METHODS OF

PROCEDURE
FOR ASP
step by step
guideline of how to
complete the
installation and
commissioning on
the sites P07 in ATM
Mobilis project
Agenda

Before to go to the site


Installation preparation
Installation on site
Integration support
Tools
Responsible Matrix
P07 Scope
Modernization with addition of new layers on
site (U2100-L1800-DCS-U900).

Hardware upgrade. Transmission capacity


expansion.

New sites
Before to • Review installation guidelines
go to the • SID – Site Installation
site Documentation should be reviewed
• Site access permission: Sites Access
permission should be received at
least 72h before going to site,
• The contact person is the
Implementation Manager assigned
to the ASP in charge of the site
• All the relevant information should
be uploaded and fetched from
Simplex.
Before to go
to the site
Roll out Manager & Implementation Management Contact

Resource Abderhamane
Name chetouane Hamza Habechi
Région Algiers Algiers
Roll out Implementation
Role Manager Management
Phone N
umber 0558 39 24 18 0661 68 18 42

Resource Mehdi redouan Djaouat Arezki Djafar Seifed


Name e Igoudjil Mohamed Amine Amir Maafa Belkacem dine
Région 13 Wilaya Grand Algiers Constantine Chlef Setif
Implementat Implementati
Roll out Implementation ion on Implementatio
Role Manager Management Management Management n Management
Phone N 0657 25 31 0555 09 90
umber 0661 69 91 73 0555 09 90 51 72 91 0560 22 18 44
Before to
go to the • Environmental, Health and Safety
information: all climbing personnel should
site know all relevant safety regulations and
instructions, Installers working at heights
should be qualified for the job and have
completed a course of instruction for climbing
and site safety
• Script uploading: The ASP will upload the
scripts in the Baseband/Digital Unit, using
Smart Laptop. This should be done before
the arrival to the site. In case any issue is
detected, the ASP must contact the
Integration team
Before to • Tools usage: With the target to optimize the
go to the operational efficiency, Ericsson is proposing the
usage of several technical tools that will help the
site project performance.
Khaled Hassani
All région • Smart Laptop (SL) application used for uploading
Support Smart Laptop the scripts in the Baseband.
0661 69 91 78
• Smart Rollout Support (SRS) tool is a mobile
Kamel Belaid Android based application that helps to perform
All Région field tests to verify Base Station equipment
Support SRS installation and to provide a reliable data about
0555 06 39 78 offered voice and data services.

Larbi Hadjadj • Remote Access (RA) is a specialized video/audio


all région conference application that allows Ericsson Suppliers
Support RSA to connect with Ericsson representatives to complete
0661 69 04 73 various Remote Site Activities
Documentation
Before to Responsibility of the ASP
go to the • Pre-Quality Check list
site • Modernization Report
• After Swap Report
• Return Note
• As-Built Report Preparation
• Single site verification report
(SSV)
• SRS report
Table N°01 -Prerequisite

RAN MW Comment
Source Tools Capacity
N° Pre-Requisite New Site Mod New Link
upgrade
SID (Site Installation
1 Simplex Doc X X X X
Document)
SA3 (Site Acquisition) Document Provided by
2 Simplex Doc X
Customer
Site transfer Document From Customer to
3 Simplex Doc X
Ericsson
BOM (Bill of Materials)
4 Simplex Doc X X X X

Operational Description Validation by ATM 48


5 Simplex/Mail Doc X X
(Customer MoP) before starting Operation
Travel Order
6 Mail Doc X X X X

Authorization Document signed and approved by

Before to 7

9
PQ

DCN
Mail

Simplex

Simplex
Doc

Doc

Doc
X X X

X
X

X
ATM

go to the 10

11
RF Suggestion

New Site Report


Simplex

Sharepoint/CMS
Doc

Doc X
X

site 12

13
Modernization Report

Pre-Quality check List


Sharepoint/CMS

Sharepoint/CMS
Doc

Doc X
X

X X X

Trans New Link Report


14 Sharepoint/CMS Doc X

Capacity Upgrade Report


15 Sharepoint/CMS Doc X

Script
16 Simplex SW X X

CDD (Cell Design Data )


