BIM Uses On Test Projects
BIM Uses On Test Projects
1
1 Background and purpose
For the BIM uses to be fully integrated in the organizations of Banedanmark and
Vejdirektoratet, a more thorough investigation on existing business-processes should
be conducted in order to establish an AS-IS picture of the existing process landscape
and then analyse how to gradually develop this picture into a more BIM and digital
integrated TO-BE landscape. An example could be existing requirements to review
process, revision procedures and QA documentation requirements. All these
requirements must eventually be integrated and/or supported by different BIM uses in
this example design review and design authoring plus more. Along this process the
organizations should consider updating their value chains and analogue
documentation requirements, so that these are more up to date with a digital,
automated setup and agile project execution. This would also require looking at a
new IT target architecture, that could support the flow of information and
documentation. The BIM uses can however be used on projects without revising
internal existing processes, if potential conflicts are highlighted and handled on the
specific projects within in the commercial requirements and legal framework
associated with these projects. It is also recommended that a competence
development strategy is established, in order to properly implement BIM uses in all
departments affected by the new digital processes.
Review and
approval
methods
Revision Existing data
procedures governance
QA Updated
documentation termanology
requirements BIM Use
Figure 1: To fully integrate BIM uses the existing methods, requirements and procedures
of an organization should be revised and integrated in all BIM uses.
Until now the infrastructure industry in Denmark, has not had a common standard on
how to apply BIM uses within a project. It has been decided from involved parties, to
1
develop a common procedure for this. BIMinfra has been working on standardization
of Banedanmark and Vejdirektoratet requirements to BIM Uses in a taskforce called
“BIM uses and BIM Maturity”.
The first task was to define a common understanding of how to setup BIM uses in a
structured way using BPMN visualization. This also included the understanding of
process maps and current requirements to existing processes, their history and the
impact of implementation in the organizations of Banedanmark and The Road
Directorate.
The next task was to find and study existing standards concerning BIM uses, and
then analyse the best match for the Danish infrastructure sector. A survey1 incl. 12
questions was conducted in the Danish infrastructure market to investigate whether
Danish companies were working in any structured way in relation to BIM uses. The
result concluded that the few companies working with BIM uses in Denmark, mostly
referred to Penn State University and their material on BIM uses2 . It was decided to
use Penn States approach on BIM uses as basis for the BIM infra development
project.
BIMinfra has worked on a set of BIM uses (processes) that can be applied to projects
and test projects in the organizations or in the industry in general.
A BIM use is defined as a method of applying building information modelling during
an asset’s lifecycle to achieve one or more specific objectives. The BIM Execution
Plan or ICT process manual (BEP or ICT) should provide a structured method for
planning the implementation of BIM uses on a project.
The procedure from Penn State University includes the following three steps:
1. Identify high-value BIM uses during the project planning, design, construction
and operational phases.
2. Design the BIM execution process by creating process maps (layouts already
in appendix to this document)
3. Define the BIM deliverables (BIM use output) in the form of information
exchanges and formulate this into a delivery specification.
The Penn State BIM uses consists of 24 uses (processes) that can be applied in one
or several phases of a project. Visualization has been added as a 25th BIM use after
discussion in the development team.
1
https://forms.office.com/Pages/ResponsePage.aspx?id=OBW-
Edh5OUmCuLdngF2CW3QZ0EYvgyFJphgubO6zaORUNVYwTjFLRlE2RTJaQTMzSFo2U0I0ODZIVS4u
2
https://www.bim.psu.edu/
2
Project phases
Plan Design Construction Operations
#1 Existing Conditions Modeling
#2 Cost Estimation (5D)
#3 Scheduling (4D)
#4 Programming
#5 Site Analysis
#6 Design Authoring
#7 Design Reviews
#8 Drawing Generation
#9 Lighting Analysis
#10 Energy Analysis
#11 Engineering Analysis
#12 Sustainability (6D)
#13 Code Validation
#14 3D Coordination
Site Utilization
#15 Planning
Construction System
#16 Design
#17 Digital Fabrication
3D Control and
#18 Planning
#19 Record Model
Maintenance Scheduling
#20 (7D)
#21 Building System Analysis
#22 Asset Management
#23 Space Mgmt/Tracking
#24 Disaster Planning
#25 Visualisation
Figure 2: List of BIM uses and the phases where they can occur. Green colour indicates
that the Use has been prioritized in the phase 1 of the development project and has been
revised in some extend according to figure 1.
Building Information Modeling (BIM) has been defined as “the act of creating a digital
model of an asset or a project for the purpose of visualization, engineering analysis,
conflict analysis, code criteria checking, cost engineering, as-built product, budgeting
and many other purposes”. To foster better communication within the industry, it is
important to define a consistent language to describe the focused use of BIM on a
project.
The Language of These BIM uses are visualized in the process maps incl.
descriptions in the appendix to this document.
BIM infra has scrutinized at the material from Penn state and is in the process of
revising these uses to match ISO19650 terms and infrastructure projects in Denmark
and the two organizations. In the initial workshop of this project a prioritization was
done, and 6 uses was selected for revision in face 1, marked in green in figure 2. It is
3
suggested to run a phase 2 where 8 more uses will be revised and examples on the
first 6 uses will be created. And then a face 3 will include updating the remaining BIM
uses and testing all uses prioritized as 1 or 2 (priority is marked in appendix
frontpage) on actual infrastructure projects depending on projects available,
technological development and the needs on the actual projects. The uses not
revised at this state can still be selected as BIM uses on projects. This only means
that the projects will have to use the generic tactical uses provided on the use by
Penn state University as basis. All 25 uses are listed in the appendix.
Please note that all uses are currently on tactical or strategic level. It is intended that
the individual projects update the tactical workflow into operational workflows
matching the project setup. BIM Uses can be classified primarily based on their
purpose in implementing BIM throughout the life of an asset. In addition to the
purpose alone, several other characteristics can be defined to properly identify and
communicate a BIM Use. These purposes and characteristics can be defined at
varying levels depending upon the level of maturity and detail required for different
applications of the Uses. The BIM Use Characteristics allow a user to further define
the BIM Use based on common asset and project attributes (Project information
requirements and asset information requirements, REF ISO19650) project element,
project phase, discipline, and Level of Development (LOD)
4
Figure 3: Way of illustrating different uses of BIM. All uses in the wheel is mapped to the
24 Penn state uses. The mapping is illustrated in appendix.
Each BIM use has one or more deliverables (the output row3) such as information
models or documents that either act as input to other BIM uses or as a “physical”
deliverable to the Appointing party or another party of the Project team always
matching the information requirement specifications set in The BEP/ICT agreement.
