

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 7 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

3. COMMISSIONING
3.1. Loop Test
Loop Test purpose is to prove that the installed instrument functions correctly and is operational. Loop
test will be performed in accordance with ITP For Instrument Loop Test”.
SL.
Test Items Tag No.
No.
Analyzer

1 CC - SUPERHEATED STEAM P3QUB01CQ001

2 NA - SUPERHEATED STEAM P3QUB01CQ002

3 SILICA - SUPERHEATED STEAM P3QUB01CQ003

4 NA - HOT REHEATED STEAM P3QUB03CQ001

5 SILICA - HOT REHEATED STEAM P3QUB03CQ002

6 PH - HOT REHEATED STEAM P3QUB03CQ003

7 SC - HOT REHEATED STEAM P3QUB03CQ004

8 CC - HOT REHEATED STEAM P3QUB03CQ005

9 CC - SEPARATOR WATER P3HAG30CQ001

10 NA - ECONOMIZER INLET P3QUA60CQ001

11 SILICA - ECONOMIZER INLET P3QUA60CQ002

12 DO - ECONOMIZER INLET P3QUA60CQ003

13 PH - ECONOMIZER INLET P3QUA60CQ004

14 SC - ECONOMIZER INLET P3QUA60CQ005

15 CC - ECONOMIZER INLET P3QUA60CQ006

16 DO - DEAERATOR OUTLET P3QUA11CQ001

17 SILICA - CPP OUTLET P3QUC30CQ001

18 SC - CPP OUTLET P3QUC30CQ002

19 CC - CPP OUTLET P3QUC30CQ003

20 NA - CPP OUTLET P3QUC30CQ004

21 DO - CEP DISCHARGE P3QUC20CQ001

22 SC - CEP DISCHARGE P3QUC20CQ002

23 CC - CEP DISCHARGE P3QUC20CQ003

24 NA - CEP DISCHARGE P3QUC20CQ004

25 SC - MAKEUP WATER P3QUC40CQ001

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 8 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

26 NA - MAKEUP WATER P3QUC40CQ002

27 SILICA - MAKEUP WATER P3QUC40CQ003

28 CC - CONDENSER HOTWELLA P3QUC13CQ001

29 CC - CONDENSER HOTWELLB P3QUC14CQ001

Valve

30 Superheated Steam Inlet Solenoid Valve P3QUB01AA051

31 Hot Reheated Steam Inlet Solenoid Valve P3QUB03AA051

32 Separator water Inlet Solenoid Valve P3HAG30AA051

33 Economizer Inlet Solenoid Valve P3QUA60AA051

34 Deaerator Outlet Sample Inlet Solenoid Valve P3QUA11AA051

35 CPP Discharge Inlet Solenoid Valve P3QUC30AA051

36 CEP Discharge Inlet Solenoid Valve P3QUC20AA051

37 Make-up Water Inlet Solenoid Valve P3QUC40AA051

38 Condenser Hotwell A Inlet Solenoid Valve P3QUC13AA051

39 Condenser Hotwell B Inlet Solenoid Valve P3QUC14AA051

40 Close Cooling Water Inlet Solenoid Valve P3PGB13AA051

41 Superheated Steam Outlet Solenoid Valve P3QUB01AA052

42 Hot Reheated Steam Outlet Solenoid Valve P3QUB03AA052

43 Separator water Outlet Solenoid Valve P3HAG30AA052

44 Economizer Outlet Solenoid Valve P3QUA60AA052

45 Deaerator Outlet Outlet Solenoid Valve P3QUA11AA052

46 CPP Discharge Outlet Solenoid Valve P3QUC30AA052

47 CEP Discharge Outlet Solenoid Valve P3QUC20AA052

48 Make-up Water Outlet Solenoid Valve P3QUC40AA052

49 Condenser Hotwell A Outlet Solenoid Valve P3QUC13AA052

50 Condenser Hotwell B Outlet Solenoid Valve P3QUC14AA052

51 Close Cooling Water Outlet Solenoid Valve P3PGB13AA052

Switch

52 Superheated Steam Temp Indicating Switch P3QUB01CT501

53 Hot Reheated Steam Temp Indicating Switch P3QUB03CT501

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 9 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

