Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 108

1

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

SUMMARY OF PROJECT COST

Err:509

### F.Y. 2077/78

S.N. Items/Description Quantity Amount Total Amount (NRs)


A Civil Work
i Building 1.00 Err:509 Err:509
ii Septic Tank Soak Pit and Manhole 1.00 525,950.91 525,950.91
iii Underground Water Tank 1.00 984,681.40 984,681.40
Total Civil Work Cost = Err:509
B Electrical Work
i Building 1.00 548,152.13 548,152.13
Total Electrical Work Cost = 548,152.13
C Sanitary Work
i. Ground Floor Sanitary Installation Work 1.00 122,587.36 122,587.36
ii. First Floor Sanitary Installation Work 1.00 71,056.75 71,056.75
iii. External Sanitary Installation Work 1.00 328,900.46 328,900.46
Total Sanitary Work Cost = 522,544.56
D Total Building Cost (A+B+C) Err:509
E Provisional Sum Err:509
F Sub- Total (D+E) Err:509
Contingencies for work charge establishment and site
G Err:509
supervision @ 4% of F
H Sub- Total (F+G) Err:509
I Provision for Physical Contingency @ 10% of H Err:509
J Provision for Price Escalation @10% of H Err:509
K Sub- Total (H+I+J) Err:509
L VAT 13% of K Err:509
M Grand Total (K+L) Err:509

Prepared by: Checked by Approved by


2

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost of Provisional Sum

Err:509
Err:509

S.N. Description Unit Amount Rate Premium


The payment/ expenditure of items
mentioned in provisional sum will be
made as per submitted original invoice
A Lab Test for construction work, materials
& others Ps 1 Job 86,908.00
B As Built Drawing
Civil engineer month 1.00 35,990.00 35,990.00
Architect month 1.00 35,990.00 35,990.00
Computer operator month 0.50 26,400.00 13,200.00
Stationary lot 1.00 L/S 20,000.00
Sub Total As built 105,180.00
C Insurance
Insurance premium for the work, plant and
materials damage for contract work for all
risk including Riot,Strike,
1 Damage,Malicious damage for contract
work of 110% of estimated cost for 2 years
+ 1 year Maintenance period.
year 3.00 Err:509 Err:509

Insurance premium for the insurance of


2 owner and consultant staff (named) Rs.
10,00,000.00 per person for 10 persons
with unlimited number of occurances per
annum year 2.00 20,010.00 40,020.00
Insurance Premium for construction
3 equipments and machines with value of Rs.
40,00,000.00 year 2.00 8,130.00 16,260.00

Insurance Premium for third party liability


4
personal only per person Rs.4,00,000.00
for 10 persons and third party property of
NRs. 50,00,000.00 for unlimited occurance year 3.00 137,140.00 411,420.00
Sub Total Insurance Err:509
Total provisional sum Err:509

Prepared by: Checked by Approved by


3

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

PREMIUM CALCULATION FOR INSURANCE

Err:509
Err:509

Project Worth NRs Err:509


1 Insurance premium for the work, plant and materials damage for contract work for all risk including
Riot,Strike, Damage,Malicious damage for contract work of 110% of estimated cost for 2 years + 1
year Maintenance period.

Works 110% of Project Worth Rs. 3.03 per thousand Rs Err:509


For stamp duty Rs 10.00
Premium with stamp duty Rs Err:509
2 Insurance premium for the insurance of owner and consultant staff (named) Rs. 10,00,000.00 per
person for 10 persons with unlimited number of occurances per annum
Personnel accident of 10,00,000.00 for
Rs.2.00 per thousand Rs 20,000.00
10
For stamp duty Rs 10.00
Premium with stamp duty Rs 20,010.00
3 Insurance Premium for construction equipments and machines with value of Rs. 40,00,000.00

Insurance premium of Rs. 40,00,000.00 Rs.2.03 per thousand Rs 8120.00

For stamp duty Rs 10.00


Premium with stamp duty Rs 8130.00
4 Insurance Premium for third party liability personal only per person Rs.4,00,000.00 for 10 persons
and third party property of NRs. 50,00,000.00 for unlimited occurance
P.A. of third party 10 person Rs. 3.03 per thousand Rs 12120.00
For Third Party Property Rs. 25 per thousand Rs 125000.00
For stamp duty Rs 20.00
Premium with stamp duty Rs 137,140.00
Total excluding. Vat Err:509 Per Annum

Prepared by: Checked by Approved by


4

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Materials Testing

Err:509
Err:509

S. No. Description of Work Unit Quantity Rate Amount Remarks


1 Concret Test
a Cubes or Cylinder crushing nos 24.00 200.00 4,800.00
2 Brick Test
a Brick Test nos 2.00 1400.00 2,800.00
3 Aggregate Test
a Aggregate Crushing Value Test nos 1.00 489.00 489.00
b Aggregate Impact Value Test nos 1.00 350.00 350.00
4 Sieve Analyais
a Sieve Analyais(Wet) nos 2.00 844.00 1,688.00
b Sieve Analyais(Dry) nos 2.00 450.00 900.00
5 U.T.M.Tensile Strength Test
a 8mm ø nos 2.00 1200.00 2,400.00
b 10mm ø nos 2.00 1200.00 2,400.00
c 12mm ø nos 2.00 1200.00 2,400.00
6 Cement Test set 1.00 3500.00 3,500.00
Total = 21,727.00
Grand
4 times Total = 86,908.00

Prepared by: Checked by Approved by


5

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost

Err:509

Err:509
SN. Description of Works Quantity Unit Rate Amount Remarks
A CIVIL WORK :-
Earthwork in excavation in medium
type soils in foundation including
1.00 10m hauling distance and 1.8 m. lift 1,400.25 cum 549.61 769,589.22
all complete in approval of site
engineer.

Supplying and Soling Local flat brick


in proper line and level with sand
2.00 filling all complete as per approved 1,166.29 sqm 2,219.88 2,589,027.52
drawing, Specification and instruction
of site engineer.

Plain cement Concrete (PCC) in 1:3;6


ratio for foundations and flooring
with approved quality of cement, sand
and machine crushed stone aggregate
3.01 including supply of materials,mixing, 87.47 cum 9,745.72 852,474.80
laying, curing the work at least 7 days
etc all complete as per approved
drawing, Specification and instruction
of site engineer.

Plain cement Concrete (PCC) for


RCC works M20 (1:1.5:3) for
slab/lintels/columns/beams with
approved quality of cement, sand and
machine crushed stone aggregate
4.00 1,158.25 cum 16,041.13 18,579,640.17
including supply of materials,mixing,
laying, curing the work at least 7 days
etc all complete as per approved
drawing, Specification and instruction
of site engineer.

TMT steel reinforcement bar of fe 500


grade including supplying,
straightening, cleaning, cutting,
binding & fixing in position with
5.00 - MT 120,797.73 -
annealed tying binding wire all
complete as per approved drawing,
Specification and instruction of site
engineer.

Prepared by: Checked by Approved by


6

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost

Err:509

Err:509
SN. Description of Works Quantity Unit Rate Amount Remarks

Formwork, shuttering, centering with


19mm thick waterproof ply board and
steel post for all works necessary
propping, scaffolding, staging,
supporting inclusive of wedging and
6.00
cutting holes for utilization till the
support if fully unyielding nett all
complete as per approved drawing,
Specification and instruction of site
engineer.

Err:509 Err:509 Err:509 Err:509 680.68 Err:509


Err:509 Err:509 Err:509 Err:509 1,135.88 Err:509
Err:509 Err:509 7,675.57 sqm 1,135.88 8,718,493.36

Good quality local chimney made


Brickwork in 1:4 C/S mortar up to
Ground floor in perfect line level
finish including supply of materials,
7.01 wetting the bricks, racking the joints 202.50 cum 15,129.66 3,063,803.08
and curing the work for at least 7 days
all complete as per approved drawing,
Specification and instruction of site
engineer.

Good quality local chimney made


Brickwork in 1:4 C/S mortar in
superstructure in perfect line level
finish including supply of materials,
wetting the bricks, racking the joints
7.02 and curing the work for at least 7 days Err:509 cum 15,473.16 Err:509
all complete as per approved drawing,
Specification and instruction of site
engineer.

Supplying and fixing aluminium


hinge fabrication, natural colour anod
aluminium door including door closer,
americian handle, stopper, aldrop,
8.01 lock, rubber, brush, gaskets and Err:509 sqm 11,913.71 Err:509
necessary hardware,etc with section
size (101.6x44.5x1.2)mm as per
specification and instruction of site
engineer

Prepared by: Checked by Approved by


7

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost

Err:509

Err:509
SN. Description of Works Quantity Unit Rate Amount Remarks

Two/three paneled Aluminium sliding


window with fixed ventilation section
8.02 size (101.6x38.1x1.2)mm and 4mm 544.86 sqm 9,843.71 5,363,474.44
clear glass, auto lock, knobs, gaskets
including mosquito-proof net panel.

Supplying and Laying of 12.5mm


thick cement sand plaster in (1:4) ratio
on ceiling of good finish including
supply of materials, racking the joint,
9.01 2,918.77 sqm 363.22 1,060,155.02
wetting of surfaces & curing the work
at least 7days all complete as per
approved drawing, Specification and
instruction of site engineer

Supplying and Laying of 12.5mm


thick cement sand plaster in (1:4) ratio
on wall of good finish including
supply of materials, racking the joint,
9.02 5,435.37 sqm 335.74 1,824,870.64
wetting of surfaces & curing the work
at least 7days all complete as per
approved drawing, Specification and
instruction of site engineer.

Supplying & applying Cement putty


on plastered surface all complete as
10.01 11,157.01 sqm 112.49 1,255,079.47
per approved drawing, Specification
and instruction of site engineer

Supplying & applying 2 coats


Emulsion painting in Internal
Room of approved colour with one
coat of primer Painting over porperly
10.02 8,354.14 sqm 182.01 1,520,510.49
cleaned surface at outside of building
all complete as per approved drawing,
Specification and instruction of site
engineer.

Prepared by: Checked by Approved by


8

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost

Err:509

Err:509
SN. Description of Works Quantity Unit Rate Amount Remarks

Supplying & applying 2 coats of


weather paint at outside of Building
of approved colour with one coat of
primer Painting over porperly cleaned
10.03 2,802.87 sqm 238.13 667,458.23
surface at outside of building all
complete as per approved drawing,
Specification and instruction of site
engineer.

Plain cement Concrete (PCC)(38mm)


in 1:2:4ratio for foundations and
flooring with approved quality of
cement, sand and machine crushed
stone aggregate including supply of
11.01 2,671.16 sqm 614.52 1,641,478.23
materials,mixing, laying, curing the
work at least 7 days etc all complete
as per approved drawing,
Specification and instruction of site
engineer.

3mm punning in 1:1 ratio for flooring


with approved quality of cement,
sand including supply of
materials,mixing, laying, curing the
11.02 1,819.02 sqm 273.75 497,948.48
work at least 7 days etc all complete
as per approved drawing,
Specification and instruction of site
engineer.

Supplying and laying 6 mm thick


porcelain glazed/non-glazed tiles in
11.03 cement sand mortar (1:4) ratio with 828.33 sqm 3,082.30 2,553,162.56
approved quality on wall and floor all
complete.

Providing and laying 16mm thick


marble on floor with 20mm 1:4 c/s
motar including grinding and
11.04 182.63 sqm 2,447.90 447,048.81
polishing as per drawing,
specification and instruction of
engineer.

Prepared by: Checked by Approved by


9

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost

Err:509

Err:509
SN. Description of Works Quantity Unit Rate Amount Remarks

Supplying, making and fitting fixing


of stainless steel pipe railling with
50mm dia. stainless steel pipe
handrail three rows 25mm dia
12.00 stainless steel pipe in between 105.53 Rm 3,232.77 341,147.83
handrail and floor and 39 mm dia.
stainless steel pipe for vertical post @
2m c/c including welding, cutting all
complete (per Rm)

Earth filling of Excavated furface in


150 mm thick layer, watering,
ramming including supply of filling
13.00 materials within 10 m distance all 866.09 cum 343.51 297,505.52
complete as per approved
drawing,Specification and instruction
of site engineer.

Elastocrete cementitious elastomeric


water proofing coating 2 components
capacity per kg 6 sq.ft for 2 coat
14.00 including supplying and applying all Err:509 sqm 643.67 Err:509
complete work as per approved
drawing ,specification and instruction
of site engineer.

Total cost = Err:509

Prepared by: Checked by Approved by


10

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost ( 25 cum Water Tank)

Err:509

Err:509
SN Description of Works Unit Rate Quantity Amount Remarks
1.0 Earthwork
Earthwork in excavation in boulder mixed
and hard soil in foundation, trenches
1.1 including timbering and shoring and 30m Cum 549.608 54.99 30,222.94
lead and 1.5m lift all complete as per
design, drawing and specifications.
Backfilling work including compaction and
1.2 levelling of the required depth all complete Cum 343.505 5.50 1,888.93
as per the instructions of the site engineer.
2.0 Masonry Works
Providing and laying of chimney made
brick in 1:4 c/s mortar with proper curing in
2.1
perfect line and level all complete as per the
instructions of the site engineer.
Cum 15,129.660 11.08 167,657.81
Providing and laying of dry stone in floor
and foundation complete to level including
2.2 sand filling on joints, as per drawing,
specification and instruction of engineer, all
complete.
Cum 3,961.43 2.34 9,269.74
3.0 Cement Concreting Works
Plain Cement Concrete ( PCC) work in
(1:3:6) in foundation with cement, sand and
crushed stone aggregate including mixing,
3.1
laying, finishing to approved level, line and
dimensions and curing all complete as per
specification.
Cum 9,745.72 1.76 17,103.74

Plain Cement Concrete (PCC) work in


(1:1.5:3) for M20 RCC works in sanitary
work, foundation, columns, beams and
slabs with cement, sand, and crushed stone
3.2 aggregate of approved size including
mixing with concrete mixture, compacting
the concrete with vibrator machine, laying,
finishing to approved level, lines and
dimensions and curing all complete.

Cum 16,041.13 7.13 114,415.74

Prepared by: Checked by Approved by


11

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost ( 25 cum Water Tank)

Err:509

Err:509
SN Description of Works Unit Rate Quantity Amount Remarks

TMT steel reinforcement bar of fe 500 grade


including supplying, straightening, cleaning,
cutting, binding & fixing in position with
3.3 annealed tying binding wire all complete as per
approved drawing, Specification and instruction
of site engineer.

Kg 680.68 839.87 571,686.11


4.0 Formworks

Centering and shuttering work with 19mm


waterproof plywood for all RCC works of
any shape or size and at any level with
necessary MS propping, scaffolding,
4.1 staging, supporting, cutting holes for
utilization works and removal of formwork
and lead up to 30m all complete as per
specification and instruction of site
engineer.

Formworks Sqm 1,135.875 60.50 68,715.92


5.0 Plastering Works
Providing, laying & curing of 12.5 mm
thick (1:4) c/s plaster work in wall surfaces
including chipping & wetting the concrete
5.1
surfaces finished in perfect plumb, lines and
level as per specification and instruction of
site engineer.
Sqm 335.74 11.08 3,720.47
Total 984,681.40

Prepared by: Checked by Approved by


12

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost ( Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works Unit Quantity Rate Amount Remarks
1.0 Earthwork

Earthwork in excavation in boulder mixed and


hard soil in foundation, trenches including
1.1 timbering and shoring and 30m lead and 1.5m lift Cum 58.36 549.61 32,074.04
all complete as per design, drawing and
specifications.

Backfilling work including compaction and


1.2 levelling of the required depth all complete as per Cum 5.84 343.51 2,004.63
the instructions of the site engineer.
2.0 Masonry Works
Providing and laying of chimney made brick in 1:4
c/s mortar with proper curing in perfect line and
2.1
level all complete as per the instructions of the site
engineer.
Cum 10.64 15,129.66 160,953.30
Providing and laying of dry stone in floor and
foundation complete to level including sand filling
2.2
on joints, as per drawing, specification and
instruction of engineer, all complete.
Cum 2.28 3,961.43 9,032.05
3.0 Cement Concreting Works
Plain Cement Concrete ( PCC) work in (1:3:6) in
foundation with cement, sand and crushed stone
3.1 aggregate including mixing, laying, finishing to
approved level, line and dimensions and curing all
complete as per specification.
Cum 1.71 9,745.72 16,665.18

Plain Cement Concrete (PCC) work in (1:1.5:3) for


M20 RCC works in sanitary work, foundation,
columns, beams and slabs with cement, sand, and
crushed stone aggregate of approved size including
3.2
mixing with concrete mixture, compacting the
concrete with vibrator machine, laying, finishing to
approved level, lines and dimensions and curing all
complete.

Cum 3.39 16,041.13 54,448.69

TMT steel reinforcement bar of fe 500 grade


including supplying, straightening, cleaning,
cutting, binding & fixing in position with annealed
3.3
tying binding wire all complete as per approved
drawing, Specification and instruction of site
engineer.

Prepared by: Checked by Approved by


13

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost ( Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works Unit Quantity Rate Amount Remarks
Kg 399.68 120.80 48,280.56

Prepared by: Checked by Approved by


14

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost ( Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works Unit Quantity Rate Amount Remarks
4.0 Formworks

Centering and shuttering work with 19mm


waterproof plywood for all RCC works of any
shape or size and at any level with necessary MS
4.1 propping, scaffolding, staging, supporting, cutting
holes for utilization works and removal of
formwork and lead up to 30m all complete as per
specification and instruction of site engineer.

Formworks Sqm 24.54 1,135.88 27,869.64


5.0 Flooring Works
Sand filling work including compaction and
5.1 levelling of the required depth all complete as per
the instructions of the site engineer.
Cum 17.36 1,799.29 31,236.47
6.0 Plastering Works

Providing, laying & curing of 12.5 mm thick (1:4)


c/s plaster work in wall surfaces including
6.1 chipping & wetting the concrete surfaces finished
in perfect plumb, lines and level as per
specification and instruction of site engineer.

Sqm 5.88 335.74 1,975.63


Total 384,540.19

Prepared by: Checked by Approved by


15

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost (Manhole)

Err:509

Err:509
SN. Description Unit Quantity Rate Amount Remarks
1.0 Earth Works

Earthwork in excavation in soft type soils in


1.1 foundation including 30m hauling distance and 1.5 cum 12.58 480.91 6,049.81
m. lift all complete in approval of site engineer.

2.0 Masonry Work


Supplying and Soling Local flat brick in proper line
and level with sand filling all complete as per
2.1 sqm 9.68 2219.88 21,488.48
approved drawing, Specification and instruction of
site engineer.
3.0 PCC Works

Plain cement concrete(PCC) in 1:3:6 ratio for


foundations and flooring with approved quality of
cement,sand and machine crushed stone aggregate
3.1 including supply of materials,mixing,laying,curing cum 0.72 9745.72 7,016.92
the work at least 7 days etc all complete as per
approved drawing specification and instruction of
site engineer.

4.0 RCC works

Plain cement Concrete (PCC) for RCC works M 20


(1:1.5:3) for slab/lintels/columns/beams with
approved quality of cement, sand and machine
4.1 crushed stone aggregate including supply of cum 0.66 16041.13 10,587.14
materials,mixing, laying, curing the work at least 7
days etc all complete as per approved drawing,
Specification and instruction of site engineer.

5.0 Metal Works

TMT steel reinforcement bar of fe 500 grade


including supplying, straightening, cleaning, cutting,
5.1 binding & fixing in position with annealed tying kg 93.26 120.80 11,265.35
binding wire all complete as per approved drawing,
Specification and instruction of site engineer.

6.0 Brick Masonary

Prepared by: Checked by Approved by


16

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost (Manhole)

Err:509

Err:509
SN. Description Unit Quantity Rate Amount Remarks

Good quality local chimney made Brickwork in 1:4


C/S mortar up to Ground floor in perfect line level
finish including supply of materials, wetting the
6.1 cum 4.89 15129.66 73,984.04
bricks, racking the joints and curing the work for at
least 7 days all complete as per approved drawing,
Specification and instruction of site engineer.

8.0 Plaster Works

Supplying and Laying of 12.5mm thick cement sand


plaster in (1:4) ratio on wall of good finish including
supply of materials, racking the joint, wetting of
8.1 sqm 32.82 335.74 11,018.98
surfaces & curing the work at least 7days all
complete as per approved drawing, Specification
and instruction of site engineer.

Total 141,410.72

Prepared by: Checked by Approved by


17

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Electrical Works)


Err:509
Err:509
SN Particulars QTY Unit Rate Amount Reference
A LUMINAIRES ( FIXTURES)
Accessories:screws, gripes, pvc tape, choke, starter, Tube,
bulbs, holder, flexible wire etc all complete.

1 6 Watt Led Panel round/square light Wipro/Fiam/Philips or 3.00 Set 584.20 1752.60 1
equivalent

2 12 Watt Led Panel round/square light Wipro/Fiam/keselec 11.00 Set 2397.75 26375.25 3
or equivalent
3 Weather proof bulkhead lamp Decon or equivalent 3.00 Set 2972.75 8918.25 6
Wall lamp 5 W WIPRO GARNET decorative etc all
4 2.00 Set 2972.75 5945.50 6
complete. Make Homedec,Decon,Fumagalli or equivalent
5 4' Led Tube light Wipro/Fiam/Philips or equivalent 2.00 Set 1362.75 2725.50 4
6 2'X2' Watt Led Recess/Surface light Wipro/Fiam/Philips or e 6.00 Set 4672.45 28034.70 8
7 24 Watt Led Recess/Surface light Wipro/Fiam/Philips or eqv12.00 Set 4697.75 56373.00 9

8 5 W Mirror light WIPRO GARNET SERIES, 3.00 Set 1132.75 3398.25 5


Fumagalli,Philips or equivalent
B FAN / EXHAUST FAN
Accssories:as per sn A +nut, bolt, hookclamp, dimmer
switch , flexible wire etc all complete.
9 36'' ceiling fan Almonard/Bajaj or eqvt.etc all complete. 9.00 Set 3499.45 31495.05 14
10 9"exhaust fan Almonard /Bajaj or eqvt.etc all complete. 3.00 Set 4037.65 12112.95 12
C SOCKET,SWITCH ,JUNCTION BOX (Modular Type)
accessories: metal box, screws ,gripes,flexible wire etc all
complete.
Dimmer for ceiling fan Dyna/CPL or eqvt.etc all
11 9.00 Set 757.27 6815.43 15
complete.
13/\15 Amps combined S/socket flat /round pin flush type
12 39.00 Set 626.75 24443.25 16
Northwest ,ABB, Siemens or eqvt. etc all complete.
16/20 A 3 pin round power socket shuttered including
13 metal box of 18 SWG for AC 1 nos. 626.75 626.75 16

1 gang 1, 2 way switch Northwest ,ABB, Siemens or eqvt.


14 9.00 Set 453.10 4077.90 17
etc all complete
2 gang 1, 2 way switch Northwest ,ABB, Siemens or eqvt.
15 4.00 Set 506.00 2024.00 18
etc all complete
3 gang 1 way switch Northwest,ABB, Siemens or eqvt. etc
16 6.00 Set 520.95 3125.70 19
all complete.
4 gang 1 way switch Northwest, ABB, Siemens or eqvt.
17 3.00 Set 575.00 1725.00 20
etc all complete.
6 gang 1 way switch Northwest, ABB, Siemens or eqvt.
18 1.00 Set 773.95 773.95 21
etc all complete.

Prepared by: Checked by Approved by


18

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Electrical Works)


Err:509
Err:509
SN Particulars QTY Unit Rate Amount Reference
Junction box made of metal with cover size 6"X4" etc. all
19 5.00 Set 357.07 1785.35 23
complete.
D MAIN DB/ DB
Accessories ;screws, gripes, nut bolt,earth cable, cable
shoe,pvc tape etc all complete.
Main Distribution board 16 way SPN made of mild steel
20 sheet double cover lock able Geco ,Standard or Nepal 1.00 3182.62 3182.62 53
made or eqvt.flush type etc all complete. Set
21 60 Amps DP MCB Siemens, ABB or eqvt . (for main) 1.00 No 1840.00 1840.00 54
a. Amp-meter 1.00 No 1125.85 1125.85 28
b. Voltmeter 1.00 No 1176.45 1176.45 27
c. Indicator 1.00 No 272.55 272.55 29
16 Amps DP MCB Siemens,ABB,Merlin Gerain or eqvt .
22 2.00 1184.50 2369.00 55
for SUB-DB. No
Ground Floor Distribution board 12 way SPN made of

23 mild steel sheet double cover lockable Geco ,Standard or 1.00 3049.22 3049.22 57

Nepal made or eqvt.flush type etc all complete. Set


6,16 Amps. SP MCB Siemens,Merlin Gerain or eqvt.for
24 12.00 236.90 2842.80 56
light , power. No
First Floor Distribution board 16 way SPN made of mild
25 steel sheet double cover lockable Geco ,Standard or Nepal 1.00 3182.62 3182.62 53
made or eqvt.flush type etc all complete. Set
6,16 Amps. SP MCB Siemens,Merlin Gerain or eqvt.for
26 16.00 236.90 3790.40 56
light , power. No
E POINT WIRING / WIRES
Accessories;HDPE polythene pipe/conduit pipe/pvc

listy,screws,pvc tape, grips, circular box etc all complete.


