100 VSC Hl1 00021 - Method Statement Propane Propylene Splitter (C 063 06)
100 VSC Hl1 00021 - Method Statement Propane Propylene Splitter (C 063 06)
: 26071-100-VSC-HL1-00021
METHOD STATEMENT
PROPANE/PROPYLENE SPLITTER
INSTALLATION
C-063-06
REVISION LOG
TABLE OF CONTENT
1. INTRODUCTION ................................................................................................................................ 4
1. INTRODUCTION
1.1 General
This Document is established to outline general procedure and implementing effective.
The purpose of this document is to provide procedures to perform the installation structure or vessel and safely
execute the project.
Furthermore, it provides verification that all reasonable considerations have been made with regards to minimize
any risks towards personnel and operation at refinery during live plant activities.
The following items are covered:
It provides documentation, verification to review and approve that all components for the intended operations listed
above are calculated, verified and that they meet to the required capacity. Furthermore, it provides that all
reasonable considerations have been made with regards to minimize any equipment malfunctions & risks towards
personnel and operation for the intended activities. The document must be considered by the execution team as
the main guide for the correct outcome of the job.
This document must be send to the client for its review and approval. In case the client does not express any
comments it will be understood that it has the client’s approval.
2. EQUIPMENT SOLUTION
SGC-90 is a Electrical Ringer Crane with maximum lifting capacity of 2500T. The configuration proposed for the
project to lift PROPANE/PROPYLENE SPLITTER weight 752.6T + 36T as a Main Crane will be SGC-90 main
boom 130m with the load chart capacity attached below.
The CC 8800-1 can be rigged into several variations (boom combinations), depending on the needed capacity on
a certain range or working height. There are 3 main combinations: SSL; SSL/LSL and SWSL, drawings of them
can be found below. Only the SSL & SWSL configurations are scheduled to be used at project site.
CC 8800-1 is a hydraulic crawler crane manufactured by Terex/Demag with maximum lifting capacity of 1600T.
The configuration proposed for the project to lift PROPANE/PROPYLENE SPLITTER, weight 752.6T + 36T and
379.55T as a Tailing Crane will be CC 8800-1 SSL main boom 84m with the load chart capacity attached below.
Doc. No. : 26071-100-VSC-HL1-00021
2.3 Others
3. CARGO
Additionally, this Method Statement will cover the Accessories of Cargo such as 36” Riser Pipe and Top Platform.
4.1 General
The safety procedures are based on Project Safety & Execution plan.
All operations will be done in such a way that CONTRACTOR’s required standards are obtained.
Access to the operation area shall be strictly restricted by SUBCONTRACTOR. Only authorized personnel shall be
present in the area. The SUBCONTACTOR’s Safety department is to assure that all personnel, not directly
involved with the operation are kept out of the working area. The working area shall be cordoned off to secure
against personnel entry.
SUBCONTRACTOR shall Barricade and/or Warning sign board around the Assembly/Disassembly area.
On a daily basis, the Site Supervisor shall organize a Toolbox meeting (also known as JSA or Job Start
Assessment meeting). At this meeting, all planned activities of the day shall be explained, specific risks are being
pointed out and the corresponding measures are discussed in detail. A toolbox or JSA Talk record shall be filled
out & signed by all operatives.
A weather report is to be provided by client prior to the lifting operation, with a forecast for the following 24 hours
and with decreasing tendencies if around the speed limits.
It is to be noted that all activities will be suspended if the wind speed exceed than 11 m/s
Doc. No. : 26071-100-VSC-HL1-00021
5. OPERATIONS
This section describes all preparations to make the CARGO ready for lifting. As some of the activities are joint
operation between SARENS & CLIENT, CLIENT’s technical documents are also referred for operation.
CONTRACTOR shall support the SUBCONTRACTOR for preparation of works such as;
1) Ground compaction and Plate Load Test
2) Heavy equipment route planning
3) Coordination work with other discipline.
Due to the potential for a serious incident involving the use of cranes and hoisting equipment, only qualified
personnel shall be allowed to operate equipment.
• All cranes shall have certificates from local regulator for equipments and operatiors (SILO, Surat Ijin Layak
Operasi) and (SIO, Surat Ijin Operator) from Migas (Indonesia Authority for Oil and Gas Activities).
• All cranes coming on site, owned and/or hired by SUBCONTRACTOR, shall be inspected by a 3rd party to
ensure they are in good operating condition.
SUBCONTRACTOR shall follow CONTRACTOR’s HSE Plan No 26070-203 G01-GHX-J0001 Article 4.5.2.4
Cranes and Material Handling Equipment.
Required PPE:
Working clothes (long sleeves)
Safety shoes
Safety helmet
ALL
Safety glasses
Gloves (when needed)
Ear protection (when needed)
Safety harness (when working at heights)
Doc. No. : 26071-100-VSC-HL1-00021
Discharging of Sarens equipment from trucks using crane/ forklift free issue crane by client (if SARENS
required).
Configured equipment is then functional tested to ensure a trouble free operation. SARENS
Upon completion, crane will be tested and certified for use to lift client’s cargo as per local SARENS
regulations.
Clearing working area during the whole work execution, setup of exclusion zone for non-authorized
people. All obstacles in the trailer/crane working area or slew path will be removed by client. The ALL
trailer/crane path for transport and lifting operation route will be covered with steel mats to withstand
the loadings caused by trailer/crane (if required).