54 Separator water Temp Indicating Switch P3HAG30CT501

55 Economizer Inlet Temp Indicating Switch P3QUA60CT501

56 Deaerator Outlet Temp Indicating Switch P3QUA11CT501

57 CPP Discharge Temp Indicating Switch P3QUC30CT501

58 CEP Discharge Temp Indicating Switch P3QUC20CT501

59 Make-up Water Temp Indicating Switch P3QUC40CT501

60 Condenser Hotwell A Temp Indicating Switch P3QUC13CT501

61 Condenser Hotwell B Temp Indicating Switch P3QUC14CT501

62 Close Cooling Water Temp Indicating Switch P3PGB13CT501

63 Superheated Steam Select Switch P3QUB01GS001

64 Hot Reheated Steam Select Switch P3QUB03GS001

65 Separator water Select Switch P3HAG30GS001

66 Economizer Inlet Select Switch P3QUA60GS001

67 Deaerator Outlet Select Switch P3QUA11GS001

68 CPP Discharge Select Switch P3QUC30GS001

69 CEP Discharge Select Switch P3QUC20GS001

70 Make-up Water Select Switch P3QUC40GS001

71 Condenser Hotwell A Select Switch P3QUC13GS001

72 Condenser Hotwell B Select Switch P3QUC14GS001

73 Close Cooling Water Select Switch P3PGB13GS001

3.2. Interlock & Trip Test


Interlock & Trip Test purpose is to verify the system protection control logic & loop, such as alarm, trip.
Perform the test through DCS and/or PLC simulation and record the status on Commissioning Record
Sheet. (Attachment 3. The test record sheet can be revised before interlock & trip test, according to the
latest control logic and loop.).

SL.
Test Items Tag No.
No.
1 Control Panel Unit P3QUY01GH001

2 Hotwell Sampling Pump 1 P3QUY01AP001

3 Hotwell Sampling Pump 2 P3QUY02AP001

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 10 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

3.3. Sampling system Commissioning


1) Commissioing for Chiller Unit
SL.
Description
No.
Prior to starting of chiller unit, verify the following preparations are met.
1) Chilled water supply and return valves are opened from chiller unit.
1 2) Water tank level is normal.
3) Refrigerant has been charged in compressor.
4) Chiller outlet water temperature has been set to 18 deg.C by temperature controller.
2 Check the inlet and outlet valves of secondary coolers are opened.

3 Start the circulation water pump by manual switch and stop momentary.

4 Check the pump direction of revolution and any abnormal conditions.

5 Restart the circulation water pump and check the cooling water flow.

6 Start the compressor by manual switch and stop momentary.

7 Check the any abnormal conditions.


Restart the compressor and observe the condenser fan has been started consequentially and
8
compressor loaded.
9 Leave the chiller unit until compressor has been unloaded condition.

10 Stop the compressor by manual switch.

11 Stop the circulating water pump by manual switch.

12 Observe chiller unit has been stopped.

2) Commissioning for Sampling Panel And Analyzer Panel

SL.
Description
No.
1 Verify the main and control power switches are “ON” position.
Verify all sample isolation valves at the sampling point has been closed.

2 Caution :
Never open the sample isolation valves without first checking to see that the coolant flow has
been established.
3 Check the cooling water flow at the sight glass of each cooler outlet is normal.

Blow down(flushing) works


The sample lines should be flushed before initial start-up of sampling and analysis system
remove the solids such as oxides of iron, grease, etc. as follows.

1) Open the root isolation valve.


- Superheated steam P3LBA10AA601/602/603/604, P3LBA20 AA601/602/603/604
- Hot Reheated steam P3LBB10AA601/602/603/604, P3LBB20 AA601/602/603/604
4
- Storage Vessel P3HAG30 AA601/602
- Economizer inlet P3LAB50AA605/606/607/608
- Deaerator P3QUA11/12/13 AA601
- CPP outlet P3QUC30AA601/602
- CEP outlet P3QUC20AA601/602
- Makeup water P3QUC40AA101

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 11 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

SL.
Description
No.
- Condenser hotwell P3QUC11AA358/601/602/603/604,
P3QUC12AA358/601/602/603/604
2) Verify the sample isolation valves for sample inlet are closed.
3) Open the bulkhead type union one by one, and connect temporary hoses.
4) Open the sample isolation valves for blow down with checking the flushing medium flow to
waste one by one.
5) After appropriate time(5-10 minutes), close the sample isolation valves for blow down.
6) Close the bulkhead type union for each sampling lines.
7) This blow down works should be done only one line at a time.
Normalize the sampling system after flushing each sampling line.
1) Open the sample isolation valves for sample inlet.
2) Open the sample isolation valves for blow down.
3) Adjust the pressure reducing valve to set the sample line flow as per the specified flow rate.
4) Watch the pressure and temperature and indicators on the panel carefully.