2x2.50 sq mm cu flexible wire for light & fan point in
27 75.00 Point 805.75 60431.25 31
20mm HDPE polythene pipe etc all complete.
2x4.0+1x1.50 sq.mm flexible cu wire for power point in
28 39.00 Point 1374.38 53600.63 32 & 35
25mm HDPE polythene pipe etc all complete.
2x6+1x1.50 sq.mm flexible cu wire for power point in 25
29 1.00 Point 1852.75 1852.75 33, 35
HDPE polythene pipe etc all complete.
10.0 sq.mm 4.0 core unarmoured copper cable for panel
30 board to DB through suitable size HDPE polythene pipe 10.00 Rm 770.67 7706.70 42
etc all complete.
35.0 sq.mm 4.0 core armoured copper cable for main
31 panel board through HDPE polythene pipe/ Trench etc all 15.00 Rm 2156.59 15.00 52
complete.
F TELECOM

Prepared by: Checked by Approved by


19

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Electrical Works)


Err:509
Err:509
SN Particulars QTY Unit Rate Amount Reference
Accessories : screws, grips, pvc tape,HDPE pipe etc all
complete.
32 Telephone socket Dyna/Cpl or eqvt. etc all complete. 6.00 Set 460.00 2760.00 44
Two pair telephone cu.cable in 1/2" HDPE polythene pipe
33 6.00 Point 49.62 297.72 45
etc all complete.
10 pair telephone cable for main in 25mm HDPE polythene
34 60.00 Rm 117.36 7041.60 47
pipe.
Telephone main distribution board (MDB) made of metal
35 1.00 Set 7381.27 7381.27 46
with crown tag double cover etc. all complete.
EPABX 4-12 expandable upto 15 line with programmable

36 master telephone set of corresponding brand Metrix, 1.00 Set 43720.70 43720.70 48

creative ,panasonic or eqvt. etc all complete.


COMPUTER (Net) SYSTEM; Accessories.jack,
G
Screws, gripes etc all complete.
37 Computer socket with box ( cat 6) etc all complete. 8.0 Set 1047.65 8381.20 49
UTP Cat 6 networking computer cable in 20mm HDPE
38 8.0 Point 812.25 6498.00 G
polythene pipe etc all complete.
UTP Cat 6 networking computer cable in 20mm HDPE
39 70.0 Rm 63.42 4439.40 50
polythene pipe etc all complete. for main.
Networking switch 16 port with adaptor CE or eqvt .etc aa
40 1.00 Set 13646.50 13646.50
complete.
H Air Conditionong System
Accesseries: Screws,grips, nut bolts, angle, channel, drain,
copper pipe, insulation etc all complete.

1 TR Wall Mounted DC inverter Air Conditioning unit


41 with complete installation power supply 220 v AC single 1.00 Set 65400.00 65400.00 Quotation
phase Trane, Midia,Mitshubishi or eqvt.
I EARTHING
Accessories :salt, coal, cu plate, HDPE polythene pipe., etc
all complete.
Earthing with cu plate size 65 cmx65cmx3.15mm with 8
SWG copper wire in 20mm HDPE polythene pipe for earth
42 1.00 Set 19619.52 19619.52 34
continuity from main switch to earthing site etc all
complete.
Total= 548152.13
The rates quoted here under are inclusive of
1. Supplying the items along with accessories to the site.
2. Fixing them in position as per specification, drawing and approval of electrical site incharge.
3. Testing ,Comissioning &
4. Maintenance upto the guaranted period as per agreement

Prepared by: Checked by Approved by


20

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks
Providing and fixing in position of all work
items with all necessary fittings complete with
testing and ready for operation as per drawings,
specifications, manufacturer's recommendations
and instructions. The rate shall include for
position marking, maintain line, level or grade
wherever required, sand filling/compaction,
earth cutting and backfilling, cutting, chasing of
walls, plasters or tiles etc. and making good and
touching up to restore to original conditions
wherever instructed and applicable for any of the
items below:

Porcelain Clay Sanitary Wares:-Hindware,


Parryware, Classica, Cera, or equivalent.
C.P Accessories: Grohe,Somany, Ark, Essel,
Jacquar , Perware or equivalent.
CPVC pipe and fittings :- Astral, Prince,
Marvel, Mangalam or equivalent.

1 W.C COMMODE
Supplying and fixing white glazed earthenware
Regular Porcelain clay White glazed (with
special fitting) Commode with dual flush with
bakelite seat cover lid with C.P. hinges and
holding down toilet bolts, with complete
accessories, pipe connector, C.I. brackets, C.P.
etc. fittings as per specifications and instruction
of site engineer, all complete. set
Porcerlain clay white Comode with special
2.00 No 25691.00 51,382.00
fitting ,seat cover all complete set.

2 WASH BASINS

Prepared by: Checked by Approved by


21

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks
Supplying and fixing white glazed
earthenwareunder Counter WASH BASIN with
, C.I. Brackets, 32 mm diameter Japer bottle
trap. C.P. waste coupling , C.P. chain and rubber
plug ,15mm diameter. swan neck type Pillar
cock, pipe connector etc.with testing and ready
for operation as per specification and instruction
of site engineer, all complete net.

White glazed Porcelain clay 16" * 20" (50X40


cm) Oval under-counter Wash basin with pipe
connector, bottle trap complete set. 2.00 No 11918.60 23,837.20
( Boolan,cera,Hindware,Parryware,Somany,or
equivalent )

4 MISCELLANEOUS

Prepared by: Checked by Approved by


22

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks
Supplying and fixing of the following as per
specification and instruction of site engineer, all
complete.
(a) C.P. Toilet Paper Holder 2.00 No 1233.38 2,466.75

(b) C.P.Special quality Soap Dish. 2.00 No 798.68 1,597.35

(c) 1/2"x18" Stainless steel Towel Rod 2.00 No 1026.95 2,053.90

(d) Glass Shelf with CP Guard Rail 2.00 No 1054.55 2,109.10

( e ) Looking mirror fancy type 400 x 550 mm


(16"x22" ) size Modi or approved mark . 2.00 No 1647.38 3,294.75

5 METAL FITTINGS
5.1 Cocks
Supplying and fixing COCKS as per
specifications and instruction of site engineer, all
complete.
i) Bib cocks
( a ) 15 mm diameter C.P. Bib-Cock. 2.00 No 1257.53 2,515.05

ii) Stop cocks


( a ) 15 mm diameter C.P. Angle Valve 2.00 No 1580.68 3,161.35

iii) Water spray (Health faucet) with 1.2 m.


2.00 No 1714.77 3,429.53
long flexible pipe complete

6 Valves

i) Ball Valves :-Supplying and fixing in


position CPVC Ball Valve CTS sockets
( Marvel , Mangalam , Astral ) or equivalent as
per specification and instruction of site engineer
all complete.

Prepared by: Checked by Approved by


23

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks

Prepared by: Checked by Approved by


24

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks
( a ) 1" (25mm) dia. Ball Valve 1.00 No 803.28 803.28

7 C.P. GRATINGS & FLOOR TRAPS


Supplying and fixing C.P. GRATINGS as per
specification and instruction of site engineer, all
complete.
( a ) 5 " dia. C.P. Gratings heavy quality. 2.00 No 129.95 259.90

( b ) 4" * 3" Multi Floor Trap PVC 2.00 No 505.43 1,010.85

8 PVC PIPES

Supplying and laying PVC PIPES SN -4 Astral


, Prince or equivalent , with all necessary ring
gaskets, MS clamp , hanges cutting, jointing ,
sealing installation of pipes and specials
including making holes and cutting grooves on
wall or floor and reparing the same to its orginal
finish. Pipe to be installed on trenches or wall or
floor or duct or hung to ceiling as per drawing
and specification . jointing by solvent welding
and whole range of injection moulded matching
fittings and specials , cleaning of the system ,
testing and ready for operation as per
specification and instruction of site engineer all
complete.

b) 3" (75 mm) dia. 6kgf/cm.sq PVC pipes


Material rate
single or double socket as per need with
5.00 RM 555.85 2,779.26 kathmandu
disregarding groove cutting, hole cutting in
District
brickwork or RCC work all complete.

c) 4" (110 mm) dia. 6kgf/cm.sq PVC pipes


Material rate
single or double socket as per need with
6.00 RM 998.20 5,989.20 kathmandu
disregarding groove cutting, hole cutting in
District
brickwork or RCC work all complete.

9 CPVC PIPE LAYING

Prepared by: Checked by Approved by


25

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks

Supplying and laying in position of Asterl ,


Marvel , Mangalam or Equivalent CPVC
PIPES SDR 11 CTS 28.1 kg/cm2 with required
fittings as Tee , Elbow , Sockets , Clamp and all
necessary CPVC/ Brass specials requred for
complete installation with grove cuting, hole
cutting supports where required .jointing by
solvent welding and whole range of injection
moulded matching fittings and specials for
complete installation. Cutting, make hole and
cutting groves on wall or floor and repairing the
same to its orginal finish. Pipe to be installed on
the trenches or wall or floor or duct as per
drawing, specification and instruction including
cleaning of the system, testing and ready for
operation. The rate shall include for all labour
and materials required. The measurment shall be
done for running meters, fittings etc not payable
sperately, as per specification and instruction of
site engineer, all complete.

(a) 20 mm dia.CPVC Pipes 7.50 RM 370.65 2,779.84

Prepared by: Checked by Approved by


26

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (Ground Floor Sanitary Installation Work )


Err:509
Err:509
SCHEDULE OF VALUES
S.N. Description Qty. Unit Rate Amount Remarks
10 PVC FITTINGS (SPECIALS)

Supplying and fixing PVC SPECIALS plain


or door, Astral , Prince or equivalent joints to be
caulked with Solvent as per specification and
instruction of site engineer, all complete.

b) 3 " ( 75mm) dia. PVC fittings even or uneven Material rate


section such as bend single or double junction. 15.00 320.47 4,807.00 kathmandu
As per need and direction of the Engineer. District

d) 4" (110mm) dia. PVC fittings even or uneven Material rate


section such as bend single or double junction. 15.00 554.07 8,311.05 kathmandu
As per need and direction of the Engineer. District

Total= 122,587.36

Prepared by: Checked by Approved by


27

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary ( First Floor Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks
Providing and fixing in position of all work items
with all necessary fittings complete with testing
and ready for operation as per drawings,
specifications, manufacturer's recommendations
and instructions. The rate shall include for position
marking, maintain line, level or grade wherever
required, sand filling/compaction, earth cutting and
backfilling, cutting, chasing of walls, plasters or
tiles etc. and making good and touching up to
restore to original conditions wherever instructed
and applicable for any of the items below:
Porcelain Clay Sanitary Wares:-Hindware,
Parryware, Classica, Cera, or equivalent.
C.P Accessories: Grohe,Somany, Ark, Essel,
Jacquar , Perware or equivalent.
CPVC pipe and fittings :- Astral, Prince,
Marvel, Mangalam or equivalent.

1 W.C COMMODE
Supplying and fixing white glazed earthenware
Regular Porcelain clay White glazed (with
special fitting) Commode with dual flush with
bakelite seat cover lid with C.P. hinges and holding
down toilet bolts, with complete accessories, pipe
connector, C.I. brackets, C.P. etc. fittings as per
specifications and instruction of site engineer, all
complete. set
Porcerlain clay white Comode with special
1.00 No 25691.00 25,691.00
fitting ,seat cover all complete set.

2 WASH BASINS
Supplying and fixing white glazed
earthenwareunder Counter WASH BASIN with ,
C.I. Brackets, 32 mm diameter Japer bottle trap.
C.P. waste coupling , C.P. chain and rubber plug ,
15mm diameter. swan neck type Pillar cock, pipe
connector etc.with testing and ready for operation
as per specification and instruction of site engineer,
all complete net.

Prepared by: Checked by Approved by


28

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary ( First Floor Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks
White glazed Porcelain clay 16" * 20" (50X40
cm) Oval under-counter Wash basin with pipe
connector, bottle trap complete set. 1.00 No 11918.60 11,918.60
( Boolan,cera,Hindware,Parryware,Somany,or
equivalent )

4 MISCELLANEOUS
Supplying and fixing of the following as per
specification and instruction of site engineer, all
complete.
(a) C.P. Toilet Paper Holder 1.00 No 1233.38 1,233.38

(b) C.P.Special quality Soap Dish. 1.00 No 798.68 798.68

(c) 1/2"x18" Stainless steel Towel Rod 1.00 No 1026.95 1,026.95

(d) Glass Shelf with CP Guard Rail 1.00 No 1054.55 1,054.55

( e ) Looking mirror fancy type 400 x 550 mm


(16"x22" ) size Modi or approved mark . 1.00 No 1647.38 1,647.38

5 METAL FITTINGS
5.1 Cocks
Supplying and fixing COCKS as per
specifications and instruction of site engineer, all
complete.
i) Bib cocks
( a ) 15 mm diameter C.P. Bib-Cock. 2.00 No 1257.53 2,515.05

ii) Stop cocks


( a ) 15 mm diameter C.P. Angle Valve 2.00 No 1580.68 3,161.35

iii) Water spray (Health faucet) with 1.2 m. long


1.00 No 1714.77 1,714.77
flexible pipe complete

Prepared by: Checked by Approved by


29

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary ( First Floor Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks
6 Valves

i) Ball Valves :-Supplying and fixing in position


CPVC Ball Valve CTS sockets ( Marvel ,
Mangalam , Astral ) or equivalent as per
specification and instruction of site engineer all
complete.

Material rate
( a ) 1" (25mm) dia. Ball Valve 1.00 No 803.28 803.28 kathmandu
District

7 C.P. GRATINGS & FLOOR TRAPS


Supplying and fixing C.P. GRATINGS as per
specification and instruction of site engineer, all
complete.
( a ) 5 " dia. C.P. Gratings heavy quality. 1.00 No 129.95 129.95

( b ) 4" * 3" Multi Floor Trap PVC 1.00 No 505.43 505.43

8 PVC PIPES

Supplying and laying PVC PIPES SN -4 Astral ,


Prince or equivalent , with all necessary ring
gaskets, MS clamp , hanges cutting, jointing ,
sealing installation of pipes and specials including
making holes and cutting grooves on wall or floor
and reparing the same to its orginal finish. Pipe to
be installed on trenches or wall or floor or duct or
hung to ceiling as per drawing and specification .
jointing by solvent welding and whole range of
injection moulded matching fittings and specials ,
cleaning of the system , testing and ready for
operation as per specification and instruction of site
engineer all complete.

Prepared by: Checked by Approved by


30

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary ( First Floor Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks
b) 3" (75 mm) dia. 6kgf/cm.sq PVC pipes single
Material rate
or double socket as per need with disregarding
2.50 RM 555.85 1,389.63 kathmandu
groove cutting, hole cutting in brickwork or RCC
District
work all complete.

c) 4" (110 mm) dia. 6kgf/cm.sq PVC pipes single


Material rate
or double socket as per need with disregarding
2.50 RM 998.20 2,495.50 kathmandu
groove cutting, hole cutting in brickwork or RCC
District
work all complete.

9 CPVC PIPE LAYING

Supplying and laying in position of Asterl ,


Marvel , Mangalam or Equivalent CPVC PIPES
SDR 11 CTS 28.1 kg/cm2 with required fittings as
Tee , Elbow , Sockets , Clamp and all necessary
CPVC/ Brass specials requred for complete
installation with grove cuting, hole cutting
supports where required .jointing by solvent
welding and whole range of injection moulded
matching fittings and specials for complete
installation. Cutting, make hole and cutting groves
on wall or floor and repairing the same to its
orginal finish. Pipe to be installed on the trenches
or wall or floor or duct as per drawing,
specification and instruction including cleaning of
the system, testing and ready for operation. The
rate shall include for all labour and materials
required. The measurment shall be done for
running meters, fittings etc not payable sperately,
as per specification and instruction of site engineer,
all complete.

(a) 20 mm dia.CPVC Pipes 5.00 RM 370.65 1,853.23

10 PVC FITTINGS (SPECIALS)

Prepared by: Checked by Approved by


31

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary ( First Floor Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks

Supplying and fixing PVC SPECIALS plain or


door, Astral , Prince or equivalent joints to be
caulked with Solvent as per specification and
instruction of site engineer, all complete.

b) 3 " ( 75mm) dia. PVC fittings even or uneven Material rate


section such as bend single or double junction. As 15.00 320.47 4,807.00 kathmandu
per need and direction of the Engineer. District

d) 4" (110mm) dia. PVC fittings even or uneven Material rate


section such as bend single or double junction. As 15.00 554.07 8,311.05 kathmandu
per need and direction of the Engineer. District

Total= 71,056.75

Prepared by: Checked by Approved by


32

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (External Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks
1 Valves
Supplying and fixing gun metal VALVES of
medium quality Laxmias or ISI Mark per
specifications and instruction of site engineer, all
complete set.
i) Check Valves

( ii ) 11/2" (40 mm) dia. Gun metal Check Valve


2.00 No 3917.48 7,834.95
full-way

a) GM Float Valve
25 mm GM Float Valve (Medium Grade) 2.00 No 1061.45 2,122.90

2 Valves

i) Ball Valves :-Supplying and fixing in position


CPVC Ball Valve CTS sockets ( Marvel ,
Mangalam , Astral ) or equivalent as per
specification and instruction of site engineer all
complete.

( a ) 3/4 " (20 mm) dia. Ball Valve , CTS


1.00 683.68 683.68
Sockets.

( b ) 1" (25 mm) dia. Ball Valve CTS Sockets 1.00 803.28 803.28

( c ) 11/2" (40 mm ) dia. Ball Valve CTS


1.00 2053.33 2,053.33
Sockets

3 PVC PIPES

Prepared by: Checked by Approved by


33

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (External Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks

Supplying and laying PVC PIPES SN -4 Astral ,


Prince or equivalent , with all necessary ring
gaskets, MS clamp , hanges cutting, jointing ,
sealing installation of pipes and specials including
making holes and cutting grooves on wall or floor
and reparing the same to its orginal finish. Pipe to
be installed on trenches or wall or floor or duct or
hung to ceiling as per drawing and specification .
jointing by solvent welding and whole range of
injection moulded matching fittings and specials ,
cleaning of the system , testing and ready for
operation as per specification and instruction of
site engineer all complete.

a) 3 " (75 mm) dia. 6kgf/cm.sq PVC pipes


Material rate
single or double socket as per need with
25.00 RM 555.85 13,896.31 kathmandu
disregarding groove cutting, hole cutting in
District
brickwork or RCC work all complete.

b) 4 " (110 mm) dia. 6kgf/cm.sq PVC pipes


Material rate
single or double socket as per need with
50.00 RM 998.20 49,910.00 kathmandu
disregarding groove cutting, hole cutting in
District
brickwork or RCC work all complete.

4 CPVC PIPE LAYING

Prepared by: Checked by Approved by


34

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (External Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks

Supplying and laying in position of Asterl ,


Marvel , Mangalam or Equivalent CPVC PIPES
SDR 11 CTS 28.1 kg/cm2 with required fittings as
Tee , Elbow , Sockets , Clamp and all necessary
CPVC/ Brass specials requred for complete
installation with grove cuting, hole cutting
supports where required .jointing by solvent
welding and whole range of injection moulded
matching fittings and specials for complete
installation. Cutting, make hole and cutting groves
on wall or floor and repairing the same to its
orginal finish. Pipe to be installed on the trenches
or wall or floor or duct as per drawing,
specification and instruction including cleaning of
the system, testing and ready for operation. The
rate shall include for all labour and materials
required. The measurment shall be done for
running meters, fittings etc not payable sperately,
as per specification and instruction of site
engineer, all complete.

-
(c) 32 mm dia.CPVC Pipes 25.00 RM 1080.28 27,006.89

5 PVC FITTINGS (SPECIALS)

Supplying and fixing PVC SPECIALS plain or


door, Astral , Prince or equivalent joints to be
caulked with Solvent as per specification and
instruction of site engineer, all complete.

c) 3 " (75mm) dia. PVC fittings even or uneven


section such as bend single or double junction. As 15.00 320.47 4,807.00
per need and direction of the Engineer.

b) 4" (110mm) dia. PVC fittings even or uneven


section such as bend single or double junction. As 15.00 554.07 8,311.05
per need and direction of the Engineer.

6 OVERHEAD WATER TANK

Prepared by: Checked by Approved by


35

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (External Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks

Hill take or its equivalent brand with required


base support including hosting and fixing in
position with inlet , outlet , overflow and clean out
connection all complete with testing and ready for
operation as per specification and instruction of
site engineer all complete .

Supplying and fitting PVC/HDP Over head water


tank with its accessories as per drawing,
specification and instruction of site engineer, all
complete.

a) 2000 Liter PVC/HDP water tank 2.00 No 30901.65 61,803.30

7 ELECTRIC PUMP

Supplying and fitting of 1 H.P. Electric water


pump multistage type (Crompton) set with 25mm
diameter Suction and Delivery with base plate,
1.00 No 21698.20 21,698.20
nuts, bolts all complete of crompton greaves or its
equivalent brand as per specification and
instruction of site Engineer all complete net .

Supplying and Fixing Pressure Senser Switch for


pump auto switch off all complete set (Italian or 1.00 4584.02 4,584.02
Eqv.)

Supplying and Fixing Motor Starter Switch all


1.00 4265.47 4,265.47
complete set with testing and ready for operation.

8 FIRE EXTINGUISHER
Providing and fixing 5-6 kg ABC type fire
extinguishers consisting of welded MS cylindrical
body, squeeze lever discharge valve fitted with
pressure indicating gauge internal discharge tube,
30 cms long high pressure discharge hose,
2.00 No 9177.00 18,354.00
discharge nozzle, suspension bracket, conforming
to ISI finished externally with red enamel paint
and fixed to wall with brackets complete with
internal charge. Fire extingusher ABC type
Minimax, eversafe or equivalent

Prepared by: Checked by Approved by


36

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Abstract of Cost Sanitary (External Sanitary Installation Work )


Err:509
Err:509
S.N. Description Qty. Unit Rate Amount Remarks

9 HIGH DENSITY POLYTHEEN PIPE (H.D.P)

Supplying and laying ( HDP PIPES ) High


Density Polethen Pipe (4 kg/cm 2) in proper
gradient, all joints to be caulked with jointing by
solvent welding and whole range of injection
moulded matching fittings and specials as per
specification and instruction of site engineer, all
complete.

a) 6" (160 mm) dia. 4kgf/cm.sq HDPE pipes as


per need with disregarding groove cutting, hole 45.00 R.m 1,703.91 76,675.91
cutting in brickwork or RCC work all complete.

10 CI MANHOLE COVER

Supplying and fixing in position medium duty


C.I. Manhole cover (16"x16") for manholes with
8.00 nos 3,011.28 24,090.20
double seal as per specification and instruction of
site engineer all complete.
Total= 328,900.46

Prepared by: Checked by Approved by


37

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Earthwork in excavation in medium type


soils in foundation including 10m hauling
1.00 distance and 1.8 m. lift all complete in
approval of site engineer.

