Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

CIVIL NO.

97-4562(JBS)
United States District Court, D. New Jersey

Data Systems Analysts, Inc. v. the Netplex Group, Inc.


Decided Aug 2, 2000

CIVIL NO. 97-4562(JBS). it is impossible to predict the probable outcome of


future negotiations, had they occurred.
August 2, 2000.
Accordingly, plaintiff's summary judgment motion
will be granted, and defendants' second
MEMORANDUM OPINION counterclaim will be dismissed.
2 Although defendants' brief characterizes
SIMANDLE, District Judge.
the second counterclaim as stating a claim
This matter comes before the Court on plaintiff's for breach of the development agreement
motion for partial summary judgment as against itself ( see Def. Br. at 6), the Court finds
the defendants' second counterclaim, pursuant to that the wording of defendants' second

Rule 56(c), Fed.R.Civ.P.1 With this counterclaim, counterclaim ("[plaintiff] breached its
obligations by its failure and refusal to take
defendants have asserted that plaintiff is liable for
any steps to negotiate the Development
breach of its duties under a primary agreement
Agreement") clearly states a claim for
signed July 11, 1995, in which the parties agreed
failure to negotiate a development
to use their "best efforts" to negotiate a secondary
agreement.
agreement — a software development contract —
within 15 days. The parties did not negotiate the BACKGROUND
anticipated agreement within 15 days. Defendants
This diverse contract and copyright infringement
contend that this failure to reach an agreement is
case arises from a dispute over a software
due to the plaintiff's failure to use its best efforts to
purchase and licensing agreement negotiated
negotiate.
between Data Systems Analysts, Inc. ("DSA"), a
1 The present Opinion does not address or software development firm, and CompLink, now
affect the parties' cross-motions for known as The NetPlex Group ("NetPlex"). In the
summary judgment filed June 23, 2000. early 1990s, DSA began a working relationship
(Docket Entry Nos. 60 61.) with, Technology Development Systems, Inc.
Plaintiff's present motion calls upon the Court to ("TDS"), which subsequently was acquired by
decide whether an agreement between the parties CompLink in December of 1993. Due to a reverse
to use their "best efforts" to reach within 15 days a merger between CompLink and NetPlex in June
further agreement concerning the development of 1996, TDS then became a subsidiary of NetPlex.
so-called "enhanced software" is enforceable On July 11, 1995, DSA purchased from
where the development agreement contains only a CompLink all rights, title and interest in the
sparse description of the subject of the proposed copyright known as "NetSwitch", a
negotiation.2 For reasons discussed herein, the communications software package having remote
Court finds that although the parties did agree to access, store-and-forward and disparate e-mail
negotiate, this agreement is unenforceable because capability, "together with all documentation,

1
Data Systems Analysts, Inc. v. the Netplex Group, Inc. CIVIL NO. 97-4562(JBS) (D.N.J. Aug. 2, 2000)

revisions, trade secrets, works in progress, support out an eleventh hour purchase of DSA's rights in
software, software tools and all rights associated the software being delivered to XcelleNet, but
therewith" for the sum of $500,000.00 (See DSA- ultimately chose to retain the entire $3 million
CompLink July 1995 Agreement (hereinafter the paid for the so-called WorldLink software. (Pl. Br.
"Prime Agreement") at 1 and 5, Pl. Ex. A.) at 4.) Plaintiff alleges that the above detailed
conduct constitutes, inter alia, copyright
In the Prime Agreement, CompLink and TDS
infringement, breach of contract, and fraud. (See
were "granted back" a limited license to use the
Am. Compl. ¶¶ 29-45.)
NetSwitch software and documentation in future
third party transactions. (Id. at ¶ 1.4.) This license In response to DSA's lawsuit, defendants filed two
was governed by provisions within the Prime contract counterclaims, the second of which
Agreement limiting the modification and use of asserts that DSA breached its obligations under
the software, and provided that CompLink would the Prime Agreement when it failed to use its best
pay DSA 10% of the gross licensing fees received efforts to negotiate a subsequent development
from the sale or installation of the software. (Id. at agreement. (Answer Counterclaim II at ¶¶ 57-59.)
¶ 5.4.) This counterclaim is based on the parties'
agreement to try to reach a secondary agreement
Once the Prime Agreement was executed, the
within 15 days, whereby DSA would pay
NetSwitch software was transferred by CompLink
CompLink up to $300,000.00 for helping to
to DSA, with the understanding DSA would
develop NetSwitch into an "Enhanced Software
thereafter begin an analysis of the software under
Product". DSA was to be the sole owner of this
the thirty-day "Acceptance Testing Period",
new software product.3 (Prime Agreement at 1-2.)
defined in Article V of the Prime Agreement.
Notably, neither the purpose nor the capabilities of
Apparently, this period was intended for DSA to
the anticipated enhanced software are described in
test NetSwitch to see if it conformed to the
the Prime Agreement.
specifications in the Prime Agreement. During this
period, CompLink was to provide support for 3 This article provided, in relevant part, that

