HARGA SATUAN HARGA MATERIAL TOTAL HARGA TOTAL HARGA

URAIAN PEKERJAAN SAT. VOLUME KONTRAK UPDATE TERBARU JASA SATUAN KONTRAK UPDATE JUMLAH HARGA
(Rp) (Rp) (Rp) Rp Rp

INSTALASI PEKERJAAN RISER SIAMESS CONECTION HIGH ZONE


- PIPA SCHEDULE 40 DIAMETER 40 MM METER 180.00 328,882.00 351,780.00 59,198,760 63,320,400
- FITTING DIAMETER 100 MM SCH 40 PCS 15.00 300,139.00 198,000.00 4,502,085 2,970,000
- MATERIAL BANTU DAN CONSUMABLE -
UNP 80 MM BTG 2.00 350,000.00 700,000
KAWAT LAS LB 52 2.6 MM SET 3.00 671,990.00 2,015,970
MATA GERINDA CUTTING 14" PACK 1.00 65,000.00 65,000
MATA GERINDA CUTING 4" PCS 10.00 7,500.00 75,000
FIRE BLANKET SET 1.00 150,000.00 150,000
U BOLT DIA. 100 MM PCS 30.00 7,500.00 225,000
THINNER DRIGEN 1.00 350,000.00 350,000
DYNA BOLT 12 MM PCS 50.00 2,500.00 125,000
-
PENGADAAN GATE VALVE 4" MERK VICTAULIC ( PRESSURE 300 PSI ) PCS 2.00 9,514,086.00 9,533,700.00 19,028,172 19,067,400
COUPLING 4" PCS 2.00 580,000.00 1,160,000
JASA GROUVING PCS 4.00 150,000.00 600,000
-
*NOTE ALAT KERJA PENUNJANG SUDAH ADA -
-
PEKERJAAN FINISHING AKIBAT BONGKARAN -
- FIRE STOP LANTAI B1 - 20 METER -
- PLAFON LANTAI 1 METER -
- PLAFON BAC LANTAI 3 METER -
-
PERHITUNGAN JASA PEKERJAAN 21 HARI KERJA ( FULL LEMBUR ) -
-
- SUPERVISOR ORANG 1.00 3,570,000.00 3,570,000
- SKILL ORANG 2.00 2,520,000.00 5,040,000
- HELPER ORANG 3.00 1,890,000.00 5,670,000
- WELDER ORANG 1.00 3,150,000.00 3,150,000
-
- LEMBUR SUPERVISOR ORANG 1.00 510,000.00 510,000
SKILL ORANG 2.00 360,000.00 720,000
HELPER ORANG 3.00 270,000.00 810,000
WELDER ORANG 1.00 450,000.00 450,000
-
- UANG MAKAN ( JIKA LEMBUR ) ORANG 7.00 2,205,000.00 15,435,000
-
-
MARGIN 20% 40,000,000
-
-
-
-

82,729,017 166,178,770
PPN 10% 91,001,919 182,796,647