REV4 Ball Valves 24 Inch

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

REV.

4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
1 L.O.I. RECEIPT 1d Fri 25/08/06 Fri 25/08/06
2 DESIGN REVIEW AND AUTHORIZATION TO PROCEED 2d Thu 22/03/07 Fri 23/03/07
3 PRELIMINARY GA DWGS, BOM'S, Q.PLAN 164 d Mon 02/10/06 Thu 19/04/07
4 ISSUE OF P.O. FOR RAW MATERIALS (MAIN COMPONENTS) 32,5 d Wed 04/04/07 Wed 16/05/07
5 VALVE TORQUE EVALUATION 40 d Mon 08/01/07 Thu 22/02/07
6 FEA BALL/SEATS SUBMISSION 60 d Mon 19/03/07 Thu 31/05/07
7 FEA BODY/BONNET SUBMISSION 150 d Sat 09/12/06 Wed 13/06/07
8 DETAILED DRAWINGS & FINAL B.O.M. 100 d Fri 01/06/07 Fri 05/10/07
9 SUBMISSION & APPROVAL OF VALVE QCP 31 d Mon 10/09/07 Mon 15/10/07
10 SUBMISSION & APPROVAL OF V.A. DOCUMENTATION 90 d Fri 01/06/07 Mon 24/09/07
11 DEFINITION OF NEW WPS: 625 OVERLAY ON BODIES 214 d Mon 02/04/07 Fri 21/12/07
12 Submission & Approval of Pwps 73 d Mon 02/04/07 Sat 30/06/07
13 Welding qualification activities 117 d Mon 02/07/07 Fri 23/11/07
14 Submission & Approval of PRODUCTION WPS/PQR 24 d Sat 24/11/07 Fri 21/12/07
15 NO. 1 24x16INCH 506 d Fri 08/12/06 Thu 21/08/08
16 Ball # 1 256 d Wed 25/07/07 Sat 07/06/08
17 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
18 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
19 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
20 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
21 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
22 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
23 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
24 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
25 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
26 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
27 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
28 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
29 Bonnet # 1 140 d Mon 03/09/07 Thu 21/02/08
30 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
31 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
32 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
33 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
34 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
35 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
36 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
37 Seats # 1 132 d Mon 03/09/07 Tue 12/02/08
38 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
39 Seat Machining 48 d Mon 10/12/07 Tue 12/02/08 GROVE
40 Stem #1 289 d Fri 08/12/06 Fri 30/11/07
41 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
42 Stem Machining 25 d Fri 08/12/06 Thu 11/01/07
43 Body casting #1 145 d Wed 05/09/07 Fri 29/02/08
44 Delivery 145 d Wed 05/09/07 Fri 29/02/08
45 Body Machining #1 84 d Mon 03/03/08 Tue 10/06/08
46 Body Pre-machining 1 - VTL Ø2.0m 6d Mon 03/03/08 Sat 08/03/08 OMPG CALCINATE TURNING 1
47 Body Pre-machining 2 - HBM Ø2.0m 4d Tue 11/03/08 Fri 14/03/08 OMPG CALCINATE BORING
48 Weld Overlay 41 d Mon 17/03/08 Mon 05/05/08 TIG MIG / ECOKIMICA
49 PWHT 6d Wed 07/05/08 Tue 13/05/08 TRATER
50 Body Machining 1 - VTL Ø2.0m (seat area) 9d Thu 15/05/08 Sat 24/05/08 OMPG CALCINATE TURNING 1
51 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Tue 27/05/08 Thu 29/05/08 OMPG CALCINATE TURNING 2
52 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Sat 31/05/08 Thu 05/06/08 OMPG CALCINATE BORING
53 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Sat 07/06/08 Tue 10/06/08 OMPG CALCINATE TURNING 1
54 Final activities # 1 62 d Wed 11/06/08 Thu 21/08/08
55 Continengency for scheduling final activities 18 d Wed 11/06/08 Tue 01/07/08
56 Assembly preparation 5d Wed 02/07/08 Mon 07/07/08 GROVE
57 Assembly 5d Tue 08/07/08 Sat 12/07/08 GROVE
58 PROTOTYPE TESTING 12 d Tue 15/07/08 Mon 28/07/08 GROVE
59 Contingency for prototype 10 d Tue 29/07/08 Fri 08/08/08
