PROCEDURE
FOR ASP
step by step
guideline of how to
complete the
installation and
commissioning on
the sites P07 in ATM
Mobilis project
Agenda
New sites
Before to • Review installation guidelines
go to the • SID – Site Installation
site Documentation should be reviewed
• Site access permission: Sites Access
permission should be received at
least 72h before going to site,
• The contact person is the
Implementation Manager assigned
to the ASP in charge of the site
• All the relevant information should
be uploaded and fetched from
Simplex.
Before to go
to the site
Roll out Manager & Implementation Management Contact
Resource Abderhamane
Name chetouane Hamza Habechi
Région Algiers Algiers
Roll out Implementation
Role Manager Management
Phone N
umber 0558 39 24 18 0661 68 18 42
RAN MW Comment
Source Tools Capacity
N° Pre-Requisite New Site Mod New Link
upgrade
SID (Site Installation
1 Simplex Doc X X X X
Document)
SA3 (Site Acquisition) Document Provided by
2 Simplex Doc X
Customer
Site transfer Document From Customer to
3 Simplex Doc X
Ericsson
BOM (Bill of Materials)
4 Simplex Doc X X X X
Before to 7
9
PQ
DCN
Mail
Simplex
Simplex
Doc
Doc
Doc
X X X
X
X
X
ATM
go to the 10
11
RF Suggestion
Sharepoint/CMS
Doc
Doc X
X
site 12
13
Modernization Report
Sharepoint/CMS
Doc
Doc X
X
X X X
Script
16 Simplex SW X X
SW 19Q4
18 Sharepoint SW X X
Release 6.1.9
19 Sharepoint SW X X
SRS Access
20 N/A Tools X X
RSA Access
21 N/A Tools X X X X
Moshell
24 Sharepoint Tools
OMT_R79
25 Sharepoint Tools X X
Before start activities:
Once the ASP is on site, the following process should be
applied
• Team leader should call the ATM front Office
Installation (0661040014 / 0661040187) to inform that we are
going to work on the site
Preparation • If there is no answer from front office call immediately
the IM/Roll out Manager
• Check OHS with RSA team for work Permit: the ASP
team should contact the RSA center for OHS work
Permit (Mandatory Action) otherwise the ASP team
will not be authorized to work on site
on Site
7 Modernization. Tower & Two technologies SWAP Antenna 3 RRU 4
8 Modernization. Mast & Two technologies SWAP Antenna 3 RRU 3
9 Modernization. Tower & Two technologies 3 RRU 2
10 Modernization. Mast & Two technologies 3 RRU 2
11 Modernization. Tower & One technology 2
12 Modernization. Mast & One technology 2
13 HW upgrade. Tower. SWAP Transmission (with AMM) 2
14 HW upgrade. Mast. SWAP Transmission (With AMM) 1
15 HW upgrade. Tower & SWAP 1
16 HW upgrade. Mast & SWAP 1
17 New site. Tower 5
18 New Site. Mast 4
Installation on Site
Modernization. Tower & Four technologies 6 RRU
Action on site SWAP Antenna + BDD (Antenna support) + 6 RRU + 9 Optical
Fiber + feeder installation + upgrade power + swap battery +
swap rack battery + dismantling RBS & feeders +swap AMM
(Transmission) + material return
Technology U2100-L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU +Optical Fiber & DC
power cable + Antennas + other indoor equipment
preparation)
Day 2 Installation clamps + Optical Fiber & DC power cable + RRU +
Digital Frame + CIPR cable (SP) + swap AMM 6p + Indoor
installation.
Day 3 Antenna swap+ Completion installation indoor + Integration
Technology U2100-L1800-DCS-U900
Day 1 Preparation of equipment (RRU + Optical Fiber & DC
cable + Antennas + indoor material preparation) +
indoor installation
Day 2 Antenna swap + installation finishing + integration.
Day 3 Dismantling + Reporting preparation + Quality Check
using RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Three technologies 6 RRU
Action on site SWAP Antenna + BDD + 6RRU + 9 Optical fiber + feeder +
upgrade Power +swap battery + swap rack battery + material
return
Technology L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU + FO&DC +
Antennas + indoor material preparation) + indoor installation
Technology L1800-DCS
Day 1 Preparation of equipment (RRU + Optical Fiber & DC
cable + Antennas + indoor material preparation) +
indoor installation
Day 2 Antenna swap + installation finishing + integration
Day 3 Dismantling + Reporting preparation + Quality Check
using RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Two technologies 3 RRU
Technology L1800-DCS
Day 1 Preparation of equipment (RRU + Optical Fiber
& DC cable + indoor material preparation) +
indoor installation
Day 2 Dismantling + Reporting preparation + Quality
Check using RSA + SRS + site cleanup + return
of materials.