Footing
F6
Rectangular porrtion 8.00 2.200 2.200 2.000 77.440
-
-
Footing -
F5 -
Rectangular porrtion 6.00 3.700 3.700 2.000 164.280
-
-
Footing -
F3 -
Rectangular porrtion 4.00 3.200 3.200 2.000 81.920
-
-
Footing -
F2 -
Rectangular porrtion 6.00 3.200 3.200 2.000 122.880
-
Footing -
F1 -
Rectangular porrtion 6.00 3.000 3.000 2.000 108.000

Footing
SF1
Rectangular porrtion 1.00 36.600 2.900 2.000 212.280
Footing
SF1
Rectangular porrtion 1.00 23.720 2.300 2.000 109.112

Footing
SF1
Rectangular porrtion 1.00 10.275 3.700 2.000 76.035

Footing
SF1
Rectangular porrtion 1.00 31.988 2.300 2.000 147.145

Footing
SF1
Rectangular porrtion 1.00 10.710 2.800 2.000 59.976

Tie beam
Block1
Grid 1-1 1.00 30.550 0.550 1.480 24.868
Grid 2-2 1.00 30.550 0.550 1.480 24.868
Grid 3-3 1.00 30.550 0.550 1.480 24.868
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.550 1.480 59.650
Block2 0.550 1.480
Grid 5-5 1.00 25.655 0.550 1.480 20.883
Grid 6-6 1.00 25.655 0.550 1.480 20.883
Grid 8-8 1.00 8.960 0.550 1.480 7.293
Grid 9-9 1.00 11.414 0.550 1.480 9.291
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.550 1.480 48.580
Total= 1,400.251 cum

Supplying and Soling Local flat brick in


proper line and level with sand filling all
2.00
complete as per approved drawing,
Specification and instruction of site
engineer.
Footing
F6
Rectangular porrtion 8.00 1.900 1.900 28.880
Footing
F5
Rectangular porrtion 6.00 3.400 3.400 69.360
Footing
F3
Rectangular porrtion 4.00 2.900 2.900 33.640
Footing
F2
Rectangular porrtion 6.00 2.900 2.900 50.460
Footing
F1
Rectangular porrtion 6.00 2.700 2.700 43.740
Footing
SF1
Rectangular porrtion 1.00 36.300 2.600 94.380
Footing
SF1
Rectangular porrtion 1.00 23.420 2.000 46.840
Footing
SF1
Rectangular porrtion 1.00 9.975 3.400 33.915
Footing
SF1
Rectangular porrtion 1.00 31.688 2.000 63.376
Footing
SF1
Rectangular porrtion 1.00 10.410 2.500 26.025
Tie beam
Block1
Grid 1-1 1.00 30.550 0.250 7.638
Grid 2-2 1.00 30.550 0.250 7.638
Grid 3-3 1.00 30.550 0.250 7.638
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.250 18.320
Block2
Grid 5-5 1.00 25.655 0.250 6.414
Grid 6-6 1.00 25.655 0.250 6.414
Grid 8-8 1.00 8.960 0.250 2.240
Grid 9-9 1.00 11.414 0.250 2.854
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.250 14.920
floor 1 1.00 area= 237.800 237.800
floor 1 1.00 area= 363.800 363.800
Total= 1,166.290 sqm

Prepared by: Checked by Approved by


38

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Plain cement Concrete (PCC) in 1:3;6


ratio for foundations and flooring with
approved quality of cement, sand and
machine crushed stone aggregate
including supply of materials,mixing,
3.00 laying, curing the work at least 7 days etc
all complete as per approved drawing,
Specification and instruction of site
engineer.

Footing
F6
Rectangular porrtion 8.00 1.900 1.900 0.075 2.166
Footing
F5
Rectangular porrtion 6.00 3.400 3.400 0.075 5.202
Footing
F3
Rectangular porrtion 4.00 2.900 2.900 0.075 2.523
Footing
F2
Rectangular porrtion 6.00 2.900 2.900 0.075 3.785
Footing
F1
Rectangular porrtion 6.00 2.700 2.700 0.075 3.281
Footing
SF1
Rectangular porrtion 1.00 36.300 2.600 0.075 7.079
Footing
SF1
Rectangular porrtion 1.00 23.420 2.000 0.075 3.513
Footing
SF1
Rectangular porrtion 1.00 9.975 3.400 0.075 2.544
Footing
SF1
Rectangular porrtion 1.00 31.688 2.000 0.075 4.753
Footing
SF1
Rectangular porrtion 1.00 10.410 2.500 0.075 1.952
Tie beam
Block1
Grid 1-1 1.00 30.550 0.250 0.075 0.573
Grid 2-2 1.00 30.550 0.250 0.075 0.573
Grid 3-3 1.00 30.550 0.250 0.075 0.573
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.250 0.075 1.374
Block2
Grid 5-5 1.00 25.655 0.250 0.075 0.481
Grid 6-6 1.00 25.655 0.250 0.075 0.481
Grid 8-8 1.00 8.960 0.250 0.075 0.168
Grid 9-9 1.00 11.414 0.250 0.075 0.214
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.250 0.075 1.119
floor 1 1.00 area= 237.800 0.075 17.835
floor 1 1.00 area= 363.800 0.075 27.285

Total= 87.472 cum

Plain cement Concrete (PCC) for RCC


works M20 (1:1.5:3) for
slab/lintels/columns/beams with approved
quality of cement, sand and machine
crushed stone aggregate including supply
of materials,mixing, laying, curing the
4.00 work at least 7 days etc all complete as
per approved drawing, Specification and
instruction of site engineer.

Footing
F6
Rectangular porrtion 8.00 1.900 1.900 0.200 5.776
Trapeziodal Portion 8.00 AvgArea 2.016 0.300 4.839

Footing
F5
Rectangular porrtion 6.00 3.400 3.400 0.200 13.872
Trapeziodal Portion 6.00 AvgArea 6.141 0.400 14.739

Footing
F3
Rectangular porrtion 4.00 2.900 2.900 0.200 6.728
Trapeziodal Portion 4.00 AvgArea 4.416 0.300 5.300

Footing
F2
Rectangular porrtion 6.00 2.900 2.900 0.200 10.092
Trapeziodal Portion 6.00 AvgArea 4.416 0.300 7.949

Footing
F1
Rectangular porrtion 6.00 2.700 2.700 0.200 8.748
Trapeziodal Portion 6.00 AvgArea 3.856 0.300 6.941

Footing
SF1
Rectangular porrtion 1.00 36.300 2.600 0.200 18.876
Trapeziodal Portion 1.00 AvgArea 57.263 0.300 17.179
Footing
SF1
Rectangular porrtion 1.00 23.420 2.000 0.200 9.368
Trapeziodal Portion 1.00 AvgArea 29.914 0.300 8.974

Footing
SF1
Rectangular porrtion 1.00 9.975 3.400 0.200 6.783
Trapeziodal Portion 1.00 AvgArea 20.199 0.300 6.060

Footing
SF1
Rectangular porrtion 1.00 31.688 2.000 0.200 12.675
Trapeziodal Portion 1.00 AvgArea 41.987 0.300 12.596

Footing
SF1
Rectangular porrtion 1.00 10.410 2.500 0.200 5.205
Trapeziodal Portion 1.00 AvgArea 16.396 0.300 4.919

Prepared by: Checked by Approved by


39

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Column upto plinth -


Column upto plinth
Block 1 24.00 0.450 0.450 2.625 12.758
Block 2 28.00 0.400 0.400 3.075 13.776
Shear wall Up to Plinth 1.00 99.03 0.230 2.625 59.790
Block 1 Shear wall first floor 1.00 52.48 0.230 3.200 38.625
Shear wall block 1&2 second floor 1.00 99.03 0.230 2.625 59.790
Ground Floor Column
Block 1 24.00 0.450 0.450 3.075 14.945
Block 2 28.00 0.400 0.400 3.075 13.776
First floor
Block 1 24.00 0.450 0.450 3.075 14.945
Block 2 28.00 0.400 0.400 3.075 13.776
Second floor
Block 1 24.00 0.450 0.450 3.075 14.945
Block 2 28.00 0.400 0.400 3.075 13.776
Third floor
Block 1 24.00 0.450 0.450 3.075 14.945
Block 2 28.00 0.400 0.400 3.075 13.776
Fourth Floor
Block 1 24.00 0.450 0.450 3.075 14.945
Top Floor Column Block 1 6.00 0.450 0.450 3.075 3.736

Tie beam
Block1
Grid 1-1 1.00 30.550 0.250 0.300 2.291
Grid 2-2 1.00 30.550 0.250 0.300 2.291
Grid 3-3 1.00 30.550 0.250 0.300 2.291
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.250 0.300 5.496
Block2
Grid 5-5 1.00 25.655 0.250 0.300 1.924
Grid 6-6 1.00 25.655 0.250 0.300 1.924
Grid 8-8 1.00 8.960 0.250 0.300 0.672
Grid 9-9 1.00 11.414 0.250 0.300 0.856
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.250 0.300 4.476

Plinth beam
Block1
Grid 1-1 1.00 30.550 0.250 0.300 2.291
Grid 2-2 1.00 30.550 0.250 0.300 2.291
Grid 3-3 1.00 30.550 0.250 0.300 2.291
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.250 0.300 5.496
Block2
Grid 5-5 1.00 25.655 0.250 0.300 1.924
Grid 6-6 1.00 25.655 0.250 0.300 1.924
Grid 8-8 1.00 8.960 0.250 0.300 0.672
Grid 9-9 1.00 11.414 0.250 0.300 0.856
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.250 0.300 4.476

Main Beam
First Floor (3200mm from plinth beam)
Block 1
Grid 1-1 1.00 30.550 0.300 0.375 3.437
Grid 2-2 1.00 30.550 0.300 0.375 3.437
Grid 3-3 1.00 30.550 0.300 0.375 3.437
Secondary beam 1.00 30.550 0.250 0.350 2.673
Grid A,B,C,D,E,F,G,H 8.00 6.735 0.300 0.375 6.062
Block2
Grid 5-5 1.00 25.655 0.300 0.375 2.886
Grid 6-6 1.00 25.655 0.300 0.375 2.886
Grid 7-7 1.00 25.655 0.300 0.375 2.886
Grid 8-8 1.00 8.960 0.300 0.375 1.008
Grid 9-9 1.00 11.414 0.300 0.375 1.284
Grid 10-10 1.00 11.414 0.300 0.375 1.284
Secondary beam 1.00 32.811 0.250 0.325 2.666
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.300 0.375 6.714

Main beam layout ( 6400mm from plinth)


Block 1
Grid 1-1 1.00 30.550 0.300 0.375 3.437
Grid 2-2 1.00 30.550 0.300 0.375 3.437
Grid 3-3 1.00 30.550 0.300 0.375 3.437
Grid 4-4 1.00 30.550 0.300 0.375 3.437
Secondary beam 1.00 30.550 0.250 0.325 2.482
Grid A,B,C,D,E,F,G,H 8.00 13.590 0.300 0.375 12.231
Block2
Grid 5-5 1.00 25.655 0.300 0.375 2.886
Grid 6-6 1.00 25.655 0.300 0.375 2.886
Grid 7-7 1.00 25.655 0.300 0.375 2.886
Grid 8-8 1.00 8.960 0.300 0.375 1.008
Grid 9-9 1.00 11.414 0.300 0.375 1.284
Grid 10-10 1.00 11.414 0.300 0.375 1.284
Secondary beam 1.00 36.931 0.250 0.325 3.001
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.300 0.375 6.714

Main beam layout ( 9600mm from plinth)


Block 1
Grid 2-2 1.00 30.550 0.300 0.375 3.437
Grid 3-3 1.00 30.550 0.300 0.375 3.437
Grid 4-4 1.00 30.550 0.300 0.375 3.437
Secondary beam 1.00 25.670 0.250 0.325 2.086
Secondary beam 1.00 26.130 0.250 0.325 2.123
Grid A,B,C,D,E,F 6.00 7.580 0.300 0.375 5.117
Grid G,H 2.00 10.157 0.300 0.375 2.285
Block2
Grid 5-5 1.00 25.655 0.300 0.375 2.886
Grid 6-6 1.00 7.735 0.300 0.375 0.870
Grid 7-7 1.00 25.655 0.300 0.375 2.886
Grid 8-8 1.00 8.960 0.300 0.375 1.008
Grid 9-9 1.00 11.414 0.300 0.375 1.284
Grid10-10 1.00 11.414 0.300 0.375 1.284
Secondary beam 1.00 36.931 0.250 0.325 3.001
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.300 0.375 6.714

Main beam layout ( 12800mm from plinth)


Block 1
Grid 2-2 1.00 30.550 0.300 0.400 3.666
Grid 3-3 1.00 30.550 0.300 0.400 3.666
Grid 4-4 1.00 30.550 0.300 0.400 3.666
Secondary beam 1.00 26.130 0.250 0.400 2.613
Grid A,B,C,D,E,F 6.00 10.157 0.300 0.400 7.313
Grid G,H 2.00 10.157 0.300 0.400 2.438
Main beam layout ( 16000mm from plinth)
Block 1

Prepared by: Checked by Approved by


40

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid 2-2 1.00 30.550 0.300 0.400 3.666


Grid 3-3 1.00 30.550 0.300 0.400 3.666
Grid 4-4 1.00 30.550 0.300 0.400 3.666
Secondary beam 1.00 30.550 0.250 0.400 3.055
Grid A,B,C,D,E,F 6.00 10.157 0.300 0.400 7.313
Grid G,H 2.00 10.157 0.300 0.400 2.438
Main beam layout ( 19200mm from plinth)
Grid 3-3 1.00 8.860 0.300 0.400 1.063
Grid 4-4 1.00 8.860 0.300 0.400 1.063
Grid C-C 1.00 4.430 0.300 0.400 0.532
Grid D-D 1.00 4.430 0.300 0.400 0.532

Slab
Block 1
Ground floor slab(3200mmfrom plinth) 1.00 7.385 34.000 0.125 31.386
deduction staircase (1.00) 4.120 4.880 0.125 (2.513)
First floor slab(6400mm from plinth) 1.00 10.360 34.000 0.125 44.030
deduction staircase (1.00) 4.120 4.880 0.125 (2.513)
Second floor slab(9600mm from plinth) 1.00 8.480 34.000 0.125 36.040
second floor slab 1.00 3.180 4.880 0.125 1.940
deduction staircase (1.00) 4.120 4.880 0.125 (2.513)
deduction staircase (1.00) 4.120 1.600 0.125 (0.824)
Third floor slab(12800mm from plinth) 1.00 11.735 34.000 0.125 49.874
deduction staircase (1.00) 4.120 4.880 0.125 (2.513)
deduction staircase (1.00) 4.120 1.600 0.125 (0.824)
Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 0.125 49.874
deduction staircase (1.00) 4.880 4.880 0.125 (2.977)

Top floor slab(19200mm from plinth) 1.00 13.510 8.630 0.125 14.574
Block 2
Second floor slab(9600mm from plinth) 1.00 28.456 8.660 0.125 30.804
second floor slab 1.00 Area= 90.134 0.125 11.267
deduction staircase (1.00) 4.120 5.520 0.125 (2.843)
Third floor slab(12800mm from plinth) 1.00 28.456 8.660 0.125 30.804
Thirdfloor slab 1.00 Area= 90.134 0.125 11.267
deduction staircase (1.00) 4.120 4.880 0.125 (2.513)
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 0.125 30.804
Fourth floor slab 1.00 Area= 90.134 0.125 11.267

Staricase
Block 1
Spiral staircase
Central Beam 1.00 7.570 0.300 0.230 2.089
waist slab 1.00 7.570 1.600 0.150 7.267
steps 21.00 1.600 0.300 0.153 3.080

Block 2
Spiral staircase
Central Beam 1.00 7.570 0.300 0.230 1.045
waist slab 1.00 7.570 1.600 0.150 3.634
steps 21.00 1.600 0.300 0.153 1.540

Open well staircase


Ground floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604
First Floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604

Sill lintel band


Block 1
Ground floor
External wall
Grid 1-1 1.00 30.529 0.230 0.150 1.053
Grid 2-2 1.00 26.109 0.230 0.150 0.901
Deduction
D1 (5.00) 1.067 0.230 0.075 (0.092)
GridA-A 1.00 4.730 0.230 0.150 0.163
Grid H-H 1.00 4.730 0.230 0.150 0.163

Internal wall
Grid B,C,D,E,F 5.00 4.730 0.230 0.150 0.816
Partition Wall
w/c 5.00 16.458 0.110 0.150 1.358
D2 (6.00) 0.914 0.110 0.075 (0.045)
room partition 1.00 8.077 0.110 0.075 0.067
Deduction
D1 (1.00) 1.067 0.110 0.075 (0.009)
D2 (1.00) 0.914 0.110 0.075 (0.008)
room partition 2 1.00 8.229 0.110 0.150 0.136
Deduction
D1 (2.00) 1.067 0.110 0.075 (0.018)
First floor
Block 1
External wall
Grid 1-1 1.00 30.529 0.230 0.150 1.053
Grid 2-2 1.00 26.109 0.230 0.150 0.901
Deduction
D1 (5.00) 1.067 0.230 0.075 (0.092)
GridA-A 1.00 4.730 0.230 0.150 0.163
Grid H-H 1.00 4.730 0.230 0.150 0.163
Railing wall 1.00 37.489 0.110 0.075 0.309
Internal wall
Grid B,C,D,E,F 5.00 4.730 0.230 0.150 0.816
Partition Wall
w/c 5.00 16.458 0.110 0.150 1.358
D2 (6.00) 0.914 0.110 0.075 (0.045)

Second Floor
Block 1
External wall
Parapet Wall 1.00 41.197 0.110 0.075 0.340

Prepared by: Checked by Approved by


41

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid 2-2 1.00 29.259 0.355 0.150 1.558


Grid 3-3 1.00 26.109 0.230 0.150 0.901
Deduction
D (6.00) 1.219 0.230 0.075 (0.126)
GridA-A 1.00 6.110 0.230 0.150 0.211
Grid H-H 1.00 6.110 0.230 0.150 0.211
Railing wall 1.00 9.303 0.110 0.075 0.077
Internal wall
Grid B,C,D,E,F 6.00 5.697 0.230 0.150 1.179

Block 2
External wall
Grid 5-5 1.00 25.640 0.230 0.150 0.885
Grid 6-6 1.00 8.191 0.230 0.150 0.283
Deduction
D1 (1.00) 1.067 0.230 0.075 (0.018)
Internal wall
Grid K-K 1.00 5.420 0.230 0.150 0.187
Grid L-L 1.00 7.460 0.230 0.150 0.257
Grid G-G 1.00 5.626 0.230 0.150 0.194
Grid H-H 1.00 5.035 0.230 0.150 0.174
W/C 1.00 73.366 0.110 0.150 1.211
Deduction -
D1 (2.00) 1.067 0.110 0.075 (0.018)
D2 (6.00) 0.914 0.110 0.075 (0.045)
Room 1 Partition
1.00 8.483 0.110 0.150 0.140
Deduction -
D1 (4.00) 1.067 0.110 0.075 (0.035)
D2 (1.00) 0.914 0.110 0.075 (0.008)

Room 2 Partition
1.00 22.149 0.230 0.150 0.764
Deduction -
D1 (1.00) 1.067 0.110 0.075 (0.009)
D (1.00) 1.219 0.110 0.070 (0.009)
W/C 1.00 5.334 0.110 0.150 0.088
Deduction
D2 (2.00) 0.914 0.110 0.070 (0.014)
230 partition wall 1.00 13.833 0.230 0.150 0.477
Third Floor
Block 1
External wall
Parapet Wall 1.00 37.692 0.110 0.075 0.311
Grid 2-2 1.00 29.259 0.355 0.150 1.558
Grid 3-3 1.00 26.109 0.230 0.150 0.901
Deduction
D (6.00) 1.219 0.230 0.075 (0.126)
GridA-A 1.00 6.110 0.230 0.150 0.211
Grid H-H 1.00 6.110 0.230 0.150 0.211
Railing wall 1.00 9.303 0.110 0.075 0.077
Internal wall
Grid B,C,D,E,F 6.00 5.697 0.230 2.825 22.208

Block 2
External wall
Grid 5-5 1.00 25.640 0.230 0.150 0.885
Grid 6-6 1.00 14.373 0.230 0.150 0.496
Deduction
D (1.00) 1.219 0.230 0.075 (0.021)
Grid 7-7 1.00 25.640 0.230 0.150 0.885
Grid O 1.00 7.429 0.230 0.150 0.256
Grid 10 1.00 8.178 0.230 0.150 0.282
Internal wall
Grid J-J 1.00 5.420 0.230 0.150 0.187
Grid K-K 1.00 5.420 0.230 0.150 0.187
Grid L-L 1.00 5.420 0.230 0.150 0.187
Grid G-G 1.00 5.626 0.230 0.150 0.194
Grid H-H 1.00 5.035 0.230 0.150 0.174
Deduction(D) (1.00) 1.219 0.230 0.075 (0.021)
Grid F-F 1.00 5.035 0.230 0.150 0.174
W/C 1.00 73.366 0.110 0.150 1.211
Deduction -
D1 (2.00) 1.067 0.110 0.075 (0.018)
D2 (6.00) 0.914 0.110 0.075 (0.045)
Room 1 Partition
1.00 8.001 0.230 0.150 0.276
Deduction -
D (1.00) 1.219 0.230 0.075 (0.021)
Fourth Floor
Block 1
External wall
Parapet Wall 1.00 35.863 0.110 0.075 0.296
Grid 2-2 1.00 29.259 0.230 0.150 1.009
Deduction
DW (6.00) 4.216 0.230 0.075 (0.436)
Grid 4-4 1.00 21.676 0.230 0.150 0.748
Deduction
D3 (1.00) 1.829 0.355 0.075 (0.049)
GridA-A 1.00 8.853 0.230 0.150 0.305
Grid H-H 1.00 8.853 0.230 0.150 0.305
Internal wall
Grid B 1.00 8.853 0.230 0.150 0.305
D (1.00) 1.219 0.230 0.075 (0.021)
Grid D 1.00 4.427 0.230 0.150 0.153
Grid E 1.00 6.161 0.230 0.150 0.213
Grid 3-3 1.00 4.419 0.230 0.150 0.152
Grid 3-3 1.00 10.770 0.110 0.150 0.178
Deduction
D1 (2.00) 1.067 0.230 0.075 (0.037)
partition wall 1.00 13.768 0.110 0.150 0.227
1.00 20.167 0.230 0.150 0.696
deduction
D (1.00) 1.219 0.230 0.075 (0.021)
D1 (1.00) 1.067 0.110 0.075 (0.009)
D2 (2.00) 0.914 0.110 0.075 (0.015)
Block 2
External wall
Grid 5-5 1.00 28.155 0.230 0.150 0.971
Deduction
W5 (4.00) 4.267 0.230 0.150 (0.589)
W6 (1.00) 3.556 0.230 0.150 (0.123)
W7 (1.00) 3.810 0.230 0.150 (0.131)
Grid 7-7 1.00 25.640 0.230 0.150 0.885
Grid O 1.00 7.429 0.230 0.150 0.256

Prepared by: Checked by Approved by


42

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid 10 1.00 8.178 0.230 0.150 0.282


Grid F-F 1.00 5.035 0.230 0.150 0.174
Internal wall
Grid J-J 1.00 5.589 0.230 0.150 0.193
Grid K-K 1.00 5.589 0.230 0.150 0.193
Grid G-G 1.00 5.626 0.230 0.150 0.194
Deduction(D2) (2.00) 0.914 0.230 0.075 (0.032)
Grid 6-6 1.00 4.477 0.110 0.150 0.074
Partion wall 1.00 9.423 0.230 0.150 0.325
Deduction(D) (1.00) 1.219 0.230 0.075 (0.021)
Partion wall 1.00 2.438 0.230 0.150 0.084
Deduction(D3) (1.00) 1.829 0.230 0.075 (0.032)
W/C 1.00 73.366 0.110 0.150 1.211
Deduction -
D1 (2.00) 1.067 0.110 0.075 (0.018)
D2 (6.00) 0.914 0.110 0.075 (0.045)
Fifth Floor
Block 1
External wall
Parapet Wall 1.00 154.602 0.110 0.075 1.275
Grid 3-3 1.00 8.853 0.230 0.150 0.305
Deduction
W8 (2.00) 3.962 0.230 0.150 (0.273)
Grid 4-4 1.00 8.853 0.230 0.150 0.305
Deduction
DW (1.00) 3.962 0.230 0.150 (0.137)
W8 (1.00) 3.962 0.230 0.150 (0.137)
Grid B-B 1.00 4.427 0.230 0.150 0.153
Grid D-D 1.00 4.427 0.230 0.150 0.153
Slanted slab
2.00 0.750 13.500 0.125 2.531
2.00 0.750 12.300 0.125 2.306
4.00 0.750 9.500 0.125 3.563
1.00 0.750 11.140 0.125 1.044
Total= 1,158.250 cum

TMT steel reinforcement bar of fe 500


grade including supplying, straightening,
cleaning, cutting, binding & fixing in
position with annealed tying binding wire Bar
5.00 all complete as per approved drawing, Please refer bending
Specification and instruction of site schedule
engineer.

Total= - MT
Formwork, shuttering, centering with
19mm thick waterproof ply board and
steel post for all works necessary
propping, scaffolding, staging, supporting
inclusive of wedging and cutting holes for
utilization till the support if fully
6.00 unyielding nett all complete as per
approved drawing, Specification and
instruction of site engineer.

