SP/SAP Computed by

Fuel Escalation Worksheet


.85 to 1.15 Ratio
NOTE: FCA = ((CFI/BFI) - 1.15) X Q X BFI
FCA = Fuel Cost Adjustment RATIO = Date
CFI* = Current Fuel Index, week work completed CFI =
BFI* = Base Fuel Index @ date of letting BFI =
Q = Weekly total gallons of fuel Q= 0.00
Fuel Escalation Provision- 12/19/2016
Mn/DOT: Fuel Escalation Index webpage FCA =

Item # Bid Item Description ** Unit Gallons Quantity of Gallons of


of Fuel Material Fuel Per
Per Unit Moved Material
Earthwork
2105 Common Excavation CY 0.17 0.00
2105 Rock Excavation CY 0.27 0.00
2105 Muck Excavation CY 0.17 0.00
2105 Subgrade Excavation CY 0.17 0.00
2105 Unclassified Excavation CY 0.23 0.00
2105 Granular Borrow (EV) CY 0.17 0.00
2105 Granular Borrow (CV) CY 0.19 0.00
2105 Granular Borrow (LV) CY 0.14 0.00
2105 Select Granular Borrow (EV) CY 0.17 0.00
2105 Select Granular Borrow (CV) CY 0.19 0.00
2105 Select Granular Borrow (LV) CY 0.14 0.00
2105 Common Borrow (EV) CY 0.17 0.00
2105 Common Borrow (CV) CY 0.19 0.00
2105 Common Borrow (LV) CY 0.14 0.00
2105 Topsoil Borrow (EV) CY 0.17 0.00
2105 Topsoil Borrow (CV) CY 0.19 0.00
2105 Topsoil Borrow (LV) CY 0.14 0.00
2106 Excavation - Common CY 0.17 0.00
2106 Excavation - Subgrade CY 0.17 0.00
2106 Excavation - Rock CY 0.27 0.00
2106 Excavation - Muck CY 0.17 0.00
2106 Common Embankment (CV) CY 0.19 0.00
2106 Granular Embankment (CV) CY 0.19 0.00
2106 Select Granular Embankment CY 0.19 0.00
2106 Select Granular Embankment Mod (__%) (CV) CY 0.19 0.00
Aggregate Base
2211 Aggregate Base Ton 0.55 0.00
2211 Aggregate Base (LV) CY 0.77 0.00
2211 Aggregate Base (CV) CY 0.99 0.00
2211 Open Graded Aggregate Base (CV) CY 0.99 0.00
Aggregate Shouldering
2221 Shoulder Base Aggregate, Class ___ Ton 0.55 0.00
2221 Shoulder Base Aggregate (LV), Class __ CY 0.77 0.00
2221 Shoulder Base Aggregate (CV), Class __ CY 0.99 0.00
Concrete Pavements Thickness
in inches
2301 Concrete Pavement ___ in SY 0.027 0.00
2301 Place Concrete Pavement ___ in SY 0.027 0.00
Bituminous Pavements Thickness
in inches
2360 Type SP( ) Wearing Course Mixture ( ) Ton 0.90 0.00
2360 Type SP( ) Non Wearing Course Mixture ( ) Ton 0.90 0.00
2360 Type ( ) Mixture ___ in thick SY 0.051 0.00
Pipe ***
2501 Pipe Culvert Lin. Ft. 0.70 0.00
2501 Pipe Arch Culvert Lin. Ft. 0.70 0.00
2501 Pipe Culvert Des 3006 Lin. Ft. 0.70 0.00
2503 Pipe Sewer Lin. Ft. 0.70 0.00
2503 Pipe Arch Sewer Lin. Ft. 0.70 0.00
2503 Pipe Sewer Des 3006 Culvert Lin. Ft. 0.70 0.00
Q= 0.00
NOTE: No price adjustments will be made on fuel used for drying and heating aggregates.
*= CFI and BFI values are reported in cents on the MnDOT Fuel Escalation pdf forms
** = Only items shown will be considered for compensation adjustments.
*** = No price adjustments will be made for pipes less than 12" in diameter,
jacked pipes or directionally drilled pipes

Form Instructions
1. Put applicable information into green boxes as follows.
2. Fill out Current Fuel Index (CFI) and Base Fuel Index (BFI) information near the top of the form
3. Fill in quantities of Material Moved for any items used.
4. Look at the Fuel Cost Adjustment value (FCA) in the yellow box at the top of the form for final value.
If the value is zero, there is no adjustment because the fuel calculation does not exceed the
less than 0.85 or more than 1.15 criteria for adjustment by specification.

You might also like