Installation on Site
Modernization. Tower & One technology
Technology DCS
Day 1 Delivery + preparation of equipment (RRU +
Optical Fiber & DC cable + indoor material
preparation) + indoor installation
Day 2 Dismantling + Reporting preparation + Quality
Check using RSA + SRS + site cleanup + return of
materials.
Installation on Site
Modernization. Mast & One technology
Technology DCS
Day 1 Delivery + preparation of equipment (RRU +
FO&DC + indoor material preparation) + indoor
installation
Day 2 Integration + Dismantling + Reporting
preparation + Quality Check using RSA + SRS +
site cleanup + return of material
Installation on Site
HW upgrade. Tower. SWAP Transmission (with AMM)
Action on site Swap antennas + AMM + coaxial cable
Technology Transmission
Day 1 Delivery + preparation of equipment
(antenna & RAU + installation coax and
antenna + alignment + uninstallation &
return of material +rapport
Installation on Site
HW upgrade. Mast & SWAP
Technology Transmission
Day 1 Delivery + preparation of equipment
(antenna & RAU + installation coax and
antenna + alignment + uninstallation &
return of material +rapport
Installation on Site
New Site. Tower
Action on site Installation of new site + new link
Tools Smart Laptop Support & Smart Roll out Support (SRS):
Support
Resource Name Khaled Hassani Kamel Belaid
Région All région All Région
Support Smart
Role Laptop Support SRS
Phone Number 0661 69 91 78 0555 06 39 78
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
ASP should be informed about the approved Installation guidelines by Ericsson 48h before
1. X
starting activity
2. Permission to Access site granted by Ericsson at least 72h before starting ant activity X
ASP team should confirm all following equipment’s are working (Power, AC, Generator,
3. batteries) in order to be sure that there is no blocking issue to perform the activity on site X
Note: Any blocking point must be highlighted to E/// (IM & CPM) on time
The ASP team should Confirm that the necessary Hardware is available on site. to complete
4. the Modernization within the deadline fixed by Ericsson X
Note: Any missing materials must be highlighted to E/// (IM & CPM) immediately
ASP team will collect site configuration and alarms logs of RBS (Initial Configuration,
5. X
Alarms, VSWR…)
Ericsson initial Tuning team should collect the reference KPI’s
6. Site Level: at least 48h before any swap SSV “Single Site verification “ X
Cluster level: at least 01 week before “Drive Test Cluster “
ASP team has appropriate tools and documentation (SID, RF suggestion, Script , SL, SRS ,
7. RSA , Modernization Report , Pre-quality Check list ) as listed on the table-1 pre-Requisite X
Note: any missing must be highlighted immediately to the IM/CPM
ASP team should start with pre-configured including pre-commissioning of BB & SAU
Note:
8. 1. If any issue on the script, please contact Ericsson Supervisor on the region (Ericsson X
Supervisor Staff table 3)
2. If any issue on the upgrade package SW19Q4, please contact Mr. Khaled Hassan for
Support (Smart Laptop Support Table 4)
Daily Activities is shown for all Modernization activities (green field or Roof top. please refer
to the table-5 as described from delivery, Preparation until return materials. Number of days X
to be used depends on the site configuration
Day-1:
9. Day-2
Day-3
Day-4
Day-5: Clean & return Materials
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
Before any Cutover on site we should contact the Front Office 0661040014/0661040187 to ask
10.
permission X
11. Cutover permission granted by customer
When the SWAP activity Completed, and site integrated the ASP should inform the front office
12.
0661040014/0661040187 and IM immediately
ASP team should perform SRS & RSA activities (Mandatory Action)
1- for HW check to be sure that there is no cross after completing the installation
13.
2- Complete Pre-Quality check list with RSA teams to confirm that the site is installed
according Ericsson Standard
After successful Moderization activity , we need Perform Concluding Routines , Before leaving
the site, perform the following procedure
14.