Footing
F6
Rectangular porrtion 8.00 7.600 0.200 12.160
Footing
F5
Rectangular porrtion 6.00 13.600 0.200 16.320
Footing
F3
Rectangular porrtion 4.00 11.600 0.200 9.280
Footing
F2
Rectangular porrtion 6.00 10.000 0.200 12.000

Footing
F1
Rectangular porrtion 6.00 10.800 0.200 12.960

Footing
SF1
Rectangular porrtion 1.00 77.800 0.200 15.560
Footing
SF1
Rectangular porrtion 1.00 50.840 0.200 10.168
Footing
SF1
Rectangular porrtion 1.00 26.750 0.200 5.350
Footing
SF1
Rectangular porrtion 1.00 67.376 0.200 13.475
Footing
SF1
Rectangular porrtion 1.00 25.820 0.200 5.164

Column upto plinth -


Column upto plinth
Block 1 24.00 1.800 2.625 113.400
Block 2 28.00 1.600 3.075 137.760
Shear wall Up to Plinth 2.00 99.03 2.625 519.913
Block 1 Shear wall first floor 2.00 52.48 3.200 335.872
Shear wall block 1&2 second floor 2.00 99.03 2.625 519.913
Ground Floor Column
Block 1 24.00 1.800 3.075 132.840
Block 2 28.00 1.600 3.075 137.760
First floor
Block 1 24.00 1.800 3.075 132.840
Block 2 28.00 1.600 3.075 137.760
Second floor
Block 1 24.00 1.800 3.075 132.840
Block 2 28.00 1.600 3.075 137.760
Third floor
Block 1 24.00 1.800 3.075 132.840
Block 2 28.00 1.600 3.075 137.760
Fourth Floor
Block 1 24.00 1.800 3.075 132.840
Top Floor Column Block 1 6.00 1.800 3.075 33.210

Tie beam
Block1
Grid 1-1 2.00 30.550 0.300 18.330
Grid 2-2 2.00 30.550 0.300 18.330
Grid 3-3 2.00 30.550 0.300 18.330

Prepared by: Checked by Approved by


43

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid A,B,C,D,E,F,G,H 16.00 9.160 0.300 43.968


Block2
Grid 5-5 2.00 25.655 0.300 15.393
Grid 6-6 2.00 25.655 0.300 15.393
Grid 8-8 2.00 8.960 0.300 5.376
Grid 9-9 2.00 11.414 0.300 6.848
Grid G,H,I,J,K,L,M,N, 16.00 7.460 0.300 35.808

Plinth beam
Block1
Grid 1-1 2.00 30.550 0.300 18.330
Grid 2-2 2.00 30.550 0.300 18.330
Grid 3-3 2.00 30.550 0.300 18.330
Grid A,B,C,D,E,F,G,H 16.00 9.160 0.300 43.968
Block2
Grid 5-5 2.00 25.655 0.300 15.393
Grid 6-6 2.00 25.655 0.300 15.393
Grid 8-8 2.00 8.960 0.300 5.376
Grid 9-9 2.00 11.414 0.300 6.848
Grid G,H,I,J,K,L,M,N, 16.00 7.460 0.300 35.808

Main Beam
First Floor (3200mm from plinth beam)
Block 1
Grid 1-1 2.00 30.550 0.250 15.275
Grid 2-2 2.00 30.550 0.250 15.275
Grid 3-3 2.00 30.550 0.250 15.275
Secondary beam 2.00 30.550 0.225 13.748
Grid A,B,C,D,E,F,G,H 16.00 6.735 0.250 26.940
Block2
Grid 5-5 2.00 25.655 0.250 12.828
Grid 6-6 2.00 25.655 0.250 12.828
Grid 7-7 2.00 25.655 0.250 12.828
Grid 8-8 2.00 8.960 0.250 4.480
Grid 9-9 2.00 11.414 0.250 5.707
Grid 10-10 2.00 11.414 0.250 5.707
Secondary beam 2.00 32.811 0.200 13.124
Grid G,H,I,J,K,L,M,N, 16.00 7.460 0.250 29.840

Main beam layout ( 6400mm from plinth)


Block 1
Grid 1-1 2.00 30.550 0.250 15.275
Grid 2-2 2.00 30.550 0.250 15.275
Grid 3-3 2.00 30.550 0.250 15.275
Grid 4-4 2.00 30.550 0.250 15.275
Secondary beam 2.00 30.550 0.200 12.220
Grid A,B,C,D,E,F,G,H 16.00 13.590 0.250 54.360
Block2
Grid 5-5 2.00 25.655 0.250 12.828
Grid 6-6 2.00 25.655 0.250 12.828
Grid 7-7 2.00 25.655 0.250 12.828
Grid 8-8 2.00 8.960 0.250 4.480
Grid 9-9 2.00 11.414 0.250 5.707
Grid 10-10 2.00 11.414 0.250 5.707
Secondary beam 2.00 36.931 0.200 14.772
Grid G,H,I,J,K,L,M,N, 16.00 7.460 0.250 29.840

Main beam layout ( 9600mm from plinth)


Block 1
Grid 2-2 2.00 30.550 0.250 15.275
Grid 3-3 2.00 30.550 0.250 15.275
Grid 4-4 2.00 30.550 0.250 15.275
Secondary beam 2.00 25.670 0.200 10.268
Secondary beam 2.00 26.130 0.200 10.452
Grid A,B,C,D,E,F 12.00 7.580 0.250 22.740
Grid G,H 4.00 10.157 0.250 10.157
Block2
Grid 5-5 2.00 25.655 0.250 12.828
Grid 6-6 2.00 7.735 0.250 3.868
Grid 7-7 2.00 25.655 0.250 12.828
Grid 8-8 2.00 8.960 0.250 4.480
Grid 9-9 2.00 11.414 0.250 5.707
Grid10-10 2.00 11.414 0.250 5.707
Secondary beam 2.00 36.931 0.200 14.772
Grid G,H,I,J,K,L,M,N, 16.00 7.460 0.250 29.840

Main beam layout ( 12800mm from plinth)


Block 1
Grid 2-2 2.00 30.550 0.275 16.803
Grid 3-3 2.00 30.550 0.275 16.803
Grid 4-4 2.00 30.550 0.275 16.803
Secondary beam 2.00 26.130 0.200 10.452
Grid A,B,C,D,E,F 12.00 10.157 0.275 33.518
Grid G,H 4.00 10.157 0.275 11.173
Main beam layout ( 16000mm from plinth)
Block 1
Grid 2-2 2.00 30.550 0.275 16.803
Grid 3-3 2.00 30.550 0.275 16.803
Grid 4-4 2.00 30.550 0.275 16.803
Secondary beam 2.00 30.550 0.200 12.220
Grid A,B,C,D,E,F 12.00 10.157 0.275 33.518
Grid G,H 4.00 10.157 0.275 11.173
Main beam layout ( 19200mm from plinth)
Grid 3-3 2.00 8.860 0.275 4.873
Grid 4-4 2.00 8.860 0.275 4.873
Grid C-C 2.00 4.430 0.275 2.437
Grid D-D 2.00 4.430 0.275 2.437

Slab
Block 1
Ground floor slab(3200mmfrom plinth) 1.00 7.385 34.000 251.090
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 100.770 0.125 12.596
First floor slab(6400mm from plinth) 1.00 10.360 34.000 352.240
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 106.720 0.125 13.340
Second floor slab(9600mm from plinth) 1.00 8.480 34.000 288.320
second floor slab 1.00 3.180 4.880 15.518
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Slab sides 1.00 102.960 0.125 12.870
Third floor slab(12800mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Slab sides 1.00 223.920 0.125 27.990

Prepared by: Checked by Approved by


44

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 398.990


deduction staircase (1.00) 4.880 4.880 (23.814)
Slab sides 1.00 110.990 0.125 13.874
Top floor slab(19200mm from plinth) 1.00 13.510 8.630 116.591
Slab sides 1.00 44.280 0.125 5.535
Block 2
Second floor slab(9600mm from plinth) 1.00 28.456 8.660 246.429
second floor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 5.520 (22.742)
Slab sides 1.00 93.512 0.125 11.689
Third floor slab(12800mm from plinth) 1.00 28.456 8.660 246.429
Thirdfloor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 92.232 0.125 11.529
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 246.429
Fourth floor slab 1.00 Area= 90.134 90.134
Slab sides 1.00 74.232 0.125 9.279

Staricase
Block 1
Spiral staircase
Central Beam 1.00 7.570 0.460 13.929
waist slab 1.00 7.570 1.600 48.448
steps 21.00 1.600 0.153 20.536

Block 2
Spiral staircase
Central Beam 1.00 7.570 0.460 6.964
waist slab 1.00 7.570 1.600 24.224
steps 21.00 1.600 0.153 10.268

Open well staircase


Ground floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604
First Floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604

Sill lintel band


Block 1
Ground floor
External wall
Grid 1-1 1.00 30.529 0.150 9.159
Grid 2-2 1.00 26.109 0.150 7.833
Deduction
D1 (5.00) 1.067 0.075 (0.800)
GridA-A 1.00 4.730 0.150 1.419
Grid H-H 1.00 4.730 0.150 1.419

Internal wall
Grid B,C,D,E,F 5.00 4.730 0.150 7.095
Partition Wall
w/c 5.00 16.458 0.150 24.688
D2 (6.00) 0.914 0.075 (0.823)
room partition 1.00 8.077 0.075 1.212
Deduction
D1 (1.00) 1.067 0.075 (0.160)
D2 (1.00) 0.914 0.075 (0.137)
room partition 2 1.00 8.229 0.150 2.469
Deduction
D1 (2.00) 1.067 0.075 (0.320)
First floor
Block 1
External wall
Grid 1-1 1.00 30.529 0.150 9.159
Grid 2-2 1.00 26.109 0.150 7.833
Deduction
D1 (5.00) 1.067 0.075 (0.800)
GridA-A 1.00 4.730 0.150 1.419
Grid H-H 1.00 4.730 0.150 1.419
Railing wall 1.00 37.489 0.075 5.623
Internal wall
Grid B,C,D,E,F 5.00 4.730 0.150 7.095
Partition Wall
w/c 5.00 16.458 0.150 24.688
D2 (6.00) 0.914 0.075 (0.823)

Second Floor
Block 1
External wall
Parapet Wall 1.00 41.197 0.075 6.180
Grid 2-2 1.00 29.259 0.150 8.778
Grid 3-3 1.00 26.109 0.150 7.833
Deduction
D (6.00) 1.219 0.075 (1.097)
GridA-A 1.00 6.110 0.150 1.833
Grid H-H 1.00 6.110 0.150 1.833
Railing wall 1.00 9.303 0.075 1.395
Internal wall
Grid B,C,D,E,F 6.00 5.697 0.150 10.254

Block 2
External wall
Grid 5-5 1.00 25.640 0.150 7.692
Grid 6-6 1.00 8.191 0.150 2.457
Deduction
D1 (1.00) 1.067 0.075 (0.160)
Internal wall
Grid K-K 1.00 5.420 0.150 1.626
Grid L-L 1.00 7.460 0.150 2.238
Grid G-G 1.00 5.626 0.150 1.688
Grid H-H 1.00 5.035 0.150 1.511

Prepared by: Checked by Approved by


45

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

W/C 1.00 73.366 0.150 22.010


Deduction
D1 (2.00) 1.067 0.075 (0.320)
D2 (6.00) 0.914 0.075 (0.823)
Room 1 Partition
1.00 8.483 0.150 2.545
Deduction
D1 (4.00) 1.067 0.075 (0.640)
D2 (1.00) 0.914 0.075 (0.137)

Room 2 Partition
1.00 22.149 0.150 6.645
Deduction
D1 (1.00) 1.067 0.075 (0.160)
D (1.00) 1.219 0.070 (0.171)
W/C 1.00 5.334 0.150 1.600
Deduction
D2 (2.00) 0.914 0.070 (0.256)
230 partition wall 1.00 13.833 0.150 4.150
Third Floor
Block 1
External wall
Parapet Wall 1.00 37.692 0.075 5.654
Grid 2-2 1.00 29.259 0.150 8.778
Grid 3-3 1.00 26.109 0.150 7.833
Deduction
D (6.00) 1.219 0.075 (1.097)
GridA-A 1.00 6.110 0.150 1.833
Grid H-H 1.00 6.110 0.150 1.833
Railing wall 1.00 9.303 0.075 1.395
Internal wall
Grid B,C,D,E,F 6.00 5.697 2.825 193.112

Block 2
External wall
Grid 5-5 1.00 25.640 0.150 7.692
Grid 6-6 1.00 14.373 0.150 4.312
Deduction
D (1.00) 1.219 0.075 (0.183)
Grid 7-7 1.00 25.640 0.150 7.692
Grid O 1.00 7.429 0.150 2.229
Grid 10 1.00 8.178 0.150 2.453
Internal wall
Grid J-J 1.00 5.420 0.150 1.626
Grid K-K 1.00 5.420 0.150 1.626
Grid L-L 1.00 5.420 0.150 1.626
Grid G-G 1.00 5.626 0.150 1.688
Grid H-H 1.00 5.035 0.150 1.511
Deduction(D) (1.00) 1.219 0.075 (0.183)
Grid F-F 1.00 5.035 0.150 1.511
W/C 1.00 73.366 0.150 22.010
Deduction
D1 (2.00) 1.067 0.075 (0.320)
D2 (6.00) 0.914 0.075 (0.823)
Room 1 Partition
1.00 8.001 0.150 2.400
Deduction
D (1.00) 1.219 0.075 (0.183)
Fourth Floor
Block 1
External wall
Parapet Wall 1.00 35.863 0.075 5.380
Grid 2-2 1.00 29.259 0.150 8.778
Deduction
DW (6.00) 4.216 0.075 (3.794)
Grid 4-4 1.00 21.676 0.150 6.503
Deduction
D3 (1.00) 1.829 0.075 (0.274)
GridA-A 1.00 8.853 0.150 2.656
Grid H-H 1.00 8.853 0.150 2.656
Internal wall
Grid B 1.00 8.853 0.150 2.656
D (1.00) 1.219 0.075 (0.183)
Grid D 1.00 4.427 0.150 1.328
Grid E 1.00 6.161 0.150 1.848
Grid 3-3 1.00 4.419 0.150 1.326
Grid 3-3 1.00 10.770 0.150 3.231
Deduction
D1 (2.00) 1.067 0.075 (0.320)
partition wall 1.00 13.768 0.150 4.131
1.00 20.167 0.150 6.050
deduction
D (1.00) 1.219 0.075 (0.183)
D1 (1.00) 1.067 0.075 (0.160)
D2 (2.00) 0.914 0.075 (0.274)
Block 2
External wall
Grid 5-5 1.00 28.155 0.150 8.446
Deduction
W5 (4.00) 4.267 0.150 (5.120)
W6 (1.00) 3.556 0.150 (1.067)
W7 (1.00) 3.810 0.150 (1.143)
Grid 7-7 1.00 25.640 0.150 7.692
Grid O 1.00 7.429 0.150 2.229
Grid 10 1.00 8.178 0.150 2.453
Grid F-F 1.00 5.035 0.150 1.511
Internal wall
Grid J-J 1.00 5.589 0.150 1.677
Grid K-K 1.00 5.589 0.150 1.677
Grid G-G 1.00 5.626 0.150 1.688
Deduction(D2) (2.00) 0.914 0.075 (0.274)
Grid 6-6 1.00 4.477 0.150 1.343
Partion wall 1.00 9.423 0.150 2.827
Deduction(D) (1.00) 1.219 0.075 (0.183)
Partion wall 1.00 2.438 0.150 0.731
Deduction(D3) (1.00) 1.829 0.075 (0.274)
W/C 1.00 73.366 0.150 22.010
Deduction
D1 (2.00) 1.067 0.075 (0.320)
D2 (6.00) 0.914 0.075 (0.823)
Fifth Floor
Block 1
External wall
Parapet Wall 1.00 154.602 0.075 23.190
Grid 3-3 1.00 8.853 0.150 2.656

Prepared by: Checked by Approved by


46

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Deduction
W8 (2.00) 3.962 0.150 (2.377)
Grid 4-4 1.00 8.853 0.150 2.656
Deduction
DW (1.00) 3.962 0.150 (1.189)
W8 (1.00) 3.962 0.150 (1.189)
Grid B-B 1.00 4.427 0.150 1.328
Grid D-D 1.00 4.427 0.150 1.328
Total= 7,675.571 sqm

Good quality local chimney made


Brickwork in 1:4 C/S mortar up to
Ground floor in perfect line level finish
including supply of materials, wetting the
bricks, racking the joints and curing the
7.01 work for at least 7 days all complete as
per approved drawing, Specification and
instruction of site engineer.

Toe wall
Plinth beam
Block1
Grid 1-1 1.00 30.550 0.230 1.825 12.823
Grid 2-2 1.00 30.550 0.230 1.825 12.823
Grid 3-3 1.00 30.550 0.230 1.825 12.823
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.230 1.825 30.759
Block2
Grid 5-5 1.00 25.655 0.230 1.825 10.769
Grid 6-6 1.00 25.655 0.230 1.825 10.769
Grid 8-8 1.00 8.960 0.230 1.825 3.761
Grid 9-9 1.00 11.414 0.230 1.825 4.791
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.230 1.825 25.051
Block 1
Ground floor
External wall
Grid 1-1 1.00 30.529 0.230 2.825 19.836
Deduction
W4 (12.00) 0.914 0.230 1.829 (4.615)
W1 (1.00) 3.353 0.230 1.829 (1.410)
Grid 2-2 1.00 26.109 0.230 2.825 16.965
Deduction
D1 (5.00) 1.067 0.230 2.311 (2.835)
GridA-A 1.00 4.730 0.230 2.825 3.073
Deduction
W4 (2.00) 0.914 0.230 1.829 (0.769)
Grid H-H 1.00 4.730 0.230 2.825 3.073
Deduction
W4 (2.00) 0.914 0.230 1.829 (0.769)

Internal wall
Grid B,C,D,E,F 5.00 4.730 0.230 2.825 15.367
Partition Wall
w/c 5.00 16.458 0.110 3.075 27.835
D2 (6.00) 0.914 0.110 2.311 (1.395)
room partition 1.00 8.077 0.110 3.075 2.732
Deduction
D1 (1.00) 1.067 0.110 2.311 (0.271)
D2 (1.00) 0.914 0.110 2.311 (0.232)
room partition 2 1.00 8.229 0.110 2.311 2.092
Deduction
D1 (2.00) 1.067 0.110 2.311 (0.542)
Total= 202.503 cum

Good quality local chimney made


Brickwork in 1:4 C/S mortar in
superstructure in perfect line level finish
including supply of materials, wetting the
bricks, racking the joints and curing the
7.02 work for at least 7 days all complete as
per approved drawing, Specification and
instruction of site engineer.

First floor
Block 1
External wall
Grid 1-1 1.00 30.529 0.230 2.825 19.836
Deduction
W4 (12.00) 0.914 0.230 1.829 (4.615)
W1 (1.00) 3.353 0.230 1.829 (1.410)
Grid 2-2 1.00 26.109 0.230 2.825 16.965
Deduction
D1 (5.00) 1.067 0.230 2.311 (2.835)
GridA-A 1.00 4.730 0.230 2.825 3.073
Deduction
W4 (2.00) 0.914 0.230 1.829 (0.769)
Grid H-H 1.00 4.730 0.230 2.825 3.073
Deduction
W4 (2.00) 0.914 0.230 1.829 (0.769)
Railing wall 1.00 37.489 0.110 0.914 3.771
Internal wall
Grid B,C,D,E,F 5.00 4.730 0.230 2.825 15.367
Partition Wall
w/c 5.00 16.458 0.110 3.075 27.835
D2 (6.00) 0.914 0.110 2.311 (1.395)

Second Floor
Block 1
External wall
Parapet Wall 1.00 41.197 0.110 0.914 4.144
Grid 2-2 1.00 29.259 0.355 3.075 31.940
Deduction
W1 (6.00) 3.353 0.355 1.829 (13.059)
Grid 3-3 1.00 26.109 0.230 2.825 16.965
Deduction
D (6.00) 1.219 0.230 2.311 (3.888)
GridA-A 1.00 6.110 0.230 2.825 3.970
Deduction
W3 (1.00) 2.438 0.230 1.829 (1.026)
Grid H-H 1.00 6.110 0.230 2.825 3.970
Deduction
W3 (1.00) 2.438 0.230 1.829 (1.026)
Railing wall 1.00 9.303 0.110 0.914 0.936
Internal wall
Grid B,C,D,E,F 6.00 5.697 0.230 2.825 22.208

Prepared by: Checked by Approved by


47

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Block 2
External wall
Grid 5-5 1.00 25.640 0.230 2.825 16.660
Deduction
W3 (5.00) 1.829 0.230 1.829 (3.846)
W2 (1.00) 3.048 0.230 1.829 (1.282)
Grid 6-6 1.00 8.191 0.230 2.825 5.322
Deduction
D1 (1.00) 1.067 0.230 2.311 (0.567)
Internal wall
Grid K-K 1.00 5.420 0.230 2.825 3.522
Grid L-L 1.00 7.460 0.230 2.825 4.847
Grid G-G 1.00 5.626 0.230 2.825 3.656
Grid H-H 1.00 5.035 0.230 2.825 3.271
W/C 1.00 73.366 0.110 3.075 24.816
Deduction -
D1 (2.00) 1.067 0.110 2.311 (0.542)
D2 (6.00) 0.914 0.110 2.311 (1.395)
Room 1 Partition
1.00 8.483 0.110 3.075 2.869
Deduction -
D1 (4.00) 1.067 0.110 2.311 (1.085)
D2 (1.00) 0.914 0.110 2.311 (0.232)

Room 2 Partition
1.00 22.149 0.230 3.075 15.665
Deduction -
D1 (1.00) 1.067 0.110 2.311 (0.271)
D (1.00) 1.219 0.110 2.311 (0.310)
W/C 1.00 5.334 0.110 3.075 1.804
Deduction
D2 (2.00) 0.914 0.110 2.311 (0.465)
230 partition wall 1.00 13.833 0.230 3.075 9.783
Third Floor
Block 1
External wall
Parapet Wall 1.00 37.692 0.110 0.914 3.791
Grid 2-2 1.00 29.259 0.355 3.075 31.940
Deduction
W1 (6.00) 3.353 0.355 1.829 (13.059)
Grid 3-3 1.00 26.109 0.230 2.825 16.965
Deduction
D (6.00) 1.219 0.230 2.311 (3.888)
GridA-A 1.00 6.110 0.230 2.825 3.970
Deduction
W3 (1.00) 2.438 0.230 1.829 (1.026)
Grid H-H 1.00 6.110 0.230 2.825 3.970
Deduction
W3 (1.00) 2.438 0.230 1.829 (1.026)
Railing wall 1.00 9.303 0.110 0.914 0.936
Internal wall
Grid B,C,D,E,F 6.00 5.697 0.230 2.825 22.208

Block 2
External wall
Grid 5-5 1.00 25.640 0.230 2.825 16.660
Deduction
W3 (5.00) 1.829 0.230 1.829 (3.846)
W2 (1.00) 3.048 0.230 1.829 (1.282)
Grid 6-6 1.00 14.373 0.230 2.825 9.339
Deduction
D (1.00) 1.219 0.230 2.311 (0.648)
Grid 7-7 1.00 25.640 0.230 2.825 16.660
Grid O 1.00 7.429 0.230 2.825 4.827
Grid 10 1.00 8.178 0.230 2.825 5.314
Internal wall
Grid J-J 1.00 5.420 0.230 2.825 3.522
Grid K-K 1.00 5.420 0.230 2.825 3.522
Grid L-L 1.00 5.420 0.230 2.825 3.522
Grid G-G 1.00 5.626 0.230 2.825 3.656
Grid H-H 1.00 5.035 0.230 2.825 3.271
Deduction(D) (1.00) 1.219 0.230 2.311 (0.648)
Grid F-F 1.00 5.035 0.230 2.825 3.271
W/C 1.00 73.366 0.110 3.075 24.816
Deduction -
D1 (2.00) 1.067 0.110 2.311 (0.542)
D2 (6.00) 0.914 0.110 2.311 (1.395)
Room 1 Partition
1.00 8.001 0.230 3.075 5.658
Deduction -
D (1.00) 1.219 0.230 2.311 (0.648)
Fourth Floor
Block 1
External wall
Parapet Wall 1.00 35.863 0.110 0.914 3.607
Grid 2-2 1.00 29.259 0.230 2.800 18.843
Deduction
DW (6.00) 4.216 0.230 2.438 (14.186)
Grid 4-4 1.00 21.676 0.230 2.800 13.959
Deduction
D3 (1.00) 1.829 0.355 2.311 (1.500)
GridA-A 1.00 8.853 0.230 2.800 5.701
Deduction
W3 (2.00) 2.438 0.230 1.829 (2.051)
Grid H-H 1.00 8.853 0.230 2.800 5.701
Deduction
W3 (1.00) 2.438 0.230 1.829 (1.026)
Internal wall
Grid B 1.00 8.853 0.230 2.825 5.752
D (1.00) 1.219 0.230 2.311 (0.648)
Grid D 1.00 4.427 0.230 2.825 2.876
Grid E 1.00 6.161 0.230 2.825 4.003
Grid 3-3 1.00 4.419 0.230 2.825 2.871
Grid 3-3 1.00 10.770 0.110 2.825 3.347
Deduction
D1 (2.00) 1.067 0.230 2.311 (1.134)
partition wall 1.00 13.768 0.110 3.075 4.657
1.00 20.167 0.230 3.075 14.263
deduction
D (1.00) 1.219 0.230 2.311 (0.648)
D1 (1.00) 1.067 0.110 2.311 (0.271)
D2 (2.00) 0.914 0.110 2.311 (0.465)
Block 2
External wall
Grid 5-5 1.00 28.155 0.230 2.825 18.294

