Professional Documents
Culture Documents
Gantt Chart: A) Make A Gantt Chart of The Listed Activity
Gantt Chart: A) Make A Gantt Chart of The Listed Activity
Gantt Chart: A) Make A Gantt Chart of The Listed Activity
GANTT CHART
22-Oct-21 11-Dec-21 30-Jan-22 21-Mar-22 10-May-22 29-Jun-22 18-Aug-22 07-Oct-22
Design
Build Prototype
Evaluate equipment
Test prototype
Write Write
Write final Test Evaluate Build
methods equipment Design
report prototype equipment Prototype
report report
Start Date 23-Sep-22 29-Jul-22 24-Jun-22 10-Jun-22 22-Apr-22 18-Mar-22 22-Oct-21
Time to complete (days) 14 56 35 14 49 35 147
E2=E1+t1,2 [t1,2=A=21]=0+21=21
E3=E2+t2,3 [t2,3=B=5]=21+5=26
E4=Max{Ei+ti,4}[i=23,]
=Max{E2+t2,4;E3+t3,4}
=Max{21+7;26+2}
=Max{28;28}
=28
E5=E4+t4,5 [t4,5=E=5]=28+5=33
E6=Max{Ei+ti,6}[i=45,]
=Max{E4+t4,6;E5+t5,6}
=Max{28+8;33+0}
=Max{36;33}
=36
E7=E6+t6,7 [t6,7=G=2]=36+2=38
L6=L7-t6,7 [t6,7=G=2]=38-2=36
L5=L6-t5,6 [t5,6=d=0]=36-0=36
L4=Min{Lj-t4,j}[j=65,]
=Min{L6-t4,6;L5-t4,5}
=Min{36-8;36-5}
=Min{28;31}
=28
L3=L4-t3,4 [t3,4=D=2]=28-2=26
L2=Min{Lj-t2,j}[j=43,]
=Min{L4-t2,4;L3-t2,3}
=Min{28-7;26-5}
=Min{21;21}
=21
L1=L2-t1,2 [t1,2=A=21]=21-21=0
The critical path is shown in Figure 3 which has been done by double lines by joining all the events where
E-values and L-values are equal. The critical paths of the project are:
(1) 1-2-3-4-6-7 and critical activities: A, B, D, F, G
(2) 1-2-4-6-7 and critical activities: A, C, F, G
Figure 3. Network Diagram with Critical Path along with E-values and L-values