17 Simplex Doc X X

SW 19Q4
18 Sharepoint SW X X

Release 6.1.9
19 Sharepoint SW X X

SRS Access
20 N/A Tools X X

RSA Access
21 N/A Tools X X X X

Smart Laptop Access


22 N/A Tools X X

Mini link Craft 20.4


23 Sharepoint Tools X X

Moshell
24 Sharepoint Tools

OMT_R79
25 Sharepoint Tools X X
Before start activities:
Once the ASP is on site, the following process should be
applied
• Team leader should call the ATM front Office
Installation (0661040014 / 0661040187) to inform that we are
going to work on the site
Preparation • If there is no answer from front office call immediately
the IM/Roll out Manager

• Collect all the alarms before starting Any Activities


(Alarms Print screen)

• Check OHS with RSA team for work Permit: the ASP
team should contact the RSA center for OHS work
Permit (Mandatory Action) otherwise the ASP team
will not be authorized to work on site

Table 2. RSA Team Contact


Profile Resources Name SIM Contact - Ooredoo SIM Contact - Mobilis E-mail Contact
RSA TL & Support Larbi Hadjadj 00213 555 00 05 20 00213 661 69 04 73 larbi.hadjadj@ericsson.com
SME-1 Chafik ACHOURI 00213 550 59 67 65 00213 661 91 39 47 chafik.achouri@ericsson.com
SME-2 Nassim Bouncer 00213 555 00 06 00 00213 661 68 18 46 nassim.bouncer@ericsson.com
SME-3 Faycal Bekrar 00213 555 09 90 77 00213 661 40 71 83 faycal.bekrar@ericsson.com
Material Verification

The three next steps should be:

• Unpacking and checking the


materials to control and report (if the
case) on any visual damages.
Installation
Preparation • Check that the items delivered
correspond to the packing list (BOM),
If any missing please highlight it
immediately to IM & CPM.

• All wrapping plastic and paper to be


collected and sorted to be used for
the dismantling materials
Table 3. Installation days per configuration and scenario
#
# Description Installation
days
1 Modernization. Tower & Four technologies 6 RRU 4
2 Modernization. Mast & Four technologies 6 RRU 3
3 Modernization. Tower & Four technologies 3 RRU 4
4 Modernization. Mast & Four technologies 3 RRU 3
5 Modernization. Tower & Three technologies 6 RRU 4
Installation 6 Modernization. Mast & Three technologies 6 RRU 3

on Site
7 Modernization. Tower & Two technologies SWAP Antenna 3 RRU 4
8 Modernization. Mast & Two technologies SWAP Antenna 3 RRU 3
9 Modernization. Tower & Two technologies 3 RRU 2
10 Modernization. Mast & Two technologies 3 RRU 2
11 Modernization. Tower & One technology 2
12 Modernization. Mast & One technology 2
13 HW upgrade. Tower. SWAP Transmission (with AMM) 2
14 HW upgrade. Mast. SWAP Transmission (With AMM) 1
15 HW upgrade. Tower & SWAP 1
16 HW upgrade. Mast & SWAP 1
17 New site. Tower 5
18 New Site. Mast 4
Installation on Site
Modernization. Tower & Four technologies 6 RRU
Action on site SWAP Antenna + BDD (Antenna support) + 6 RRU + 9 Optical
Fiber + feeder installation + upgrade power + swap battery +
swap rack battery + dismantling RBS & feeders +swap AMM
(Transmission) + material return
Technology U2100-L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU +Optical Fiber & DC
power cable + Antennas + other indoor equipment
preparation)
Day 2 Installation clamps + Optical Fiber & DC power cable + RRU +
Digital Frame + CIPR cable (SP) + swap AMM 6p + Indoor
installation.
Day 3 Antenna swap+ Completion installation indoor + Integration

Day 4 Dismantling + Reporting preparation + Quality Check using RSA


+ SRS + site cleanup + return of materials
Installation on Site
Modernization. Mast & Four technologies 6 RRU

Action on site SWAP Antenna + BDD (Antenna Support) + 6 RRU + 9 Optical


Fiber + feeder + upgrade power +swap battery +swap rack
battery +dismantling RBS & feeders + Swap AMM+ material
return.
The 3 days are estimated without cable try
Technology U2100-L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU + Optical Fiber & DC
cable + Antennas + indoor material preparation) + indoor
installation
Day 2 Antenna swap + installation finishing + integration
Day 3 Dismantling + Reporting preparation + Quality Check using RSA
+ SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Four technologies 3 RRU
Action on site SWAP Antenna + 3RRU +3 Optical Fiber + upgrade power
+swap battery + swap rack battery + dismantling RBS & feeders
+swap AMM + material return
Technology U2100-L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU + Optical Fiber &
DC cable + Antennas + indoor equipment preparation)

Day 2 Installation clamps + Optical Fiber & DC cable + RRU + Digital


Frame + CPRI SP + swap AMM 6p + indoor installation.