DSA. (Id. at 9-10.) According to the Prime


[w]ithin 15 days of the effective
Agreement, if DSA found non-conformities in the
date of this Agreement, the
software during this period, CompLink would parties will use their best efforts
assist in their correction. (Id. at ¶¶ 5.2 and 5.3.) to negotiate and enter into
Development Agreement for the
Plaintiff filed suit in this Court in 1997, alleging
development of the Enhanced
that beginning in August 1995, one month after
Software, involving expected fees
entering into the Prime Agreement, TDS began
of up to $300,000.00. Nothing in
modifying DSA-owned software and licensing it
this paragraph shall abrogate or
to customers without notifying or compensating otherwise invalidate any other
DSA. DSA alleges that TDS renamed the provision of this Agreement.
NetSwitch program "WorldLink", but that the
WorldLink program was essentially made up of (Prime Agreement ¶ 8.1.)

DSA's NetSwitch source code. DSA alleges that in According to the defendants, once the NetSwitch
December 1996, NetPlex sold the TDS WorldLink software had been transferred to DSA, and the
asset, with all its unauthorized enhancements and parties had entered into the 30 day testing period
modifications to DSA's copyrighted code, to described above, DSA inappropriately expanded
XcelleNet for $3,000,000.00. Plaintiff alleges that the scope of the assistance it required of
NetPlex's CEO, Gene Zaino, attempted to work CompLink. CompLink's CEO became convinced

2
Data Systems Analysts, Inc. v. the Netplex Group, Inc. CIVIL NO. 97-4562(JBS) (D.N.J. Aug. 2, 2000)

that the assistance demanded during this period Catrett, 477 U.S. 317, 322-23 (1987)). However,
was really consulting work compensable under the "the nonmoving party creates a genuine issue of
then-unwritten Enhanced Software Development material fact if it provides sufficient evidence to
Agreement rather than generalized troubleshooting allow a reasonable jury to find for him at trial."
as provided for in the Prime Agreement. Brewer, 72 F.3d at 330 (citing Anderson, 477 U.S.
Defendants theorize that DSA was attempting to at 248). Once the moving party has carried its
disingenuously extend the testing period so that it burden of establishing the absence of a genuine
could receive at no cost consulting services that it issue of material fact, "its opponent must do more
would have to pay for after the finalization of the than simply show that there is some metaphysical
Enhanced Software Development agreement doubt as to material facts."Matsushita Elec. Indus.
detailed above. (Dep. of CompLink CEO Gene Co. v. Zenith Radio Corp., 475 U.S. 574, 586
Zaino at 331-335, Def. Ex. A.) (1986). Thus, if the non-movant's evidence is
merely "colorable" or is "not significantly
DISCUSSION probative," the court may grant summary
A. Summary Judgment Standard judgment.Anderson, 477 U.S. at 249-50.

