No Jenis Pengujian Sudah Dilaksanakan Belum Dilaksanakan KETERANGAN

1 Individual Test MTU


Circuit Breaker
Visual + Kontruksi
Earthing Resistance Main Equipment
Resistansi Isolasi
Main Contak Resistance Measurment
Witstand Voltage Test
Time Main Contak Measurment
- Colsing Time
- Opening Time -1
- Opening Time - 2
Purity SF6 Test

Auxilliary Operating Minimum Voltage


- Closing Coil
- Tripping Coil -1

Indication Function
- Local/Remote Mode
- Indikasi Close & Open
- Loss of Spring Energi
- SF6 1st Stage
- SF6 2nd Stage
- TCS1 & TCS2
- Poles Discrapancy Test
- Supply Motor Fault
- Interlock to Other Equipment

Pemisah Bus-1
Visual + Konstruksi
Earthing Resistance Main Equipment
Resistansi Isolasi Mesurement
Main Contak Resistance Measurement
Time Measurement
- Opening Time
- Closing Time
Indication & Function
- Local/remote mode
- Supply motor fault
- Interlock to other Equipment

Pemisah Bus-2
Visual + Konstruksi
Earthing resistance main equipemnt
Resistansi Isolasi mesurment
Main Contak resistance measurment
Time Measurment
No Jenis Pengujian Sudah Dilaksanakan Belum Dilaksanakan KETERANGAN
- Opening Time
- Closing Time
Indication & Function
- Local/remote mode
- Supply motor fault
- Interlock to other Equipment

Pemisah Line
Visual + Konstruksi
Earthing resistance main equipemnt
Resistansi Isolasi mesurment
Main Contak resistance measurment
Time Measurment
- Opening Time
- Closing Time
Indication & Function
- Local/remote mode
- Supply motor fault
- Interlock to other Equipment

Pemisah Tanah
Visual + Konstruksi
Earthing Resistance measurment
Indikasi Close open
Indication & Function
- Local/remote mode
- Supply motor fault
- Interlock to other Equipment

Aresster
Visual + Konstruksi
Earthing Resistance measurment
Resistansi Isolasi
Operation function counter

Voltage Transformer
Visual + Konstruksi
Earthing Resistance measurment
Resistansi Isolasi
Tangen Delta
Ratio
Resistance secundary circuit
Burden secundary circuit to equpiment
Indication & Protection
- MCB VT Open
No Jenis Pengujian Sudah Dilaksanakan Belum Dilaksanakan KETERANGAN
Current Transformer
Visual + Kontruksi
Earthing Resistance measurment
Resistansi Iolasi
Tangen Delta
Ratio
Secundary windding DC resistance
DC Resistance secundary circuit to equipment
Burden secundary circuit to equpiment
Knee point mesurment each secunder coil

2 Stability Test
Differential Relays
- Conditio Stabil & Unstabil
- REF stabil & Unstabil
3 Busbar Protection
- Visual & Contruction
- Individual test
Stability test of bus bar protection
- stabil condition
- unstabil condition
4 Telecommunication
Teleprotection
Function Multiplexer
Signal send & Recive
Data
Voice ( PAX & PABX) Equipment
5 Relay
Differential Protection relay
Visual+ Contruction
Calcualtion setting
Functon & Indication
- Trip Sequnce
- Alarm Sequnce
- Watch dog ( internal relay fault )
OCR & GFR Protection
Visual+ Contruction
Calcualtion setting
Carakteristik test all schame
Functon & Indication
- Trip Sequnce
- Alarm Sequnce
- Watch dog ( internal relay fault )
Restricted relay protection
Visual+ Contruction
Calcualtion setting
No Jenis Pengujian Sudah Dilaksanakan Belum Dilaksanakan KETERANGAN

Charactireistic test/individual test


Functon & Indication
- Trip Sequnce
- Alarm Sequnce
- Watch dog ( internal relay fault )
Standbay earth fault ( SEF/SBEF)
Visual+ Contruction
Calcualtion setting
Charactireistic test/individual test
Functon & Indication
- Trip Sequnce
- Alarm Sequnce
- Watch dog ( internal relay fault )
Automatic Voltage Regulator
Visual + Contruction
Individual at site point
Sequence function test
Relay chek syncron
Visual + Contruction
Individual at site point
Sequence function test
Under Voltage relay
Visual + Contruction
Individual at site point
Sequence function test
Under frequenycy rela relay
Visual + Contruction
Individual at site point
Sequnce function test (load sheding)
Breaker Management (Recloser)
Visual + Contruction
Individual at site point
Function test
- Scheme test mode