Crane crawling by itself the route condition need to be check and maximum driving based on crane SARENS
manual (if required)
Inspection of site conditions (e.g. ground levelness/ ground overall conditions/ ground compaction
strength, space, crane access etc.). An assessment will be made to ensure that client has addressed
the requirements for ground bearing capacity, identified and underground services/installations which ALL
need to be circumvented/protected and removed any obstruction. Earthworks to be prepared by
CLIENT.
To ensure that the level tolerances of the trailers/cranes are not exceeded, a level control of the lift
area will be performed. In general, the cranes may operate with level differences up to +/- 0.1 ALL
degree. Level variations exceeding this, may be accepted, depending on the lifting arrangements
and configurations.
Superlift preparation usually using auxiliary crane and timing for superlift preparation is depend on SARENS
superlift counterweight amount approximately will not be over 3 hour (if required)
All required permits will be applied for, and acquired, prior to the operation. CLIENT
All new personnel involved with the operation will undergo a safety induction to establish a safe
system of work. The entire operations team will receive a comprehensive toolbox talk to ensure ALL
everyone understands their responsibilities throughout the job. This will include a safety briefing
mirroring the Job Safety Analysis (JSA) and instructions for the proper usage of Personal Protective
Equipment (PPE). The phrase “Safety First” will be emphasized.
The lifting tackle will be inspected for condition, correct color code and valid certification prior to the SARENS
lifting operation.
The weather forecast will be checked and conditions will be closely monitored prior to the lifting ALL
operation. In the event of lightening alerts, heavy rainfall, storms, etc. appropriate action will be
taken as per the Job Safety Analysis and Emergency Response Procedure.
The lifting tackle with tag lines will be attached to the crane’s hook as per the approved rigging SARENS
study (if required).
The lifting tackle will be attached to the lifting points of the Cargo, as per the approved rigging study. SARENS
A man-lift or ladder will be used if lifting points are at a great height.
Conformity of the rigging and pre-lifting operations will be checked and signed by Sarens and Client ALL
representative.
A safety check will be carried out to ensure all lifting tackle is secure and the Cargo is free of any SARENS
loose items.
The crane will lift until all the lifting slings are taut. The load will be monitored using the crane’s SLI SARENS
equipment ensuring that the operation is as predicted.
The Cargo will be lifted and continuously checked as it slightly clears the trailer. The load will be SARENS
monitored using the crane’s SLI equipment and checked by the Lifting Supervisor that it is as
predicted.
Confirmation to proceed with the operation will be approved by the Lifting Supervisor. SARENS
The Cargo will be hoisted and slewed in accordance with the approved rigging study until it is SARENS
aligned above the pier/support. During the slewing, the position of the different crane’s components
will be monitored to ensure they do not collide with any plant and equipment.
The Cargo will be checked for proper orientation and lowered its down onto pier/support gradually SARENS
until the load decreases about 50% on the cranes SLI.
Once the Cargo is fully supported by pier/support, the lifting tackle will be released from the lifting SARENS
points by slowly hoisting down the hook.
1. In the case of a site emergency, the CARGO is to be secured by lowering down again onto the
saddles/support, or if not possible, to be remained hoisted in the air clear of all obstructions
depending on the severity of the emergency. Sarens will have to be advised by the RDMP
representative as to which procedure to adopt. SARENS
2. In the case of mechanical failure of the crane, the CARGO is to be lowered to the ground if
possible, if not, the CARGO would be made safe whilst the necessary repairs are carried out.
3. Pre tension the Main Crane & Tailing Crane to approximately 50% of the expected
crane load.
4. Check verticality of hoist lines and attach hand lines to guide the CARGO during the lift and
prevent it from turning towards the crane boom during the lift.
6. Slew the boom of Tailing Crane so that the both Main Crane & Tailing Crane’s booms are
aligned. Main Crane’s to boom down and connect back mast to Superlift tray. The crane
controls and load cell on both cranes’ computer to be monitored by both Cranes’ operator.
Crane operators will only act on instructions of Heavy lift supervisor (and/or Site
Manager/Engineer).
7. The Tailing Crane is to be crawled towards the Main Crane resulting in increasing angle and
this verticality of the CARGO. The radius of the Tailing Crane shall be kept constant at all-time SARENS
unless instructed otherwise by Heavy Lift Supervisor. The crane controls and load cell on both
cranes’ computer to be monitored by both Cranes’ operator. Crane operators will only act on
instructions of Heavy lift supervisor (and/or Site Manager/Engineer).
8. When the Tailing Crane reaches the end of the mats, the boom is to be boomed down to reach
maximum radius where the CARGO will be in vertical position. 100% of the CARGO’s weight is
to be taken by Main Crane.
10. Once the CARGO is lifted, the crane controls and load cell readings on the crane’s computer
are to be monitored by the crane operator.
11. Superlift counterweight’s tray is to be monitored by Heavy lift supervisor and should still lay
firmly on the ground.
12. Once the initial lift is stabilised and sufficient underside’s clearance has been achieved, the lift
radius to be increased and Superlift counterweight’s tray to be monitored by Heavy lift
supervisor to ensure sufficient float has been achieved. Tag lines to be handled appropriately SARENS
to maintain orientation of the CARGO.