Day 3 Antenna swap + indoor installation finishing + integration.

Day 4 Dismantling + Reporting preparation + Quality Check using RSA


+ SRS + site cleanup + return of materials
Installation on Site
Modernization. Mast & Four technologies 3 RRU
Action on site SWAP Antenna + 3RRU +3 Optical Fiber + upgrade
power +swap battery + swap rack battery +dismantling
RBS & feeders +swap AMM + material return

Technology U2100-L1800-DCS-U900
Day 1 Preparation of equipment (RRU + Optical Fiber & DC
cable + Antennas + indoor material preparation) +
indoor installation
Day 2 Antenna swap + installation finishing + integration.
Day 3 Dismantling + Reporting preparation + Quality Check
using RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Three technologies 6 RRU
Action on site SWAP Antenna + BDD + 6RRU + 9 Optical fiber + feeder +
upgrade Power +swap battery + swap rack battery + material
return
Technology L1800-DCS-U900
Day 1 Delivery & preparation of equipment (RRU + FO&DC +
Antennas + indoor material preparation) + indoor installation

Day 2 Installation clamps + Optical Fiber & DC cable + RRU + Digital


Frame + CPRI cable (SP) + swap AMM6p.
Day 3 Antenna swap+ Completion of the installation + Integration

Day 4 Dismantling + Reporting preparation + Quality Check using RSA


+ SRS + site cleanup + return of materials
Installation on Site
Modernization. Mast & Three technologies. 6 RRU
Action on site SWAP Antenna + BDD + 6 RRU + 9 Optical Fiber +
feeder + upgrade power +swap battery +swap rack
battery + material return
Technology L1800-DCS-U900
Day 1 Preparation of equipment (RRU + FO&DC + Antennas
+ indoor material preparation) and indoor
installation
Day 2 Antenna swap + installation finishing + integration.

Day 3 Dismantling + Reporting preparation + Quality Check


using RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Two technologies SWAP Antenna 3 RRU

Action on site SWAP Antenna + 3RRU +3 Optical Fiber + upgrade power


+swap battery + swap rack battery +dismantling RBS &
feeders +swap AMM + material return
Technology L1800-DCS
Day 1 Delivery & preparation of equipment (RRU + FO&DC +
Antennas + indoor material preparation)
Day 2 Installation clamps + Optical Fiber & DC cable+ RRU + Digital
Frame + CPRI cable (SP) + swap AMM6p + indoor
installation
Day 3 Antenna swap + installation finishing + integration
Day 4 Dismantling + Reporting preparation + Quality Check using
RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Mast & Two technologies SWAP Antenna 3 RRU
Action on site SWAP Antenna + 3RRU +3 Optical Fiber + upgrade
power +swap battery + swap rack battery + dismantling
RBS & feeders +swap AMM + material return

Technology L1800-DCS
Day 1 Preparation of equipment (RRU + Optical Fiber & DC
cable + Antennas + indoor material preparation) +
indoor installation
Day 2 Antenna swap + installation finishing + integration
Day 3 Dismantling + Reporting preparation + Quality Check
using RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Tower & Two technologies 3 RRU

Action on site 3RRU +3 Optical Fiber + upgrade power +swap battery +


swap rack battery +dismantling RBS & feeders + swap AMM +
material return
Technology L1800-DCS

Day 1 Preparation of equipment (RRU + Optical Fiber & DC cable +


Antennas + indoor material preparation) + indoor installation
Day 2 Antenna swap + installation finishing + integration.

