RAMSON - ABP III CONSTRUCTION ARCHITECTS * ENGINEERS * BUILDERS * CONTRACTORS

BLK 8 LOT 5 CHRYSANTHEMUM ST. CAMELLA HOMES B.L.S BRGY. DON BOSCO, PARANAQUE CITY

Project : PROJECT AZOTIEA RESORT WORLD MANILA


Location : Newport Boulevard, Newport City, Pasay 1309, Metro Manila, Phillipines QUOTATION NO. RWM-2019-06

Subject : RETROFITTING WORKS AT CHIPPED BEAM AT 2F COLLAB MEZZANINE


BREAKDOWN OF COST PROPOSAL

MATERIAL
PARTICULAR QTY UNIT LABOR COST UNIT COST TOTAL COST
COST

I General Requirements
a) Mobilization 1.00 lot 20,000.00 20,000.00 20,000.00
b) Power and Water Consumption 1.00 lot 15,000.00 15,000.00 15,000.00
d) Temporary Facilities 1.00 lot 15,000.00 15,000.00 15,000.00
e) Safety 1.00 lot 15,000.00 15,000.00 15,000.00
f) Demobilization 1.00 lot 20,000.00 20,000.00 20,000.00
Total "I" 85,000.00

II 11TH FLOOR STRUCTURAL STEEL AND RETROFITTING WORKS


a) Chipping Works 35.00 lm 3,500.00 3,500.00 122,500.00
1. Disposal of debris 1.00 lot 20,000.00 20,000.00 20,000.00
3. Hauling 1.00 lot 30,000.00 30,000.00 30,000.00
b) Concreting
1. on chipped beam 3.00 cu.m. 7,500.00 1,500.00 9,000.00 27,000.00
c) Reinforcing bars
1. Slab on grade
12mm 500.00 kgs 80.00 50.00 130.00 65,000.00
d) Form Works 1.00 lot 20,000.00 20,000.00 20,000.00
d) Others
1. G.I. Wire # 16 80.00 kgs 150.00 50.00 200.00 16,000.00
2. Chem Anchor 10.00 tube 6,500.00 500.00 7,000.00 70,000.00
3. Tools and Equipment 1.00 lot 60,000.00 60,000.00 60,000.00
Total "II" 430,500.00
NET AMOUNT 515,500.00
2% EWT 10,310.00
12% VAT 61,860.00
TOTAL AMOUNT(VAT Inclusive) 587,670.00

We anticipate your positive response and look forward to serve this requirement soon.

Best regards,

ENGR. SONNY PANALIGAN


President/ General Manager
RAMSON-ABPII CONSTRUCTION
sonnypanaligan1977@yahoo.com
CP: +639455276226

1 of 2
RAMSON - ABP III CONSTRUCTIONARCHITECTS * ENGINEERS * BUILDERS * CONTRACTORS
BLK 8 LOT 5 CHRYSANTHEMUM ST. CAMELLA HOMES B.L.S BRGY. DON BOSCO, PARANAQUE CITY

Project : PROJECT AZOTIEA RESORT WORLD MANILA


Location : Newport Boulevard, Newport City, Pasay 1309, Metro Manila, Phillipines QUOTATION NO. RWM-2019-05

2 of 2

You might also like