Prepared by: Checked by Approved by


48

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Deduction
W5 (4.00) 4.267 0.230 2.825 (11.090)
W6 (1.00) 3.556 0.230 2.825 (2.310)
W7 (1.00) 3.810 0.230 2.825 (2.475)
Grid 7-7 1.00 25.640 0.230 2.825 16.660
Grid O 1.00 7.429 0.230 2.825 4.827
Grid 10 1.00 8.178 0.230 2.825 5.314
Grid F-F 1.00 5.035 0.230 2.825 3.271
Internal wall
Grid J-J 1.00 5.589 0.230 2.825 3.631
Grid K-K 1.00 5.589 0.230 2.825 3.631
Grid G-G 1.00 5.626 0.230 2.825 3.656
Deduction(D2) (2.00) 0.914 0.230 2.311 (0.972)
Grid 6-6 1.00 4.477 0.110 2.825 1.391
Partion wall 1.00 9.423 0.230 3.075 6.664
Deduction(D) (1.00) 1.219 0.230 2.311 (0.648)
Partion wall 1.00 2.438 0.230 3.075 1.724
Deduction(D3) (1.00) 1.829 0.230 2.311 (0.972)
W/C 1.00 73.366 0.110 3.075 24.816
Deduction -
D1 (2.00) 1.067 0.110 2.311 (0.542)
D2 (6.00) 0.914 0.110 2.311 (1.395)
Fifth Floor
Block 1
External wall
Parapet Wall 1.00 154.602 0.110 0.914 15.550
Grid 3-3 1.00 8.853 0.230 2.800 5.701
Deduction
W8 (2.00) 3.962 0.230 2.800 (5.103)
Grid 4-4 1.00 8.853 0.230 2.800 5.701
Deduction
DW (1.00) 3.962 0.230 2.800 (2.552)
W8 (1.00) 3.962 0.230 2.800 (2.552)
Grid B-B 1.00 4.427 0.230 2.800 2.851
Grid D-D 1.00 4.427 0.230 2.800 2.851
Total= 544.863 sqm

9.00 Plaster Works

Supplying and Laying of 12.5mm thick


cement sand plaster in (1:4) ratio on
ceiling of good finish including supply of
materials, racking the joint, wetting of
9.01
surfaces & curing the work at least 7days
all complete as per approved drawing,
Specification and instruction of site
engineer

Ceiling
Block 1
Ground floor slab(3200mmfrom plinth) 1.00 7.385 34.000 251.090
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 100.770 0.125 12.596
First floor slab(6400mm from plinth) 1.00 10.360 34.000 352.240
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 106.720 0.125 13.340
Second floor slab(9600mm from plinth) 1.00 8.480 34.000 288.320
second floor slab 1.00 3.180 4.880 15.518
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Slab sides 1.00 102.960 0.125 12.870
Third floor slab(12800mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Slab sides 1.00 223.920 0.125 27.990
Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.880 4.880 (23.814)
Slab sides 1.00 110.990 0.125 13.874
Top floor slab(19200mm from plinth) 1.00 13.510 8.630 116.591
Slab sides 1.00 44.280 0.125 5.535
Block 2
Second floor slab(9600mm from plinth) 1.00 28.456 8.660 246.429
second floor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 5.520 (22.742)
Slab sides 1.00 93.512 0.125 11.689
Third floor slab(12800mm from plinth) 1.00 28.456 8.660 246.429
Thirdfloor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 4.880 (20.106)
Slab sides 1.00 92.232 0.125 11.529
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 246.429
Fourth floor slab 1.00 Area= 90.134 90.134
Slab sides 1.00 74.232 0.125 9.279

Staricase
Block 1
Spiral staircase
Central Beam 1.00 7.570 0.460 13.929
waist slab 1.00 7.570 1.600 48.448
steps 21.00 1.600 0.153 20.536

Block 2
Spiral staircase
Central Beam 1.00 7.570 0.460 6.964
waist slab 1.00 7.570 1.600 24.224
steps 21.00 1.600 0.153 10.268

Open well staircase


Ground floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604
First Floor
First flight
Steps 9.00 1.200 Area= 0.023 0.243
landing 1.00 2.550 1.500 0.150 0.574
waist slab 1.00 3.354 1.200 0.150 0.604
second flight
Steps 9.00 1.200 Area= 0.023 0.243
waist slab 1.00 3.354 1.200 0.150 0.604

Total= 2,918.767 sqm

Prepared by: Checked by Approved by


49

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Supplying and Laying of 12.5mm thick


cement sand plaster in (1:4) ratio on wall
of good finish including supply of
materials, racking the joint, wetting of
9.02
surfaces & curing the work at least 7days
all complete as per approved drawing,
Specification and instruction of site
engineer.

External Wall
Plinth beam
Block1
Grid 1-1 1.00 30.550 0.750 22.913
Grid 2-2 1.00 30.550 0.750 22.913
Grid 3-3 1.00 30.550 0.750 22.913
Grid A,B,C,D,E,F,G,H 8.00 9.160 0.750 54.960
Block2
Grid 5-5 1.00 25.655 0.750 19.241
Grid 6-6 1.00 25.655 0.750 19.241
Grid 8-8 1.00 8.960 0.750 6.720
Grid 9-9 1.00 11.414 0.750 8.561
Grid G,H,I,J,K,L,M,N, 8.00 7.460 0.750 44.760
Block 1 Shear wall first floor 2.00 52.48 3.200 335.872
Shear wall block 1&2 second floor 2.00 99.03 2.625 519.913
Block 1
Ground floor
External wall
Grid 1-1 1.00 34.129 3.075 104.946
Deduction
W4 (12.00) 0.914 1.829 (20.065)
W1 (1.00) 3.353 1.829 (6.131)
Grid 2-2 1.00 29.709 2.825 83.929
Deduction
D1 (5.00) 1.067 2.311 (12.327)
GridA-A 1.00 5.630 3.075 17.312
Deduction
W4 (2.00) 0.914 1.829 (3.344)
Grid H-H 1.00 5.630 3.075 17.312
Deduction
W4 (2.00) 0.914 1.829 (3.344)
First floor
Block 1
External wall
Grid 1-1 1.00 34.129 3.075 104.946
Deduction
W4 (12.00) 0.914 1.829 (20.065)
W1 (1.00) 3.353 1.829 (6.131)
Grid 2-2 1.00 29.709 3.075 91.356
Deduction
D1 (5.00) 1.067 2.311 (12.327)
GridA-A 1.00 5.630 3.075 17.312
Deduction
W4 (2.00) 0.914 1.829 (3.344)
Grid H-H 1.00 5.630 3.075 17.312
Deduction
W4 (2.00) 0.914 1.829 (3.344)
Railing wall 1.00 37.489 0.914 34.278
Second Floor
Block 1
External wall
Parapet Wall 1.00 41.197 0.914 37.668
Grid 2-2 1.00 30.174 3.075 92.784
Deduction -
W1 (6.00) 3.353 1.829 (36.786)
Grid 3-3 1.00 29.709 3.075 91.356
Deduction -
D (6.00) 1.219 2.311 (16.906)
GridA-A 1.00 7.460 3.075 22.940
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Grid H-H 1.00 7.460 3.075 22.940
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Railing wall 1.00 9.303 0.914 8.506

Block 2
External wall
Grid 5-5 1.00 28.440 3.075 87.454
Deduction -
W3 (5.00) 1.829 1.829 (16.721)
W2 (1.00) 3.048 1.829 (5.574)
Grid 6-6 1.00 9.391 2.825 26.530
Deduction -
D1 (1.00) 1.067 2.311 (2.465)
Third Floor
Block 1
External wall
Parapet Wall 1.00 37.692 0.914 34.464
Grid 2-2 1.00 30.174 3.075 92.784
Deduction
W1 (6.00) 3.353 1.829 (36.786)
Grid 3-3 1.00 29.709 3.075 91.356
Deduction
D (6.00) 1.219 2.311 (16.906)
GridA-A 1.00 7.460 3.075 22.940
Deduction
W3 (1.00) 2.438 1.829 (4.459)
Grid H-H 1.00 7.460 3.075 22.940
Deduction
W3 (1.00) 2.438 1.829 (4.459)
Railing wall 1.00 9.303 0.914 8.506

Block 2
External wall
Grid 5-5 1.00 28.440 3.075 87.454
Deduction -
W3 (5.00) 1.829 1.829 (16.721)
W2 (1.00) 3.048 1.829 (5.574)
Grid 6-6 1.00 16.173 3.075 49.731
Deduction -
D (1.00) 1.219 2.311 (2.818)
Grid 7-7 1.00 28.440 3.075 87.454
Grid O 1.00 8.629 3.075 26.535
Grid 10 1.00 8.578 3.075 26.378
Fourth Floor
Block 1

Prepared by: Checked by Approved by


50

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

External wall
Parapet Wall 1.00 35.863 0.914 32.792
Grid 2-2 1.00 30.174 3.075 92.784
Deduction -
DW (6.00) 4.216 2.438 (61.680)
Grid 4-4 1.00 24.376 3.075 74.955
Deduction -
D3 (1.00) 1.829 2.311 (4.226)
GridA-A 1.00 10.203 3.075 31.375
Deduction -
W3 (2.00) 2.438 1.829 (8.918)
Grid H-H 1.00 10.203 3.075 31.375
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Block 2
External wall
Grid 5-5 1.00 30.955 3.075 95.186
Deduction
W5 (4.00) 4.267 2.825 (48.217)
W6 (1.00) 3.556 2.825 (10.045)
W7 (1.00) 3.810 2.825 (10.763)
Grid 7-7 1.00 28.440 3.075 87.454
Grid O 1.00 8.629 3.075 26.535
Grid 10 1.00 8.578 3.075 26.378
Grid F-F 1.00 5.835 3.075 17.943
Fifth Floor
Block 1
External wall
Parapet Wall 1.00 154.602 0.914 141.361
Grid 3-3 1.00 10.203 3.075 31.375
Deduction -
W8 (2.00) 3.962 2.800 (22.188)
Grid 4-4 1.00 10.203 3.075 31.375
Deduction -
DW (1.00) 3.962 2.800 (11.094)
W8 (1.00) 3.962 2.800 (11.094)
Grid B-B 1.00 5.327 3.075 16.379
Grid D-D 1.00 5.327 3.075 16.379
Total 2,802.873 SqM
Internal Wall
Block 1
Ground floor
External wall
Grid 1-1 1.00 30.529 3.075 93.876
Deduction -
W4 (12.00) 0.914 1.829 (20.065)
W1 (1.00) 3.353 1.829 (6.131)
Grid 2-2 1.00 26.109 3.075 80.286
Deduction -
D1 (5.00) 1.067 2.311 (12.327)
GridA-A 1.00 4.730 3.075 14.545
Deduction -
W4 (2.00) 0.914 1.829 (3.344)
Grid H-H 1.00 4.730 3.075 14.545
Deduction -
W4 (2.00) 0.914 1.829 (3.344)

Internal wall
Grid B,C,D,E,F 10.00 4.730 3.075 145.448
Partition Wall -
w/c 10.00 16.458 3.075 506.096
D2 (12.00) 0.914 2.311 (25.359)
room partition 2.00 8.077 3.075 49.672
Deduction -
D1 (2.00) 1.067 2.311 (4.931)
D2 (2.00) 0.914 2.311 (4.226)
room partition 2 2.00 8.229 3.075 50.610
Deduction -
D1 (4.00) 1.067 2.311 (9.862)
First floor
Block 1
External wall
Grid 1-1 1.00 30.529 3.075 93.876
Deduction -
W4 (12.00) 0.914 1.829 (20.065)
W1 (1.00) 3.353 1.829 (6.131)
Grid 2-2 1.00 26.109 3.075 80.286
Deduction -
D1 (5.00) 1.067 2.311 (12.327)
GridA-A 1.00 4.730 3.075 14.545
Deduction -
W4 (2.00) 0.914 1.829 (3.344)
Grid H-H 1.00 4.730 3.075 14.545
Deduction -
W4 (2.00) 0.914 1.829 (3.344)
Internal wall -
Grid B,C,D,E,F 10.00 4.730 3.075 145.448
Partition Wall -
w/c 10.00 16.458 3.075 506.096
D2 (12.00) 0.914 2.311 (25.359)
-
Second Floor
Block 1
External wall
Grid 2-2 1.00 29.259 3.075 89.973
Deduction -
W1 (6.00) 3.353 1.829 (36.786)
Grid 3-3 1.00 26.109 3.075 80.286
Deduction -
D (6.00) 1.219 2.311 (16.906)
GridA-A 1.00 6.110 3.075 18.788
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Grid H-H 1.00 6.110 3.075 18.788
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Internal wall -
Grid B,C,D,E,F 12.00 5.697 3.075 210.201

Block 2
External wall
Grid 5-5 1.00 25.640 3.075 78.844
Deduction -
W3 (5.00) 1.829 1.829 (16.721)
W2 (1.00) 3.048 1.829 (5.574)

Prepared by: Checked by Approved by


51

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid 6-6 1.00 8.191 3.075 25.188


Deduction -
D1 (1.00) 1.067 2.311 (2.465)
Internal wall -
Grid K-K 2.00 5.420 3.075 33.333
Grid L-L 2.00 7.460 3.075 45.879
Grid G-G 2.00 5.626 3.075 34.602
Grid H-H 2.00 5.035 3.075 30.965
W/C 2.00 73.366 3.075 451.201
Deduction -
D1 (4.00) 1.067 2.311 (9.862)
D2 (12.00) 0.914 2.311 (25.360)
Room 1 Partition -
2.00 8.483 3.075 52.172
Deduction -
D1 (8.00) 1.067 2.311 (19.724)
D2 (2.00) 0.914 2.311 (4.227)
-
Room 2 Partition -
2.00 22.149 3.075 136.215
Deduction -
D1 (2.00) 1.067 2.311 (4.931)
D (2.00) 1.219 2.311 (5.636)
W/C 2.00 5.334 3.075 32.802
Deduction -
D2 (4.00) 0.914 2.311 (8.453)
230 partition wall 2.00 13.833 3.075 85.073
Third Floor
Block 1
External wall
Grid 2-2 1.00 29.259 3.075 89.973
Deduction -
W1 (6.00) 3.353 1.829 (36.786)
Grid 3-3 1.00 26.109 3.075 80.286
Deduction -
D (6.00) 1.219 2.311 (16.906)
GridA-A 1.00 6.110 3.075 18.788
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Grid H-H 1.00 6.110 3.075 18.788
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Internal wall -
Grid B,C,D,E,F 12.00 5.697 2.825 193.112

Block 2
External wall
Grid 5-5 1.00 25.640 3.075 78.844
Deduction -
W3 (5.00) 1.829 1.829 (16.721)
W2 (1.00) 3.048 1.829 (5.574)
Grid 6-6 1.00 14.373 3.075 44.196
Deduction -
D (1.00) 1.219 2.311 (2.818)
Grid 7-7 1.00 25.640 3.075 78.844
Grid O 1.00 7.429 3.075 22.845
Grid 10 1.00 8.178 3.075 25.148
Internal wall -
Grid J-J 2.00 5.420 3.075 33.333
Grid K-K 2.00 5.420 3.075 33.333
Grid L-L 2.00 5.420 3.075 33.333
Grid G-G 2.00 5.626 3.075 34.602
Grid H-H 2.00 5.035 3.075 30.965
Deduction(D) (2.00) 1.219 2.311 (5.636)
Grid F-F 2.00 5.035 3.075 30.965
W/C 2.00 73.366 3.075 451.201
Deduction -
D1 (4.00) 1.067 2.311 (9.862)
D2 (12.00) 0.914 2.311 (25.360)
Room 1 Partition -
2.00 8.001 3.075 49.204
Deduction -
D (2.00) 1.219 2.311 (5.636)
Fourth Floor
Block 1
External wall
Grid 2-2 1.00 29.259 3.075 89.973
Deduction -
DW (6.00) 4.216 2.438 (61.680)
Grid 4-4 1.00 21.676 3.075 66.653
Deduction -
D3 (1.00) 1.829 2.311 (4.226)
GridA-A 1.00 8.853 3.075 27.223
Deduction -
W3 (2.00) 2.438 1.829 (8.918)
Grid H-H 1.00 8.853 3.075 27.223
Deduction -
W3 (1.00) 2.438 1.829 (4.459)
Internal wall
Grid B 2.00 8.853 3.075 54.447
D (2.00) 1.219 2.311 (5.635)
Grid D 2.00 4.427 3.075 27.223
Grid E 2.00 6.161 3.075 37.890
Grid 3-3 2.00 4.419 3.075 27.179
Grid 3-3 2.00 10.770 3.075 66.237
Deduction
D1 (4.00) 1.067 2.311 (9.862)
partition wall 2.00 13.768 3.075 84.675
2.00 20.167 3.075 124.025
deduction
D (2.00) 1.219 2.311 (5.635)
D1 (2.00) 1.067 2.311 (4.931)
D2 (4.00) 0.914 2.311 (8.453)
Block 2
External wall
Grid 5-5 1.00 28.155 3.075 86.576
Deduction -
W5 (4.00) 4.267 2.825 (48.217)
W6 (1.00) 3.556 2.825 (10.045)
W7 (1.00) 3.810 2.825 (10.763)
Grid 7-7 1.00 25.640 3.075 78.844
Grid O 1.00 7.429 3.075 22.845
Grid 10 1.00 8.178 3.075 25.148
Grid F-F 1.00 5.035 3.075 15.483
Internal wall -

Prepared by: Checked by Approved by


52

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Grid J-J 2.00 5.589 3.075 34.371


Grid K-K 2.00 5.589 3.075 34.371
Grid G-G 2.00 5.626 3.075 34.602
Deduction(D2) (4.00) 0.914 2.311 (8.453)
Grid 6-6 2.00 4.477 3.075 27.531
Partion wall 2.00 9.423 3.075 57.952
Deduction(D) (2.00) 1.219 2.311 (5.636)
Partion wall 2.00 2.438 3.075 14.995
Deduction(D3) (2.00) 1.829 2.311 (8.453)
W/C 2.00 73.366 3.075 451.201
Deduction -
D1 (4.00) 1.067 2.311 (9.862)
D2 (12.00) 0.914 2.311 (25.360)
Fifth Floor
Block 1
External wall
Grid 3-3 1.00 8.853 3.075 27.223
Deduction -
W8 (2.00) 3.962 2.800 (22.188)
Grid 4-4 1.00 8.853 3.075 27.223
Deduction -
DW (1.00) 3.962 2.800 (11.094)
W8 (1.00) 3.962 2.800 (11.094)
Grid B-B 1.00 4.427 3.075 13.612
Grid D-D 1.00 4.427 3.075 13.612
Total= 5,435.373 sqm

10.00 Painting Works

Supplying & applying 3 coats Cement


putty on plastered surface all complete as
10.01
per approved drawing, Specification and
instruction of site engineer

same as plaster in walls 11,157.013


Total= 11,157.013 sqm

Supplying & applying 2 coats Emulsion


painting in Internal Room of approved
colour with one coat of primer Painting
10.02 over porperly cleaned surface at outside
of building all complete as per approved
drawing, Specification and instruction of
site engineer.

same as plaster in internal wall 8,354.140


Total= 8,354.140 sqm

Supplying & applying 2 coats of weather


paint at outside of Building of approved
colour with one coat of primer Painting
10.03 over porperly cleaned surface at outside
of building all complete as per approved
drawing, Specification and instruction of
site engineer.

same as plaster in external wall

2,802.873
Total= 2,802.873 sqm

11.00 Flooring:-

Plain cement Concrete (PCC)(38mm) in


1:2:4ratio for foundations and flooring
with approved quality of cement, sand
and machine crushed stone aggregate
11.01 including supply of materials,mixing,
laying, curing the work at least 7 days etc
all complete as per approved drawing,
Specification and instruction of site
engineer.

Block 1
Ground floor slab(3200mmfrom plinth) 1.00 7.385 34.000 251.090
deduction staircase (1.00) 4.120 4.880 (20.106)
First floor slab(6400mm from plinth) 1.00 10.360 34.000 352.240
deduction staircase (1.00) 4.120 4.880 (20.106)
Second floor slab(9600mm from plinth) 1.00 8.480 34.000 288.320
second floor slab 1.00 3.180 4.880 15.518
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Third floor slab(12800mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.120 4.880 (20.106)
deduction staircase (1.00) 4.120 1.600 (6.592)
Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.880 4.880 (23.814)
Top floor slab(19200mm from plinth) 1.00 13.510 8.630 116.591
Block 2
Second floor slab(9600mm from plinth) 1.00 28.456 8.660 246.429
second floor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 5.520 (22.742)
Third floor slab(12800mm from plinth) 1.00 28.456 8.660 246.429
Thirdfloor slab 1.00 Area= 90.134 90.134
deduction staircase (1.00) 4.120 4.880 (20.106)
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 246.429
Fourth floor slab 1.00 Area= 90.134 90.134

Total= 2,671.161 sqm

3mm punning in 1:1 ratio for flooring


with approved quality of cement, sand
including supply of materials,mixing,
11.02 laying, curing the work at least 7 days etc
all complete as per approved drawing,
Specification and instruction of site
engineer.

same as 38mm PCC 1,819.016


Total= 1,819.016 sqm

Prepared by: Checked by Approved by


53

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Supplying and laying 6 mm thick


porcelain glazed/non-glazed tiles in
11.03 cement sand mortar (1:4) ratio with
approved quality on wall and floor all
complete.
Block 1
Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.880 4.880 (23.814)
Top floor slab(19200mm from plinth) 1.00 13.510 8.630 116.591
Block 2
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 246.429
Fourth floor slab 1.00 Area= 90.134 90.134
Total= 828.330 sqm

Providing and laying 16mm thick marble


on floor with 20mm 1:4 c/s motar
11.04 including grinding and polishing as per
drawing, specification and instruction of
engineer.
Staricase
Block 1
Spiral staircase
steps 21.00 1.600 0.453 60.856

Block 2
steps 21.00 1.600 0.453 30.428

Open well staircase


Ground floor
First flight
Steps 9.00 1.200 0.450 4.860
landing 1.00 2.550 1.500 3.825
second flight
Steps 9.00 1.200 0.450 4.860
First Floor
First flight
Steps 9.00 1.200 0.450 4.860
landing 1.00 2.550 1.500 3.825
second flight
Steps 9.00 1.200 0.450 4.860
2.00 area= 32.126 64.251

Total= 182.626 sqm

Supplying, making and fitting fixing of


stainless steel pipe railling with 50mm
dia. stainless steel pipe handrail three
rows 25mm dia stainless steel pipe in
12.00
between handrail and floor and 39 mm
dia. stainless steel pipe for vertical post @
2m c/c including welding, cutting all
complete (per Rm)

Staircase railing 1.000 105.528 105.528


Total= 105.528 Rm

Earth filling of Excavated furface in 150


mm thick layer, watering, ramming
including supply of filling materials
within 10 m distance all complete as per
13.00 approved drawing,Specification and
instruction of site engineer.

35% OF Excavated Surface 490.088


floor 1 1.00 area= 237.800 0.625 148.625
floor 1 1.00 area= 363.800 0.625 227.375
Total= 866.088 cum

14.00 Surface dressing and filling hole 1.00 area= 237.800 237.800
1.00 area= 363.800 363.800
Total= 601.600 sqm

Elastocrete cementitious elastomeric


water proofing coating 2 components
capacity per kg 6 sq.ft for 2 coat
15.00 including supplying and applying all
complete work as per approved drawing
,specification and instruction of site
engineer.