Day 3 Dismantling + Reporting preparation + Quality Check using


RSA + SRS + site cleanup + return of materials
Installation on Site
Modernization. Mast & Two technologies 3 RRU
Action on site 3RRU +3 Optical Fiber + upgrade power +swap
battery + swap rack battery +dismantling RBS &
feeders +swap AMM + material return

Technology L1800-DCS
Day 1 Preparation of equipment (RRU + Optical Fiber
& DC cable + indoor material preparation) +
indoor installation
Day 2 Dismantling + Reporting preparation + Quality
Check using RSA + SRS + site cleanup + return
of materials.
Installation on Site
Modernization. Tower & One technology

Action on site 3RRU +3 Optical Fiber + swap AMM+ material


return

Technology DCS
Day 1 Delivery + preparation of equipment (RRU +
Optical Fiber & DC cable + indoor material
preparation) + indoor installation
Day 2 Dismantling + Reporting preparation + Quality
Check using RSA + SRS + site cleanup + return of
materials.
Installation on Site
Modernization. Mast & One technology

Action on site 3RRU +3 Optical Fiber +swap AMM –


Transmission + material return

Technology DCS
Day 1 Delivery + preparation of equipment (RRU +
FO&DC + indoor material preparation) + indoor
installation
Day 2 Integration + Dismantling + Reporting
preparation + Quality Check using RSA + SRS +
site cleanup + return of material
Installation on Site
HW upgrade. Tower. SWAP Transmission (with AMM)
Action on site Swap antennas + AMM + coaxial cable

Technology Transmission expansion


Day 1 Delivery + preparation of equipment (antenna &
RAU + installation coax + indoor installation AMM)
configuration + alignment + uninstallation & return
of material
Day 2 Dismantling + Reporting preparation + Quality
Check using RSA + SRS + site cleanup + return of
materials.
Installation on Site
HW upgrade. Mast. SWAP Transmission (With AMM)

Action on site Swap antennas + AMM + coax

Technology Transmission expansion


Day 1 Delivery + preparation of equipment
(antenna & RAU + installation coax + indoor
installation AMM) configuration + alignment
+ uninstallation & return of material + report.
Installation on Site
HW upgrade. Tower & SWAP

Action on site Swap antennas + coax

Technology Transmission
Day 1 Delivery + preparation of equipment
(antenna & RAU + installation coax and
antenna + alignment + uninstallation &
return of material +rapport
Installation on Site
HW upgrade. Mast & SWAP

Action on site Swap antennas + coax

Technology Transmission
Day 1 Delivery + preparation of equipment
(antenna & RAU + installation coax and
antenna + alignment + uninstallation &
return of material +rapport
Installation on Site
New Site. Tower
Action on site Installation of new site + new link

Technology New site as per the configuration requested by the customer

Day 1 Delivery & preparation of equipment (RRU + Optical Fiber &


DC cable + feeders +Antennas + indoor material
preparation).
Day 2 Indoor installation
Day 3 Antenna swap+ Completion installation indoor + Integration

Day 4 Antenna installation + installation link + integration


Day 5 Dismantling + Reporting preparation + Quality Check using
RSA + SRS + site cleanup + return of materials
Installation on Site
New Site. Mast
Action on site Installation of new site + new link

Technology New site as per the configuration requested by the customer

Day 1 Delivery & preparation of equipment (RRU + Optical Fiber & DC


cable + feeders +Antennas + indoor material preparation).

Day 2 Installation clamps + Fiber Optical & DC cable + RRU + Digital


Frame.
Day 3 Indoor installation + Antenna installation + installation link +
integration
Day 4 Dismantling + Reporting preparation + Quality Check using RSA
+ SRS + site cleanup + return of materials.
• The installation is completed, and
Integration hardware/cabling is correctly
connected. The scripts have been
Support already uploaded in the
Baseband/Digital Unit, trough
Smart Laptop.