The standard for granting summary judgment is a B. The Parties' Agreement to Negotiate
stringent one. A court may grant summary
Plaintiff argues that defendants' second
judgment only when the materials of record "show
counterclaim should be dismissed because (1) the
that there is no genuine issue as to any material
parties' agreement to negotiate is unenforceable,
fact and that the moving party is entitled to
and (2) even assuming that the clause is
judgment as a matter of law." Fed.R.Civ.P. 56(c).
enforceable, defendants have failed to present any
In deciding whether there is a disputed issue of
evidence that DSA failed to use its best efforts to
material fact the court must view the evidence in
negotiate a software development agreement.
favor of the non-moving party by extending any
Because the Court now finds that the agreement to
reasonable favorable inference to that party. See
negotiate lacks sufficient detail to be enforceable,
Aman v. Cort Furniture Rental Corp., 85 F.3d
the Court does not reach plaintiff's second
1074, 1080-81 (3d Cir. 1996); Kowalski v. L F
argument.
Prods., 82 F.3d 1283, 1288 (3d Cir. 1996); Meyer
v. Riegel Prods. Corp., 720 F.2d 303, 307 n. 2 (3d The Court first considers whether the best efforts
Cir. 1983), cert. denied, 465 U.S. 1091 (1984). clause here is enforceable as a matter of law. As
The threshold inquiry is whether there are "any detailed above, paragraph 8.1 of the Prime
genuine factual issues that properly can be Agreement described the parties' agreement that
resolved only by a finder of fact because they may they would use their best efforts to negotiate a
reasonably be resolved in favor of either party." subsequent contract. Specifically, the Prime
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, Agreement provides that the parties would use
250 (1986). their best efforts to within 15 days reach an
agreement concerning the development of so-
Supreme Court decisions mandate that: "[w]hen
called "enhanced software". Enhanced software is
the nonmoving party bears the burden of
defined in the Prime Agreement as "computer
persuasion at trial, the moving party may meet its
programs" which have been "upgraded" and
burden on summary judgment by showing that the
"enhanced" pursuant to the fulfillment of the
nonmoving party's evidence is insufficient to carry
development agreement. (Prime Agreement at 3,
its burden of persuasion at trial." Brewer v.
Pl. Ex. A.)
Quaker State Oil Refining Corp., 72 F.3d 326,
329-330 (3d Cir. 1995) (citing Celotex Corp. v.

3
Data Systems Analysts, Inc. v. the Netplex Group, Inc. CIVIL NO. 97-4562(JBS) (D.N.J. Aug. 2, 2000)

Plaintiff argues that the issue here is cut and dried: Machinery Corp. v. CSC, Ltd., 184 F.3d 257, 264
paragraph 8.1 was only an agreement to negotiate, (3d Cir. 1999) (distinguishing Channel Home
and agreements to negotiate are not enforceable as Centers, supra.) While the Supreme Court of New
a matter of contract and public policy. (Pl. Br. at 6 Jersey has not yet directly addressed the issue of
(citing Honolulu Waterfront Limited Partnership v. whether an promise to use best efforts to negotiate
Aloha Tower Development Corp., 692 F. Supp. is enforceable, this Court is satisfied that it would
1230, 1235 (D. Ha. 1998) ("the overwhelming follow the reasoning of the Channel Home Centers
weight of authority holds that courts will not court, and hold that, given the right circumstances,
enforce an agreement to negotiate").) Defendants an agreement to negotiate is enforceable so long as
counter that paragraph 8.1 is still binding even it the parties have clearly defined the goals of the
does not explicitly describe the goals of the future negotiation and evinced an intent to be bound by
negotiation. (Def. Br. at 6-7 (citing Berg Agency their promise.
v. Sleepworld-Willingboro, Inc., 136 N.J. Super. 4 As a preliminary matter, the Court finds
369, 376-377 (App.Div. 197 5.))
that the parties' use of the phrase "best