Block 1
Fourth floor slab(16000mm from plinth) 1.00 11.735 34.000 398.990
deduction staircase (1.00) 4.880 4.880 (23.814)
Top floor slab(19200mm from plinth) 1.00 13.510 8.630 116.591
Block 2
Fourth floor slab(16000mm from plinth) 1.00 28.456 8.660 246.429
Fourth floor slab 1.00 Area= 90.134 90.134
Total= 828.330 sqm

16.00 Door window


Block 1
Ground floor
W4 (12.00) 0.914 1.829 20.065
W1 (1.00) 3.353 1.829 6.131
D1 (5.00) 1.067 2.311 12.327
W4 (2.00) 0.914 1.829 3.344
W4 (2.00) 0.914 1.829 3.344
D2 (6.00) 0.914 2.311 12.679
D1 (1.00) 1.067 2.311 2.465
D2 (1.00) 0.914 2.311 2.113
D1 (2.00) 1.067 2.311 4.931
First floor
Block 1
W4 (12.00) 0.914 1.829 20.065
W1 (1.00) 3.353 1.829 6.131
D1 (5.00) 1.067 2.311 12.327
W4 (2.00) 0.914 1.829 3.344
W4 (2.00) 0.914 1.829 3.344
D2 (6.00) 0.914 2.311 12.679
-
Second Floor
Block 1
W1 (6.00) 3.353 1.829 36.786
D (6.00) 1.219 2.311 16.906
W3 (1.00) 2.438 1.829 4.459
W3 (1.00) 2.438 1.829 4.459

Prepared by: Checked by Approved by


54

Detailed Estimate

Item Breadth Height


Description No. Length (m) Quantity Unit
No. (m) (m)

Block 2
W3 (5.00) 1.829 1.829 16.721
W2 (1.00) 3.048 1.829 5.574
D1 (1.00) 1.067 2.311 2.465
D1 (2.00) 1.067 2.311 4.931
D2 (6.00) 0.914 2.311 12.680
D1 (4.00) 1.067 2.311 9.862
D2 (1.00) 0.914 2.311 2.113

D1 (1.00) 1.067 2.311 2.466


D (1.00) 1.219 2.311 2.818
D2 (2.00) 0.914 2.311 4.227
Third Floor
Block 1
W1 (6.00) 3.353 1.829 36.786
D (6.00) 1.219 2.311 16.906
W3 (1.00) 2.438 1.829 4.459
W3 (1.00) 2.438 1.829 4.459
Block 2
W3 (5.00) 1.829 1.829 16.721
W2 (1.00) 3.048 1.829 5.574
D (1.00) 1.219 2.311 2.818
Deduction(D) (1.00) 1.219 2.311 2.818
D1 (2.00) 1.067 2.311 4.931
D2 (6.00) 0.914 2.311 12.680
D (1.00) 1.219 2.311 2.818
Fourth Floor
Block 1
DW (6.00) 4.216 2.438 61.680
D3 (1.00) 1.829 2.311 4.226
W3 (2.00) 2.438 1.829 8.918
W3 (1.00) 2.438 1.829 4.459
D (1.00) 1.219 2.311 2.818
D1 (2.00) 1.067 2.311 4.931
D (1.00) 1.219 2.311 2.818
D1 (1.00) 1.067 2.311 2.465
D2 (2.00) 0.914 2.311 4.226
Block 2
External wall
W5 (4.00) 4.267 2.825 48.217
W6 (1.00) 3.556 2.825 10.045
W7 (1.00) 3.810 2.825 10.763
Deduction(D2) (2.00) 0.914 2.311 4.227
Deduction(D) (1.00) 1.219 2.311 2.818
Deduction(D3) (1.00) 1.829 2.311 4.227
D1 (2.00) 1.067 2.311 4.931
D2 (6.00) 0.914 2.311 12.680
Fifth Floor
Block 1
W8 (2.00) 3.962 2.800 22.188
DW (1.00) 3.962 2.800 11.094
W8 (1.00) 3.962 2.800 11.094
Total= 601.553 Sq.M

17.00 Miscellaneous

Salnted slab
i Brick work 1.00 Area= 8.780 12.496 109.711 Sq.M
ii Tile work 1.00 area= 65.373 65.373 Sq.M

iii Timber Column


18.00 Area= 0.171 2.743 8.424
18.00 area= 0.279 0.200 1.005
Total 9.428 CuM

iv Gajur 7.00 7.000 Nos

Prepared by: Checked by Approved by


55

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works No. Length Breadth Height Quantity Remarks
1.0 Earthwork

Earthwork in excavation in boulder mixed and


hard soil in foundation, trenches including
1.1 timbering and shoring and 30m lead and 1.5m
lift all complete as per design, drawing and
specifications.
Construction of Septic tank as per drawing and
1 7.600 3.000 1.800 41.040
specification.
Construction of Soak pit as per drawing and
1 Area= 9.621 1.800 17.318
specification.
Total 58.358 Cum
Backfilling work including compaction and
1.2 levelling of the required depth all complete as
per the instructions of the site engineer.
Backfill @ 10% of Excavation Work Quantity 5.836
Total 5.836 Cum

2.0 Masonry Works


Providing and laying of chimney made brick in
1:4 c/s mortar with proper curing in perfect line
2.1
and level all complete as per the instructions of
the site engineer.
Construction of Septic tank as per drawing and
specification.
Long wall 1 7.340 0.600 0.300 1.321
Short wall 1 2.440 0.600 0.300 0.439
Long wall 1 7.040 0.450 0.300 0.950
Short wall 1 2.240 0.450 0.300 0.302
Long wall 1 6.840 0.350 0.300 0.718
Short wall 1 2.000 0.350 0.300 0.210
Long wall 1 6.600 0.230 0.770 1.169
Short wall 1 1.540 0.230 0.770 0.273
Partation wall 1 1.540 0.110 1.480 0.251
Construction of Soak pit as per drawing and
1 Perimeter= 2.780 1.800 5.005
specification.
Total 10.638 Cum
Providing and laying of dry stone in floor and
foundation complete to level including sand
2.2
filling on joints, as per drawing, specification
and instruction of engineer, all complete.

Prepared by: Checked by Approved by


56

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works No. Length Breadth Height Quantity Remarks
Construction of Septic tank as per drawing and
1 7.600 3.000 0.100 2.280
specification.
Total 2.280 Cum
3.0 Cement Concreting Works

Plain Cement Concrete ( PCC) work in (1:3:6) in


foundation with cement, sand and crushed stone
3.1 aggregate including mixing, laying, finishing to
approved level, line and dimensions and curing
all complete as per specification.

Construction of Septic tank as per drawing and


1 7.600 3.000 0.075 1.710
specification.
Total 1.710 Cum

Plain Cement Concrete (PCC) work in (1:1.5:3)


for M20 RCC works in sanitary work,
foundation, columns, beams and slabs with
cement, sand, and crushed stone aggregate of
3.2
approved size including mixing with concrete
mixture, compacting the concrete with vibrator
machine, laying, finishing to approved level,
lines and dimensions and curing all complete.

Construction of Septic tank as per drawing and


specification.
Base 1 7.600 3.000 0.075 1.710
Cover 1 6.600 2.000 0.080 1.056
Construction of Soak pit as per drawing and
specification.
Slab cover 2 Area= 3.142 0.100 0.628
Total 3.394 Cum

TMT steel reinforcement bar of fe 500 grade


including supplying, straightening, cleaning,
cutting, binding & fixing in position with
3.3
annealed tying binding wire all complete as per
approved drawing, Specification and instruction
of site engineer.

@ 1.5% of RCC Volume 399.681


Total 399.681 Kg
4.0 Formworks

Prepared by: Checked by Approved by


57

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works No. Length Breadth Height Quantity Remarks

Centering and shuttering work with 19mm


waterproof plywood for all RCC works of any
shape or size and at any level with necessary MS
4.1 propping, scaffolding, staging, supporting,
cutting holes for utilization works and removal
of formwork and lead up to 30m all complete as
per specification and instruction of site engineer.

Construction of Septic tank as per drawing and


specification.
Base side 1 perimeter 20.760 0.100 2.076
Cover 1 6.600 2.000 13.200
Cover side 1 perimeter 17.200 0.100 1.720
Construction of Soak pit as per drawing and
specification.
Cover 2 Area= 3.142 6.283
Cover Side 2 Perimeter= 6.283 0.100 1.257
Total 24.536 Sqm
5.0 Flooring Works
Sand filling work including compaction and
5.1 levelling of the required depth all complete as
per the instructions of the site engineer.
Soak Pit 1 Perimeter= 9.645 1.800 17.360
Total 17.360 Sqm
6.0 Plastering Works

Providing, laying & curing of 12.5 mm thick


(1:4) c/s plaster work in wall surfaces including
6.1 chipping & wetting the concrete surfaces
finished in perfect plumb, lines and level as per
specification and instruction of site engineer.

Construction of Septic tank as per drawing and


specification.
Long wall 1 7.340 0.600 0.300 1.321
Short wall 1 2.440 0.600 0.300 0.439
Long wall 1 7.040 0.450 0.300 0.950
Short wall 1 2.240 0.450 0.300 0.302
Long wall 1 6.840 0.350 0.300 0.718
Short wall 1 2.000 0.350 0.300 0.210
Long wall 1 6.600 0.230 0.770 1.169
Short wall 1 1.540 0.230 0.770 0.273

Prepared by: Checked by Approved by


58

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (Septic Tank and Soak Pit)

Err:509

Err:509
SN Description of Works No. Length Breadth Height Quantity Remarks
Partation wall 2 1.540 0.110 1.480 0.501
Total 5.884 Sqm

Prepared by: Checked by Approved by


59

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (25 cum Water Tank)

Err:509

###
SN Description of Works No. Length Breadth Height Quantity Remarks
1.0 Earthwork
Earthwork in excavation in boulder mixed
and hard soil in foundation, trenches
1.1 including timbering and shoring and 30m
lead and 1.5m lift all complete as per design,
drawing and specifications.
1 9.000 2.600 2.350 54.990
Total 54.990 Cum

Backfilling work including compaction and


1.2 levelling of the required depth all complete as
per the instructions of the site engineer.

Backfill @ 10% of Excavation Work Quantity 5.499


Total 5.499 Cum

2.0 Masonry Works


Providing and laying of chimney made brick
in 1:4 c/s mortar with proper curing in perfect
2.1
line and level all complete as per the
instructions of the site engineer.
Long wall 2 8.910 0.230 2.200 9.017
Short wall 2 2.040 0.230 2.200 2.064
Total 11.081 Cum

Providing and laying of dry stone in floor and


foundation complete to level including sand
2.2 filling on joints, as per drawing,
specification and instruction of engineer, all
complete.
1 9.000 2.600 0.100 2.340
Total 2.340 Cum
3.0 Cement Concreting Works
Plain Cement Concrete ( PCC) work in
(1:3:6) in foundation with cement, sand and
crushed stone aggregate including mixing,
3.1
laying, finishing to approved level, line and
dimensions and curing all complete as per
specification.
1 9.000 2.600 0.075 1.755
Total 1.755 Cum

Prepared by: Checked by Approved by


60

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (25 cum Water Tank)

Err:509

###
SN Description of Works No. Length Breadth Height Quantity Remarks

Plain Cement Concrete (PCC) work in


(1:1.5:3) for M20 RCC works in sanitary
work, foundation, columns, beams and slabs
with cement, sand, and crushed stone
3.2 aggregate of approved size including mixing
with concrete mixture, compacting the
concrete with vibrator machine, laying,
finishing to approved level, lines and
dimensions and curing all complete.

Long wall 2 8.450 0.100 2.000 3.380


Short Wall 2 1.840 0.100 2.000 0.736
Base 1 8.450 2.040 0.075 1.293
Slab cover 1 8.450 2.040 0.100 1.724
Total 7.133 Cum

TMT steel reinforcement bar of fe 500 grade


including supplying, straightening, cleaning,
cutting, binding & fixing in position with
3.3
annealed tying binding wire all complete as
per approved drawing, Specification and
instruction of site engineer.

@ 1.5% of RCC Volume 839.870


Total 839.870 Kg
5.0 Formworks

Centering and shuttering work with 19mm


waterproof plywood for all RCC works of
any shape or size and at any level with
necessary MS propping, scaffolding, staging,
5.1
supporting, cutting holes for utilization works
and removal of formwork and lead up to
30m all complete as per specification and
instruction of site engineer.

Long Wall 2 8.450 2.000 33.800


Short Wall 2 1.840 2.000 7.360
Cover 1 8.450 2.040 17.238
Cover Side 1 Perimeter= 20.980 0.100 2.098
Total 60.496 Sqm

Prepared by: Checked by Approved by


61

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detailed Estimate (25 cum Water Tank)

Err:509

###
SN Description of Works No. Length Breadth Height Quantity Remarks
7.0 Plastering Works

Providing, laying & curing of 12.5 mm thick


(1:4) c/s plaster work in wall surfaces
including chipping & wetting the concrete
7.1
surfaces finished in perfect plumb, lines and
level as per specification and instruction of
site engineer.

Long wall 2 8.910 0.230 2.200 9.017


Short wall 2 2.040 0.230 2.200 2.064

Total 11.081 Sqm

Prepared by: Checked by Approved by


62

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detail Estimate (Manhole)


Err:509
Err:509

S.N. Description of Work No. Length Breadth Height Quantity Unit Remarks
Construction work of Manholes:-8 nos
Earthwork in excavation in soft type soils in
foundation including 30m hauling distance
1 and 1.5 m. lift all complete in approval of 8 1.10 1.100 1.300 12.58 m3
site engineer.

Supplying and Soling Local flat brick in


proper line and level with sand filling all
complete as per approved drawing,
2 8 1.10 1.100 9.68 sqm
Specification and instruction of site engineer.

Plain cement concrete(PCC) in 1:3:6 ratio


for foundations and flooring with approved
quality of cement,sand and machine crushed
stone aggregate including supply of
3 8 1.10 1.100 0.075 0.72 m3
materials,mixing,laying,curing the work at
least 7 days etc all complete as per approved
drawing specification and instruction of site
engineer.

Good quality local chimney made


Brickwork in 1:4 C/S mortar in perfect line
level finish including supply of materials,
wetting the bricks, racking the joints and
curing the work for at least 7 days all
4 complete as per approved drawing,
Specification and instruction of site engineer.

Long Wall :- 16 0.91 0.250 0.900 3.27


Short Wall:- 16 0.45 0.250 0.900 1.62
Total= 4.89 m3
Plain cement Concrete (PCC) for RCC works
M 20 (1:1.5:3) with approved quality of
cement, sand and machine crushed stone
aggregate including supply of
5 materials,mixing, laying, curing the work at 8 0.91 0.910 0.100 0.66 m3
least 7 days etc all complete as per approved
drawing, Specification and instruction of site
engineer.

Prepared by: Checked by Approved by


63

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Detail Estimate (Manhole)


Err:509
Err:509

S.N. Description of Work No. Length Breadth Height Quantity Unit Remarks

TMT steel reinforcement bar of Fe 500 grade


including supplying, straightening, cleaning,
cutting, binding and fixing in position with
6 annealed tying binding wire including 30m 93.26 kg
haulage all complete as per approved
drawing specification and instruction of site
engineer.

Supplying and Laying of 12.5mm thick


cement sand plaster in (1:4) ratio on wall of
good finish including supply of materials,
racking the joint, wetting of surfaces &
7 curing the work at least 7days all complete
as per approved drawing, Specification and
instruction of site engineer.

Surface 8 1.80 0.900 12.96


At base of manholes 8 0.45 0.450 1.62
At cover of man holes 8 1.51 1.510 18.24
Total= 32.82 m2

Prepared by: Checked by Approved by


SUMMARY OF COSTS FOR SANITARY WORKS

Project :

Site Location: KAILALI ward-9


Date: 16th October 2020

S.NO DESCRIPTION OF WORKS AMOUNT (NRs.)

A. TOTAL COST OF SANITARY WORKS FOR GROUND FLOOR 122,587.36


B. TOTAL COST OF SANITARY WORKS FOR FIRST FLOOR 71,056.75
C. TOTAL COST OF EXTERNAL SANITARY WORKS 328,900.46
SUB TOTAL (A+B+C+D+E+F) 522,544.56

GRAND TOTAL 522,544.56


In words:FIVE LAKH THIRTEEN THOUSAND FIVE HUNDRED AND TEN RUPEES SEVENTY FOUR PAISE ONLY

Kanya Mandir Secondary School Summary : Page 64 of 108


65

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078

Site prepatation for fascine laying, each works in excavation of trench in soft clay and silty soil including
1.5m lift and 10m lead (per cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.70000 580.00 406.00 406.00
2 Total cost including 3% for tools and plants 418.18
3 15% Contractor Overhead 62.73
4 Grand Total 480.91 Rs/cum

Site prepatation for fascine laying, each works in excavation of trench in hard clay and gravel containing
soil including 1.5m lift and 10m lead (per cum) (upto 30 cm.)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.80000 580.00 464.00 464.00
2 Total cost including 3% for tools and plants 477.92
3 15% Contractor Overhead 71.69
4 Grand Total 549.61 Rs/cum

Backfilling work including compaction and levelling of the required depth all complete (per cum)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.50000 580.00 290.00 290.00
2 Material Cost
Soil cum 0.00000 832.20 0.00 0.00
3 Cost including 3% for tools and plants 298.70
4 15% Contractor Overhead 44.81
5 Grand Total 343.51 Rs/cum

Brick masonry work in 1:4 cement sand mix ratio (per cum) for ground Floor
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 1.50000 850.00 1275.00
Unskilled Labour md 2.40000 580.00 1392.00 2667.00
2 Material Cost
Bamboo no 2.00000 380.00 760.00

Prepared by: Checked by Approved by


66

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Ropes kg 1.00000 131.00 131.00
Bricks no 560.00000 13.39 7498.40
Cement kg 100.00000 17.28 1728.00
Sand cum 0.28000 1042.20 291.82 10409.22
3 Cost including 3% for tools and plants 13156.23
4 15% Contractor Overhead 1973.43
5 Grand Total 15129.66 Rs/cum

Brick masonry work in 1:4 cement sand mix ratio (per cum) for above ground floor
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 1.50000 850.00 1275.00
Unskilled Labour md 2.90000 580.00 1682.00 2957.00
2 Material Cost
Bamboo no 2.00000 380.00 760.00
Ropes kg 1.00000 131.00 131.00
Bricks no 560.00000 13.39 7498.40
Cement kg 100.00000 17.28 1728.00
Sand cum 0.28000 1042.20 291.82 10409.22
3 Cost including 3% for tools and plants 13454.93
4 15% Contractor Overhead 2018.24
5 Grand Total 15473.16 Rs/cum

Stone masonry work in 1:4 cement sand mix ratio (per cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 1.50000 850.00 1275.00
Unskilled Labour md 5.00000 580.00 2900.00 4175.00
2 Material Cost
Stone cum 1.10000 1954.29 2149.72
Cement bag 3.18000 864.00 2747.52
Sand cum 0.45000 1042.20 468.99 5366.23
3 Cost including 3% for tools and plants 9666.48
4 15% Contractor Overhead 1449.97
5 Grand Total 11116.45 Rs/cum

Prepared by: Checked by Approved by


67

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Dry Brick Soling (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.50000 850.00 425.00
Unskilled Labour md 1.50000 580.00 870.00 1295.00
2 Material Cost
Sand cum 0.07000 1042.20 72.95
Brick no 42.00000 13.39 562.38 635.33
3 Sub - total 1930.33
4 15% Contractor Overhead 289.55
5 Grand Total 2219.88 Rs/sqm

Dry Stone Soling (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.50000 850.00 425.00
Unskilled Labour md 1.50000 580.00 870.00 1295.00
2 Material Cost
Stone cum 1.10000 1954.29 2149.72 2149.72
3 Sub - total 3444.72
4 15% Contractor Overhead 516.71
5 Grand Total 3961.43 Rs/cum

1:3:6 P.C.C. work in foundation (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.50000 850.00 425.00
Unskilled Labour md 3.50000 580.00 2030.00 2455.00
2 Material Cost
Cement kg 220.00000 17.28 3801.60
Sand cum 0.47000 1042.20 489.83
Aggregate of 40 mm cum 0.65000 1729.50 1124.18
Aggregate of 20 mm cum 0.24000 2209.50 530.28 5945.89
3 Cost including 3% for tools and plants 8474.54
4 15% Contractor Overhead 1271.18
5 Grand Total 9745.72 Rs/cum

Prepared by: Checked by Approved by


68

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078

1:1.5 :3 R.C.C. work in superstructural component (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.80000 850.00 680.00
Unskilled Labour md 7.00000 580.00 4060.00 4740.00
2 Material Cost
Cement kg 400.00000 17.28 6912.00
Sand cum 0.42500 1042.20 442.94
Aggregate of 20 mm cum 0.57000 2209.50 1259.42
Aggregate of 10 mm cum 0.29000 1559.50 452.26 9066.61
3 Cost including 3% for tools and plants 13948.81
4 15% Contractor Overhead 2092.32
5 Grand Total 16041.13 Rs/cum

1:2:4 R.C.C. work in superstructural component (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.50000 850.00 425.00
Unskilled Labour md 3.50000 580.00 2030.00 2455.00
2 Material Cost
Cement kg 320.00000 17.28 5529.60
Sand cum 0.44500 1042.20 463.78
Aggregate of 40 mm cum 0.52000 1729.50 899.34
Aggregate of 20 mm cum 0.33000 2209.50 729.14 7621.85
3 Cost including 3% for tools and plants 10150.50
4 15% Contractor Overhead 1522.58
5 Grand Total 11673.08 Rs/cum

1:1:2 R.C.C. work in superstructural component (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.80000 850.00 680.00
Unskilled Labour md 7.00000 580.00 4060.00 4740.00
2 Material Cost
Cement kg 610.00000 17.28 10540.80

Prepared by: Checked by Approved by


69

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Sand cum 0.42500 1042.20 442.94
Aggregate of 20 mm cum 0.64000 2209.50 1414.08
Aggregate of 10 mm cum 0.21000 1559.50 327.50 12725.31
3 Cost including 3% for tools and plants 17607.51
4 15% Contractor Overhead 2641.13
5 Grand Total 20248.64 Rs/cum

Reinforcement for R.C.C. work (per kG)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.01200 850.00 10.20
Unskilled Labour md 0.01200 580.00 6.96 17.16
2 Material Cost
Steel kg 1.05000 82.20 86.30
Binding wire kg 0.01000 106.20 1.06 87.37
3 Cost including 3% for tools and plants 105.04
4 15% Contractor Overhead 15.76
5 Grand Total 120.80 Rs/kg

Form work in column(per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.15740 850.00 133.79
Unskilled Labour md 0.23610 580.00 136.94 270.73
2 Material Cost
Nails kg 0.25000 115.20 28.80
Local Wood cum 0.00190 35317.54 67.10
metal prop no 0.05400 1942.93 104.92
plywood 19mm sqm 0.06930 1619.48 112.23 313.05
3 Cost including 3% for tools and plants 591.90
4 15% Contractor Overhead 88.78
5 Grand Total 680.68 Rs/sqm

Form work in beam and slab(per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost

Prepared by: Checked by Approved by


70

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Skilled Labour md 0.26700 850.00 226.95
Unskilled Labour md 0.40000 580.00 232.00 458.95
2 Material Cost
Nails kg 0.25000 115.20 28.80
Local Wood cum 0.00400 35317.54 141.27
metal prop no 0.04000 1942.93 77.72
plywood 19mm sqm 0.16500 1619.48 267.21 515.00
3 Cost including 3% for tools and plants 987.72
4 15% Contractor Overhead 148.16
5 Grand Total 1135.88 Rs/sqm

38 mm thick Salwood paneled door and window shutter work (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 4.71698 850.00 4009.43
Unskilled Labour md 0.47170 580.00 273.58 4283.02
2 Material Cost
Saal Wood cum 0.03962 204367.54 8097.58
100mm hinge no. 2.83019 27.58 78.07
150mm cheskini no. 0.94340 80.20 75.66
225 mm locking set no. 0.47170 430.20 202.92
Simple handle no. 0.94340 50.20 47.35
Screw and nails no. 1.00000 60.00 60.00 8561.58
3 Sub - total 12844.60
4 15% Contractor Overhead 1926.69
5 Grand Total 14771.29 Rs/sq.m.

Salwood chaukhat work (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 34.00000 850.00 28900.00
Unskilled Labour md 3.40000 580.00 1972.00 30872.00
2 Material Cost
Timber cum 1.10000 204367.54 224804.30
Hold fast no. 92.00000 20.91 1923.65
Screw no. 184.00000 3.80 698.28 227426.23
3 Sub - total 258298.23
4 15% Contractor Overhead 38744.73

Prepared by: Checked by Approved by


71

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
5 Grand Total 297042.97 Rs/cu.m.

