F.F. CRUZ & CO., INC.

Civil & Geodetic Engineers • Constructors


800 EDSA, Quezon City
DAILY REPORT

PROJECT TITLE: ATI MANILA SOUTH HARBOUR EXPANSION PROJECT : EIB RECLAMATION DATE: Friday, March 15, 2019
LOCATION: ATI MANILA SOUTH HARBOUR, MANILA DR. NO. DR-023

DETAILS OF WORK / ACTIVITY

START FINISH LOCATION DESCRIPTION OF WORK ISSUES/CONCERN

• Stripping - off formworks to the two (2) casted RC Sinker. After


removal of formworks, retouching to surface edges and removal
Back of Site Office at of laitances (Completed).
whole day TIPSI • Installation and fixing of formworks for the two (2) remaining
not casted RC sinker (completed)
• Schedule of next pouring will be on March 16, 2019 on the early
morning

Completed the remaining activities on the adjustment of the new


temporary perimeter fence at TIPSI - Area. The remaining
On- going 9:30 A.M TIPSI, Pier 3 activities include dismantling of previously installed perimeter
fence, lifting and placing of concrete barrriers and installation of
board up and wire mesh walls to the new fence line (Completed).

whole day near SMC Area On -going operational works of drag flow at SMC Area. Temporary
unloaded sand were suctioned inside the basin.

• ASC ROSARIO completed the unloading of sand inside the basin


at around 5:35 P.M having a volume of 2,980 cu.m loaded on the
on-going 5:35 PM Offshore barge.

whole day at inside Felipe 2 Two (2) numbers of RC Sinker (Concrete Block) and MS Plate Bouy
Barge was lifted and placed toward the designated seabed location.

TIPSI Unloading Completion of welding works for the checkered plate installation
on-going 3:45 PM Facility, Pier 3 on the walk-way at Berth Number 1.

arrival of Barge Neo at Site : 7:40 Offshore Barge Neo arrived at the ATI - EIB Reclamation Project site at
A.M around 7:40 A.M.

Prepared by: Reviewed by: Noted by:

Engr. Marck Angelo Fernandez


Engr. Victor Bartolome
Engr. Raymond Fruto Engr. Joey Albert Cipriano
Field Engineer Project Engineer Project Manager

FFC-F-EIB-001 Revision: 0 Effective: 03-01-2019