Doc. No. : 26071-100-VSC-HL1-00021
13. Once the lift is stabilised, aligned the main boom in parallel with the tracks and travel. The
CARGO is to be slewed onto the foundation area. Tag lines to be handled appropriately to
maintain orientation of the CARGO.
14. Final adjustments can be made using the crane slew, derrick, hoisting and lowering functions.
15. Once in place, the CARGO is to be lowered down over the bolts and touched down onto the
foundations. Upon final set down the full weight of the CARGO is slowly released onto the
foundations.
16. Superlift counterweight tray to be monitored and made sure it is to be set down properly onto
timber mats.
SARENS
17. Alignment & elevation of the CARGO on the foundation to be checked. If it is not satisfactory,
the CARGO is to be lifted up again to make the necessary improvements for correct placement
(e.g. shimming).
19. Lifting tackles to be removed by means of suitable assist equipment (e.g. EWP or crane with
man basket)
20. Once tackle is removed from CARGO, superlift counterweight tray is to be detached from main
crane and main boom to be slewed away from the CARGO area.
Status Status
No Permit Registry No No Permit Registry No
Open 🗸 Close 🗸 Open 🗸 Close 🗸
periodically checked.
Three points of contact
must be maintained at
all times (three limbs in
contact) and
equipment/tools must
be hoisted separately
Tangga harus dalam
keadaan baik dan
diperiksa secara berkala.
Peralatan atau alat
kerja yang dibawa harus
diangkat terpisah ketika
menaiki tangga.
• Safety body harness to
be used
Menggunakan Full body
harness
• Approved static line and
anchoring system to be
utilised if appropriate
Menggunakan garis
statis, lifeline, sistem
penahan yang disetujui
• Must use appropriate
PPE
Menggunakan PPE yang
layak dan sesuai
Under the work Fell the object • Hitting limb • Tool lanyards are to be Supervisor /
place • Injuries used when working at Foreman
• Fatality height. Rigger
Peralatan yang
3 4 M 2 2 L
digunakan untuk bekerja
diketinggian
menggunakan lanyard /
Tali pengikat.
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
authorised personnel
out of danger
Memiliki area yang
cukup dan memadai
untuk membongkar dan
merakit crane, dan
mencegah personnel
yang tidak berwenang
dari bahaya.
• Coordination with the
appointed competent
person must take place
at all times
Koordinasi dengan
orang kompeten yang
ditunjuk setiap saat.
• Relevant information is
to be passed to the
crane operator by the
lift supervisor prior to
commencing work
Informasi yang relevan
harus diteruskan ke
operator crane oleh
supervisor lift sebelum
memulai pekerjaan
• Transporters movement
procedure to be
explained to all persons
involved with the
process in the form of
toolbox
Prosedur pergerakan
transporter dijelaskan
pada semua orang yang
terlibat
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
• Appoint one
superintendent only
Penunjukan oleh satu
pengawas
• Escort
crawlers/supports
Escort crawler / support
• Check the
crawlers/supports
beforehand
Periksa crawler dan
support
• Check the conditions of
the hammers
beforehand
Periksa kondisi palu
sebelum digunakan
• Wear safety gloves
Gunakan sarung tangan
• Be aware of body
position and avoid pinch
points
Waspada posisi tubuh
dan hindari titik jepit
Working at Height Fall from height • Injuries • Wear safety harness
• Fatality (Attach to assembled
boom part)
Kenakan tali pengaman
(pasang ke bagian boom
yang dirakit)
4 3 M 2 2 L
• It is forbidden for
persons to be on the
boom parts or other
crane parts which are in
the hook of the auxiliary
crane.
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
• Appoint one
superintendent only
Penunjukan oleh satu
pengawas
• Communication
instructions
Berkomunikasi
pengarahan
• Guiding of the boom
parts by guiding ropes
Control boom dan part
menggunakan tali
control (Tagline)
• Cordon of life
equipment
• Check the boom parts
beforehand
Pemeriksaan boom dan
part
• Check the condition of
the hammers and the
pins beforehand
Pemeriksan palu dan pin
sebelum digunakan
• Wear safety gloves
Gunakan sarung tangan
• Use boom supports
Gunakan Boom support
• Wear safety harness as
attached to assembled
boom part.
Gunakan safety harness
dan kaitkan pada boom
yang di assembly
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
11 General Working without Failure to provide Injuries or fatality • Emergency contacts are Supervisor /
PPEs emergency available and known Employee
equipment, PPE or Emergency kontak
amenities tersedia dan jelas
• When available, post
First aider on work site
Jika tersedia, posisikan
first aider di lokasi kerja
• Safety hat, Safety shoes
and visibility vest are
mandatory. Gloves,
1 3 L 1 2 L
safety glasses, safety
harness and hearing
protection must be worn
where required.
Helmet, safety shoes,
dan reflective wajib
digunakan. Sarung
tangan, kaca mata,
harness, dan earplug
digunakan jika
diperlukan.
Noise Noise Injuries on ears • Isolate equipment from Supervisor
majority of employees
in the areas.