Based on the projects overall BIM strategy including the mission, vision, goals and
objectives for a project or organization, the planning team should identify the
appropriate BIM Uses in an early phase.
Each BIM Use has an initial description, including identified potential values. These
values can be used in the initial assessment on how to fulfil the goals of the project.
3
See BPMN process maps in appendix
5
A challenge and opportunity faced early on by planning team is identifying the most
appropriate uses for BIM on a project given the project characteristics. Many different
traditional tasks and processes can benefit by being replaced or optimized by the
implementation of BIM.
The appendix lists the 25 BIM uses where several are still under construction at this
moment. each BIM use consists of
1. A description, on what, when and why.
2. A description on the BIM use
3. Required competencies within the delivery team to execute the BIM use
4. Required applications to execute the BIM use
5. A workflow diagram containing:
a. Input row (data input necessary to carry out the BIM use, not processed
in previous BIM Uses. This data is provided either by appointing party
or appointed party (should be agreed in information assignment matrix
and information protocol ref. ISO19650)
b. A workflow for the executing party. including responsibilities for each
step in the workflow along with a description for each step
c. An output row describing the outcome of the BIM use as actual
deliveries. The output of a BIM use is measurable and subject to a
checklist. the output should always be documented by the executing
party. An output either acts as input in other BIM uses or as required
data handover to appointing party or third party e.g. contractor.
6
6. Figure 4: Structure of each BIM use
For better understanding on how to work with and implement BIM uses, it is
recommended that the reader studies the framework on this topic provided by Penn
State University ad https://www.bim.psu.edu/ (some of this framework is described
and summarized in section 4 and 5)
When setting up your BIM project it is important that you have a plan for when to
implement different BIM uses and who is responsible for executing the uses, in which
phases of the project these will be applied and exactly what output you expect.
1st a BIM kickoff workshop/meeting should be prepared. See section 6. The purpose
is to find relevant BIM uses supporting the goals of the project. Next it is decided
when to introduce the individual uses to the project
7
When this is done it is possible to set up the process maps and detailed
data/information delivery plan for each BIM use. and finally, the exchange
requirements in the information models should be set. The output either works as
delivery to other parties of the project team or as a specific contractual delivery.
Figure 5: Three overall phases when choosing, defining and executing your BIM uses
The goal for developing this structured procedure is to stimulate planning and direct
communication by the project team during the early phases of a project. The team
leading the planning process should include members from all the organizations with
a significant role in the project. Since there is no single best method for BIM
implementation on every project, each team must effectively design a tailored
execution strategy by understanding the project goals, the project characteristics,
and the capabilities of the team members.
A closer look at phase 1: This is where a value list is created, provided for each BIM
use, select the uses that ad most value in the specific project. After your organization
has defined overall BIM uses you should make a list describing pros and cons for
each BIM use so that project managers and BIM managers have a valid basis for
selecting the correct uses. Potential values but also team requirements are listed in
each BIM use of the appendix to make this task easier.
8
Figure 6: Phase 1, mapping value to use
A closer look at phase 2: This is where the processes are defined for the use.
Remember these must be supplemented with software specific guides that supports
the execution (operationalized)
Figure 7: Phase 2, Here an example of how 3D coordination could look like in practical
use
A closer look at phase 3: This is where the output and delivery associated with each
BIM use is defined. The output=the information model is either a delivery to another
party in the project or a delivery to another BIM use that needs the data as basis for
its own execution.
9
Figure 8: Phase 3, defining the output from the BIM uses. This is part of delivery
specification or scope of service on the project.
By following the chapters in this document along with the detailed planning guide
from Pennstate, it is expected that the goals and supporting BIM uses can be
10
defined, including the overall success criteria for implementing BIM on any given
project
Develop the information protocol, responability Sections in BEP developed Project specific for the
matrix and the Level of detail for each BIM use given project
One of the most important steps in the planning process is to clearly define the
potential value of BIM on the project and for project team members through defining
the overall goals for BIM implementation. These goals could be based on project
performance and include items such as reducing the schedule duration, achieving
higher field productivity, increasing quality, reducing cost of change orders, or
obtaining important operational data for the facility. Goals may also relate to
advancing the capabilities of the project team members, for example, the owner may
wish to use the project as a pilot project to illustrate information exchanges between
design, construction and operations or a design team may seek to gain experience in
the efficient use of digital design applications. Once the team has defined
measurable goals, both from a project perspective and company perspective, then
the specific BIM uses on the project can be identified.
11
Priority (1-3) Goal Description Potential BIM Uses
1- Most
Value added objectives
Important
Design Reviews, 3D
2 Increase Field Productivity Coordination
Design Authoring, Design
1 Increase effectiveness of Design Reviews, 3D Coordination
Accurate 3D Record Model for O&M Team Record Model, 3D
3 Coordination
Engineering Analysis, LEED
3 Increase effectiveness of Sustainable Goals Evaluation
2 Track progress during construction 4D Modeling
1 Identify concerns accosiated with phasing on campus 4D Modeling
3 Review Design progress Design Reviews
3 Quickly Asses cost associated with design changes Cost Estimation
2 Eliminate field conflicts 3D Coordination
All potential values for each BIM use are listed in the appendix containing BIM uses.
The uses are originally developed by Pennsylvania University and are part of the
American national building standards (NBIMS).
Once the goals are defined, the project team should identify the appropriate tasks
that the team would like to perform using BIM. This analysis of BIM Uses should
initially focus on the desired outcomes for the overall process. Therefore, the team
should begin with the Operations phase, and identify the value for each of the BIM
Uses as it specifically relates to the project by providing a High, Medium or Low
priority to each use. The team can then progress to each preceding project phase
To help facilitate this BIM Use review process, a BIM Selection Worksheet has been
developed. This template includes a list of the potential BIM Uses, along with fields to
review the value, responsible party, capabilities, additional notes, and the decision
from the team on whether to implement the BIM Use. below is an example only
containing 4 uses.
12
Value to Additional Resources /
Value to Responsible Capability Proceed
BIM Use* Resp Competencies Required to Notes
Project Party Rating with Use
Party Implement
High / Med / High / Med Scale 1-3 YES / NO /
Low / Low (1 = Low) MAYBE
Competency
Experience
Resources
Record Modeling HIGH Contractor MED 2 2 2 Requires training and software YES
Facility Manager HIGH 1 2 1 Requires training and software
Designer MED 3 3 3
Cost Estimation MED Contractor HIGH 2 1 1 Need training on latest software High value to owner due to NO
phasing complications, but costly to
Infrastructure needs implement at current stage
Classification system pending
4D Modeling HIGH Contractor HIGH 3 2 2 Need training on latest software High value to owner due to YES
Infrastructure needs phasing complications
Use for Phasing & Construction
Once the team has identified the BIM Uses, a process mapping procedure for
planning the BIM implementation needs to be performed. Initially, a high-level map
showing the sequencing and interaction between the primary BIM Uses on the
project is developed (see next figure as an example). This allows all team members
to clearly understand how their work processes interact with the processes performed
by other team members.