If the pressure reaches their maximum allowable pressure(60 psig = 4.1barg) close the sample
isolation valves for sample inlet immediately. (normal 1.0~2.5 barg)
5

5) Adjust the sample flow to give the correct flow to each analyzer and grab sample.
• PH 150~200 cc/Min.
• Conductivity(CC & SC) 150~200 cc/Min.
• Dissolved oxygen 150~200 cc/Min.
• Sodium 150~200 cc/Min.
• Silica 150~200 cc/Min

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 12 of 13


EVN Vinh Tan 4 Extension Thermal Power Project
DMPP Consortium

4. ATTACHMENT
Attachment 1. Inspection and Test Plan
Attachment 2. Commissioning Record Sheet For Loop Test
Attachment 3. Commissioning Record Sheet For Interlock & Trip Test
Attachment 4. Outstanding Works
Attachment 5. P&ID

DOC.NO. VT4E-DN05- P3QU-830001 Rev. C 13 of 13


Attachment 1. Inspection and Test Plan

VIETNAM
ELECTRICITY Inspection and Test Plan DMPP

Inspection & Test Activities


Description of Applicable
No. Remark
Inspection/Test Documentation
DMPP PMB/C

VT4E-DH01-
1 Loop Test W W
P3ZEN-160218

Interlock and Trip This Document,


2 W W
Test Section 3.2

Abbreviation :
S: Surveillance R: Report Review W: Witness Inspection H: Holding Inspection
EVN/VTTPM Vinh Tan 4 Extension Thermal Power Plant
DMPP Consortium

Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR NO.
BINARY LOOP TEST REPORT
CONTRACTOR DMPP (LS, PS, TS, ….etc) DATE

SUBCONTRACTOR PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

DCS/PLC Graphic Checked


NO KKS TAG Description TYPE NO/NC Opend Closed Remark
Yes No
Superheated Steam SampleTemp Indicating
1 P3QUB01CT501
Switch
Hot Reheated Steam Sample Temp
2 P3QUB03CT501
Indicating Switch
Separator water Sample Temp Indicating
3 P3HAG30CT501
Switch
4 P3QUA60CT501 Economizer SampleTemp Indicating Switch

5 P3QUA11CT501 Deaerator Outlet Temp Indicating Switch

6 P3QUC30CT501 CPP Discharge Temp Indicating Switch

7 P3QUC20CT501 CEP Discharge Temp Indicating Switch

8 P3QUC40CT501 Make-up Water Temp Indicating Switch


Condenser Hotwell A Temp Indicating
9 P3QUC13CT501
Switch
Condenser Hotwell B Temp Indicating
10 P3QUC14CT501
Switch
Close Cooling Water Temp Indicating
11 P3PGB13CT501
Switch
Verified/Approved By:
Checked By: Owner's Representative Owner's Engineer Contractor
(PMB) (PMC) (DMPP) SUB-CONTRACTOR
Signature

Name

Date

VT4E-PH01-P3ZEN-160218 Rev. A 5 of 5
Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR NO.
BINARY LOOP TEST REPORT
CONTRACTOR DMPP (LS, PS, TS, ….etc) DATE

SUBCONTRACTOR PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

DCS/PLC Graphic Checked


NO KKS TAG Description TYPE NO/NC Opend Closed Remark
Yes No

12 P3QUB01GS001 Superheated Steam Select Switch

13 P3QUB03GS001 Hot Reheated Steam Select Switch

14 P3HAG30GS001 Separator water Sample Select Switch

15 P3QUA60GS001 Economizer Outlet Select Switch

16 P3QUA11GS001 Deaerator Outlet Select Switch

17 P3QUC30GS001 CPP Discharge Select Switch

18 P3QUC20GS001 CEP Discharge Select Switch

19 P3QUC40GS001 Make-up WaterSelect Switch

20 P3QUC13GS001 Condenser Hotwell A Select Switch

21 P3QUC14GS001 Condenser Hotwell B Select Switch

22 P3PGB13GS001 Close Cooling Water Select Switch

Verified/Approved By:
Checked By: Owner's Representative Owner's Engineer Contractor
(PMB) (PMC) (DMPP) SUB-CONTRACTOR
Signature

Name

Date
Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR NO.