Pisahkan equipment dari
area yang banyak
pekerja
1 2 L • Rotate workers who are 1 2 L
exposed to the noise
source
Rotasikan pekerja yang
terpapar kebisingan
• Insulate the noise
source
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
Isolasi sumber
kebisingan
• Wear hearing protection
(obligatory ≥ 85 dB(A))
Kenakan pelindung
pendengaran
(wajib ≥ 85 dB(A))
Working in Hot Heat Stress • Injuries • Access to control Supervisor /
weather • Exhaustion drinking water and Manager
adequate intake of it
Akses untuk
mengkontrol air minum
dan asupan yang
memadai
• Regular rest breaks
Istirahat teratur
• Hot heavy tasks to be
carried out in early
morning or late
afternoon
Tugas yang berat
3 3 M dilakukan di pagi dan 2 2 L
sore hari
• Awareness of signs of
heat illnesses
Kepedulian akan tanda
tanda penyakit panas
• Education about
personal factors that
effects their ability to
cope with heat such as:
Edukasi tentang faktor
diri tentang kemampuan
untuk mengatasi panas
seperti
o Fitness
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
Kebugaran
o Weight
Berat badan
o Diet
o Cardio-vascular
disease or
metabolic disorder
Penyakit
kardiovaskular
atau gangguan
metabolisme
o Heat
acclimatization
Aklimatisasi panas
o Medication
Pengobatan
Working in Hot UV Radiation • Injuries • Provision for overhead Supervisor /
weather • Heat Stress shade protection Manager
Penyediaan untuk
perlindungan sinar
diatas kepala
• Provision for Personal
Protective Equipment
such as:
Penyediaan alat
4 3 M pelindung diri seperti 2 2 L
o Sunglasses
Kaca mata hitam / sun
proteksi
o Safety hat with brim and
flap
Topi pengaman dengan
pinggiran dan tutup
o Coverall
Coverall
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
• Cancel operations if
deemed unsafe (HOLD
procedure)
Batalkan operasi jika
dianggap tidak aman
(prosedur HOLD)
• The minimum
illumination level must
be ≥ 20 lux
Tingkat penerangan
minimum harus ≥ 20 lux
12 Manual Handling Lifting items • Sprains • Injuries • Before you start moving, Supervisor /
manually • Muscle strains lifting or carrying heavy Foreman
• Tendon and loads ensure that:
Ligament damage Sebelum Anda mulai
• Spinal damage bergerak, mengangkat
atau membawa beban
berat pastikan bahwa:
- You are fit for the job
Kondisi tubuh anda
dalam keadaan fit
- Have warned up
stretches before starting
4 3 M 2 2 L
any manual work
- Melakukan pemanasan
sebelum memulai
pekerjaan manual
apapun
- The use of all available
mechanical methods to
move the load have
been considered
Penggunaan semua
metode mekanis yang
tersedia untuk
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
memindahkan beban
telah dipertimbangkan
o Assess the area
Kaji area
- Try not to lift in a
restricted area
Coba untuk tidak
mengangkat di area
terlarang
- Ensure there is nothing
you can trip over when
carrying something
Pastikan tidak ada yang
tersandung saat
membawa sesuatu
• Size up the load
Ukur bebannya
o Only lift to your own
capabilities. Don’t lift
more than you can
comfortably handle
Pengangkatan sesuai
kemampuan, jangan
mengangkat lebih dari
kemampuan atau
merasa tidak nyaman
o Remember the 10-
meter rule when
carrying a load:
Ingat aturan sepuluh
meter saat membawa
beban
After 10 meters your
muscles will fatigue
rapidly, and the chances
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
13 Access and egress Bad housekeeping Slips, trips, falls • Injuries • Housekeeping – ensure Supervisor /
– General • Property damage that construction Foreman /
materials are kept in Employee
designated area
Pastikan material
disimpan di area yang
ditentukan
• Take care on
uneven/wet/slippery
grounds
Berhati hati di tanah
3 2 M atau lantai yang tidak 1 1 L
rata, basah, licin
• Ensure safe, stable and
hard access ways are
maintained
Pastikan cara akses
yang aman, stabil dan
keras selalu terjaga
• Access ways must be
clear at all times
Akses harus aman setiap
saat
14 Pre-start inspection Not checking crane Safety walk • Property damage • Inspection of equipment Supervisor /
of equipment condition before to be carried out prior to Operator
work starting on site
Inspeksi peralatan yang
akan digunakan sebelum
memulai
3 2 M 1 1 L
• Daily pre-start
inspection to be carried
out by operator
Inspeksi awal harian
yang dilakukan oleh
operator
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
Harus
mempertimbangkan
rencana kendali yang
memadai untuk lalu
lintas
• Must discuss with driver
routes to be used and
loading area
Harus berdiskusi dengan
pengeudi tentang rute
yang akan digunakan
dan area pemuatan
• Check for overhead
obstructions (e.g. Power
lines, structures)
Periksa rintangan diatas
kepasa seperti kabel
listrik, bangunan dll.
16 Work preparation Bad Ground Tipping of the crane • Damage Property • Calculate the max. Supervisor /
Preparation • Injuries Ground pressure under Foreman
the crane mats. Check
whether the calculated
ground pressure does
not exceed the bearing
capacity of the soil.