1-Clean the site and remove objects such as wrapping paper and cable clippings X
Dismantling Materials:
1. 1-Pack Old Equipment dismantled
15. X
2. 2-Transport Equipment to Dedicated Warehouse with Return Note
Note: We should inform the warehouse at least 48h before returning materials
Simplex Upload: Upload the following Deliverable
1- Pre-Quality Check list X
2- Modernization Report
16.
3- After Swap Report
4- Return Note
5- As-Built Report Preparation
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
Rollback: In case during the Modernization process there would be any
problem to put on service the site (i.e. integration) the rollback process must be
activated.
This process must be triggered according to RAN Integration team and
Implementation Management only when is sure that is not possible
troubleshoot in the Cutover window. The rollback will be validated by Customer
(ATM)
1. Ask Customer for green light to proceed with the rollback
2. Re install the old equipment in its original situation.
17.
3. Call Integration team to bring up the existing equipment back on-air. X
4. Make test call and make sure the existing equipment is working
properly
Note: It must be considered that there will be typologies where the rollback
process will be very difficult or impossible, for example if in modernization the
old Equipment has been removed by a crane from the site. In these case we
should go on with the troubleshooting until solve the problem
Responsibility matrix- Capacity
upgrade
Responsible
Step Step Description
ATM Ericsson ASP
ASP should be informed about the approved installation guidelines by Ericsson
18. 48h before starting activity X
Permission to Access sites granted by Ericsson at least 72h before starting ant
19. activity X
ASP team should confirm all following equipment’s are working (Power, AC ,
Generator , batteries ) in order to be sure that there is no blocking issue to
20. perform the activity on site X
Note: Any blocking point must be highlighted to E/// ( IM & CPM ) on time
The ASP team should Confirm that the necessary Hardware is available on both
21. sites. to complete the capacity Upgrade within the deadline fixed by Ericsson X
Note: Any missing materials must be highlighted to E/// (IM & CPM) immediately
ASP team will collect the links configuration and alarms logs (Initial
22. Configuration, Alarms , … ) X
ASP team has appropriate tools and documentation (SID, PQ, DCN, RSA, Capacity
upgrade Report , Pre-quality Check list ) as listed on the table-1 pre-Requisite
23. for Capacity upgrade X
Note: any missing must be highlighted immediately to the IM/CPM
Daily Activities is shown for all Capacity upgrade activities (green field or Roof
top. please refer to the table-6 as described from delivery, Preparation until return X
materials. Number of sites depends on the configuration of the link
24. Day-1:
Day-2
Clean & return Materials
Responsibility matrix- Capacity
upgrade
Responsible
Step Step Description
ATM Ericsson ASP
25 Before any Cutover on site we should contact the Front Office 0661040014/0661040187 to ask permission
X
26 Cutover permission granted by customer
When the Upgrade Capacity activity Completed and links integrated the ASP should inform the front office
27
0661040014/0661040187 and IM immediately
ASP team should perform RSA activity (Mandatory Action)
28
1- Complete Pre-Quality check list with RSA teams to confirm that the links is upgraded according Ericsson Standard
After successful upgrade capacity activity, we need Perform Concluding Routines , Before leaving the site, perform the
following procedure
29
1-Clean the sites and remove objects such as wrapping paper and cable clippings X
Dismantling Materials:
1. 1-Pack Old Equipment dismantled
30 X
2. 2-Transport Equipment to Dedicated Warehouse with Return Note
Note: We should inform the warehouse at least 48h before returning materials
Simplex Upload: Upload the following Deliverable
1. Pre-Quality Check list X
31 2. Upgrade capacity Report
3. Return Note
4. As-Built Report Preparation
Rollback: In case during the Upgrade capacity process there would be any problem to put on service the links (i.e.
integration) the rollback process must be activated.
This process must be triggered according to Trans Integration team and Implementation Management only when is sure
that is not possible troubleshoot in the Cutover window. The rollback will be validated by Customer (ATM)
32
1. Ask Customer for green light to proceed with the rollback
2. Re install the old equipment in its original situation.
3. Call trans Integration team confirm if all the existing links back on-air. X
4. make sure the existing links is working properly without alarms
Safety Equipment
Lanyard Carabineer
Automatic lock
Adjustable
Tools required
Personal Health and Safety
Special Hazard Symbols