CONTRACTOR DMPP ON-OFF VALVE LOOP TEST REPORT DATE

SUBCONTRACTOR PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

Command(DO) Feedback(DI) DCS/PLC Graphic Checked


NO KKS TAG Description NO/NC PA(DI) ENGD(DI) Remark
Open Close Opend Closed Yes No
Superheated Steam Inlet Solenoid
1 P3QUB01AA051
Valve
Hot Reheated Steam Inlet Solenoid
2 P3QUB03AA051
Valve
Separator water Inlet Solenoid
3 P3HAG30AA051
Valve

4 P3QUA60AA051 Economizer Inlet Solenoid Valve

Deaerator Outlet Inlet Solenoid


5 P3QUA11AA051
Valve

6 P3QUC30AA051 CPP Discharge Inlet Solenoid Valve

7 P3QUC20AA051 CEP Discharge Inlet Solenoid Valve

8 P3QUC40AA051 Make-up Water Inlet Solenoid Valve

Condenser Hotwell A Inlet Solenoid


9 P3QUC13AA051
Valve
Condenser Hotwell B Inlet Solenoid
10 P3QUC14AA051
Valve
Close Cooling Water Inlet Solenoid
11 P3PGB13AA051
Valve

Verified/Approved By:
Checked By:
Owner's Representative Owner's Engineer Contractor
SUB-CONTRATOR
(PMB) (PMC) (DMPP)

Signature

Name

Date

Note : PA : Power Available, ENGD : ENGAGED


Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR NO.

CONTRACTOR DMPP ON-OFF VALVE LOOP TEST REPORT DATE

SUBCONTRACTOR PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

Command(DO) Feedback(DI) DCS/PLC Graphic Checked


NO KKS TAG Description NO/NC PA(DI) ENGD(DI) Remark
Open Close Opend Closed Yes No
Superheated Steam Outlet Solenoid
12 P3QUB01AA052
Valve
Hot Reheated Steam Outlet
13 P3QUB03AA052
Solenoid Valve
Separator water Outlet Solenoid
14 P3HAG30AA052
Valve

15 P3QUA60AA052 Economizer Outlet Solenoid Valve

Deaerator Outlet Outlet Solenoid


16 P3QUA11AA052
Valve
CPP Discharge Outlet Solenoid
17 P3QUC30AA052
Valve
CEP Discharge Outlet Solenoid
18 P3QUC20AA052
Valve
Make-up Water Outlet Solenoid
19 P3QUC40AA052
Valve
Condenser Hotwell A Outlet
20 P3QUC13AA052
Solenoid Valve
Condenser Hotwell B Outlet
21 P3QUC14AA052
Solenoid Valve
Close Cooling Water Outlet
22 P3PGB13AA052
Solenoid Valve

Verified/Approved By:
Checked By:
Owner's Representative Owner's Engineer Contractor
SUB-CONTRATOR
(PMB) (PMC) (DMPP)

Signature

Name

Date

Note : PA : Power Available, ENGD : ENGAGED


Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR No.
ANALOG LOOP TEST REPORT
CONTRACTOR DMPP (PIT, DPIT, LIT,TT …etc ) DATE

SUBCONTRACTOR DELTA PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

Signal/ DCS/PLC
NO KKS TAG Description Type 0% 25% 50% 75% 100% 75% 50% 25% 0% Unit/Range Remark
Range INDICATION

1 P3QUB01CQ001XQ01 CC - SUPERHEATED STEAM

2 P3QUB01CQ002XQ01 NA - SUPERHEATED STEAM

SILICA - SUPERHEATED
3 P3QUB01CQ003XQ01
STEAM

4 P3QUB03CQ001XQ01 NA - HOT REHEATED STEAM

5 P3QUB03CQ002XQ01 SILICA - HOT REHEATED STEAM

6 P3QUB03CQ003XQ01 PH - HOT REHEATED STEAM

7 P3QUB03CQ004XQ01 SC - HOT REHEATED STEAM

8 P3QUB03CQ005XQ01 CC - HOT REHEATED STEAM

9 P3HAG30CQ001XQ01 CC - SEPARATOR WATER

10 P3QUA60CQ001XQ01 NA - ECONOMIZER INLET

11 P3QUA60CQ002XQ01 SILICA - ECONOMIZER INLET

12 P3QUA60CQ003XQ01 DO - ECONOMIZER INLET

Verified/Approved By:
Checked By: Owner's Representative Owner's Engineer Contractor
SUB-CONTRACTOR
(PMB) (PMC) (DMPP)
Signature