13
Figure 12: Level 1 BIM use showing the relation and output from different level 2 uses in
different project phases
After the high-level map is developed, then more detailed process maps should be
selected or designed by the team members responsible for each detailed BIM Use.
For example, the high-level map will show how the BIM authoring, Design Review,
cost estimating, and 4D modeling are sequenced and interrelated. A detailed map
will show the detailed process that will be performed executing party. these detailed
maps are provided already by BIMinfra on tactical level.
Once the appropriate process maps have been developed, the information
exchanges which occur between the project participants should be clearly identified.
It is important for the team members, in particular the author and receiver for each
information exchange transaction, to clearly understand the information content. This
information content for the exchange can be defined in the Information Exchange
protocol. It is also possible to use Penn State's information exchange sheet if a
standard protocol is not set up on the project itself.
14
Figure 13: Example on information exchange sheet.
Keep in mind that above sheet must be revised to match Danish terminology
discipline definition and the project phases of the specific project. The Current ICT
specification from BIM Infra gives the possibility of describing the delivery information
exchange through section 2. It is recommended that a table showing the output from
each BIM use is integrated to section 2 along with responsible party, receiving party
and format of the information delivery. See more on ICT specification through
reference list in the end.
After the BIM uses for the project have been identified, the project process maps are
customized, and the BIM deliverables are defined, the team must develop the
infrastructure needed on the project to support the planned BIM process. This will
include the definition of the delivery structure and contract language; defining the
communication procedures; defining the technology infrastructure; and identifying
quality control procedures to ensure high quality information models. All this should
be explained in the Projects BIM execution plan (BEP) or ICT specifications. See
reference list in chapter 11 for more info on these.
15
exchange, do not necessarily require collaboration. The key to successfully
developing the plan is to ensure that meetings are scheduled for the collaborative
tasks when needed, and that the non-collaborative tasks are completed in a timely
manner, in preparation for these meetings. The BIM Plan can be developed through
a series of collaborative meetings, followed by work tasks which take place between
the meetings. A series of four meeting have been defined to develop the BEP or ICT
incl. the BIM uses. The goal of presenting this four-meeting series is to illustrate one
structure that the team can use to effectively develop the plan. For some projects, the
team may be able to reduce the number of meetings through effective collaboration
between meetings.
The first meeting should focus on the discussion of the overall goals for implementing
BIM, along with identifying the BIM Uses. A draft agenda for this meeting would
include:
1. Introduce and Discuss BIM Experiences (both individual and organizational)
2. Develop BIM goals (reference BIM Goal template document found in
reference list)
3. Identify which BIM Uses to pursue (reference the BIM Uses worksheet found
in reference list)
4. Develop the frequency and sequencing for the BIM Uses and identify a
responsible party to develop the high level (Level One) BIM Overview process
map
5. Identify the responsible parties to develop detailed BIM Use process maps,
e.g., the level two maps (some uses are defined on level 2 in appendix)
6. Organize the schedule for future meetings
7. Agree on the tasks ahead and who is responsible for each
16
1. Review the initial BIM Goals and Uses
2. Review the high-level BIM Overview Process Map
3. Review the more detailed workflows from the various parties and identify
areas of overlap or gaps between the various modeling tasks
4. Review the process to address opportunities and concerns
5. Identify the primary information exchanges within the process
6. Identify responsible parties for coordinating each information exchange
including the author and user of each exchange
7. Allow sub-teams for each information exchange to coordinate potential interim
meetings as needed to discuss the information exchange requirements
8. Agree on the tasks ahead and who is responsible for each
This meeting should be attended by the owner, BIM managers and project manager
for the project (depending on stage and contract form).. It may also be valuable to
have contracting managers in attendance or have them briefed soon after this
meeting.
1. Review the initial BIM Goals and BIM Uses to ensure that the project planning
remains consistent with the initial goals
2. Review the information exchange requirements developed by the team
members between Meeting Two and Meeting Three
3. Identify the IT infrastructure needed to support the process and information
exchanges as defined in Chapter Five
4. Agree on tasks ahead and who is responsible for each
This meeting should be attended by the BIM managers. It may also be valuable to
have contracting managers in attendance or briefed soon after this meeting.
17
The categories and information should be compiled into the final BIM Execution Plan
or ICT specification and distributed to the project team in preparation for the final
BEP/ICT review meeting.
8 Acknowledgements
COWI a/s (For BIM wheel and other material on BIM uses)
18
9 Reference list
19
APPENDIX
The following pages will present the 25
BIM uses. They have been grouped into
categories dictated by the BIM wheel and
some workflows are still missing or
under development. Please note that all
uses are currently on tactical or strategic
level. It is intended that the individual
projects update the tactical workflow
into operational workflows. BIM Uses can
be classified primarily based on their
purpose in implementing BIM throughout
the life of an asset. In addition to the
purpose alone, several other
characteristics can be defined to properly
identify and communicate a BIM Use.
These purposes and characteristics can
be defined at varying levels depending
upon the level of maturity and detail
required for different applications of the
Uses. The BIM Use Characteristics allow
a user to further define the BIM Use
based on common asset and project
attributes (Project information
requirements and asset information
requirements, REF ISO19650) project
element, project phase, discipline, and
Level of Development (LOD)
20
BIM Uses
A guide on understanding and selecting BIM uses
Sept. 2020
Appendix
The 25 BIM Uses
Generic project phases
Priority in
Plan Design Construction Operations
BIMInfra
#1 Existing Conditions Modeling 1
#2 Cost Estimation (5D) 1
#3 Scheduling (4D) 1
#4 Programming
#5 Site Analysis 1
#6 Design Authoring 1
#7
Design Reviews 1
#8
Drawing Generation 2
#9 Lighting Analysis 2
#10 Energy Analysis 2
Engineering Analysis 1
#11
Value examples
› Establishment of a 3D model with details and information for specific purposes
› Rapidly collects information for communication and visualisation of existing conditions
› Enhances the efficiency and accuracy of existing condition information
› Provides accurate documentation of the environment for future use
› Verifies real-time progress
EXISTING CONDITIONS MODELLING
Description:
A process in which a project team develops a 3D model of the existing conditions for a site, facilities on a site, or a specific area within a
project. This model can be developed in multiple ways: including laser scanning and conventional surveying techniques, depending on what is
desired and what is most efficient. Once the model is constructed, it can be queried for information, whether it is for new construction or a
modernization project.