60 Painting 5d Sat 09/08/08 Thu 14/08/08 GROVE
61 Marking / preservation 2d Sat 16/08/08 Mon 18/08/08 GROVE
62 Packing & EXW shipment 3d Tue 19/08/08 Thu 21/08/08
REV. 4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
63 NO. 2 24x16INCH 328 d Wed 25/07/07 Sat 30/08/08
64 Ball # 2 256 d Wed 25/07/07 Sat 07/06/08
65 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
66 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
67 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
68 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
69 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
70 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
71 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
72 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
73 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
74 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
75 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
76 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
77 Bonnet # 2 140 d Mon 03/09/07 Thu 21/02/08
78 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
79 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
80 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
81 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
82 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
83 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
84 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
85 Seats # 2 144 d Mon 03/09/07 Tue 26/02/08
86 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
87 Seat Machining 48 d Mon 31/12/07 Tue 26/02/08 GROVE
88 Stem # 2 102 d Tue 04/09/07 Wed 09/01/08
89 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
90 Stem Machining 25 d Mon 03/12/07 Wed 09/01/08 SAB
91 Body casting #2 145 d Tue 04/09/07 Thu 28/02/08
92 Delivery 145 d Tue 04/09/07 Thu 28/02/08
93 Body Machining # 2 84 d Sat 01/03/08 Mon 09/06/08
94 Body Pre-machining 1 - VTL Ø2.0m 6d Sat 01/03/08 Fri 07/03/08 OMPG CALCINATE TURNING 1
95 Body Pre-machining 2 - HBM Ø2.0m 4d Mon 10/03/08 Thu 13/03/08 OMPG CALCINATE BORING
96 Weld Overlay 41 d Sat 15/03/08 Sat 03/05/08 TIG MIG / ECOKIMICA
97 PWHT 6d Tue 06/05/08 Mon 12/05/08 TRATER
98 Body Machining 1 - VTL Ø2.0m (seat area) 9d Wed 14/05/08 Fri 23/05/08 OMPG CALCINATE TURNING 1
99 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Mon 26/05/08 Wed 28/05/08 OMPG CALCINATE TURNING 2
100 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Fri 30/05/08 Wed 04/06/08 OMPG CALCINATE BORING
101 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Fri 06/06/08 Mon 09/06/08 OMPG CALCINATE TURNING 1
102 Final activities #2 71 d Tue 10/06/08 Sat 30/08/08
103 Continengency for scheduling final activities 26 d Tue 10/06/08 Wed 09/07/08
104 Assembly preparation 5d Thu 10/07/08 Tue 15/07/08 GROVE
105 Assembly 5d Mon 04/08/08 Fri 08/08/08 GROVE
106 F.A.T. 6d Mon 11/08/08 Sat 16/08/08 GROVE
107 Painting 5d Tue 19/08/08 Sat 23/08/08 GROVE
108 Marking / preservation 2d Tue 26/08/08 Wed 27/08/08 GROVE
109 Packing & EXW shipment 3d Thu 28/08/08 Sat 30/08/08
REV. 4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
110 NO. 3 24x16INCH 333 d Wed 25/07/07 Fri 05/09/08
111 Ball # 3 256 d Wed 25/07/07 Sat 07/06/08
112 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
113 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
114 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
115 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
116 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
117 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
118 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
119 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
120 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
121 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
