MEP SUMMARY

PROJECT: GYM
Mandatory Equipment’s & Materials items
MATERIAL
BILL SECTION QTY UNIT AMOUNT ONLY
AED

1 Mandatory Mechanical Items

DX Split 5 Item 14,000.00

Package Units 4 Item 144,200.00

Fans 5 Item 13,000.00

Booster Pump (1D +1S) 1 Item 17,000.00

Water Tank 1 Item 16,000.00

Electric Water Heater 1 Item 3,600.00

Sanitary Ware 1 Item 25,000.00

2 Mandatory Electrical Item

LV Panel 1 Item 38,100.00

Isolators 1 Item 8,237.45

Wiring Accessories(Floor Box etc…) 1 Item 34,998.25

Light Fittings 1 Item 55,636.00

Emergency Lights 1 Item 30,600.00

Structute Cabling System 1 Item 17,500.00

IPTV System 1 Item 8,800.00

BGM System 1 Item 49,100.00

TOTAL SUMMARY AED 475,771.70