Professional Documents
Culture Documents
EPCC 1 - Critical Valves Writeup - 20200112
EPCC 1 - Critical Valves Writeup - 20200112
EPCC 1 - Critical Valves Writeup - 20200112
for
EPCC 1 – THARJATH OILFIELD
CONTRACT NO: SPOC/24/20-435
SPECS SPECS
Issued for
15/01/2021
review Tahir Amin Abdul Rehman
Lead Process
Project Manager
Engineer
REINSTATEMENT OF BLOCK 5A FACILITIES
EPCC 1 – THARJATH OILFIELD
The critical valves have been marked by following below mentioned criteria:
Safety Valves:
All PSVs, SDVs, NRVs and solenoid valves which are including in SOW EPCC-1
(1+1 arrangement), shall be considered as safety critical.
Isolation valves:
Main isolation valves of each equipment related to main process lines & critical
utilities for the operational and standby trains only shall be considered as safety
critical. Sampling points at OGMs are safety critical due to their frequent use.
Critical check valves have also been highlighted and needs to be inspected
FFS strategy:
There must be some FFS strategy which needs to be followed for the equipment &
related piping & fittings which had been affected by bush fire
Drain Valves:
Drain valves related to closed drain network has been highlighted in P&IDs in CPF
area which are directly connected to closed drain header related to SOW (EPCC-1,
1+1 arrangement) need to be considered as safety critical due to their importance
during any unforeseen/emergency situation.
Further, below 2” isolation valves connected to open & closed drain header which
were passing and not found good in visual inspection shall be replaced. However, 2”
REINSTATEMENT OF BLOCK 5A FACILITIES
EPCC 1 – THARJATH OILFIELD
and above passing drain valves shall be made operable after maintenance if possible,
otherwise replaced.
Pressure:
Although the system design pressure is 300# rating except export pipeline, some of
the valves are marked considering pressure critical service.
General Considerations:
Except critical valves, the rest of the valves should be check and maintenance
activities would be performed by following the below checks
I. Perform stroke test for SDVs which are marked on the P&IDs not included in
SOW EPCC-1 (1+1 reinstatement).
II. Visual inspection and maintenance must be done for all fittings and valves, if
there is any leakages or disturbance found need to be inspected 100 %.