• After that, the ASP should check


transmission. If ping is ok, the team
on site will contact integrator
according to the specific region
Table 4. Integration team. 13 Wilaya Table 5. Integration team. Algiers
Saer Yahia
Integration Lead Saer Yahia Agha 0550 00 22 45 Integration Lead 0550 00 22 45
Agha
13 Wilaya ATM Algiers ATM Rabie Aoun
Ahmed Yataghen 0561 67 60 25 0568 79 81 75
Integration TL Integration TL Seghir
All Wilaya License All Wilaya License
Ahmed hami 0557 09 59 15 Ahmed hami 0557 09 59 15
SPOC SPOC

13 Wilaya Initial Algiers Initial tuning


Khelil Akilal 0661 68 11 52 Nadira Chikh 0671 21 11 86
tuning Team leader Team leader

13 Wilaya Roll out Mehdi redouane Algiers Roll out Abderhamane


0661 69 91 73 0558 39 24 18
Manager Igoudjil Manager chetouani
In case the ASP is requiring support in terms of tools,
the contact is below listed:

Tools Smart Laptop Support & Smart Roll out Support (SRS):

Support
Resource Name Khaled Hassani Kamel Belaid
Région All région All Région
Support Smart
Role Laptop Support SRS
Phone Number 0661 69 91 78 0555 06 39 78
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
ASP should be informed about the approved Installation guidelines by Ericsson 48h before
1. X
starting activity
2. Permission to Access site granted by Ericsson at least 72h before starting ant activity X
ASP team should confirm all following equipment’s are working (Power, AC, Generator,
3. batteries) in order to be sure that there is no blocking issue to perform the activity on site X
Note: Any blocking point must be highlighted to E/// (IM & CPM) on time
The ASP team should Confirm that the necessary Hardware is available on site. to complete
4. the Modernization within the deadline fixed by Ericsson X
Note: Any missing materials must be highlighted to E/// (IM & CPM) immediately
ASP team will collect site configuration and alarms logs of RBS (Initial Configuration,
5. X
Alarms, VSWR…)
Ericsson initial Tuning team should collect the reference KPI’s
6. Site Level: at least 48h before any swap SSV “Single Site verification “ X
Cluster level: at least 01 week before “Drive Test Cluster “
ASP team has appropriate tools and documentation (SID, RF suggestion, Script , SL, SRS ,
7. RSA , Modernization Report , Pre-quality Check list ) as listed on the table-1 pre-Requisite X
Note: any missing must be highlighted immediately to the IM/CPM
ASP team should start with pre-configured including pre-commissioning of BB & SAU
Note:

8. 1. If any issue on the script, please contact Ericsson Supervisor on the region (Ericsson X
Supervisor Staff table 3)
2. If any issue on the upgrade package SW19Q4, please contact Mr. Khaled Hassan for
Support (Smart Laptop Support Table 4)
Daily Activities is shown for all Modernization activities (green field or Roof top. please refer
to the table-5 as described from delivery, Preparation until return materials. Number of days X
to be used depends on the site configuration
Day-1:
9. Day-2
Day-3
Day-4
Day-5: Clean & return Materials
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
Before any Cutover on site we should contact the Front Office 0661040014/0661040187 to ask
10.
permission X
11. Cutover permission granted by customer
When the SWAP activity Completed, and site integrated the ASP should inform the front office
12.
0661040014/0661040187 and IM immediately
ASP team should perform SRS & RSA activities (Mandatory Action)
1- for HW check to be sure that there is no cross after completing the installation
13.
2- Complete Pre-Quality check list with RSA teams to confirm that the site is installed
according Ericsson Standard
After successful Moderization activity , we need Perform Concluding Routines , Before leaving
the site, perform the following procedure
14.
1-Clean the site and remove objects such as wrapping paper and cable clippings X

Dismantling Materials:
1. 1-Pack Old Equipment dismantled
15. X
2. 2-Transport Equipment to Dedicated Warehouse with Return Note
Note: We should inform the warehouse at least 48h before returning materials
Simplex Upload: Upload the following Deliverable
1- Pre-Quality Check list X
2- Modernization Report
16.
3- After Swap Report
4- Return Note
5- As-Built Report Preparation
Responsibility matrix- Radio
modernization
Responsible
Step Step Description
ATM Ericsson ASP
Rollback: In case during the Modernization process there would be any
problem to put on service the site (i.e. integration) the rollback process must be
activated.
This process must be triggered according to RAN Integration team and
Implementation Management only when is sure that is not possible
troubleshoot in the Cutover window. The rollback will be validated by Customer
(ATM)
1. Ask Customer for green light to proceed with the rollback
2. Re install the old equipment in its original situation.
17.
3. Call Integration team to bring up the existing equipment back on-air. X