122 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
123 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
124 Bonnet # 3 140 d Mon 03/09/07 Thu 21/02/08
125 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
126 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
127 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
128 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
129 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
130 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
131 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
132 Seats # 3 156 d Mon 03/09/07 Tue 11/03/08
133 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
134 Seat Machining 48 d Wed 16/01/08 Tue 11/03/08 GROVE
135 Stem # 3 114 d Tue 04/09/07 Wed 23/01/08
136 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
137 Stem Machining 25 d Mon 17/12/07 Wed 23/01/08 SAB
138 Body casting #3 145 d Tue 04/09/07 Thu 28/02/08
139 Delivery 145 d Tue 04/09/07 Thu 28/02/08
140 Body Machining # 3 84 d Sat 01/03/08 Mon 09/06/08
141 Body Pre-machining 1 - VTL Ø2.0m 6d Sat 01/03/08 Fri 07/03/08 OMPG CALCINATE TURNING 1
142 Body Pre-machining 2 - HBM Ø2.0m 4d Mon 10/03/08 Thu 13/03/08 OMPG CALCINATE BORING
143 Weld Overlay 41 d Sat 15/03/08 Sat 03/05/08 TIG MIG / ECOKIMICA
144 PWHT 6d Tue 06/05/08 Mon 12/05/08 TRATER
145 Body Machining 1 - VTL Ø2.0m (seat area) 9d Wed 14/05/08 Fri 23/05/08 OMPG CALCINATE TURNING 1
146 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Mon 26/05/08 Wed 28/05/08 OMPG CALCINATE TURNING 2
147 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Fri 30/05/08 Wed 04/06/08 OMPG CALCINATE BORING
148 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Fri 06/06/08 Mon 09/06/08 OMPG CALCINATE TURNING 1
149 Final activities #3 76 d Tue 10/06/08 Fri 05/09/08
150 Continengency for scheduling final activities 26 d Tue 10/06/08 Wed 09/07/08
151 Assembly preparation 5d Wed 16/07/08 Mon 21/07/08 GROVE
152 Assembly 5d Sat 09/08/08 Thu 14/08/08 GROVE
153 F.A.T. 6d Sat 16/08/08 Fri 22/08/08 GROVE
154 Painting 5d Mon 25/08/08 Fri 29/08/08 GROVE
155 Marking / preservation 2d Mon 01/09/08 Tue 02/09/08 GROVE
156 Packing & EXW shipment 3d Wed 03/09/08 Fri 05/09/08
REV. 4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
157 NO. 4 24x16INCH 340 d Wed 25/07/07 Sat 13/09/08
158 Ball # 4 256 d Wed 25/07/07 Sat 07/06/08
159 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
160 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
161 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
162 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
163 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
164 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
165 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
166 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
167 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
168 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
169 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
170 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
171 Bonnet # 4 140 d Mon 03/09/07 Thu 21/02/08
172 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
173 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
174 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
175 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
176 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
177 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
178 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
179 Seats # 4 168 d Mon 03/09/07 Tue 25/03/08
180 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
181 Seat Machining 48 d Wed 30/01/08 Tue 25/03/08 GROVE
182 Stem # 4 126 d Tue 04/09/07 Wed 06/02/08
183 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
184 Stem Machining 25 d Wed 09/01/08 Wed 06/02/08 SAB