Turning to discuss whether the instant agreement efforts" is meaningful. The Third Circuit
recently has defined best efforts to mean
to negotiate an enhanced software development
something other than the generalized duty
agreement is enforceable,4 the Court first
to negotiate in good faith: "The duty of best
considers the Third Circuit's holding that such
efforts `has diligence as its essence' and is
agreements are enforceable under Pennsylvania `more exacting' than the usual contractual
law, albeit under certain limited circumstances. In duty of good faith." National Payment
Channel Home Centers, the parties had executed a Data Systems, Inc. v. Meridian Bank , 212
detailed letter of intent to enter into a contract for F.3d 849, 854 (3d Cir. 2000) (citing 2 E.
the lease of certain commercial property. Channel Allan Farnsworth, Farnsworth on
Home Centers v. Grossman, 795 F.2d 291 (3d Cir. Contracts , 383-84 (2d ed. 1998)). Thus,
1986) (Becker, J.). The letter contained an the parties' use of the phrase "best efforts"
unequivocal promise to withdraw the property can be interpreted to mean that they agreed

from the rental market so that the parties could to use "good faith plus diligence" in

negotiate the lease. Id. at 300. The property owner negotiating the enhanced software
development agreement.
breached his promise to negotiate a lease, and the
prospective lessor sued. Id. at 296. Now-Chief In this case, a review of paragraph 8.1 shows that
Judge Becker began by noting that, under it is too indefinite to be enforceable. While it may
Pennsylvania law, evidence of preliminary be presumed from the context of the agreement
negotiations, or an agreement to enter into a that the proposed enhanced software would be an
binding contract in the future, does not alone improved commercial version of the NetSwitch
constitute a contract.Id. at 298. Nevertheless, the software that DSA was purchasing from
court held that the parties' detailed letter of intent CompLink, the Prime Agreement does not provide
"had sufficient specificity to make it an any further description of the enhanced software.
enforceable contract". Id. at 300. Under The Prime Agreement does not describe the
Pennsylvania law, therefore, the determination of purpose of designing the proposed enhanced
whether an agreement to negotiate is actionable is software, nor does paragraph 8.1 describe the
a fact-sensitive one, and the court must examine anticipated capabilities, performance features,
whether the preliminary agreement contained appearance or retail cost of such computer
enough detail to show an intent to be bound by the programs. Additionally, the cost of developing the
agreement to negotiate in good faith. See USA

4
Data Systems Analysts, Inc. v. the Netplex Group, Inc. CIVIL NO. 97-4562(JBS) (D.N.J. Aug. 2, 2000)

enhanced software was left unclear, with agreement to negotiate expressed in paragraph 8.1
paragraph 8.1 providing only that CompLink is devoid of the factual detail necessary to show
would be paid fees up to $300,000.00. that the parties understood the parameters of the
enhanced software, and because of the paragraph's
The Court finds that paragraph 8.1 by its own
open-ended financial terms, the parties' agreement
terms is incomplete; it provides that the parties'
to negotiate a putative software development
would try to reach an subsequent agreement to
agreement is unenforceable.
develop improved software, the capabilities of
which would be defined by the subsequent CONCLUSION
agreement. Because the exact nature of the
For the reasons discussed above, plaintiff's motion
enhanced software is not defined within the Prime
for partial summary judgment will be granted, and
Agreement, its physical design, as well as the
defendants' second counterclaim will be
financial terms of its development, had yet to be
dismissed. The accompanying Order is entered.
negotiated at the time the parties signed the Prime
Agreement. Because of the inchoate nature of the ORDER
parties' promise to negotiate, the Court is unable to
THIS MATTER having come before the Court on
determine what the result would have been had the
plaintiff's motion for partial summary judgment as
parties engaged in negotiation. Furthermore, the
against defendants' second counterclaim pursuant
Court would be unable to fashion a remedy for
to Rule 56, Fed.R.Civ.P. (Docket Entry No. 57),
violation of this agreement, because the value and
and the Court having considered the parties'
cost of developing the software was left open.
submissions;
In sum, the Court finds that the terms of paragraph
IT IS this day of August, 2000
8.1 do not show that the parties intended to be
bound without a further manifestation of assent. ORDERED that plaintiff's motion be, and
Simply because the parties stated a willingness to hereby is GRANTED ; and it is further
enter into a future bargain, this does not mean that
ORDERED that defendants' second
the parties intended to be bound without additional
counterclaim be, and hereby is,
detail conclude the negotiation. See Restatement
DISMISSED .
(Second) Contracts § 26. This is not a case like
Channel Home Centers where the outcome of the
future negotiation was predictable, the probable
outcome reduced to a letter of intent, and the
damages clearly ascertainable. Here, because the

You might also like