4. Make test call and make sure the existing equipment is working
properly

Note: It must be considered that there will be typologies where the rollback
process will be very difficult or impossible, for example if in modernization the
old Equipment has been removed by a crane from the site. In these case we
should go on with the troubleshooting until solve the problem
Responsibility matrix- Capacity
upgrade
Responsible
Step Step Description
ATM Ericsson ASP
ASP should be informed about the approved installation guidelines by Ericsson
18. 48h before starting activity X
Permission to Access sites granted by Ericsson at least 72h before starting ant
19. activity X
ASP team should confirm all following equipment’s are working (Power, AC ,
Generator , batteries ) in order to be sure that there is no blocking issue to
20. perform the activity on site X
Note: Any blocking point must be highlighted to E/// ( IM & CPM ) on time
The ASP team should Confirm that the necessary Hardware is available on both
21. sites. to complete the capacity Upgrade within the deadline fixed by Ericsson X
Note: Any missing materials must be highlighted to E/// (IM & CPM) immediately
ASP team will collect the links configuration and alarms logs (Initial
22. Configuration, Alarms , … ) X
ASP team has appropriate tools and documentation (SID, PQ, DCN, RSA, Capacity
upgrade Report , Pre-quality Check list ) as listed on the table-1 pre-Requisite
23. for Capacity upgrade X
Note: any missing must be highlighted immediately to the IM/CPM
Daily Activities is shown for all Capacity upgrade activities (green field or Roof
top. please refer to the table-6 as described from delivery, Preparation until return X
materials. Number of sites depends on the configuration of the link
24. Day-1:
Day-2
Clean & return Materials
Responsibility matrix- Capacity
upgrade
Responsible
Step Step Description
ATM Ericsson ASP
25 Before any Cutover on site we should contact the Front Office 0661040014/0661040187 to ask permission
X
26 Cutover permission granted by customer
When the Upgrade Capacity activity Completed and links integrated the ASP should inform the front office
27
0661040014/0661040187 and IM immediately
ASP team should perform RSA activity (Mandatory Action)
28
1- Complete Pre-Quality check list with RSA teams to confirm that the links is upgraded according Ericsson Standard
After successful upgrade capacity activity, we need Perform Concluding Routines , Before leaving the site, perform the
following procedure
29
1-Clean the sites and remove objects such as wrapping paper and cable clippings X

Dismantling Materials:
1. 1-Pack Old Equipment dismantled
30 X
2. 2-Transport Equipment to Dedicated Warehouse with Return Note
Note: We should inform the warehouse at least 48h before returning materials
Simplex Upload: Upload the following Deliverable
1. Pre-Quality Check list X
31 2. Upgrade capacity Report
3. Return Note
4. As-Built Report Preparation
Rollback: In case during the Upgrade capacity process there would be any problem to put on service the links (i.e.
integration) the rollback process must be activated.
This process must be triggered according to Trans Integration team and Implementation Management only when is sure
that is not possible troubleshoot in the Cutover window. The rollback will be validated by Customer (ATM)
32
1. Ask Customer for green light to proceed with the rollback
2. Re install the old equipment in its original situation.
3. Call trans Integration team confirm if all the existing links back on-air. X
4. make sure the existing links is working properly without alarms
Safety Equipment

High Visibility Safety gloves


against mechanical
Work wear
risks

Lanyard Carabineer
Automatic lock
Adjustable
Tools required
Personal Health and Safety
Special Hazard Symbols

Chemical Hazard Heat Hazard

Electrical Hazard Laser Hazard

Fire Hazard RF Exposure


Hazard
To ensure that persons are not injured
when working with equipment:
• Items of jewelry, for example rings,
watches and necklaces should be
removed as they can catch on
Personal Health moving parts, or when lifting
equipment.
and Safety • Pay attention to the hazard labels
General Safety and other information labels on
products.
Precautions • Never remove or cover hazard
symbols as this can endanger
persons working with the product.
• Only use the tools described and in
the manner indicated in the
instructions
The following precautions must be
observed when working with
electrical equipment:
Personal Health • The AC mains is switched off.
and Safety • Power cables are installed
according to instructions.
Working with
• Installed cables are always clearly
Electrical marked with labels.
Equipment • All personnel are familiar with and
understand the warning signs on
equipment.
• Only tested electrical tools are used.
• Holes are never drilled in equipment,
or walls, without ensuring that there
are no concealed cables.