185 Body casting #4 110 d Wed 14/11/07 Sat 29/03/08
186 Delivery 110 d Wed 14/11/07 Sat 29/03/08
187 Body Machining # 4 84 d Tue 01/04/08 Wed 09/07/08
188 Body Pre-machining 1 - VTL Ø2.0m 6d Tue 01/04/08 Mon 07/04/08 OMPG CALCINATE TURNING 1
189 Body Pre-machining 2 - HBM Ø2.0m 4d Wed 09/04/08 Sat 12/04/08 OMPG CALCINATE BORING
190 Weld Overlay 41 d Tue 15/04/08 Tue 03/06/08 TIG MIG / ECOKIMICA
191 PWHT 6d Thu 05/06/08 Wed 11/06/08 TRATER
192 Body Machining 1 - VTL Ø2.0m (seat area) 9d Fri 13/06/08 Mon 23/06/08 OMPG CALCINATE TURNING 1
193 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Wed 25/06/08 Fri 27/06/08 OMPG CALCINATE TURNING 2
194 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Mon 30/06/08 Fri 04/07/08 OMPG CALCINATE BORING
195 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Mon 07/07/08 Wed 09/07/08 OMPG CALCINATE TURNING 1
196 Final activities #4 57 d Thu 10/07/08 Sat 13/09/08
197 Continengency for scheduling final activities 21 d Thu 10/07/08 Sat 02/08/08
198 Assembly preparation 5d Mon 04/08/08 Fri 08/08/08 GROVE
199 August slow/shutdown (9th-24th) 7d Sat 09/08/08 Sat 16/08/08
200 Assembly 5d Mon 18/08/08 Fri 22/08/08 GROVE
201 F.A.T. 6d Mon 25/08/08 Sat 30/08/08 GROVE
202 Painting 5d Tue 02/09/08 Sat 06/09/08 GROVE
203 Marking / preservation 2d Tue 09/09/08 Wed 10/09/08 GROVE
204 Packing & EXW shipment 3d Thu 11/09/08 Sat 13/09/08
REV. 4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
205 NO. 5 24x16INCH 345 d Wed 25/07/07 Fri 19/09/08
206 Ball # 5 256 d Wed 25/07/07 Sat 07/06/08
207 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
208 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
209 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
210 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
211 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
212 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
213 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
214 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
215 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
216 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
217 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
218 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
219 Bonnet # 5 140 d Mon 03/09/07 Thu 21/02/08
220 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
221 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
222 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
223 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
224 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
225 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
226 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
227 Seats # 5 180 d Mon 03/09/07 Tue 08/04/08
228 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
229 Seat Machining 48 d Wed 13/02/08 Tue 08/04/08 GROVE
230 Stem # 5 138 d Tue 04/09/07 Wed 20/02/08
231 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
232 Stem Machining 25 d Wed 23/01/08 Wed 20/02/08 SAB
233 Body casting #5 110 d Tue 13/11/07 Fri 28/03/08
234 Delivery 110 d Tue 13/11/07 Fri 28/03/08
235 Body Machining #5 84 d Mon 31/03/08 Tue 08/07/08
236 Body Pre-machining 1 - VTL Ø2.0m 6d Mon 31/03/08 Sat 05/04/08 OMPG CALCINATE TURNING 1
237 Body Pre-machining 2 - HBM Ø2.0m 4d Tue 08/04/08 Fri 11/04/08 OMPG CALCINATE BORING
238 Weld Overlay 41 d Mon 14/04/08 Mon 02/06/08 TIG MIG / ECOKIMICA
239 PWHT 6d Wed 04/06/08 Tue 10/06/08 TRATER
240 Body Machining 1 - VTL Ø2.0m (seat area) 9d Thu 12/06/08 Sat 21/06/08 OMPG CALCINATE TURNING 1
241 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Tue 24/06/08 Thu 26/06/08 OMPG CALCINATE TURNING 2
242 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Sat 28/06/08 Thu 03/07/08 OMPG CALCINATE BORING