Name

Date
Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR No.
ANALOG LOOP TEST REPORT
CONTRACTOR DMPP (PIT, DPIT, LIT,TT …etc ) DATE

SUBCONTRACTOR DELTA PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

Signal/ DCS/PLC
NO KKS TAG Description Type 0% 25% 50% 75% 100% 75% 50% 25% 0% Unit/Range Remark
Range INDICATION

13 P3QUA60CQ004XQ01 PH - ECONOMIZER INLET

14 P3QUA60CQ005XQ01 SC - ECONOMIZER INLET

15 P3QUA60CQ006XQ01 CC - ECONOMIZER INLET

16 P3QUA11CQ001XQ01 DO - DEAERATOR OUTLET

17 P3QUC30CQ001XQ01 SILICA - CPP OUTLET

18 P3QUC30CQ002XQ01 SC - CPP OUTLET

19 P3QUC30CQ003XQ01 CC - CPP OUTLET

20 P3QUC30CQ004XQ01 NA - CPP OUTLET

21 P3QUC20CQ001XQ01 DO - CEP DISCHARGE

22 P3QUC20CQ002XQ01 SC - CEP DISCHARGE

23 P3QUC20CQ003XQ01 CC - CEP DISCHARGE

24 P3QUC20CQ004XQ01 NA - CEP DISCHARGE

Verified/Approved By:
Checked By: Owner's Representative Owner's Engineer Contractor
SUB-CONTRACTOR
(PMB) (PMC) (DMPP)
Signature

Name

Date
Attachment 2. Commissioning Record Sheet for Loop Test

OWNER IR No.
ANALOG LOOP TEST REPORT
CONTRACTOR DMPP (PIT, DPIT, LIT,TT …etc ) DATE

SUBCONTRACTOR DELTA PAGE

PROJECT NAME VINH TAN4 EXTENSION THERMAL POWER PLANT UNIT NO.

INFORMATION DATA

Signal/ DCS/PLC
NO KKS TAG Description Type 0% 25% 50% 75% 100% 75% 50% 25% 0% Unit/Range Remark
Range INDICATION

25 P3QUC40CQ001XQ01 SC - MAKEUP WATER

26 P3QUC40CQ002XQ01 NA - MAKEUP WATER

27 P3QUC40CQ003XQ01 SILICA - MAKEUP WATER

CC - CONDENSER
28 P3QUC13CQ001XQ01
HOTWELLA
CC - CONDENSER
29 P3QUC14CQ001XQ01
HOTWELLB

30

31

32

33

34

35

36

Verified/Approved By:
Checked By: Owner's Representative Owner's Engineer Contractor
SUB-CONTRACTOR
(PMB) (PMC) (DMPP)
Signature

Name

Date
Attachment3. Commissioning Record Sheet For Interlock & Trip Test

COMMISSIONING RECORD SHEET


VIETNAM ELECTRICITY DMPP
FOR INTERLOCK & TRIP TEST

STATION : 1 x 600MW VINHTAN 4 EXTENSION THERMAL POWER PLANT UNIT :


DWG NO. : VT4E-YF00-P3CBA-150161 LOCATION : BOP
PLANT ITEM : HOTWELL SAMPLING PUMP A(P3QUY01AP001) DATE :

NO. DESCRIPTION TAG NO. ACTION VALUE RESULT


1 MANUAL - MANUAL START/STOP OPERATION PASS / FAIL

AND GATE (+) OR GATE (/)


NO. DESCRIPTION TAG NO. ACTION VALUE RESULT
- (1) HOTWELL SAMPLING PUMP-A NOT TAG OUT PASS/FAIL
P3QUY01AP001 XB11 +(3) HOTWELL SAMPLING PUMP-A BREAKER READY PASS/FAIL
1 START PERMISSIVE P3QUY01AP001 XN42 +(4) HOTWELL SAMPLING PUMP-A REMOTE SELECTED PASS/FAIL
P3QUY01AP001 XN02 +(5) HOTWELL SAMPLING PUMP-A NOT FAULT PASS/FAIL
- (1) (NOT)CONDR LEVEL LO -300mm PASS/FAIL
2 STOP PERMISSIVE - NA
3 AUTO START - NA
4 AUTO STOP - NA
PROTECTION NA
5 -
CONDITION TO START