Potential Value:
• Enhances the efficiency and accuracy of existing conditions documentation
• Provides documentation of environment for future uses
• Aids in future modeling and 3D design coordination
• Provides an accurate representation of work that has been put into place
• Real-time quantity verification for accounting purposes
• Provides detailed layout information
• Use for visualization purposes
Resources Required:
• CAD software
• 3D Laser scanning (depending on BAS model required)
• Conventional surveying equipment (depending on BAS model required)
• BAS models in Denmark can be downloaded at:
http://kortforsyningen.dk/ http://ler.dk/
Team Competencies Required:
• Ability to manipulate, navigate, and review a 3D model
• Knowledge of Building Information Model authoring tools
• Knowledge of 3D laser scanning tools
• Knowledge of conventional surveying tools and equipment
• Ability to sift through mass quantities of data that is generated by a 3D laser scan
• Ability to determine what level of detail will be required to add “value” to the project
• Ability to generate Building Information Model from 3D laser scan and/or conventional survey data
BIM USE, EXISTING CONDITIONS MODELING
Geotechnical Historical Site /
Basis data
1.2
Survey Existing
Facilities
Responsible Party
1.2
Survey Existing Site
1.1 Conditions
NO
1.3 1.4
Process
Responsible Party
1.2
Laser Scan Existing
Conditions
Responsible Party
Information models
Value examples
› Defines detailing, information enrichment and design requirements in the model, and provides a solid basis
for the design team
› Enables efficient and accurate assessment of design performance such as requirements to areas, spaces,
rooms, surfaces, materials etc.
› Captures design changers during the design process
› Enables ongoing digital verification of the design model against the specified project requirements
PROGRAMMING
Description:
A process in which a spatial program is used to efficiently and accurately assess design performance in regard to spatial
requirements. The developed BIM model allows the project team to analyze space and understand the complexity of space
standards and regulations. Critical decisions are made in this phase of design and bring the most value to the project when
needs and options are discussed with the client and the best approach is analyzed.
Potential Value:
• Efficient and accurate assessment of design performance in regard to spatial requirements by the owner.
Resources Required:
• Design Authoring Software
Identify Building
Use/Type
Owner
NO
Identify Cost
Targets
Owner
Information models
Value examples
› Establishes a 3D model of the project
› Promotes collaboration, communication and transparency internally and externally on the project
› Encourages sharing of project information across the design team and other stakeholders which reduces
communication time and increases quality
DESING AUTHORING
Description:
A process in which 3D software is used to develop a Building Information Model based on criteria that is important to the translation of the
project's design. Authoring tools create models while audit and analysis tools study or add to the richness of information in a designed model.
Most of audit and analysis tools can be used for Design Review and Engineering Analysis BIM Uses.
Design authoring tools are a first step towards BIM and the key is connecting the 3D model with a powerful database of properties, quantities,
means and methods, costs and schedules.
Potential Value:
• Improved communcation of design to all stakeholders
• Improved ability for quality control of project design, costs and schedule
• Powerful design visualization
• True collaboration between project stakeholders and BIM users
Resources Required:
• Design Authoring Software
• Common Data Platform for sharing design models
START
6.5
YES NO
6.1 6.2 6.4 Create Design Model 6.6 6.7 6.8
Process
6.5
Agreed schedule for
update of
Create Design Model
disciplinary models
considering the
Discipline C
critical path of
process iteration
Information models
Centerlines Corridors Centerlines Corridors Disciplinary Disciplinary Disciplinary Disciplinary Disciplinary Disciplinary Disciplinary
Program Model model A model B model C model A model B model C model D
DESING AUTHORING
Description:
6.1 Identify which models are required.
6.2 Identify what the content shall be for the models (e.g. CAD manual or Modelstandard)
It is important to know the geometric prerequisites and to have basis data/models available.
6.3 It is important to identify the critical path for updating the disciplinary models in the iteration process of a design proje ct. The different
disciplines are interdependent and updating the different disciplinary models must be planned and stage of models must be kno wn at
all times. All the disciplines must be aware of and agree to this schedule.
6.4 Initial designmodels for Centerlines and Corridors are created and shared. In Civil works Centerlines and Corridors serve as basic
models for other disciplines.
6.5 According to schedule disciplines creates a design model. Starting from updated disciplinary models from other disciplines.
These models are all shared as disciplinary models according to schedule and as to a certain point of stage (WIP). These model are
now avaible to other disciplines and adjustments to design in models will take place.
NB! Before sharing a disciplinary model, each discipline performs a Discipline Control. Relevant models and areas to check are
predefined. Depending on phase and stages of models, the check will contain controls like Grafical Control and Consistency Co ntrol.
Each discipline consider if the design meets the requirements.
6.6 Have relevant changes been made? Consider if relevant changes is made and locate which disciplines it will affect.
If "YES" relevant changes have been made go back to 6.5. and adjust design, the iterative proces will begin or continue.
if "NO", no changes OR all changes have been implemented in all disciplines, then the iterative process will end, go to 6.7
6.7 Perform final Consistency Control.
6.8 Does the model meet the requirements?
If "YES" then the you have some finish design models to be used in the further BIM uses.
If "NO" then you have to go back to process 6.4 and adjust the design models.
3D COORDINATION
Why When What
With virtual 3D coordination of Design stages. A process in which the model
the project during the design, information and geometry are used
critical clashes can be managed for ongoing coordination of interfaces
and solved before construction, among all the disciplines. E.g.
reduces costs and increase automated clash detection to
efficiency. determine inconsistencies across
disciplines in the project. The goal of
clash detection is to eliminate critical
clashes during design and prior to
construction.
Value examples
› Coordinates through a digital model, and reduces and eliminates critical clashes
› Leads to more accurate design results and reduced construction costs and time
› Ensures improved and more efficient ongoing coordination throughout the design stages
3D COORDINATION
Description:
A process in which Collision control software is used during the coordination process to determine field conflicts by comparing Disciplinary 3d
models . The goal of clash detection is to eliminate the major disciplinary conflicts prior to construction.