243 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Sat 05/07/08 Tue 08/07/08 OMPG CALCINATE TURNING 1
244 Final activities #5 63 d Wed 09/07/08 Fri 19/09/08
245 Continengency for scheduling final activities 26 d Wed 09/07/08 Thu 07/08/08
246 Assembly preparation 5d Fri 08/08/08 Wed 13/08/08 GROVE
247 Assembly 5d Sat 23/08/08 Thu 28/08/08 GROVE
248 F.A.T. 6d Sat 30/08/08 Fri 05/09/08 GROVE
249 Painting 5d Mon 08/09/08 Fri 12/09/08 GROVE
250 Marking / preservation 2d Mon 15/09/08 Tue 16/09/08 GROVE
251 Packing & EXW shipment 3d Wed 17/09/08 Fri 19/09/08
REV. 4
RAS GAS EXPANSION II PROJECT NOV. 05, 2007
24x16" Top Entry Ball Valves
WH10 & 11
ID ACTIVITY Duration START FINISH Nov Jan Mar May Jul Sep
21/09 11/10 01/11 21/11 11/12 01/01 21/01 11/02 01/03 21/03 11/04 01/05 21/05 11/06 01/07 21/07 11/08 01/09 21/09 11/10
252 NO. 6 24x16INCH 350 d Wed 25/07/07 Thu 25/09/08
253 Ball # 6 256 d Wed 25/07/07 Sat 07/06/08
254 Ball Forging 121 d Wed 25/07/07 Fri 21/12/07 FMA
255 Ball Machining - pre-machining 10 d Mon 31/12/07 Sat 12/01/08 GERVASONI
256 Contingency for batch run at Gervasoni 18 d Mon 14/01/08 Sat 02/02/08
257 Weld Overlay 10 d Mon 04/02/08 Thu 14/02/08 GERVASONI
258 Contingency for batch run at Gervasoni 32 d Fri 15/02/08 Sat 22/03/08
259 PWHT 7d Tue 25/03/08 Tue 01/04/08 TRATER
260 Ball Machining - final machining 18 d Thu 03/04/08 Wed 23/04/08 GERVASONI
261 Contingency for batch run at Gervasoni 17 d Thu 24/04/08 Thu 15/05/08
262 Ball Grinding - pre-TCC 7d Sat 17/05/08 Sat 24/05/08 GROVE
263 Tungsten Carbide Coating 5d Tue 27/05/08 Sat 31/05/08 PRAXAIR
264 Ball Grinding - post-TCC 3d Mon 02/06/08 Wed 04/06/08 PRAXAIR
265 Lapping with seats 3d Thu 05/06/08 Sat 07/06/08 PRAXAIR
266 Bonnet # 6 140 d Mon 03/09/07 Thu 21/02/08
267 Bonnet Forging 96 d Mon 03/09/07 Sat 22/12/07 FMA
268 Bonnet Pre-machining - VTL Ø2.0m 7d Wed 02/01/08 Thu 10/01/08 OMPG CIVIDINO TURNING 1
269 Weld Overlay 7d Sat 12/01/08 Sat 19/01/08 TigMig
270 PWHT 7d Tue 22/01/08 Tue 29/01/08 TRATER
271 Bonnet Machining - VTL Ø2.0m 8d Thu 31/01/08 Fri 08/02/08 OMPG CIVIDINO TURNING 1
272 Bonnet Machining - HBM Ø2.0m (bolt holes / pin drill) 5d Mon 11/02/08 Fri 15/02/08 OMPG CALCINATE BORING
273 NDE 4d Mon 18/02/08 Thu 21/02/08 OMPG CALCINATE
274 Seats # 6 192 d Mon 03/09/07 Tue 22/04/08
275 Seat Forging 83 d Mon 03/09/07 Fri 07/12/07 FORGITAL
276 Seat Machining 48 d Wed 27/02/08 Tue 22/04/08 GROVE
277 Stem # 6 150 d Tue 04/09/07 Wed 05/03/08
278 Stem Forging 76 d Tue 04/09/07 Fri 30/11/07 INOXFUCINE
279 Stem Machining 25 d Wed 06/02/08 Wed 05/03/08 SAB
280 Body casting #6 110 d Tue 13/11/07 Fri 28/03/08
281 Delivery 110 d Tue 13/11/07 Fri 28/03/08
282 Body Machining #6 84 d Mon 31/03/08 Tue 08/07/08
283 Body Pre-machining 1 - VTL Ø2.0m 6d Mon 31/03/08 Sat 05/04/08 OMPG CALCINATE TURNING 1
284 Body Pre-machining 2 - HBM Ø2.0m 4d Tue 08/04/08 Fri 11/04/08 OMPG CALCINATE BORING
285 Weld Overlay 41 d Mon 14/04/08 Mon 02/06/08 TIG MIG / ECOKIMICA
286 PWHT 6d Wed 04/06/08 Tue 10/06/08 TRATER
287 Body Machining 1 - VTL Ø2.0m (seat area) 9d Thu 12/06/08 Sat 21/06/08 OMPG CALCINATE TURNING 1
288 Body Machining 2 - VTL/HBM Ø2.0m (bnt/trn area) 3d Tue 24/06/08 Thu 26/06/08 OMPG CALCINATE TURNING 2
289 Body Machining 3 - HBM Ø2.0m (drill bnt flg) 5d Sat 28/06/08 Thu 03/07/08 OMPG CALCINATE BORING
290 Body Machining 4 - VTL Ø2.0m (finish seats) 3d Sat 05/07/08 Tue 08/07/08 OMPG CALCINATE TURNING 1
291 Final activities #6 68 d Wed 09/07/08 Thu 25/09/08
292 Continengency for scheduling final activities 39 d Wed 09/07/08 Fri 22/08/08
293 Assembly preparation 5d Sat 23/08/08 Thu 28/08/08 GROVE
294 Assembly 5d Fri 29/08/08 Wed 03/09/08 GROVE
295 F.A.T. 6d Fri 05/09/08 Thu 11/09/08 GROVE
296 Painting 5d Sat 13/09/08 Thu 18/09/08 GROVE
297 Marking / preservation 2d Sat 20/09/08 Mon 22/09/08 GROVE
298 Packing & EXW shipment 3d Tue 23/09/08 Thu 25/09/08