Hitung maksimal,
tekanan tanah di bawah
4 4 H 2 2 L
alas crane, periksa
apakah tekanan tanah
yang dihitung tidak
melebihi daya dukung
tanah
• Arrange a sand bed and
adequate load spreading
under the crawlers of the
crane
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
• Appoint one
superintendent only
Penunjukan oleh satu
pengawas saja
• Communication
instructions
Komunikasi yang baik
untuk instruksi
• Guiding of the boom
parts by guiding ropes
Pengendalian bagian
boom atau peralatan
menggunakan tali
kontrol
• Cordon of life equipment
• Check the boom parts
beforehand
Terlebih dulu periksa
bagian boom
• Check the condition of
the hammers and the
pins beforehand
Periksa kondisi hammer
dan pin sebelum
digunakan
• Wear safety gloves
Gunakan sarung tangan
• Use boom supports
Gunakan support boom
• Wear safety harness as
attached to assembled
boom part.
gunakan harness dan
kaitkan ke boom yang
sedang di assembly
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
18 Crane set up Use of unsafe lifting Drop loads • Damage Property • Check whether the crane Supervisor /
devices • Injuries has CE certification Manager
Periksa apakah crane
memiliki sertifikasi CE
• Check the validity of the
crane certification
Periksa validitas
sertifikasi crane
• Arrange functional
testing of the crane after
set up
1 4 M 1 2 L
Atur pengujian
fungsional crane setelah
penyetelan
• Arrange certification by
a notified body,
according to national
legislation
Atur sertifikasi oleh
badan yang berwenang,
sesuai dengan undang
undang nasional
Uncontrolled crane • Drop loads • Damage Property • The sail area of the load Supervisor /
movements due to • Flip of crane • Injuries may not exceed 1.2m² operator /
excessive wind per ton capacity Manager
speed. Beban area tidak boleh
melebihi 1.2M² per ton
kapasitas
• In case the max. Sail
2 4 M 2 2 L
area of the load exceeds
1.2m² per ton capacity,
the max. Admissible
wind speed has to be
reduced accordingly.
Dalam kasus maksimal,
beban kerja layar
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
• Cancel operations if
deemed unsafe (HOLD
procedure)
Batalkan operasi jika
dianggap tidak aman
19 Start lifting No communication Communication loss • Time loss • Explain procedures Supervisor /
operations between Operator • Injuries Menjelaskan prosedur Foreman /
and signal man • Ensure everyone Operator
understands
Pastikan semua orang
mengerti
• Use hand and whistle
signals
Gunakan sinyal tangan
dan peluit
• Use two way radios in
necessary
Gunakan radio dua arah
jika diperlukan
1 3 L • Check that the batteries 1 1 L
are fully charged
Periksa apakah baterai
terisi penuh
• Do a radio check
Melakukan pemeriksaan
radio
• Charging of batteries
must be done at the end
of shift or sooner if
required
Pengisian baterai harus
diakukan di akhir shift
atau lebih cepat jika
diperlukan
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
21 Lifting / Unloading of No proper lifting Drop of the load or • Injuries • Check the load for small Supervisor /
the load / Load Test points objects • Damage Property objects left behind Foreman /
(welding electrodes, Operator
bolts, nuts,...) before
lifting
Periksa beban apakah
ada benda kecil
2 4 M 2 2 L
tertinggal( elektroda las,
baut, mur dll) sebelum
mengangkat
• Wear a safety helmet
Gunakan safety helmet
• Clear the lifting area.
Amankan lifting area
Using Bypass during Tipping of the crane • Damage Property • Do not use the manual Supervisor /
lifting • Injuries override key during Operator
lifting operations.
2 4 M 1 1 L
Jangan gunakan tombol
manual override selama
operasi
22 Unslinging the load Working at height Fall from height Injuries • Slingers wear safety Supervisor /
harness Foreman /
Slinger menggunakan Operator
4 3 M safety harness 2 2 L
• Use cherry picker (with
fall harness in the
basket)
Not using proper Hand injuries Injuries 2 2 L • Wear safety gloves 1 1 L Supervisor /
PPEs Gunakan sarung tangan Foreman /
23 Fueling of Crane Fueling of crane • Miscommunication • Injuries • Crane operator to assist Supervisor /
• Falls from heights • Soil pollution cougar fuels in the Foreman /
• Dropped fuel hose fueling process. AT NO Operator
3 2 M 2 2 L
from heights TIME WILL COUGAR
• Spills – Fuel splash FUEL OPERATORS
back
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
merusak (bersandar
pada pagar pengaman
• Fuel hose will be
secured onto the rope
Selang bahan bakar
akan diamankan
menggunakan tali
• Crane will be equipped
with a spill tray, spill kit,
use of drip cloth.
Goggles and fuel gloves.
Crane akan dilengkapi
dengan spill tray, spill
kit, penggunaan
kacamata dan sarung
tangan bahan bakar
• All spills will be
contained and
immediately reported to
Sunlake.