Potential Value:
• Coordinate construction project through a model
• Reduce and eliminate field conflicts; which reduces RFI's significantly compared to other manually methods
• Visualize construction
• Increase productivity
• Reduced construction cost; potentially less cost growth (i.e. less change orders)
• Decrease construction time
• Increase productivity on site
• Models become more accurate to construct from
Resources Required:
• Design Authoring Software
• Model Review Software
3d disciplinary models
(Conflict Matrix)
Standards Requirements Requirements
Develop Schedule for Compile Composite Perform Collision Fill out Clash check Any Identify Solutions to Return to
YES
START Coordination Model (Interdisciplinary control form collisions Collisions Design
models) ? Authoring
All Disciplines BIM Coordinator BIM Coordinator All Disciplines
BIM Coordinator
NO
END
Information models
Description:
14.1 Develop a schedule for how offen 3D Coordination shall be done
14.2 Make a compile model to where to perform 3D coordination
Perform collision control. Use predefined Clash check form. This form tells you which models and elements that needs to be ch eck against
14.3 each other.
14.4 Fill out the Clash check form .
14.5 Check clash check form. If there are not Clash, you are finish with this process. If there are Clash you need to continue to process 14.6.
14.6 Consider if the clashes are relevant to correct. If yes, find a solution to correct the clashes and return to the BIM uses #6 - Design authoring to
correct the clash.
If no, the process will end and there will be an approved clash check form.
DESIGN REVIEW
Why When What
Model-based design review During planning and The process of ongoing model
ensures continuous evaluation design. review as part of the QA process
and QA of the evolving design, which implies that model content is
and enables visual validated within and across
communication and feedback disciplines. It allows the design team
directly in the model. and other stakeholders to provide
their feedback directly into the
model. This includes evaluation of
the design criteria and layout in a
virtual environment.
Value examples
› Increases coordination and communication among different parties which improves design decisions
› Ensures that all model content is reviewed and that the review is fed directly into the model
› Ensures effective evaluation of design against project criteria
› Ensures an efficient design review and QA process
DESIGN REVIEW
Description:
A process in which stakeholders view a 3D collaboration model and provide their feedbacks to validate multiple design aspects. These aspects include
evaluating meeting the program, in a virtual environment, and setting criteria such as. This BIM use can be done by using computer software only. This
use is executed through projectmeetings, internally and externally.
Potential Value:
• All reviews are recorded within the collaboration model and it provides you with a detailed history of the reviews
• Different design options and alternatives may be easily modeled and changed during design phase.
• Create shorter and more efficient design
• Evaluate to what extent the design meet the project criteria and owner's needs
• Enhance constructability and work safety
• Easily communicate the design to the owner, construction team and end users
• Get instant feedbacks on meeting program requirements and owner's needs.
• Greatly increase coordination and communication between different parties. More likely to generate better decisions for design
Resources Required:
• Common Data Platform
• Design Review Software
• Interactive review space
• Hardware which is capable of processing potential large model files
Standards Requirements
7.4
Perform User Review
Create virtual Mock-
7.9
ups
7.1 Supplier Return to Compile Design
Create Virtual Design Review Feedback
viewpoints in Authoring
collaboration tool BIM coordinator
BIM coordinator
7.5
Perform User Review
Create virtual Mock-
ups
NO
Client
7.8
Design YES
Process
7.2 7.6
Create Virtual Perform O & M Review
viewpointsfor Create virtual Mock-
O & M Review ups
BIM coordinator Asset owner
7.3 7.7
Perform
Compile Model for Constructability Review
constructability Review Create virtual Mock-
ups
BIM coordinator Contractor
Information models
Description:
7.1 BIM coordinator create Virtual viewpoints in collaboration tool
7.2 BIM coordinator link nesserary infomation and create Virtual viewpoints for operation and maintenance review.
7.3 BIM coordinator link nesserary infomation and create Virtual viewpoints for constructability Review
7.4 Supplier perform user review, create virtual Mock-ups
7.5 Client perform user review, create virtual Mock-ups
7.6 Asset owner perform operation and maintenance review, create virtual Mock-ups
7.7 Contractor perform constructability Review, create virtual Mock-ups
7.8 Client and supplier evaluate if design is acceptable. If the model not meet the requirements, you need to go to pocess 7.9.
7.9 BIM coordinator compile design review feedback, and you need to go back to design authoring adjust the model.
VISUALISATION
Why When What
Simple visual communication to During planning, design A process intended to communicate
all project stakeholders by using and construction. the design or analysis results based
the model content and on the model. Visualisations include
information to early involvement photorealistic images, presentations
and enhance understanding to of flow (sequencing, people etc.)
improve the basis for decisions. and advanced augmented reality
presentations. It also includes
dynamic visualisations such as walk-
throughs and virtual reality
experiences with acoustics.
Value examples
› Easy communication of design intent to non-technical stakeholders
› Basis for faster decision making
› Simple visualisation of results from technical analysis and simulations
› Co-creation with external parties such as end users and operational staff
› Marketing and publicising the project using virtual reality
VISUALISATION
Description:
A process intended to communicate the design or analysis results based on the model. Visualisations include photorealistic images,
presentations of flow (sequencing, people etc.) and advanced augmented reality presentations.
Potential Value:
• Easy communication of design intent to non-technical stakeholders
• Basis for faster decision making
• Simple visualisation of results from technical analysis and simulations
• Co-creation with external parties such as end users and operational staff
• Marketing and publicising the project using virtual reality
Resources Required:
• Model Review Software
NO
Process
Design Models
(Design Authoring)
ANALYSIS
Why When What
Model-based analysis enables During planning and The process of performing analyses
creating multiple virtual scenarios design and construction. based on the model content or
to support project decisions enriching the model with the results
during design, reducing time from an analysis by use or reuse of
spent in planning, design and information. The design process can
operation. also be automated using advanced
analysis tools based on artificial
intelligence (AI) applied to the
digital model.