PROTECTION NA
6 -
CONDITION TO TRIP

COMMENT

COMPANY NAME SIGNATURE DATE

DMPP

PMC

PMB
Attachment3. Commissioning Record Sheet For Interlock & Trip Test

COMMISSIONING RECORD SHEET


VIETNAM ELECTRICITY DMPP
FOR INTERLOCK & TRIP TEST

STATION : 1 x 600MW VINHTAN 4 EXTENSION THERMAL POWER PLANT UNIT :


DWG NO. : VT4E-YF00-P3CBA-150161 LOCATION : BOP
PLANT ITEM : HOTWELL SAMPLING PUMP B(P3QUY02AP001) DATE :

NO. DESCRIPTION TAG NO. ACTION VALUE RESULT


1 MANUAL - MANUAL START/STOP OPERATION PASS / FAIL

AND GATE (+) OR GATE (/)


NO. DESCRIPTION TAG NO. ACTION VALUE RESULT
- (1) HOTWELL SAMPLING PUMP-B NOT TAG OUT PASS/FAIL
P3QUY02AP001 XB11 +(3) HOTWELL SAMPLING PUMP-B BREAKER READY PASS/FAIL
1 START PERMISSIVE P3QUY02AP001 XN42 +(4) HOTWELL SAMPLING PUMP-B REMOTE SELECTED PASS/FAIL
P3QUY02AP001 XN02 +(5) HOTWELL SAMPLING PUMP-B NOT FAULT PASS/FAIL
- (1) (NOT)CONDR LEVEL LO -300mm PASS/FAIL
2 STOP PERMISSIVE - NA
3 AUTO START - NA
4 AUTO STOP - NA
PROTECTION NA
5 -
CONDITION TO START

PROTECTION NA
6 -
CONDITION TO TRIP

COMMENT

COMPANY NAME SIGNATURE DATE

DMPP

PMC

PMB
Attachment3. Commissioning Record Sheet For Interlock & Trip Test

COMMISSIONING RECORD SHEET


VIETNAM ELECTRICITY DMPP
FOR INTERLOCK & TRIP TEST

STATION : 1 x 600MW VINHTAN 4 EXTENSION THERMAL POWER PLANT UNIT :


DWG NO. : VT4E-YF00-P3CBA-150161 LOCATION : BOP
PLANT ITEM : SWAS GROUP MASTER(LCP INTERFACE) DATE :

AND GATE (+) OR GATE (/)


NO. DESCRIPTION TAG NO. ACTION VALUE RESULT
1 SET AUTO NA
2 SET MANUAL NA
(1) (NOT) SWAS GROUP 2 FAULT
START
3 - +(2)SWAS GROUP REMOTE PASS/FAIL
PERMISSIVE
+(3)(NOT) SWAS GROUP RUNNING
STOP (1) SWAS GROUP REMOTE
4 - PASS/FAIL
PERMISSIVE +(2)SWAS GROUP RUNNING
5 AUTO START - NA
6 AUTO STOP - NA

COMMENT

COMPANY NAME SIGNATURE DATE

DMPP

PMC

PMB
Attachment 4. Outstanding Works

VIETNAM
ELECTRICITY Outstanding Works DMPP

Outstanding Works List

No Description

Date Representative Name Signature

DMPP

PMB

PMC

Outstanding Works Clearance

No Date DMPP PMB PMC

Final Clearance

Date Representative Name Signature

DMPP

PMB

PMC
Attachment 5. P&ID System Boundary

VIETNAM ELECTRICITY

POWER ENGINEERING POWER ENGINEERING


CONSULTING JS COMPANY 3 CONSULTING JS COMPANY 4

VINH TAN 4 EXTENSION


THERMAL POWER PLANT PROJECT
(600MW x 1 unit)
VIETNAM ELECTRICITY

POWER ENGINEERING POWER ENGINEERING


CONSULTING JS COMPANY 3 CONSULTING JS COMPANY 4

VINH TAN 4 EXTENSION


THERMAL POWER PLANT PROJECT
(600MW x 1 unit)
VIETNAM ELECTRICITY

POWER ENGINEERING POWER ENGINEERING


CONSULTING JS COMPANY 3 CONSULTING JS COMPANY 4

VINH TAN 4 EXTENSION


THERMAL POWER PLANT PROJECT
(600MW x 1 unit)

You might also like