38 mm thick 1:2:4 Cement Concrete flooring (Screening) (per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
Labour Cost
1 Skilled Labour md 0.13000 850.00 110.50
Unskilled Labour md 0.20000 580.00 116.00 226.50
Material Cost
Sand cum 0.02000 1042.20 20.84
Aggregate (12.5 mm ) cum 0.04000 1559.50 62.38
Cement kg. 13.00000 17.28 224.64 307.86
3 Sub - total 534.36
4 15% Contractor Overhead 80.15
5 Grand Total 614.52 Rs/sqm

Porcelene glazed tile work in 1:4 cement sand mortar (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 1.30000 850.00 1105.00
Unskilled Labour md 0.45000 580.00 261.00 1366.00
Material Cost
2 Cement bag 0.11000 864.00 95.04
Sand cum 0.02000 1042.20 20.84
Porcelene glazed tile sqm 1.10000 1077.38 1185.11
White cement kg. 0.33000 40.20 13.26 1314.26
3 Sub - total 2680.26
4 15% Contractor Overhead 402.04
5 Grand Total 3082.30 Rs/sqm

Sand Filling (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.70000 580 406.00 406.00
2 Material Cost
Sand cum 1.10000 1042.20 1146.42 1146.42
3 Cost including 3% for tools and plants 1564.60

Prepared by: Checked by Approved by


72

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
4 15% Contractor Overhead 234.69
5 Grand Total 1799.29 Rs/cum

Soil Filling without soil (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.50000 580.00 290.00 290.00
2 Material Cost
Soil cum 0.00000 832.20 0.00 0.00
3 Cost including 3% for tools and plants 298.70
4 15% Contractor Overhead 44.81
5 Grand Total 343.51 Rs/cum

Soil Filling including soil (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.50000 580.00 290.00 290.00
2 Material Cost
Soil cum 1.50000 832.20 1248.30 1248.30
3 Cost including 3% for tools and plants 1547.00
4 15% Contractor Overhead 232.05
5 Grand Total 1779.05 Rs/cum

3 mm thick cement punning (per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.10000 850.00 85.00
Unskilled Labour md 0.10000 580.00 58.00 143.00
2 Material Cost
Cement bag 0.11000 864.00 95.04 95.04
3 Sub - total 238.04
4 15% Contractor Overhead 35.71
5 Grand Total 273.75 Rs/sqm

16 mm thick marble flooring in 20 mm thick 1:4 cement sand mix ratio mortar including grinding and
polishing (per sqm)

Prepared by: Checked by Approved by


73

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
Labour Cost
1 Skilled Labour md 0.13000 850.00 110.50
Unskilled Labour md 0.20000 580.00 116.00 226.50
Material Cost
2 Cement kg. 13.00000 17.28 224.64
Sand cum 0.02000 1042.20 20.84
Marble (16 mm) sqm 1.10000 1461.95 1608.15
Oxalic acid kg. 0.04000 170.20 6.81
Candle polish kg. 0.01000 620.20 6.20
Tarpentine oil litre 0.05000 193.20 9.66
Carborandom stone no 0.04000 645.20 25.81 1902.11
3 Sub - total 2128.61
4 15% Contractor Overhead 319.29
5 Grand Total 2447.90 Rs/sqm

12.5 mm thick cement plaster work in 1:4 cement sand mix ratio (per sqm) other than ceiling
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.12000 850.00 102.00
Unskilled Labour md 0.16000 580.00 92.80 194.80
2 Material Cost
Bamboo no 0.02000 380.98 7.62
Ropes kg 0.01000 131.20 1.31
Cement kg 3.82000 17.28 66.01
Sand cum 0.01570 1042.20 16.36 91.30
3 Cost including 3% for tools and plants 291.95
4 15% Contractor Overhead 43.79
5 Grand Total 335.74 Rs/sqm

12.5 mm thick cement plaster work in 1:4 cement sand mix ratio (per sqm) in ceiling
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.12000 850.00 102.00
Unskilled Labour md 0.20000 580.00 116.00 218.00
2 Material Cost

Prepared by: Checked by Approved by


74

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Bamboo no 0.02000 380.98 7.62
Ropes kg 0.01000 131.20 1.31
Cement kg 3.82000 17.28 66.01
Sand cum 0.01570 1042.20 16.36 91.30
3 Cost including 3% for tools and plants 315.84
4 15% Contractor Overhead 47.38
5 Grand Total 363.22 Rs/sqm

Two Coat of washable distemper paint with one coat primer (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.05800 850.00 49.30
Unskilled Labour md 0.05800 580.00 33.64 82.94
2 Material Cost
Cement Primer kg 0.08000 413.20 33.06
Washable Distemper lit 0.16000 264.20 42.27 75.33
3 Sub- Total 158.27
4 15% Contractor Overhead 23.74
5 Total Cost 182.01 Rs/sqm

Two Coat of weathercoat paint on plaster surface (per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.12000 850.00 102.00
Unskilled Labour md 0.08000 580.00 46.40 148.40
2 Material Cost
Primer lit 0.08100 413.20 33.47
weathercoat paint lit 0.02000 1260.20 25.20 58.67
3 Sub- Total 207.07
4 15% Contractor Overhead 31.06
5 Total Cost 238.13 Rs/sqm

Readymade enamel paint two coats (per sqm)


a. Primer
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost

Prepared by: Checked by Approved by


75

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Skilled labour md 0.03000 850.00 25.50
Unskilled Labour md 0.03000 580.00 17.40 42.90
2 Material Cost
Primer litre 0.08100 369.20 29.90 29.90
3 Sub - total 72.80
4 15% Contractor Overhead 10.92
5 Grand Total 83.73 Rs/sqm
b. First coat
1 Labour Cost
Skilled labour md 0.05000 850.00 42.50
Unskilled Labour md 0.02000 580.00 11.60 54.10
2 Material Cost
Prepared enamel color litre 0.09000 630.20 56.72 56.72
3 Sub - total 110.82
4 15% Contractor Overhead 16.62
5 Grand Total 127.44 Rs/sqm
c. Second coat
1 Labour Cost
Skilled labour md 0.04000 850.00 34.00
Unskilled Labour md 0.03000 580.00 17.40 51.40
2 Material Cost
Prepared enamel color litre 0.07000 630.20 44.11 44.11
3 Sub - total 95.51
4 15% Contractor Overhead 14.33
5 Grand Total 109.84 Rs/sqm
6 Total cost for double coat 321.01 Rs/sqm
Supplying & applying 3 coats Cement putty on plastered surface all complete as per approved
drawing, Specification and instruction of site engineer (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
a First Coat
Skilled labour md 0.00800 850.00 6.80
Unskilled Labour md 0.00700 580.00 4.06 10.86
b Second coat
Skilled labour md 0.01500 850.00 12.75
Unskilled Labour md 0.01100 580.00 6.38 19.13

Prepared by: Checked by Approved by


76

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
c Third coat
Skilled labour md 0.03000 850.00 25.50
Unskilled Labour md 0.02700 580.00 15.66 41.16
2 Material Cost
a First Coat
White cement kg 0.12000 40.20 4.82
gum lit 0.00480 0.00 0.00 4.82
b Second coat
White cement kg 0.22000 40.20 8.84
gum lit 0.00880 16.00 0.14 8.98
c Third coat
White cement kg 0.32000 40.20 12.86
gum lit 0.01280 0.00 0.00 12.86
3 Sub- Total 97.82
4 15% Contractor Overhead 14.67
5 Total Cost 112.49 Rs/sqm

Supplying and laying of one layer of polyethene sheet (500 Gauge) (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.06000 850.00 51.00

UnSkilled labour md 0.06000 580.00 34.80 85.80

2 Material Cost
Polyethene Sheet sqm 1.10000 220.29 242.32 242.32
3 Sub - total 328.12
4 15% Contractor Overhead 49.22
5 Grand Total 377.34 Rs/sqm
Elastocrete cementitious elastomeric water proofing coating (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost

Elastocrete cementitious
elastomeric water sqm 1.00000 559.72 559.72 559.72
proofing

2 15% Contractor Overhead 83.96

Prepared by: Checked by Approved by


77

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
3 Grand Total 643.67 Rs/sqm
Providing, fabricating & fixing metal spiral stair using 25x25x5mm angle, 20x4.5mm grill plate, 32mm
dia. MS black pipe (medium) hand rail and 20x20x2mm square pipe with 750mm wide steps and
100mm dia main post all complete (per Rm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Metal Spiral Stair Rm 1.00000 9433.63 9433.63 9433.63
2 15% Contractor Overhead 1415.04
3 Grand Total 10848.67 Rs/Rm
Supplying, making and fitting fixing of stainless steel pipe railling with 50mm dia. stainless steel pipe
handrail three rows 25mm dia stainless steel pipe in between handrail and floor and 39 mm dia.
stainless steel pipe for vertical post @ 2m c/c including welding, cutting all complete (per Rm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Stainless Steel Pipe Rm 1.00000 2811.11 2811.11 2811.11
2 15% Contractor Overhead 421.67
3 Grand Total 3232.77 Rs/Rm

Two/three paneled Aluminium sliding window with fixed ventilation section size (101.6x38.1x1.2)mm
and 4mm clear glass, auto lock, knobs, gaskets including mosquito-proof net panel.

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Sliding Window sqm 1.00000 8559.75 8559.75 8559.75
2 15% Contractor Overhead 1283.96
3 Grand Total 9843.71 Rs/Sqm

Supplying and fixing aluminium hinge fabrication, natural colour anod aluminium door including
door closer, americian handle, stopper, aldrop, lock, rubber, brush, gaskets and necessary
hardware,etc with section size (101.6x44.5x1.2)mm as per specification and instruction of site
engineer. per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Door sqm 1.00000 10359.75 10359.75 10359.75
2 15% Contractor Overhead 1553.96
3 Grand Total 11913.71 Rs/Sqm

Laying Interlocking concrete paver (per sqm)

Prepared by: Checked by Approved by


78

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.10000 850.00 85.00
Unskilled Labour md 1.00000 580.00 580.00 665.00
2 Material Cost
Interlocking block sqm 1.10000 1193.79 1313.17
Stone Dust (area*5cm) sqm 0.05500 40.00 2.20
Stone Dust cum 0.07100 614.75 43.65 1359.02
3 Sub total 2024.02
4 15% Contractor Overhead 303.60
5 Total Cost 2327.62 Rs/sqm

Gabion Crate in stone filling with gabion box, assembling binding all complete (per cum)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.30000 850.00 255.00
Unskilled Labour md 0.84000 580.00 487.20 742.20
2 Material Cost
Stone cum 1.10000 1954.29 2149.72

gabion bax of mesh size


100X120 mm, mesh wire
3 mm, selvedge wire 3.9 cum 1.00000 0.00 0.00 2149.72
mm and lacing wie 2.4
mm
3 Sub total 2891.92
4 15% Contractor Overhead 433.79
5 Total Cost 3325.71 Rs/cum

Supplying, making and fitting fixing of mild steel hollow pipe including welding, cutting and two coat
primer all complete as per specification and instruction of site engineer (per Kg)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.04000 850.00 34.00
Skilled labour md 0.04000 580.00 23.20 57.20
2 Material Cost
All sizes mild steel pipe Kg 1.10000 99.20 109.11
Primer Paint lit 0.01000 369.20 3.69 112.81

Prepared by: Checked by Approved by


79

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
3 Sub - total 170.01
4 15% Contractor Overhead 25.50
5 Grand Total 195.51 Rs/Kg

50 mm thick flage stone paving in 1:4 cement sand motar (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.20000 850.00 170.00
Unskilled Labour md 0.45000 580.00 261.00 431.00
2 Material Cost
50 mm thick flage stone sqm 1.10000 0.29 0.32
Cement bag 0.12600 864.00 108.86
Sand cum 0.01700 1042.20 17.72 126.90
3 Sub - total 557.90
4 15% Contractor Overhead 83.69
5 Grand Total 641.59 Rs/sqm

Roofing work by Slate (per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.40000 850.00 340.00
Unskilled Labour md 0.50000 580.00 290.00 630.00
2 Material Cost
Slate sqm 2.40000 0.00 0.00
Nails kg 0.15000 115.20 17.28 17.28
3 Sub - total 647.28
4 15% Contractor Overhead 97.09
5 Grand Total 744.37 Rs/sqm

Trufing work including cutting, hauling for 1 m and watering (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Unskilled Labour md 0.05000 580.00 29.00 29.00
2 Total cost including 3% for tools and plants 29.87 Rs/sqm

Roofing work by UPVC Sheet 3mm thick with PMMA Coating and mesh( tile) (per sqm)

Prepared by: Checked by Approved by


80

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.15000 850.00 127.50
Unskilled Labour md 0.10000 580.00 58.00 185.50
2 Material Cost
UPVC Roof Sheet with
PMMA Coating and mesh sqm 1.20000 0.98 1.17
(Tile) 3mm thick
Self Tapping Screw 3" No 2.80000 0.20
Clip No 1.40000 0.20 0.27 1.44
3 Sub - total 186.94
4 15% Contractor Overhead 28.04
5 Grand Total 214.98 Rs/sqm

Roofing work by UPVC Sheet 3mm thick with PMMA Coating and mesh( Regular) (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.15000 850.00 127.50
Unskilled Labour md 0.10000 580.00 58.00 185.50
2 Material Cost

UPVC Roof Sheet with


PMMA Coating and mesh sqm 1.20000 0.98 1.17
(Regular) 3mm thick

Self Tapping Screw 3" No 2.80000 0.20


Clip No 1.40000 0.20 0.27 1.44
3 Sub - total 186.94
4 15% Contractor Overhead 28.04
5 Grand Total 214.98 Rs/sqm

UPVC Sheet Ridge Cover 3mm thick with PMMA Coating and mesh( Regular/ Tile) (per rm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.15000 850.00 127.50
Unskilled Labour md 0.10000 580.00 58.00 185.50
2 Material Cost
Ridge Cover 3mm thick Rm 1.20000 0.98 1.17

Prepared by: Checked by Approved by


81

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Self Tapping Screw 2.5" No 2.80000 0.20
Clip No 1.40000 0.20 0.27 1.44
3 Sub - total 186.94
4 15% Contractor Overhead 28.04
5 Grand Total 214.98 Rs/Rm

Roofing work by Slate (per sqm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.40000 850.00 340.00
Unskilled Labour md 0.50000 580.00 290.00 630.00
2 Material Cost
Slate Rm 2.40000 0.00 0.00
Nails kg 0.15000 115.20 17.28 17.28
3 Sub - total 647.28
4 15% Contractor Overhead 97.09
5 Grand Total 744.37 Rs/sqm

Roofing work by Slate for Ridge Cover(per Rm)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.05000 850.00 42.50
Unskilled Labour md 0.05000 580.00 29.00 71.50
2 Material Cost
Slate Rm 8.00000 0.00 0.00
Nails kg 0.15000 115.20 17.28 17.28
3 Sub - total 88.78
4 15% Contractor Overhead 13.32
5 Grand Total 102.10 Rs/Rm

Carved Woodern Surface (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 2.25734 850.00 1918.74
Unskilled Labour md 5.64334 580.00 3273.14 5191.87
2 Material Cost

Prepared by: Checked by Approved by


82

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Local Wood cum 1.10000 203700.00 224070.00 224070.00
3 Sub - total 229261.87
4 15% Contractor Overhead 34389.28
5 Grand Total 263651.15 Rs/cum

Supplying and fixing of 14 to 18 gauge MS Sheet on MS angle frame sections for preparation of gate
and providing one coat of primer paint on the gate all complete as per specification and instruction of
site engineer. (per sqm)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Metal gate sqm 1.00000 7013.50 7013.50 7013.50
2 15% Contractor Overhead 1052.03
3 Grand Total 8065.53 Rs/Sqm

Supplying and fixing of 16 gauge metal rolling shutter and providing one coat of primer paint on the
shutter all complete as per specification and instruction of site engineer. (per sqm)

S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Rolling Shutter sqm 1.00000 19.50 19.50 19.50
2 15% Contractor Overhead 2.93
3 Grand Total 22.43 Rs/Sqm

Supplying and fixing of chicken wire mesh for fencing (per sqm)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour+ Material Cost
Chicken Wire mesh sqm 1.10000 3454.23 3799.65 3799.65
2 15% Contractor Overhead 569.95
3 Grand Total 4369.60 Rs/sqm
Laying, fitting and fixing of hume pipe of length 2.5 m of diameter 600mm (per nos)
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled labour md 0.13000 850.00 110.50
Unskilled Labour md 0.53000 580.00 307.40 417.90
2 Material Cost
Cement kg 7.50000 17.28 129.60

Prepared by: Checked by Approved by


83

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

RATE ANALYSIS (Civil Works)

Err:509
Err:509 F.Y.: 2077-078
Sand cum 0.01000 1042.20 10.42
Pipe no 1.00000 1848.00 1848.00 1988.02
3 Sub - total 2405.92
4 15% Contractor Overhead 360.89
5 Grand Total 2766.81 Rs/no

Earthwork in excavation with excavater of capacity upto 110 Hp (per cum)


S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Diesel lit 0.14500 0.000 0.000
2 Mobil, Grease lit 0.04530 682.000 30.895
3 Operator & Helper md 0.01810 850.000 15.385
4 Equipment hrs 0.01490 1200.000 17.880 64.16
5 Sub - total 64.16
6 15% Contractor Overhead 9.62
7 Grand Total 73.78 Rs/cum

Earthwork in excavation in ordinary soil of foundation of structures by manual means Depth 3m to


6m, including construction of shoring and bracing, removal of stumps and other deleterious matter
and backfilling with approved materials , all complete work.
S.N. Description Unit Quantity Rate (Rs/Unit) Amount Total Amt. Remarks
1 Labour Cost
Skilled Labour md 0.10000 850.00 85.00
Unskilled Labour md 1.20000 580.00 696.00 781.00
2 Equipment Cost
Dewatering 15% of Labour Cost 117.15 117.15
3 Sub - total 898.15
4 15% Contractor Overhead 134.72
5 Grand Total 1032.87 Rs/cum
6 Including Shoring and Shuttering 1043.20 Rs/cum

Prepared by: Checked by Approved by


84

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

6 Watt Led Panel round/square light Wipro/Fiam/Philips or equivalent


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.5 nos 850.00 425.00
1 Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
a.6 Watt Led Panel
materials light 10 nos 423.00 4230.00
b, screw, grips etc. 10 LS 9.00 90.00
4320.00
Actual rate 5080.00
15% conctractor overhead 762.00
Rate per set Rs. 584.20 Total (Rs.) 5842.00

12 Watt Led Surface round/square light Wipro/Fiam/Philips or equivalent


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.5 nos 850.00 425.00
3 Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
a.12 Watt Led Panel
materials light 10 nos 2000.00 20000.00
b, screw, grips etc. 10 LS 9.00 90.00
20090.00
Actual rate 20850.00
15% conctractor overhead 3127.50
Rate per set Rs. 2397.75 Total (Rs.) 23977.50

4' Led Tube light Wipro/Fiam/Philips or equivalent


sources Level Qty Unit Rate/unit cost Total Cost
4 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
materials a.4' Led Tube light 10 nos 1100.00 11000.00
b. Rod, screw, grips
etc. 10 LS 9.00 90.00

Prepared by: Checked by Approved by


85

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

11090.00
Actual rate 11850.00
15% conctractor overhead 1777.50
Rate per set Rs. 1362.75 Total (Rs.) 13627.50

Mirror light best quality 5 Watt D530565 WIPRO GARNET, Homedec,Fumagalli or equivalent
sources Level Qty Unit Rate/unit cost Total Cost
5 labour skilled 0.5 nos 850.00 425.00
. Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
a. 5 LED Watt Mirror
materials light 10 nos 900.00 9000.00
b. screw, grips etc. 10 LS 9.00 90.00
9090.00
Actual rate 9850.00
15% conctractor overhead 1477.50
Rate per set Rs. 1132.75 Total (Rs.) 11327.50

Wall bracket/spout light/mirror light / bulk head best quality with 5 Watt LED
sources Level Qty Unit Rate/unit cost Total Cost
6 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
a. 5 Watt LED Wall
materials light 10 nos 2500.00 25000.00
b, screw, grips etc. 10 LS 9.00 90.00

25090.00
Actual rate 25850.00
15% conctractor overhead 3877.50
Rate per set Rs. 2972.75 Total (Rs.) 29727.50

2'*2' Watt Led recess light Wipro/Fiam/Philips or equivalent

Prepared by: Checked by Approved by


86

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

sources Level Qty Unit Rate/unit cost Total Cost


8 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
materials 2'x2' Led tube light 10 nos 3978.00 39780.00
b, screw, grips etc. 10 LS 9.00 90.00
39870.00
Actual rate 40630.00
15% conctractor overhead 6094.50
Rate per set Rs. 4672.45 Total (Rs.) 46724.50
24 Watt Led recess/surface light Wipro/Fiam/Philips or equivalent
sources Level Qty Unit Rate/unit cost Total Cost
9 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
materials 1'x1' Led tube light 10 nos 4000.00 40000.00
b, screw, grips etc. 10 LS 9.00 90.00
40090.00
Actual rate 40850.00
15% conctractor overhead 6127.50
Rate per set Rs. 4697.75 Total (Rs.) 46977.50
161 BULKHEAD SINGLE DECON\
sources Level Qty Unit Rate/unit cost Total Cost
11 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
a. Wall/S.light/Bulk
materials Light 10 nos 361.00 3610.00
b. Cfl Bulb 10 nos 232.00 2320.00
c. CM, Screws, Grips
etc. 10 nos 32.00 320.00
6250.00
Actual rate 7010.00
Rate per set Rs. 806.15 15% conctractor overhead 1051.50

Prepared by: Checked by Approved by


87

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

Total (Rs.) 8061.50

Fan: Crompton/ Almonard/Bajaj or equivalent.


9" Exhaust Fan
sources Level Qty Unit Rate/unit cost Total Cost
12 labour skilled 1 nos 850.00 850.00
Semi skilled 1 nos 670.00 670.00
un skilled 0 nos 580.00 0.00 1520.00
materials a. Fan 1 nos 1803.00 1803.00
b. Wooden Frame 1 LS 100.00 100.00
c. Nut bolts 4 nos LS 50.00
d. CM, Cement Paints
etc. LS 38.00
1991.00
Actual rate 3511.00
Rate per set Rs. 4037.65 15% conctractor overhead 526.65
Total (Rs.) 4037.65
36" Ceiling Fan
sources Level Qty Unit Rate/unit cost Total Cost
14 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.5 nos 670.00 335.00
un skilled 0 nos 580.00 0.00 760.00
materials a. Fan 1 nos 2163.00 2163.00
b. Iron clamps LS 60.00
c. Ceiling rose 1 nos 35.00 35.00
d. CM, Screws, Grips
etc. LS 25.00
2283.00
Actual rate 3043.00
Rate per set Rs. 3499.45 15% conctractor overhead 456.45
Total (Rs.) 3499.45

Northwest switches and socket (White Plate)


Dimmer Single 300 Watt F

Prepared by: Checked by Approved by


88

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

sources Level Qty Unit Rate/unit cost Total Cost


15 labour skilled 0.5 nos 850.00 425.00
Semi skilled 1 nos 670.00 670.00
un skilled 0 nos 580.00 0.00 1095.00
materials a. Switch 10 nos 486.00 4860.00
b.Box 10 nos 52.00 520.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
5490.00
Actual rate 6585.00
Rate per set Rs. 757.27 15% conctractor overhead 987.75
Total (Rs.) 7572.75

13-15 Amp Power Socket


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
16 un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch Socket 10 nos 263.00 2630.00
b.PVC /M Box 10 nos 52.00 520.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
3260.00
Actual rate 5450.00
Rate per set Rs. 626.75 15% conctractor overhead 817.50
Total (Rs.) 6267.50

1 Gang Two way Switch F


sources Level Qty Unit Rate/unit cost Total Cost
17 labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch with Plate 10 nos 112.00 1120.00

Prepared by: Checked by Approved by


89

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

b.PVC /M Box 10 nos 52.00 520.00


c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
1750.00
Actual rate 3940.00
Rate per set Rs. 453.10 15% conctractor overhead 591.00
Total (Rs.) 4531.00

2 Gang one way Switch F


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
18 un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch with Plate 10 nos 158.00 1580.00
b.PVC /M Box 10 nos 52.00 520.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
2210.00
Actual rate 4400.00
Rate per set Rs. 506.00 15% conctractor overhead 660.00
Total (Rs.) 5060.00

3 Gang one way Switch F


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 850.00 850.00
19 Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch with Plate 10 nos 167.00 1670.00
b.PVC /M Box 10 nos 56.00 560.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
2340.00
Actual rate 4530.00

Prepared by: Checked by Approved by


90

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

Rate per set Rs. 520.95 15% conctractor overhead 679.50


Total (Rs.) 5209.50

4Gang one way Switch F


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 1 nos 850.00 850.00
20 Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch with Plate 10 nos 202.00 2020.00
b.PVC /M Box 10 nos 68.00 680.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
2810.00
Actual rate 5000.00
15% conctractor overhead 750.00
Rate per set Rs. 575.00 Total (Rs.) 5750.00

6Gang one way Switch F


sources Level Qty Unit Rate/unit cost Total Cost
21 labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. Switch with Plate 10 nos 307.00 3070.00
b.PVC /M Box 10 nos 136.00 1360.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
4540.00
Actual rate 6730.00
15% conctractor overhead 1009.50
Rate per set Rs. 773.95 Total (Rs.) 7739.50

Join Box Metal/PVC


Join Box Metal 4"x6"

Prepared by: Checked by Approved by


91

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

sources Level Qty Unit Rate/unit cost Total Cost


23 labour skilled 0.5 nos 850.00 425.00
Semi skilled 1 nos 670.00 670.00
un skilled 0 nos 580.00 0.00 1095.00
materials a. M.Box 10 nos 150.00 1500.00
b. CM, Screws, Grips
etc. 10 LS 51.00 510.00
2010.00
Actual rate 3105.00
Rate per set Rs. 357.07 15% conctractor overhead 465.75
Total (Rs.) 3570.75

Voltmeter (0-500)
sources Level Qty Unit Rate/unit cost Total Cost
27 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. Voltmeter 1 nos 1023.00 1023.00
c. CM, Screws, Grips
etc. LS 0.00
1023.00
Actual rate 1023.00
Rate per set Rs. 1176.45 15% conctractor overhead 153.45
Total (Rs.) 1176.45

Amp. Meter (0-500)


sources Level Qty Unit Rate/unit cost Total Cost
28 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. Amp.Meter 1 nos 979.00 979.00
b. CM, Screws, Grips
etc. LS 0.00

Prepared by: Checked by Approved by


92

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

979.00
Actual rate 979.00
Rate per set Rs. 1125.85 15% conctractor overhead 146.85
Total (Rs.) 1125.85

Indicator
sources Level Qty Unit Rate/unit cost Total Cost
29 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. Indicator 1 nos 237.00 237.00
b. CM, Screws, Grips
etc. LS 0.00
237.00
Actual rate 237.00
Rate per set Rs. 272.55 15% conctractor overhead 35.55
Total (Rs.) 272.55

