11/2/21, 1:17 PM Ch.

1: Questions Flashcards by Brian Weldon | Brainscape

Brainscape

Find Flashcards
Make Flashcards
Why It Works
Educators
Teachers & professors
Content partnerships
Tutors & resellers
Businesses
Employee training
Content partnerships
Tutors & resellers
Academy
more...
Educators
Teachers & professors
Content partnerships
Tutors & resellers
Businesses
Employee training
Content partnerships
Tutors & resellers
Academy
About

Get Started
Log In
Get Started

Find Flashcards
Make Flashcards
Why It Works
Educators
Teachers & professors
Content partnerships
Tutors & resellers
Businesses
Employee training
Content partnerships
Tutors & resellers
About
Academy

Log In
Get Started

e.g. MCAT, pharma, bar exam SearchGo

Brainscape's Knowledge GenomeTM


Browse over 1 million classes created by top students, professors, publishers, and experts.

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 1/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

Entrance Exams

Professional Certifications

Foreign Languages

Medical & Nursing

Science

English

Humanities & Social Studies

Mathematics

Law

Vocations

Health & Fitness

Business & Finance

Technology & Engineering

Food & Beverage

Fine Arts

Random Knowledge

See full index

Ch. 1: Questions Flashcards Preview


PMP Exam > Ch. 1: Questions > Flashcards
Study These Flashcards
Study These Flashcards
Flashcards in Ch. 1: Questions Deck (20)
Loading flashcards...
1

A series of activities to create a unique product or service by a specific


date is best described as which one

of the following?

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 2/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

A. A program

B. An operation

C. A project

D. A subproject
C

Which of the following is likely to be part of an operation?

A. Providing electricity to a community

B. Designing an electrical grid for a new community

C. Building a new dam as a source for electricity

D. Informing the public about changes at the electrical company

Of the following, which one is the best example of progressive


elaboration?

A. It is the process of decomposing the work into small, manageable


tasks.

B. It is the process of taking a project from concept to completion.

C. It is the process of taking a project concept to a project budget.

D. It is the process of identifying the business needs of a potential


project.
B

Your organization would like to create a new product based on market


research. This new product will be

created by a project. This is an example of which one of the following


reasons to launch a new project?

A. Organizational need

B. Customer request

C. Market demand

D. Legal requirement
https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 3/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

A program is which one of the following?

A. A very large, complex project

B. A collection of small projects with a common goal

C. A collection of projects with a common cause

D. A collection of subprojects with a common customer


C
6

Who manages programs?

A. Management

B. Project sponsors

C. Project managers

D. Program managers
D

You have an excellent idea for a new project that can increase
productivity by 20 percent in your

organization. Management, however, declines to approve the proposed


project because too many resources

are already devoted to other projects. You have just experienced


what?

A. Parametric modeling

B. Management by exception

C. Project portfolio management

D. Management reserve
C
8

Of the following, which is not part of the Iron Triangle?

A. Quality

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 4/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

B. Time

C. Scope

D. Cost
A

Of the following, which statement is correct?

A. A project manager must use every process identified within the


PMBOK on every project.

B. A project must use every tool and technique as identified within the
PMBOK on every project.

C. A project manager must use the most appropriate processes on


every project.

D. A project manager must agree that he will use the most appropriate
tools and techniques on every

project.
C

10

Projects are temporary endeavors to create a unique product, service,


or result. Which one of the following

does not relate to the concept of "temporary" in project management?

A. The project team

B. The market window status on which the project is capitalizing

C. The project deliverable

D. The project manager


C

11

A project creates a unique product, service, or result. Which one of the


following is a result?

A. A new piece of software

B. A new airplane

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 5/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

C. A feasibility study

D. A call center
C

12

What is the difference between a standard and a regulation?

A. A standard is optional; regulations are not.

B. A standard is not optional; a regulation may be.

C. A standard is rarely optional; regulations are never optional.

D. A standard is a guideline; a regulation is a request.


A

13

A project manager needs five areas of expertise to be successful.


Which one is not one of the five areas of

expertise?

A. Application area knowledge

B. An understanding of the project environment

C. PMP or CAPM certification

D. Interpersonal skills
C

14

Which one of the following is not a characteristic of a project's


cultural and social environment?

A. Economics

B. Time zone differences

C. Demographics

D. Ethics
B
15

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 6/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

You are the project manager of the KHGT Project, which will span
four countries around the world. You will

need to consider all of the following characteristics of the international


and political environment except for

which one?

A. International, national, regional, and local laws

B. Customs

C. Customers

D. Holidays
C

16

Which one of the following is not an example of an interpersonal skill?

A. Financial management and accounting

B. Sales and marketing

C. Conflict management

D. Health and safety practices


A

17

What is a subproject?

A. It is a smaller project that supports a parent project.

B. It is a project that is performing below expectations.

C. It is a project that has been experiencing project spin-off.

D. It is delegation of a project phase.


A

18

Where will a project manager most likely get project management


mentoring?

A. Project Management International

B. American Society for Quality

C. The project management office

D. Subject matter experts


https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 7/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

19

Which one of the following is an example of operations?

A. Creating a new community park

B. Designing a new car


C. Sending monthly invoices to an organization's 25,000 customers

D. Removing an old server and replacing it with a newer one


C
20

When considering the selection of projects to be initiated, project


portfolio management considers all of the

following except for which one?

A. Risk/reward categories

B. Lines of business

C. The project manager's experience

D. General types of projects


C

e.g. MCAT, pharma, bar exam SearchGo

Decks in PMP Exam Class (26):


Ch. 2: Managing A Project
Ch. 1: Questions
Ch. 2: Questions
Ch. 3: Examining The Project Processes
Ch. 3: Questions
Ch. 4: Project Integration
Ch. 4: Questions
Ch. 5: Managing The Project Scope
Ch. 5: Questions
Ch. 6: Managing Project Time
Ch. 6: Questions
Ch. 7: Managing Project Cost
Ch. 7: Questions
Ch. 8: Managing Project Quality
Ch. 8: Questions
Ch. 9: Managing Human Resources
Ch. 9: Questions
Ch. 10: Managing Project Communications

https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 8/9
11/2/21, 1:17 PM Ch. 1: Questions Flashcards by Brian Weldon | Brainscape

Ch. 10: Questions


Ch. 11: Managing Project Risk
Ch. 11: Questions
Ch. 12: Project Procurement
Ch. 12: Questions
Ch. 13: Code Of Conduct
Ch. 13: Questions
Ch. 1: Preparing For Exam

Key Links

Pricing
Corporate Training
Teachers & Schools
iOS App
Android App
Help Center

Subjects

Medical & Nursing


Law Education
Foreign Languages
All Subjects A-Z
All Certified Classes

Company

About Us
Earn Money!
Academy
Contact

Find Us

Brainscape is a web and mobile study platform that helps you learn things faster. Our mission is to create a
smarter world by simplifying and accelerating the learning process.
© 2021 Bold Learning Solutions. Terms and
Conditions
https://www.brainscape.com/flashcards/ch-1-questions-462564/packs/969527 9/9