Value examples
› Enhanced design progress by performing analysis directly in the model such as energy, comfort,
environmental, structural, fire and evacuation and lighting analyses
› Improves the quality of the design analyses and more accurate predictions by auto-determining model
information
› Reduces time consumption by performing automated code checks
› Makes it easy to assess different design options, alternatives and consequences
ANALYSIS
Potential Value:
• Save time and cost on creating extra models
• Easier transition BIM authoring tools allowing new firms implementing this use model
• Improve specialized expertise and services offered by the design firm
• Achieve optimum efficient design solutions by applying various rigorous analyses
• Faster return on investment with applying audit and analysis tools for lighting analyses
• Improve the quality of the design analyses
• Reduce the cycle time of the design analyses
Resources Required:
• Design Authoring Tools
• Lighting Analysis analysis tools and software
• Design standards and codes
• Adequate hardware for running software
Lighting Engineer
NO
Identify Lighting Generate Lighting Generate Basic Modify Model for YES
Lighting Analysis building Lighting Design
START Criteria Layout Lighting Model Analysis Lighting Levels lighting Model
PROCESS Application Application END PROCESS
acceptab
Lighting Engineer Lighting Engineer Lighting Engineer Lighting Engineer Lighting Engineer Lighting Engineer le? Lighting Engineer Lighting Engineer
Lighting Engineer
Information models
Architecture Model Other Applicable Models Structural Model Lighting Design Model Lighting Analysis Model Lighting Design Model
(Draft)
ANALYSIS
Potential Value:
• Use calculated decision making to determine if potential sites meet the required criteria according to project requirements, technical factors, and
financial factors
• Decrease costs of utility demand and demolition
• Increase energy efficiency
• Minimize risk of related to MSSS (health, safety and welfare)
• Maximize return on investment
Resources Required:
• CAD and GIS software (Basis models)
• 3D Model manipulation
5.3
Analyze Project Site
Data NO
NO
5.1 5.2 5.5
Is site Responsible Party Determine Project
Process
Potential Value:
• Automating analysis and saving time and cost
• Analysis tools are less costly than BIM authoring tools, easier to learn and implement and less disruptive to established workflow
• Improve specialized expertise and services offered by the design firm
• Achieve optimum, energy-efficient design solution by applying various rigorous analyses
• Faster return on investment with applying audit and analysis tools for engineering analyses
• Improve the quality and reduce the cycle time of the design analyses
Resources Required:
• Design Authoring Tools
• Engineering analysis tools and software
Potential Value:
• Facilitates interaction, collaboration and coordination of team members early in the project process are considered to be favorable to sustainable projects.
• Enables early and reliable evaluation of design alternatives.
• Availability of critical information early helps problem resolution efficiently in terms of cost premium and schedule conflicts.
• Shortens the actual design process by the help of early facilitated design decisions. Shorter design process is cost effective and provides more time for other projects.
• Leads to delivery better project quality.
• Reduces documentation load after design and accelerates certification because concurrently prepared calculations can be used for verification.
• Reduces operational costs of the facility due to the energy performance of the project. It optimized building performance via improved energy management.
• Increases the emphasis on environmentally friendly and sustainable design.
• Assists project team with potential future revisions throughout the life cycle.
Resources Required:
• Design authoring software
Potential Value:
• Validate that building design is in compliance with specific codes, e.g. IBC International Building Code, ADA Americans with Disabilities Act
guidelines and other project related codes using the 3D BIM model.
• Code validation done early in design reduces the chance of code design errors, omissions or oversights that would be time consuming and more
expensive to correct later in design or construction.
• Code validation done automatically while design progresses gives continuous feedback on code compliance .Â
• Reduced turnaround time for 3D BIM model review by local code officials or reduced time that needs to be spent meeting with code
commissioners, visiting the site, etc. or fixing code violations during punch list or closeout phase.
• Saves time on multiple checking for code compliance and allows for a more efficient design process since mistakes cost time and money.
Resources Required:
• Local codes
• Model checking software
• 3D Model manipulation
Potential Value:
• More easily identify and allocate space for appropriate building use
• Increase the efficiency of transition planning and management
• Proficiently track the use of current space and resources
• Assist in planning future space needs for the facility
Resources Required:
• Bi-directional 3D Model Manipulation; software and record model integration
• Space mapping and management input application (Mapguide, Maximo, etc.)
Potential Value:
• Provide police, fire, public safety officials, and first responders access to critical building information in real-time
• Improve the effectiveness of emergency response
• Minimize risks to responders
Resources Required:
• Design review software to view Record Model and components
• Building Automation System (BAS) linked to Record Model
• Computerized Maintenance Management System (CMMS) linked to Record Model
Potential Value:
• Ensure building is operating to specified design and sustainable standards
• Identify opportunities to modify system operations to improve performance
• Create a "what if" scenario and change different materials throughout the building to show better or worse performance conditions
Resources Required:
• Building Systems Analysis Software(Energy, Lighting, Mechanical, Other)
Facility Manager NO NO
Adjust BIM for Validate
Process
n? le?
Responsible Party Responsible Party Responsible Party Facility Manager Facility Manager
Facility Manager
Information models
Potential Value:
• Increase constructability of a complex project
• Increase construction productivity
• Increase safety awareness of a complex building system
• Decrease language barriers
Resources Required:
• 3D System design software
Value examples
› Generation of coherent plans, elevations and sections for documentation
› Improves communication of design intent with additional 2D and 3D views and sketches
› Increases consistency between different type of drawings as the geometry and other information are
extracted from the same model
DRAWING PRODUCTION
Description:
A process in which building information modeling and the model itself is used to create drawings and drawing sets. This inclu ding
Schematic, Design Development, Construction and Shop Drawing. "With building information modeling, each building object
instance - its shape, properties, and placement in the model - is defined only once." (Eastman et al. 2008). The same building
model can be used to create all drawing, reports, and analysis datasets. This eliminates the need to manully update each drawing
for each design change. Additionally standard construction details can be generated directly from the model, however it may b e
necessary to add additional information that is not contained within the facility model.
Potential Value:
• Quickly generate multiple views(plan, elevations, sections, and details) from a single facility model
• Improved quality of drawing that better explain design intent with additional views such as isometric and 3D views
• Automatically update drawing sets based on changes in the model
• Autopopulate schedules
• All data is extracted from the same model therefore increasing consistency between different views of the same data
Resources Required:
• Design authoring software with the ability to generate drawings
Value examples
› Identifies scheduling, sequencing or phasing issues, enabling improved resource allocation
› Conveys the spatial complexities of the project and provides a better upfront understanding of the phasing
schedule by showing the critical path of the project
› Space and workspace conflicts are identified and resolved ahead of the construction process
› Detailed location-based scheduling in major projects to accurately understand the construction phase
SCHEDULING
SUB Use : SCHEDULING (4D)
Description:
A process in which a 4D model (3D models with the added dimension of time) is utilized to effectively plan the phased occupancy in a renovation,
retrofit, addition, or to show the construction sequence schedule update, workflow, space utilization and challanges on a building site. 4D modeling
is a powerful visualization and communication tool that can give planner, designer, contractor, operator including the owner a better understanding
of project milestones and live updates to avoid collision in same working area, to optimize cost and execution time schedule and increase
effictivity.