2.5 sq.mm multistrand flexible copper wire


sources Level Qty Unit Rate/unit cost Total Cost
31 labour skilled 0.75 nos 850.00 637.50
Semi skilled 1.3 nos 670.00 871.00
un skilled 1.2 nos 580.00 696.00 2204.50
materials a.Cu wire 100 Rm 26.90 2690.00
b.Pvc pipe 100 LS 7.11 711.00
3401.00
Actual rate 5605.50
Rate per Rm Rs. 64.46 15% conctractor overhead 840.83
Total (Rs.) 6446.33

4 sq.mm multistrand flexible copper wire


sources Level Qty Unit Rate/unit cost Total Cost
32 labour skilled 0.75 nos 850.00 637.50
Semi skilled 1.3 nos 670.00 871.00

Prepared by: Checked by Approved by


93

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

un skilled 1.2 nos 580.00 696.00 2204.50


materials a.Cu wire 100 Rm 43.48 4348.00
Pvc Pipe 100 LS 9.91 991.00
5339.00
Actual rate 7543.50
Rate per Rm Rs. 86.75 15% conctractor overhead 1131.53
Total (Rs.) 8675.03

6 sq.mm multistrand flexible copper wire


sources Level Qty Unit Rate/unit cost Total Cost
33 labour skilled 1 nos 850.00 850.00
Semi skilled 1.5 nos 670.00 1005.00
un skilled 2 nos 580.00 1160.00 3015.00
materials a.Cu wire 100 Rm 68.66 6866.00
b.Pvc Pipe 100 LS 9.91 991.00
7857.00
Actual rate 10872.00
Rate per Rm Rs. 125.02 15% conctractor overhead 1630.80
Total (Rs.) 12502.80

EARTHING
sources Level Qty Unit Rate/unit cost Total Cost
34 labour skilled 0.2 nos 850.00 170.00
Semi skilled 1.5 nos 670.00 1005.00
un skilled 2 nos 580.00 1160.00 2335.00
a.CU
PLATE(60x60x3.15)
materials mm 1 nos 10893.96 10893.96
b. 8 SWG WIRE 10 mtr 209.27 2092.70
b. Coal 4 Bag, Salt
40Kg, Soil,etc. 1 nos 1738.80 1738.80 14725.46
14725.46
Actual rate 17060.46
Rate per set Rs. 19619.52 15% conctractor overhead 2559.07

Prepared by: Checked by Approved by


94

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

Total (Rs.) 19619.53

1.5 sq.mm multistrand flexible copper wire


sources Level Qty Unit Rate/unit cost Total Cost
35 labour skilled 0.75 nos 850.00 637.50
Semi skilled 1.3 nos 670.00 871.00
un skilled 1.2 nos 580.00 696.00 2204.50
materials a.Cu wire 100 Rm 18.31 1831.00
b.Pvc Pipe 100 LS 0.00 0.00
1831.00
Actual rate 4035.50
Rate per Rm Rs. 46.40 15% conctractor overhead 605.33
Total (Rs.) 4640.83

10 mm2 4 core Nepal, Prakash Or NS


sources Level Qty Unit Rate/unit cost Total Cost
42 labour skilled 1 nos 850.00 850.00
Semi skilled 1.5 nos 670.00 1005.00
un skilled 2 nos 580.00 1160.00 3015.00
materials a.Cu wire 100 Rm 618.00 61800.00
b.Saddle,Grips,
Screws 100 LS 22.00 2200.00

64000.00
Actual rate 67015.00
Rate per Rm Rs. 770.67 15% conctractor overhead 10052.25
Total (Rs.) 77067.25

T.Phone Socket
sources Level Qty Unit Rate/unit cost Total Cost
44 labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. Tel. Socket 10 nos 118.00 1180.00

Prepared by: Checked by Approved by


95

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

b.PVC /M Box 10 nos 52.00 520.00


c. CM, Screws, Grips
etc. 10 LS 11.00 110.00
1810.00
Actual rate 4000.00
Rate per set Rs. 460.00 15% conctractor overhead 600.00
Total (Rs.) 4600.00

2 pair telephone cable


sources Level Qty Unit Rate/unit cost Total Cost
45 labour skilled 0.75 nos 850.00 637.50
Semi skilled 1.3 nos 670.00 871.00
un skilled 1.2 nos 580.00 696.00 2204.50
materials a.Cu wire 100 Rm 14.00 1400.00
b.HDP, hooks 100 LS 7.11 711.00
2111.00
Actual rate 4315.50
Rate per Rm Rs. 49.62 15% conctractor overhead 647.33
Total (Rs.) 4962.83

Telephone Main DB double cover push type lock with necessary crone tag etc all complete.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.75 nos 670.00 502.50
46 un skilled 0 nos 580.00 0.00 927.50
materials a. Telephone Sub DB 1 nos 5446.00 5446.00
double cover push
c. CM, Screws, Grips
type lock
etc. LS 45.00 45.00
5491.00
Actual rate 6418.50
Rate per set Rs. 7381.27 15% conctractor overhead 962.78
Total (Rs.) 7381.28

10 Pair Telephone cable(20*2*0.45)mm heavy.

Prepared by: Checked by Approved by


96

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

sources Level Qty Unit Rate/unit cost Total Cost


47 labour skilled 1 nos 850.00 850.00
Semi skilled 1.5 nos 670.00 1005.00
un skilled 2 nos 580.00 1160.00 3015.00
a.20 pair telephone
materials cable 100 Rm 62.00 6200.00
b.HDP, hooks 100 LS 9.91 991.00
7191.00
Actual rate 10206.00
Rate per/Rm set Rs. 117.36 15% conctractor overhead 1530.90
Total (Rs.) 11736.90

4-12 Line EPABX,with 1set programmable master telephone set of corresponding brand Pansonic,
Creative, Matrix Or Eqv

sources Level Qty Unit Rate/unit cost Total Cost


labour skilled 0.5 nos 850.00 425.00
48 Semi skilled 1 nos 670.00 670.00
un skilled 0 nos 580.00 0.00 1095.00
materials EPABX 1 set 36823.00 36823.00
b. CM, Screws, Grips
etc. 1 LS 100.00 100.00
36923.00
Actual rate 38018.00
Rate per set Rs. 43720.70 15% conctractor overhead 5702.70
Total (Rs.) 43720.70
Computer Net Socket Northwest
sources Level Qty Unit Rate/unit cost Total Cost
49 labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
un skilled 0 nos 580.00 0.00 2190.00
materials a. socket 10 nos 629.00 6290.00
b.Box 10 nos 52.00 520.00
c. CM, Screws, Grips
etc. 10 LS 11.00 110.00

Prepared by: Checked by Approved by


97

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

6920.00
Actual rate 9110.00
Rate per set Rs. 1047.65 15% conctractor overhead 1366.50
Total (Rs.) 10476.50

Computer Net cable


sources Level Qty Unit Rate/unit cost Total Cost
50 labour skilled 0.75 nos 850.00 637.50
Semi skilled 1.3 nos 670.00 871.00
un skilled 1.2 nos 580.00 696.00 2204.50
materials a.Cu wire 100 Rm 26.00 2600.00
b.HDP, hooks 100 LS 7.11 711.00
3311.00
Actual rate 5515.50
Rate per Rm Rs. 63.42 15% conctractor overhead 827.33
Total (Rs.) 6342.83

computer cable
G 64.98 * 12.50 812.25

35 sq.mm 4 Core Armoured Power Cable copper wire


sources Level Qty Unit Rate/unit cost Total Cost
52 labour skilled 1 nos 850.00 850.00
Semi skilled 2 nos 670.00 1340.00
un skilled 3 nos 580.00 1740.00 3930.00
materials a.Cu wire 100 Rm 1803.00 180300.00
b.Pvc Pipe 100 LS 33.00 3300.00
183600.00
Actual rate 187530.00
Rate per Rm Rs. 2156.59 15% conctractor overhead 28129.50
Total (Rs.) 215659.50

Prepared by: Checked by Approved by


98

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

16 Way SPN DB Double Cover


sources Level Qty Unit Rate/unit cost Total Cost
53 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.75 nos 670.00 502.50
un skilled 0 nos 580.00 0.00 927.50
materials a. Cover 1 nos 1795.00 1795.00
b. CM, Screws, Grips
etc. LS 45.00
1840.00
Actual rate 2767.50
Rate per set Rs. 3182.62 15% conctractor overhead 415.13
Total (Rs.) 3182.62

60 Amp DP MCB
sources Level Qty Unit Rate/unit cost Total Cost
54 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. M.C.B 10 nos 1600.00 16000.00
b. CM, Screws, Grips
etc. LS 0.00
16000.00
Actual rate 16000.00
Rate per Nos Rs. 1840.00 15% conctractor overhead 2400.00
Total (Rs.) 18400.00

16 Amp DP MCB
sources Level Qty Unit Rate/unit cost Total Cost
55 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. M.C.B 10 nos 1030.00 10300.00
b. CM, Screws, Grips LS 0.00
etc.
10300.00

Prepared by: Checked by Approved by


99

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Electrical Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

Actual rate 10300.00


Rate per Nos Rs. 1184.50 15% conctractor overhead 1545.00
Total (Rs.) 11845.00

6-16 Amp SP MCB


sources Level Qty Unit Rate/unit cost Total Cost
56 labour skilled 0 nos 850.00 0.00
Semi skilled 0 nos 670.00 0.00
un skilled 0 nos 580.00 0.00 0.00
materials a. M.C.B 10 nos 206.00 2060.00
b. CM, Screws, Grips
etc. LS 0.00
2060.00
Actual rate 2060.00
Rate per Nos Rs. 236.90 15% conctractor overhead 309.00
Total (Rs.) 2369.00

12 Way SPN DB Double Cover


sources Level Qty Unit Rate/unit cost Total Cost
57 labour skilled 0.5 nos 850.00 425.00
Semi skilled 0.75 nos 670.00 502.50
un skilled 0 nos 580.00 0.00 927.50
materials a. Cover 1 nos 1679.00 1679.00
b. CM, Screws, Grips
etc. LS 45.00
1724.00
Actual rate 2651.50
Rate per set Rs. 3049.22 15% conctractor overhead 397.73
Total (Rs.) 3049.22

Prepared by: Checked by Approved by


100

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

1
Porcelain clay white glaze Regular with special fitting Comode all complete set (Hindware, Paryware,
Somany, cera or eqv.).

sources Level Qty Unit Rate/unit cost Total Cost


labour skilled 3 nos 850.00 2,550.00
un skilled 3 nos 580.00 1,740.00 4,290.00
a. White glazed porcelain clay commode with
'P ' & 's ' trap and seat cover complete set.
18,000.00 18,000.00
With special fittings (Hindware, Paryware,
Somany, cera or eqv.) 1 nos
b. screw, etc. Ls 50.00 18,050.00
Actual rate 22,340.00
15% contractor overhead 3,351.00
Rate per set 25691.00 Total (Rs.) 25,691.00

3
Porcelain clay white glazed Oval under counter Wash basin with mixer Complete set. (Duravit, Grohe,
American Standard, Thai or equivalent)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 2 nos 850.00 1,700.00
un skilled 2 nos 580.00 1,160.00 2,860.00
a. 50x40cm Porcelain clay O- counter white
2,625.00 2,625.00
materials glaze Wash basin 1 nos
b. 32 mm pvc bottle trap including 32mm CP
waste coupling with CP chain and rubber plug 476.00 476.00
etc. 1 nos
c.15 mm CP basin mixer 1 nos 3,891.00 3,891.00
d. 1.5x45Cm (½"x24") pipe connector 2 nos 231.00 462.00
e. screw etc Ls 50.00 7,504.00
Actual rate 10,364.00
15% contractor overhead 1,554.60
Rate per set 11918.60 Total (Rs.) 11,918.60

6
2000 Ltr. PVC\HDPE Water Tank
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 3 nos 850.00 2,550.00
un skilled 6 nos 580.00 3,480.00 6,030.00
a.2000 Ltr.PVC water tank with Inlet, outlet,
20,600.00
materials over flow, cleanout hole etc. 1 nos 20,600.00
b.Tanki nipples with wash out plug etc. Ls 241.00 20,841.00
Actual rate 26,871.00
15% contractor overhead 4,030.65

Prepared by: Checked by Approved by


101

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

Rate per nos30901.65 Total (Rs.) 30,901.65

7
1 H.P. Electrical motor water pump Multi stage
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 4 nos 850.00 3,400.00
un skilled 2 nos 580.00 1,160.00 4,560.00
a.1 H P Electric motor pump with base plate
14,258.00 14,258.00
materials nuts, bolts etc.set Multi stage 1 nos
b.Zink oxide screws etc. Ls 50.00 14,308.00
Actual rate 18,868.00
15% contractor overhead 2,830.20
Rate per set 21698.20 Total (Rs.) 21,698.20

8
Motor Starter Switch (Cromption or Eqv.)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.17 nos 580.00 98.60 311.10
a. Motor Starter Switch (Cromptionor Eqv.)
3,398.00
materials 1 nos 3,398.00 3,398.00
Actual rate 3,709.10
15% contractor overhead 556.37
Rate per no 4265.47 Total (Rs.) 4,265.47

9
Pressure Senser Switch (Italian or Eqv.)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.17 nos 580.00 98.60 311.10
materials Pressure Senser Switch (Italian or Eqv.) 1 nos 3,675.00 3,675.00 3,675.00
Actual rate 3,986.10
15% contractor overhead 597.92
Rate per no 4584.02 Total (Rs.) 4,584.02

10
Chrome Plate Toilet Paper Holder
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a.Chrome plate toilet paper holder 1 nos 929.00 929.00
b.Zink oxide screw etc. Ls 50.00 979.00
Actual rate 1,072.50
15% contractor overhead 160.88
Rate per nos1233.38 Total (Rs.) 1,233.38

Prepared by: Checked by Approved by


102

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

11
Special Chrome Plate Soap Dish.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a.C.P Soap dish 1 nos 551.00 551.00
b.Zink oxide screw etc. Ls 50.00 601.00
Actual rate 694.50
15% contractor overhead 104.18
Rate per nos798.68 Total (Rs.) 798.68

12
Stainless Steel towel rod 1.5x45cm (½"x18") size (heavy Type)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 850.00 187.00 187.00
materials a . Stainless Steel Towel rod 1 nos 656.00 656.00
b. Screws etc. Ls 50.00 706.00
Actual rate 893.00
15% contractor overhead 133.95
Rate per nos1026.95 Total (Rs.) 1,026.95

13
Glass Shelf with CP Guard Rail
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 850.00 187.00 187.00
materials a. C P Guard rail with glass 1 nos 680.00 680.00
b. Screws etc. Ls 50.00 730.00
Actual rate 917.00
15% contractor overhead 137.55
Rate per nos1054.55 Total (Rs.) 1,054.55

14
Looking Mirror 55x40cm (22"x 16")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled(1/3) 0.33 nos 850.00 280.50 280.50
materials a.Bevelled edge looking mirror 1 nos 1,102.00 1,102.00
b . Screws Ls 50.00 1,152.00
Actual rate 1,432.50
15% contractor overhead 214.88
Rate per nos1647.38 Total (Rs.) 1,647.38

Prepared by: Checked by Approved by


103

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

18
15mm CP Bib Cock
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials 15mm CP bib cock 1 nos 1,000.00 1,000.00 1,000.00
Actual rate 1,093.50
15% contractor overhead 164.03
Rate per nos1257.53 Total (Rs.) 1,257.53

20
15mm C.P. Angle valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50 93.50
materials a. 15mm C.P. Angle valve 1 nos 1,281.00 1,281.00 1,281.00
Actual rate 1,374.50
15% contractor overhead 206.18
Rate per nos1580.68 Total (Rs.) 1,580.68

26
15mm C.P. Commode Spray
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.17 nos 580.00 98.60 311.10
a.Water spray (Health faucet) with 1.2 m. long
materials
flexible pipe. 1 sets 1,180.00 1,180.00 1,180.00
Actual rate 1,491.10
15% contractor overhead 223.67
Rate per No 1714.77 Total (Rs.) 1,714.77

38
G.M. 25mm Float Valve
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.22 nos 850.00 187.00 187.00
materials G.M. 25mm float valve 1 nos 736.00 736.00 736.00
Actual rate 923.00
15% contractor overhead 138.45
Rate per nos1061.45 Total (Rs.) 1,061.45

39
PVC Floor Trap 11x7.5cm (4" X 2½")
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
un skilled 0.10 nos 580.00 58.00 151.50

Prepared by: Checked by Approved by


104

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

materials PVC Floor Trap 11x7.5cm (4" X 2½") 1 nos 288.00 288.00 288.00
Actual rate 439.50
15% contractor overhead 65.93
Rate per nos505.43 Total (Rs.) 505.43

40
C P Grating 12.5cm (5") dia
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.06 nos 850.00 51.00 51.00
materials C P Grating 12.5cm (5") dia size 1 nos 62.00 62.00 62.00
Actual rate 113.00
15% contractor overhead 16.95
Rate per nos129.95 Total (Rs.) 129.95

42
75 mm dia PVC Pipe 6 kg/cm2.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
un skilled 0.11 nos 580.00 63.80 157.30
materials a.75 mm dia. PVC pipe 6 kg/cm2. 1 Rm 223.00 223.00
b. Jointing materialsetc. Ls 25.00 248.00
fittings 35% of pipe cost 78.05
Actual rate 483.35
15% contractor overhead 72.50
Rate per Rm555.85 Total (Rs.) 555.85

43
110 mm dia PVC Pipe 6 kg/cm2.
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.17 nos 850.00 144.50
un skilled 0.20 nos 580.00 116.00 260.50
materials a.110 mm dia. PVC pipe 6 kg/cm2. 1 Rm 466.00 466.00
b. Jointing material setc. Ls 25.00 491.00
fittings 25% of pipe cost 116.50
Actual rate 868.00
15% contractor overhead 130.20
Rate per Rm998.20 Total (Rs.) 998.20

44
CI Cover 18" X 18" (14 kg) Medium Duty
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.33 nos 850.00 280.50 280.50

Prepared by: Checked by Approved by


105

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

materials CI Cover 18" X 18" (14 kg) Medium Duty 1 nos 2,338.00 2,338.00 2,338.00
Actual rate 2,618.50
15% contractor overhead 392.78
Rate per set 3011.28 Total (Rs.) 3,011.28

46
5 kg Fire extingusher ABC type Minimax, eversafe or equivalent
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 1.0 nos 850.00 850.00 850.00
a.5 kg Fire extingusher ABC type Minimax, 1.0 nos 7,130.00
materials eversafe or equivalent 7,130.00 7,130.00
Actual rate 7,980.00
15% contractor overhead 1,197.00
Rate per no 9177.00 Total (Rs.) 9,177.00

47
160mm dia. HDP Pipe (4 Kg/cm2)
sources Level Qty Unit Rate/unit cost Total cost
labour skilled 0.25 nos 850.00 212.50
un skilled 0.33 nos 580.00 191.40 403.90
materials a.160mm dia.HDP Pipe (4 Kg/cm2) 1.0 RM 1,077.76 1,077.76 1,077.76
Actual rate 1,481.66
15% contractor overhead 222.25
Rate per Rm1703.91 Total (Rs.) 1,703.91

48
20 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.01 nos 850.00 8.50
un skilled 0.01 nos 580.00 5.80 14.30
materials a. 20 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm 1 Rm 353.00 178.00
b. Cpvc fittings Ls 100.00
c. Jointing materials (flow guard adesive soln) Ls 30.00 308.00
Actual rate 322.30
15% contractor overhead 48.35
Rate per Rm370.65 Total (Rs.) 370.65

50
32 mm CPVC (Chlorinated Polyvinyl Chloride) Pipe SDR 11 CTS, 28.1 kg/cm2 (Flowguard or ISI Standard)
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.011 nos 850.00 9.35
un skilled 0.019 nos 580.00 11.02 20.37
materials a. 32 mm CPVC Pipe SDR 11 CTS, 28.1 kg/cm 1 Rm 769.00 769.00

Prepared by: Checked by Approved by


106

Janaki Rural Municipality


Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2077/078 for Kailali District


Err:509
Err:509

b. Cpvc fittings Ls 120.00


c. Jointing materials (flow guard adesive soln) Ls 30.00 919.00
Actual rate 939.37
15% contractor overhead 140.91
Rate per Rm1080.28 Total (Rs.) 1,080.28

53
20 mm CPVC Ball Valve, CTS sockets
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 20 mm CPVC ball valve, CTS sockets, 1 set 501.00 501.00 594.50
Actual rate 594.50
15% contractor overhead 89.18
Rate per no 683.68 Total (Rs.) 683.68

54
25 mm CPVC Ball Valve, CTS sockets
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 25 mm CPVC ball valve, CTS sockets, 1 set 605.00 605.00 698.50
Actual rate 698.50
15% contractor overhead 104.78
Rate per no 803.28 Total (Rs.) 803.28

56
40 mm CPVC Ball Valve, CTS socket
sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.11 nos 850.00 93.50
materials a. 40 mm CPVC ball valve, CTS sockets, 1 set 1,692.00 1,692.00 1,785.50
Actual rate 1,785.50
15% contractor overhead 267.83
Rate per no 2053.33 Total (Rs.) 2,053.33

57

40mm GM Check Valve


sources Level Qty Unit Rate/unit cost Total Cost
labour skilled 0.33 nos 850.00 280.50 280.50
materials a. 40 mm G M check valve 1 nos 3,126.00 3,126.00 3,126.00
Actual rate 3,406.50
15% contractor overhead 510.98
Rate per nos3917.48 Total (Rs.) 3,917.48

Prepared by: Checked by Approved by


47
Janaki Rural Municipality
Office of the Rural Municipal Executive
Durgauli, Kailali
Sudurpaschim Province

Sanitary Rate Analysis 2076/077 for Kailali District


Err:509
Err:509
75 mm dia PVC pipe specials supplying , fixing,Jointing, laying all complete
UNIT : 1.0 nos
Materials cost Labour cost
Jointing Total Skilled @Rs unSkilled Total
Description of Fittings Total Net Overhead
S.N material amount 850/day @Rs 580/day amount Remark
materials labour amount 15%
(Rs.)
No Amount No Amount amount

4 Vent cowl 53.00 5.00 58.00 0.11 93.50 0.10 58.00 151.50 209.50 31.43 240.93
5 Plain tee 147.00 5.00 152.00 0.11 93.50 0.10 58.00 151.50 303.50 45.53 349.03
6 Plain door tee 198.00 5.00 203.00 0.11 93.50 0.10 58.00 151.50 354.50 53.18 407.68
7 Bend 90 degree 108.00 5.00 113.00 0.11 93.50 0.10 58.00 151.50 264.50 39.68 304.18
8 Door bend 139.00 5.00 144.00 0.11 93.50 0.10 58.00 151.50 295.50 44.33 339.83
9 Bend 45 degree 88.00 5.00 93.00 0.11 93.50 0.10 58.00 151.50 244.50 36.68 281.18
10 Y- Branch 168.00 5.00 173.00 0.11 93.50 0.10 58.00 151.50 324.50 48.68 373.18
11 Cross tee 322.00 5.00 327.00 0.11 93.50 0.10 58.00 151.50 478.50 71.78 550.28
12 Pipe clip 28.00 5.00 33.00 0.00 0.00 0.00 0.00 0.00 33.00 4.95 37.95
320.47
110 mm dia PVC pipe specials supplying , fixing,Jointing, laying all complete
UNIT : 1.0 nos
Materials cost Labour cost
Jointing Total Skilled @Rs unSkilled Total
Description of Fittings Total Net Overhead
S.N material amount 850/day @Rs 580/day amount Remark
materials labour amount 15%
(Rs.)
No Amount No Amount amount

13 Vent cowl 87.00 5.00 92.00 0.16 136.00 0.20 116.00 252.00 344.00 51.60 395.60
14 Plain tee 279.00 5.00 284.00 0.16 136.00 0.20 116.00 252.00 536.00 80.40 616.40
15 Door tee 369.00 5.00 374.00 0.16 136.00 0.20 116.00 252.00 626.00 93.90 719.90
16 Bend 90 degree 200.00 5.00 205.00 0.16 136.00 0.20 116.00 252.00 457.00 68.55 525.55
17 Door bend 242.00 5.00 247.00 0.16 136.00 0.20 116.00 252.00 499.00 74.85 573.85
18 Bend 45 degree 158.00 5.00 163.00 0.16 136.00 0.20 116.00 252.00 415.00 62.25 477.25
19 Y- Branch 363.00 5.00 368.00 0.16 136.00 0.20 116.00 252.00 620.00 93.00 713.00
20 Cross tee 510.00 5.00 515.00 0.16 136.00 0.20 116.00 252.00 767.00 115.05 882.05
21 Pipe clip 37.00 5.00 42.00 0.00 0.00 0.00 0.00 0.00 42.00 6.30 48.30
22 Gully trap 255.00 5.00 260.00 0.16 136.00 0.20 116.00 252.00 512.00 76.80 588.80
554.07

Prepared by: Checked by: Approved by:

You might also like