Professional Documents
Culture Documents
Continous Cooling Uptime
Continous Cooling Uptime
Continous Cooling Uptime
Continuous Cooling
Uptime Institute is an unbiased advisory organization focused on improving the performance, efficiency, and availability
of business critical infrastructure through innovation, collaboration, and independent certifications.
Abstract
This technical paper clarifies the requirements for Continuous Cooling in the context of Uptime Institute’s Tier Standard:
Topology. Tier IV is the only Tier that requires Continuous Cooling. However, Uptime Institute recommends Continuous Cooling
at densities beyond 4 kilowatts (kW) per rack, regardless of the Tier level.
WWW.UPTIMEINSTITUTE.COM
Consideration must also be given to the time required to restore mechanical cooling. While
ASHRAE uses 15-minute periods to define the maximum allowed temperature changes,
A Continuous Cooling solution
the Tier Standard: Topology additionally requires that a Continuous Cooling solution is
must be capable of providing
capable of providing the stable thermal environment for the entire amount of time it takes
the stable thermal environment
for the mechanical cooling system to restart following any interruption of the cooling
for the entire amount of time
production or the loss of utility power. The mechanical system restart time is measured
it takes for the mechanical
from the moment of the loss of utility up until the engine generators (or other on-site power
cooling system to restart.
production systems) start and close into the critical load, when the mechanical system has
power restored, is in operation, and is providing rated cooling in a steady state operating
condition. For example, a chiller is not officially operational until it is restarted and running with normal supply and return water
conditions and flow rates.
Although manufacturers are reducing equipment restart times, the interval between the loss of power and a resumption of the
system’s ability to produce stable cooling needs to be incorporated as a data point in determining the ride-through time. For
example, if it takes 10 minutes to resume stable mechanical cooling after a loss of power, then the thermal energy storage (TES)
must be able to provide 10 minutes of chilled water storage.
Although Tier IV is the only Tier level that requires Continuous Cooling, data centers with higher than average IT load densities
should consider Continuous Cooling to mitigate large temperature increases due to a loss of utility power or component
failure. As a point of reference, Uptime Institute conducted a demonstration on a 6-kW/rack average computer room. Intake air
temperatures in the computer room exceeded the top value in this range within 60 seconds after a loss of cooling or even after
just loss of air movement. Additionally, this demonstration showed that a 1-minute loss of cooling required 20 minutes to recover.
Consider the scenario of a public utility failure during which the UPS continues to power
the IT devices, but mechanical plant operation is interrupted. Depending on the technology Continuous Cooling provides
of the cooling deployed, this interruption may continue for several minutes. During this the bridge to enable the thermal
time, any elevation in temperatures in the computer room may damage IT equipment. environment to remain stable
Continuous Cooling provides the bridge to enable the thermal environment to remain stable until the mechanical or other
until the mechanical or other cooling system resumes. A properly designed Continuous cooling system resumes.
Cooling solution will prevent any increase in the average server inlet air temperature.
WWW.UPTIMEINSTITUTE.COM
Example 4:
Continuous Cooling for 100% outside air systems that can provide cooling throughout the year require the fans (or the
system that delivers the air to the computer room) to be on Fault Tolerant UPS power sources.
When rotary UPS systems are deployed as the IT UPS, and the cooling systems are on a no-break bus, additional
Continuous Cooling measures may not be needed because the mechanical system would not experience an interruption
during a transfer from utility to engine-generator (or other on-site) power. If there is a chilled water system deployed in
tandem with a rotary UPS with no batteries, the site must demonstrate that the average server inlet temperature will not
increase beyond the limits stated previously if there is no TES installed.
Each specific case should be reviewed to ensure the requirement for a stable thermal environment will be met during a loss of
power event.
Conclusion
By providing thermal stability to the IT environment during any interruption in the cooling Continuous Cooling is a
system, such as the transition from utility outage to engine-generator power, Continuous justifiable safeguard for any
Cooling ensures that a utility event does not result in costly heat damage to IT hardware or facility with average densities
critical equipment, nor increase the UPS output load to the point of overload. Continuous above 4 kW in light of the
Cooling is a requirement only for Tier IV Certification, but is a justifiable safeguard for any potential damage to facilities
facility with average densities above 4 kW in light of the potential damage to facilities and and IT assets.
IT assets.
Modifications
ATD Technical Paper Series: Continuous Cooling. All updates specific to this version are
effective October 2017.
Related Publications
Tier Standard: Topology
Accredited Tier Designer Technical Paper Series
Further information can be found at www.uptimeinstitute.com.
Uptime Institute serves all stakeholders responsible for IT service availability through Uptime Institute is a division of The 451 Group, a leading
industry leading standards, education, peer-to-peer networking, consulting, and award technology industry analyst and data company. Uptime Institute
programs delivered to enterprise organizations and third-party operators, manufacturers, has office locations in the U.S., Mexico, Costa Rica, Brazil,
and providers. Uptime Institute is recognized globally for the creation and administration of U.K., Spain, U.A.E., Russia, Taiwan, Singapore, and Malaysia.
the Tier Standards & Certifications for Data Center Design, Construction, and Operational
© 2009-2021 Uptime Institute, LLC. All rights reserved.
Sustainability along with its Management & Operations reviews, FORCSS® methodology, and
Efficient IT Stamp of Approval. UITPCCEN211
WWW.UPTIMEINSTITUTE.COM