Potential Value:
• Better understanding of the phasing schedule by the owner and project participants and showing risk buffers including Critical Path of the project
• Risk analysis with mitigated or un-mitigated aspects
• Dynamic phasing plans of occupancy offering multiple options and solutions to site space conflicts
• Integrate planning of human, equipment, location and material resources with the BIM model to better schedule and cost estimate the projects
• Space and workspace conflicts identified and resolved ahead of the construction process
• Preliminary design assesment (black box) Early stage assumption of future elements allocation and proportions
• Avoiding collision in same working area or to follow chronological steps, such as earthworks, sewage system, sleepers and then catenary masts
• Control of quantity (removal, dispocal, intermidiate storage, reusage, incoming)
• Optimize location vs. time as much as possible
• Client has overview of planned vs. actual (real time) progress on site
• Early implementation of Facility Management to contribute data for optimization.
• Better method for tender/bidding procedure, and contractors will be able to see the complexity of individual task, and to influate the conditions
(turnkey contracts)
• Workshop for site planning with participants from all interface projects - optimizing Site Management
• Marketing purposes and publicity
• Weekly or regular Design update to project owner
• Weekly or regular site update based on progress, which show planned progress vs. actual progress and result of remaining works (depend on
units)
• Animation showing execution possibilities (methods)
• Identification of schedule, sequencing or phasing issues
• More readily constructible, operable and maintainable project
• Monitor procurement status of project materials
• Increased productivity and decreased waste on job sites
• Conveying the spatial complexities of the project, planning information, and support conducting additional analyses
SCHEDULING
3.3
Prepare schedule of the 3.9
execution process for Prepare schedule of the
4D execution process for
3.1 4D
3.7
All Disciplines Update/report 4D- All Disciplines
model of the execution
process NO
Prepare entire project 3.2 3.4 3.6
for production of 4D All Disciplines 3.10
Tender Prepare 3D-model for Tender
3.8 is result of 3.7 Prepare 3D-model for Model &
START 4D
3.8 4D schedule
Consultant/Designer All available Disciplines Contractor correct?
As-built material All available Disciplines
All Disciplines 3.5 YES
All available Disciplines 3.11
Asset-/meta data for
4D Contractor biding/preparation Asset-/meta data for
Process
Bygherre 4D
All available Disciplines
All available Disciplines
Rådgiver/bygherr
e Client/inspection
NO
NO
3.12 3.13 3.14
Link 3D Elements to Validation Accuracy Review 4D
YES Schedule YES
Activities of 4D Models Model Model/Schedule
optimize END
correct?
All Disciplines d?
4D Modeler All Disciplines
Information models
Forecast the schedule in advance of (delayed) tasks or clearing area for upcoming material delivery within
the nearest future
SCHEDULING
SUB Use: SITE UTILIZATION PLANNING
Description:
A process in which BIM is used to graphically represent both permanent and temporary facilities on site during multiple phases of the
construction process. It may also be linked with the construction activity schedule to convey space and sequencing requirements. Additional
information incorporated into the model can include labor resources, materials with associated deliveries, and equipment location. Because
the 3D model components can be directly linked to the schedule, site management functions such as visualized planning, short-term re-
planning, and resource analysis can be analyzed over different spatial and temporal data.
Potential Value:
• Efficiently generate site usage layout for temporary facilities, assembly areas, and material deliveries for all phases of construction
• Quickly identify potential and critical space and time conflicts
• Accurately evaluate site layout for safety concerns
• Select a feasible construction scheme
• Effectively communicate construction sequence and layout to all interested parties
• Easily update site organization and space usage as construction progresses
• Minimize the amount of time spent performing site utilization planning
Resources Required:
• Design authoring software
• Scheduling software
• 4D model integration software
• Detailed existing conditions site plan
Add Construction
Equipment
Contractor
Analyze Site
Layout for Phase
NO Transition
NO
Process
Contractor
Identify Determine Are all
phases Distribute Plan to
Construction Temporary YES Is plan YES
START analyzed acceptab Various Parties
PROCESS Phases Facilities (occurs END PROCESS
Contractor
Information models
Value examples
› Quick generation of quantities from the model for cost estimates
› Better visual representation of cost elements that must be estimated in the model
› Allows estimators to focus on more value-adding activities in estimating such as identifying construction
assemblies, generating pricing and factoring in risks, which are essential for high quality estimates
› Easier exploration of different design options and concepts based on project budget
› More accurate cost estimation from early stages to tendering
COST ESTIMATION
Description:
A process in which BIM can be used to assist in the generation of accurate quantity take-offs and cost estimates throughout the lifecycle of a project. This process allows the project team
to see the cost effects of their changes, during all phases of the project, which can help curb excessive budget overruns due to project modifications. Specifically, BIM can provide cost
effects of additions and modifications, with potential to save time and money and is beneficial already from early design stages to Facility Management stage of any project.
Potential Value:
• Precisely quantify modeled materials
• Earn Value Analyse graphs (EVA) to control the actual budget to follow the planned
• Resource utilization diagram within contractors - to control site safety measures
• Cost risk analysis and easy way to add values to the system, no matter of units
• Quickly generate quantities to assist in the decision making process
• Generate more cost estimates at a faster rate
• Better visual representation of project and construction elements that must be estimated
• Provide cost information to the owner during the early decision making phase of design and throughout the lifecycle, including changes during construction
• Saves estimator's time by reducing quantity take-off time
• Allows estimator's to focus on more value adding activities in estimating such as: identifying construction assemblies, generating pricing and factoring risks, which are essential for high
quality estimates
• Added to a construction schedule (such as a 4D Model), a BIM developed cost estimate can help track budgets throughout construction
• Easier exploration of different design options and concepts within the owner's budget
• Quickly determine costs of specific objects and processes
• Easier to strain new estimators through this highly visual process
• Real time budget/payment updates and billing process throughout all phases
• Lifecycle planning of components and its validity included to cost estimation
• FM overall budget specifies individual object/component based on FM system requirement (E.g. SAP S/4 HANA)
• Time schedule has an impact on cost estimation
Resources Required:
• Model-based estimating software (4D-model is prefered)
• Design authoring software
• Accurately built design model Accurately built design model combined with reduced level of information/models
• Cost data (Including Masterformat and Uniformat data)
• Access to asset data/pricebook for overall/detail price estimation
2.1
Prepare 4D-model
(Synchro file) for 5D
2.3 2.4 NO NO
2.18
All available Disciplines Request costs by 2.5 2.6
Establish Cost Incorporate
Tender objects/schedule/resou Review
Estimates to YES Contingencies/
rce Cost Adjust BIM for Takeoff Model
2.2 Overhead
objects/resource Estimate
Contractor Client YES ready
Asset-/meta data for Contractor accept Contractor
Contractor
5D
Bygherre
END
2.10
Process
Contractor
Value examples
› Optimises and measures field performance of construction trends across progress and quality
› Allows the model to be used in daily inspections and to produce information take-off and 2D/3D views on the fly
› Supports daily reporting and communication of the construction progress directly in the model
› Improves construction quality control programs by creating and assigning issues directly in the model
› Provides accurate collection and documentation of asset data for commissioning and maintenance
FIELD INFORMATION
Potential Value:
• Ensuring quality of information
• Minimize tolerances through machine fabrication
• Increase fabrication productivity and safety
• Reduce lead time
• Adapt late changes in design
• Reduced dependency on 2D paper drawings
Resources Required:
• Design Authoring Software
• Machine readable data for fabrication
• Fabrication methods
Potential Value:
• Decrease layout errors by linking model with real world coordinates
• Increase efficiency and productivity by decreasing time spent surveying in the field
• Reduce rework because control points are received directly from the model
• Decrease/Eliminate language barriers
Resources Required:
• Machinery with GPS capabilities
• Digital Layout Equipment
• Model Transition Software (what software takes model and converts it to usable information).
