All Messer discuss the current status of elevator works regarding each phase as
the following:-
Execution
ExecutionProgress
Progress
A_2: Elec. Works are stopping because there is no permanent electrical power
source 3 phase in the site, Schindler informed that there is no objection in
using Diesel Generator is allowable via Arabtec provided that ( permanent
cable feeder for elevator is done , Lighting fixtures inside the shaft shall be
executed with deviator switch in up & down shaft , disconnect switch for
elevator shall be existed and the dedicated MCCB @ EMDB Panel board for
Bldg. ( 5,6,7,8 ) and Service Panels for Bldg. (9,10,11) shall be provided with
RCD 300 milli amper as a machine protection from current leakage “ Not
Found as per IFC drawing – knowing that EMDBs are delivered in site”.
A_3: Arabtec shall send RFI regarding Schindler requirements for RCDs to
coordinate with GILA – Factory (panel builder supplier) to provide these
RCDs inside the panel boards (EMDBs & Service panels)
A_4: Schindler will provide with all factory test certificates for all elevators’
parts (Elevator by Elevator) max Thursday November 11, 2021.
A_5: Arabtec will complete all remaining works in elevator shaft (install
deviator wiring devices – shaft’s luminaires – Earthing works – Data’s cables
regarding IP telephone).
A_6: Arabtec will study with Schindler to complete electrical works in all
elevators by providing temporary devices (Disconnect Switches and RCDs)
till EMAAR provide in the site and test & commissioning will be performed in
case of completing all missing items as permanent.
Page 1
6 b o u l o s h a n n a │ t h i r d f l o o r │ d o k k i g i z a │ e g y p t
t e l + 2 0 2 . 7 6 0 . 7 9 3 3 │ f a x + 2 0 2 . 7 6 0 . 7 5 9 3
MOM – Coordination Meeting ( Elevator works @ PKG 89/1 & 89/2)
A_7: Arabtec informed that the permanent electrical current will be ready via
transformers after finishing all Landscape works above MV- Cables as per
EMAAR ‘s instructions to be protected from any damage may be occur “ i.e.
all transformer & infrastructure works @ Village Z3 in Arabtec Scope”.
A_8 : Schindler informed that will finish Elevator threshold doors after
Arabtec shall scavenge shaft elevators knowing that all elevator cabinet still
hold till providing all items are mentioned in clause A_2.
A_9: Schindler informed that each elevator will take 10 days / team for
remaining works (Electrical & QC TEST) to be ready for test &
commissioning.
A_10: Schindler obligates with informing both MC & consultant that the
elevators are ready to be tested in presence of Schindler QC audit.
A_11: Arabtec will review time schedule as whole including elevators’ works
to feedback us the accurate times for elevators’ handover.
B_1: All Mech. Works (Brackets – Guide Rails “cabinet & counter weight “–
Elevator Machine – Threshold door frame only ) have been finished.
B_2: Elec. Works are stopping because there is no permanent electrical power
source 3 phase in the site, Schindler informed that there is no objection in
using Diesel Generator is allowable via DMC provided that ( permanent cable
feeder for elevator is done , Lighting fixtures inside the shaft shall be executed
with deviator switch in up & down shaft , disconnect switch for elevator shall
be existed and the dedicated MCCB @ EMDB Panel board shall be provided
with RCD 300 milli amper as a machine protection from current leakage “ Not
Found as per IFC drawing – knowing that EMDBs are delivered in site”.
B_3: DMC shall send RFI regarding Schindler requirements for RCDs to
coordinate with Hager – Factory (panel builder supplier) to provide these
RCDs inside the panel boards (EMDBs & Service panels) also deviator
switches inside all shafts.
Page 2
6 b o u l o s h a n n a │ t h i r d f l o o r │ d o k k i g i z a │ e g y p t
t e l + 2 0 2 . 7 6 0 . 7 9 3 3 │ f a x + 2 0 2 . 7 6 0 . 7 5 9 3
MOM – Coordination Meeting ( Elevator works @ PKG 89/1 & 89/2)
B_5: Schindler will provide with all factory test certificates for all elevators’
parts (Elevator by Elevator) max Thursday November 11, 2021.
B_7: Schindler obligates with informing both MC & consultant that the
elevators are ready to be tested in presence of Schindler QC audit.
B_8: Schindler informed that each elevator will take 10 days / team for
remaining works (Electrical & QC TEST) to be ready for test &
commissioning.
B_9: DMC will study with Schindler to complete electrical works in all
elevators by providing temporary devices (Disconnect Switches and RCDs)
till EMAAR provide in the site and test & commissioning will be performed in
case of completing all missing items as permanent.
B_10: DMC will review time schedule as whole including elevators’ works to
feedback us the accurate times for elevators’ handover.