Semua tumpahan akan
ditempatkan dan segera
melaporkan ke petu
24 Conduct the During Maintenance • Oil spills • Fall down • Identify spill potential Mechanic /
maintenance required • Slips trips and falls • Soil pollution hazard on FLHA Supervisor /
Mengidentifikasi potensi Operator
bahaya tumpahan pada
FLHA
• Large Spill kit on
2 3 M standby 1 2 L
Kit tumpahan ukuran
besar dalam keadaan
siaga
• Pre- check transfer
process for all oil
containment equipment
JOB SAFETY ANALYSIS (JSA) AND RISK ASSESSMENT FORM
Pemeriksaan sebelum
transfer untuk semua
peralatan penahan
minyak
• Ensure clean oil free
work area to occupy
Pastikan area kerja
bersih bebas minyak
untuk ditempati
10
11
12
13
14
15
Doc. No. : 26071-100-VSC-HL1-00007
SARENS SGC-90
33600 CL TANK
CE 75%
CONFIGURATION MB CL TANK
45900 C
L TANK
L
C TANK
L TANK
C
33600
* TACKLE 6.7 6.7 6.7 6.7 t 23800
% OF DIN/ISO CHART 39.7 36.7 71.6 67.9 %
R4
75
00
00
92000
4
R130000
R26
90°
90000
11400
Clearance=6673
Drive : 7432
180°
0°
6
R4370
6200
Hook C
270°
learanc
0
e : 122
R5
15300
1
27
500
0°
18
0°
0
Cleara 000
n ce : 28 R20
7
0°
90
°
10500
15500
17500
5000
R13000
Notes
R84000
8700
N
EC UTIO E 10/02/2021 Updated Tailing Crane M.M.R D,C I.S
FOR EX D 09/28/2021 Updated Tailing Crane Position and Item Weight (including P/F weights) M.M.R D.C I.S
C 24/05/2021 Updated Crane Load Box M.M.R D.C I.S
63242
Ground preparations
Area to be hardened & levelled by the client
Ground bearing pressure up to 220 kN/m²
Level requirements : 0° ± 0.3 ° (± 0.5 %) Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
No license under any patent, or copyright, nor any other intellectual property, proprietary or
Compacted material : crushed concrete other right shall be granted to other parties, except for Sarens.
2 layer Wooden Mats : 400
equipment:
SGC90 MB 130M & TEREX/DEMAG CC8800-1 SSL 84m
Ground Elevation : 800
description:
Reference Drawings LIFTING OF C-063-06
FDN + Anchor : 775
76
6792
Clearance : 200
°
0°
1000
500
26071-200-DB-063-00007_002
18
4 Foundation Details
0°
33600
23800
General
Configuration SSL - 60t CB R4
75
Track Width 10.5 x 10.5 m 00
Boom System
00
92000
4
R130000
R26
90°
Main Boom Length 84 m 90000
11400
Clearance=6673
Drive : 7432
180°
0°
Counterweight 6
R4370
6200
Hook C
270°
Superstructure CW 295 t learanc
0
e : 122
R5
15300
Superstructure CW Radius 9.5 m 1
27
500
0°
18
0°
Central CW 60 t
0
Cleara 000
n ce : 28 R20
7
0°
Hook Block
90
°
10500
15500
17500
HB Weight 40 t
# Reeving 20
5000
Reeving Capacity 645.8 t
R13000
Ground preparations Tailing Crane 788.6t C-063-06 Notes
R84000
8700
Area to be hardened & levelled by the client 1 2 1 Position of COG to be confirmed by client
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6001_E.dwg, 08/10/2021 13:36:06
Ground bearing pressure up to 300 kN/m² Load Case 2 Position and details of lifting points to be confirmed by client
Level requirements : 0° ± 0.3 ° (± 0.5 %) 3 Final weights to be confirmed by client
Compacted material : crushed concrete Crane Parameters 4 Soil stability is client responsability
Radius m 13 20 5 The slewing area for the derrick ballast has to be level and free of obstacles
90° Slew Range ° 267 200 6 P/F 8th ~ 24th will be installed prior to lifting and its weight shall be verified by client
Superstructure CW Radius m 9.5 9.5
7 P/F 25th will be partially installed prior to lifting and its weight shall be verified by client
Derrick Radius m 26.4 26.4
C A Ballast Radius m 30 30 8 Pipe diameter 16" will be installed prior to lifting and all weights includes P/F is 36ton.
Ballast Weight t 0 0
Active Ballast Weight t 0 0 E 10/02/2021 Updated Tailing Crane M.M.R D,C I.S
180° 0° Load Chart Capacity t 502.5 314 D 09/28/2021 Updated Tailing Crane Position and Item Weight (including P/F weights) M.M.R D.C I.S
Load Parameters C 24/05/2021 Updated Crane Load Box M.M.R D.C I.S
63242
equipment:
B: 5 m (Width) kN/m² 177 0 SGC90 MB 130M & TEREX/DEMAG CC8800-1 SSL 84m
Ground Elevation : 800
6792
0°
1000
500
975
5
ION
X ECUT
R 50
E
FOR
6
94
3563
1888
2413
50596 54502
105098
Clearance=4585
4 Foundation Details 26071-200-DB-063-00007_002
5 Platforms Details 26071-V1C-C-063-06-01051 ~ 01100
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6001_E.dwg, 08/10/2021 13:36:12
Ho
11400
Cleara ok
R130000
nce=1 Notes
0 04
1 Position of COG to be confirmed by client
2 Position and details of lifting points to be confirmed by client
Clear 3 Final weights to be confirmed by client
ance=
1 1075 4 Soil stability is client responsability
5 The slewing area for the derrick ballast has to be level and free of obstacles
2 2 6 P/F 8th ~ 24th will be installed prior to lifting and its weight shall be verified by client
7 P/F 25th will be partially installed prior to lifting and its weight shall be verified by client
8 Pipe diameter 16" will be installed prior to lifting and all weights includes P/F is 36ton.
3 3
62°
503
A 13/04/2021 Updated Main Crane and Lifting Tackle D.C D.C I.S
- 17/02/2021 First Issue Y.K D.C D.C
rev. date description designed verified approved
4 4 client:
7070
Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
No license under any patent, or copyright, nor any other intellectual property, proprietary or
73
other right shall be granted to other parties, except for Sarens.