NO NO
18.1 18.2 18.3 18.4 18.5 18.6 18.7
Is
Process
Determine Scope of Identify Alternative Model Alternative Analyze Various Compare and Select Coordinate Construc- constructi Generate Construction
Is model YES YES
Work to be Analyzed Construction Methods Methods Methods Options tion Sequences on Plans
START acceptab END
sequence
le? acceptabl
Contractor Contractor Contractor Contractor Contractor Contractor Contractor
e?
Information models
Value examples
› Exports as-built information for the model to be reused in an external asset management system
› Stores and maintains up-to-date facility and equipment data, including but not limited to maintenance schedules,
warranties, manufacturer’s data and equipment functionality
› Produces accurate quantity take-offs of current company assets to support financial reporting, tendering and
estimating the future cost
› The model allows users to visualise the asset before servicing it, potentially reducing service time
ASSET MANAGEMENT
SUB Use: Record Modeling
Description:
Record Modeling is the process used to depict an accurate representation of the physical conditions, environment, and assets of a facility.
The record model should, at a minimum, contain information relating to the main architectural, structural, and MEP elements. It is the
culmination of all the BIM Modeling throughout the project, including linking Operation, Maintenance, and Asset data to the As-Built model
(created from the Design, Construction, 4D Coordination Models, and Subcontractor Fabrication Models) to deliver a record model to the
owner or facility manager. Additional information including equipment and space planning systems may be necessary if the owner intends
to utilize the information in the future.
Potential Value:
• Aid in future modeling and 3D design coordination for renovation
• Improve documentation of environment for future uses, e.g., renovation or historical documentation
• Aid in the permitting process (e.g. continuous change vs. specified code.)
• Minimize facility turnover dispute (e.g. link to contract with historical data highlights expectations and comparisons drawn to final
product.)
• Ability for embedding future data based upon renovation or equipment replacement
• Provide owner with accurate model of building, equipment, and spaces within a building to create possible synergies with other BIM
Uses
• Minimize building turnover information and required storage space for this information
• Better accommodate owner's needs and wants to help foster a stronger relationship and promote repeat business
• Easily assess client requirement data such as room areas or environmental performance to as-designed, as-built or as-performing data.
Resources Required:
• 3D Model Manipulation Tools
• Compliant Model Authoring Tools to Accommodate Required Deliverable
• Access to Essential Information in Electronic Format
• Database of Assets and Equipment with Metadata (Based upon Owner's Capabilities)
Additional Information:
In order to properly exhaust all opportunities for utilizing such a model, dialog must take place before the
project begins. The critical factor to the success of creating a record model comes with properly documenting
the owner's intended use of the information stored within the model. Once these uses are outlined, the
necessary parties can produce the required information and embed the necessary infrastructure into the
model to support this future information. Other resources such as a deliver/turnover strategy, comprehensive
implementation plan and level of detail documents must also be established. Â Furthermore, with the
continuous updating and improvement of the record model and the capability to store more information, the
model serves as a living document that contains an accurate snapshot of the completed space. The model
should contain necessary links to pertinent information such as serial codes, warranties, and operation and
maintenance history of all the components within the building. Subsequently, this model could be used to
monitor the efficiency of the building from an operating standpoint. The record model also contains information
linking pre-build specifications to as-built conditions as well as post-construction/operations/renovations. This
allows the owner to monitor the project relative to the specifications provided. Additionally, if the model
contains the systems described herein, the owner could potentially use the model to aid in future projects and
can effectively serve as an existing conditions model for any subsequent projects. This process should repeat
with every modification to the building in order to maintain an accurate depiction of the space and equipment
within. Finally, it is important that the owner views the facilities maintenance as beyond just a “glorified janitor”
while the A/E and CM/GC’s consider post-construction design issues just as much as early design phases and
pre-construction activities.
BIM USE, RECORD MODELING
Project Submittal
Equipment Information Information COBIE Requirements
Basis data
NO
Process
Potential Value:
• Plan maintenance activities proactively and appropriately allocate maintenance staff
• Track maintenance history
• Reduce corrective maintenance and emergency maintenance repairs
• Increase productivity of maintenance staff because the physical location of equipment/system is clearly understood
• Evaluate different maintenance approaches based on cost
• Allow facility managers to justify the need and cost of establishing a reliability centered maintenance program
Resources Required:
• Design review software to view Record Model and components
• Building Automation System (BAS) linked to Record Model
• Computerized Maintenance Management System (CMMS) linked to Record Model
• User-Friendly Dashboard Interface linked to Record Model to provide building performance information and/or other information to educate
building users
NO
Process
Facility Manager Facility Manager Facility Manager Responsible Party Responsible Party Facility Manager
Information models
Potential Value:
• Store operations, maintenance owner user manuals, and equipment specifications for faster access.
• Perform and analyze facility and equipment condition assessments
• Maintain up-to-date facility and equipment data including but not limited to maintenance schedules, warranties, cost data, upgrades, replacements, damages/deterioration,
maintenance records, manufacturer's data, and equipment functionality
• Provide one comprehensive source for tracking the use, performance, and maintenance of a building's assets for the owner, maintenance team, and financial department
• Produce accurate quantity takeoffs of current company assets which aids in financial reporting, bidding, and estimating the future cost implications of upgrades or
replacements of a particular asset.
• Allow for future updates of record model to show current building asset information after upgrades, replacements, or maintenance by tracking changes and importing new
information into model.
• Aid financial department in efficiently analyzing different types of assets through an increased level of visualization
• Increase the opportunity for measurement and verification of systems during building occupation
• Automatically generate scheduled work orders for maintenance staff.
Resources Required:
• Asset Management system
• Ability to Bi-directional link facilities record model and Asset Management System.