2007-010 RH120E Cat18 Ladeluftleitung 01
2007-010 RH120E Cat18 Ladeluftleitung 01
Karl−Funke−Str. 36
44149 Dortmund
Germany
Tel. +49 (0) 231 / 922−3
Fax +49 (0) 231 / 922−5005
ISSUE
Air tightness of air charge system is not ensured; dust could enter the system.
This could lead to a total damage of the engine.
ACTION
Modification kit needs to be installed.
Required tools:
• hand tools
• torque wrench for 7,5 Nm
Required torques:
• constant torque hose clamp 7,5 Nm
(Pos. 3 / type teebolt and
spring)
Welding:
• welding of nozzle (Fig. 1, 5, Pos. 1) onto radiator
material: ALMG3MN
• Electrodes: DIN 1732 EL-AlSi5
. DIN EN ISO 18273 AlSi5
. AWS A 5.3 E4043
Ø 2,5 x 250
examples: a) ESAB OK96.40 .
. b) Castolin Eutectic 2103
• Electrodes need to be dried for 1 hour at 80° C prior use
• Preheating for welding not necessary
Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 7: Location of plate for bracket Pos. 10/11/12/13 – to be welded onto frame