1000
° equipment:
SGC90 MB 130M & TEREX/DEMAG CC8800-1 SSL 84m
description:
LIFTING OF C-063-06
R55000 PROPANE/PROPYLENE SPLITTER (752.6TON + 36TON)
site: proj.:
ID - RDMP BALIKPAPAN PROJECT
owner: drawing type: size:
SID Tackle Drawing A3
Detail Tackle Arrangement Detail Crane Side View appr. state:
For Approval
project:
S-18-13306
scale:
-
Scale 1/200 Scale 1/1500 doc No.: sheet:
S-18-13306_DR6001_E 1-3
L TANK
C
L TANK
C
CLTANK
CLTANK
C
L TANK
CLTANK
L TANK
C
CLTANK
7700 97895
6800 43000 54900
ref. point
8200
11268
15600
18000
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6001_E.dwg, 08/10/2021 13:36:21
24700
- 10/08/2021 First Issue M.M.R D.C I.S
rev. date description designed verified approved
Reference Drawings Notes client:
420
SARENS SGC-90
L TANK
C
CE 75%
CONFIGURATION MB
OUTER RING DIA. 45.9 m
L TANK
C
COUNTERWEIGHT 2400 t
TANK L
C
MB Clearance : 1659
TANK L
C
22 C TANK
L
TANK L
C
TANK LC
33600
* TACKLE 0.1 0.1 0.1 t
Ground preparations
% OF DIN/ISO CHART 7.2 7.2 7.2 %
Area to be hardened & levelled by the client R4
75
Ground bearing pressure up to 200 kN/m² 00
Timber:2x14000
Level requirements : 0° ± 0.3 ° (± 0.5 %)
0
Compacted material : crushed concrete
R13000
90°
11400
N
UTIO
180°
0°
13400
8400
EC
CC 2800-1
R EX A A"
85
270°
FO R29300
00
R4750
7100
0
500
Hand Rail should 22
be on HOLD 8500
33600
C C"
4 x 6m Polyester Sling
SWL : 6 TON
3200
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6015.dwg, 16/10/2021 09:48:09
90°
B
chocked
5900
5900
2700
0° 180°
5
10532
2700 3200
B" 270°
7 equipment:
happens during lifting SGC90 MB 130m
Ground Elevation : 800
description:
LIFTING OF Top Platform (C-063-06)
Reference Drawings
76
°
5000
N
R4800
C: 5 m (Width) kN/m² 57 57 57
EC UTIO D: 5 m (Width) kN/m² 57 57 57
R EX
0
FO
t061
13900
Ground preparations
t05
R84000
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6015.dwg, 16/10/2021 09:48:13
Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
6 The weight for supporting crane in the middle shall be verified by client
R30
No license under any patent, or copyright, nor any other intellectual property, proprietary or
other right shall be granted to other parties, except for Sarens.
Subcontractor have no responsibility of damage such as deflection of riser pipe which
2 layer Wooden Mats : 400
7 equipment:
happens during lifting SGC90 MB 130m & TEREX/DEMAG CC2800-1 SWSL 84+48m
Ground Elevation : 800
description:
LIFTING OF MAN BASKET (1 TON)
Reference Drawings
76
FOR C-063-06
°
°
85
SARENS SGC-90
CE 75%
8700
R100
00
CONFIGURATION MB R1400 R1400
0 0
OUTER RING DIA. 45.9 m
R76400
COUNTERWEIGHT 2400 t 20000
BM
BM
00
MAIN BOOM 130 m
3
R82
49300 50600
169
VALVE + ACTUATOR
CENTER OF GRAVITY
393
7°
R483
* HOOK BLOCK 57.0 57.0 57.0 57.0 t
00
C TANK L
330
CENTER OF GRAVITY
VALVE + ACTUATOR
165
* TACKLE 0.2 0.2 0.2 0.2 t
% OF DIN/ISO CHART 9.1 10.2 7.2 7.2 % C TANK L
L TANK
C
0
R13000
11400
L TANK
C
5100
L
C TANK
5100
N
TANK L
C
TIO
EX ECU CL TANK
FOR
C TANK L
CL
TANK
1000
C TANK L
K-052-01-S2BK-052-01-S2A
OIL FILTER 2 OIL FILTER 1
ACCUMULATOR
K-052-01-S03
K-052-01-EA1A
K-052-01-EA1B
OIL COOLER 1
OIL COOLER 2
K-052-01-GM3
K-052-01-GM1
K-052-01-GM2
K-052-01-GM4
EMERGENCY OIL PUMP
K-052-01-G1
K-052-01-G2
OIL PUMÜ 2
OIL PUMP 1
K-052-01-G4
K-052-01-S3
EMERGENCY OIL FILTER
K-052-01-K1
K-052-01-K2
33600
N14
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6014.dwg, 15/10/2021 10:01:35
N16
90°
R4
180°
0°
83
00
270°
33600
Notes
1 Position of COG to be confirmed by client
2 Position and details of lifting points to be confirmed by client
3 Final weights to be confirmed by client
4 Soil stability is client responsability - 17/02/2021 First Issue D.C M.M.R I.S
5 The slewing area for the derrick ballast has to be level and free of obstacles rev. date description designed verified approved
client:
6 The weight for supporting crane in the middle shall be verified by client
Subcontractor have no responsibility of damage such as deflection of riser pipe which
7
happens during lifting
Reference Drawings Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
No license under any patent, or copyright, nor any other intellectual property, proprietary or
1 Plot Plan 26071-200-P1-062-00001_001 other right shall be granted to other parties, except for Sarens.
2 layer Wooden Mats : 400
equipment:
2 Item Drawing 26071-V1C-C-063-06-00001_003 SGC90 MB 130M & ATF220G-5 & SCC1500 42m
Ground Elevation : 800
5100
20000
16000 8000
49300 50600
SANY SCC1500
CE 75%
CONFIGURATION MB
TRACK 5.63 x 6.23 m
COUNTERWEIGHT 50t + 53t CB t
TION
MAIN BOOM 42.0 m
CU
EXE
FOR
RADIUS 14.0 m
CAPACITY 42.9 t
Reference Drawings
TOTAL LOAD: 18.15 t
1 Plot Plan 26071-200-P1-062-00001_001
R55000
* LOAD 16.7 t Item Drawing
2 26071-V1C-C-063-06-00001_003
* HOOK BLOCK 1.25 t Item Drawing 26071-V1C-C-063-06-00004_001
3
* TACKLE 0.2 t 4 Foundation Details 26071-200-DB-063-00007_002
% OF DIN/ISO CHART 42.3 % 5 Platforms Details 26071-V1C-C-063-06-01051 ~ 01100
Notes
C:\Users\dcheong\OneDrive - Sarens (1)\S-18-13306\01. Engineering\01. Lifting Plan CAD\#DR6000\S-18-13306_DR6014.dwg, 15/10/2021 10:01:38
Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
No license under any patent, or copyright, nor any other intellectual property, proprietary or
other right shall be granted to other parties, except for Sarens.
0
equipment:
00
description:
LIFTING OF 36" Riser Pipe (C-063-06)
PROPANE/PROPYLENE SPLITTER 36" Riser (33.6TON)
site: proj.:
R14000 R10000 ID - RDMP BALIKPAPAN PROJECT
owner: drawing type: size:
34800 35800 SKR Lifting Drawing A3
appr. state: project: scale:
For Approval S-18-13306 1/750
doc No.: sheet:
S-18-13306_DR6014 1-2
LIFTING GEAR ARRANGEMENT Main Crane Man Basket Main Crane CC 2800-1 Main Crane 1t Man Basket
SCALE 1:75
Max. Wind Speed according to Load Chart 9.8 m/s General 1 2 3
Load Case
Max. Wind Sail Area according to Load Chart 7 m² Configuration SWSL - 0tCB
Chain Sling x 4, Wind Resistance Coefficient Cw 1.2 Track Width 8.4 x 8.4 m Crane Parameters
SWL : 10t, L=2.3m Projected Surface of the Load 4 m²
Boom System Radius m 29.3 29.3 29.3
Actual Surface of the Load 4 m²
Actual Surface of the Load < Max Sail Area Main Boom Length 84 m Slew Range ° 0 0 - -270 90
Jib Length 54 m MB Angle ° 85 85 85
Max. Wind Speed for Lifting (3 sec. gust) 9.8 m/s Derrick Radius m 15 15 15
Shackles x 4, SWL : 4.75t Counterweight
Load Chart Capacity t 55.5 55.5 55.5
90° Superstructure CW 160 t
Superstructure CW Radius 6.18 m Load Parameters
Central CW 0t Load t 1 1 1
Hook Block Tackle t 0.2 0.2 0.2
C A
Hook Block t 4.8 4.8 4.8
HB Weight 4.8 t
Runner HB Weight t 2.8 2.8 2.8
# Reeving 5
sneraS
sneraS
0
R13000
5000
Static Ground Bearing Pressure
R4800
A: 5 m (Width) kN/m² 57 57 57
B: 5 m (Width) kN/m² 57 57 57
0
10100
t061
C: 5 m (Width) kN/m² 57 57 57
t05
D: 5 m (Width) kN/m² 57 57 57
4900
sneraS
sneraS
N
C UTIO
EXE
FOR
Timber:2x14000
90°
°
72
180°
0°
13400
8400
CC 2800-1
270°
R29300
R84000
Reference Drawing
y:25000
Item Drawing 26071-V1C-C-063-06-00001_003
E:\SARENS INDONESIA\S-18-13306 - Balikpapan JO - ID RDMP Project\workspace\S-18-13306_DR6014_Man Basket.dwg, 14/10/2021 13:05:30
1
2 Item Drawing 26071-V1C-C-063-06-00004_001
x:16400 3 Platforms Details 26071-V1C-C-063-06-01051 ~ 01100
113300
Notes
1 Soil stability is client responsability
2 The slewing area for the derrick ballast has to be level and free of obstacles
3 Maximum person are two person for deshackling lifting gear
Subcontractor have no responsibility of damage such as deflection of riser pipe which
Reference Point 4
happens during lifting
Copyright Sarens group. All rights reserved. This document is the sole property of Sarens.
No license under any patent, or copyright, nor any other intellectual property, proprietary or
other right shall be granted to other parties, except for Sarens.
76
equipment:
Terex Demag CC 2800-1 SWSL 84 + 48m
°
°
85
description:
LIFTING OF 36" Riser Pipe (C-063-06)
500