Marine

Engineering

ME091325
Maintenance Management

Work Book 7:
Planning and Scheduling
Course Instructor:
Dwi Priyanta
Department of Marine Engineering – ITS
8
EDUCATE – ENHANCE – EMPOWER
Rev. December 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

CONTENTS

1. The Nature of Maintenance Practice ......................................................................3


2. Planning – Scheduling – Coordination ....................................................................3
3. Planning and Scheduling : The Key Steps ................................................................4
4. Palnning Horizon .....................................................................................................5
5. Planning and Scheduling Tools................................................................................7
6. Planning and Scheduling Sequence ........................................................................7
7. Backlog Management Model ..................................................................................8
8. Case Study : Development of Maintenance Work Program ...................................9

The Icon

 Information icon; instruction icon

Text Book Icon – You are required to read your


text book or hand out materials before you fill
 out the blank text, to complete the graph or
others depend on the given instruction.
Pencil Icon – You are required to write down or
 to draw on your workbook.
Discussion Icon – You and your group members
 are required to discuss the given problems and
find the solutions.

© Dwi Priyanta Page 2 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

1. The Nature of Maintenance Practice

2. Planning – Scheduling – Coordination


Planning
  Planning is the development of a detailed program to achieve
an end.
 Insure job execution in the future.
 Detailed analysis:
Work type; Resources; Cost; Identify safety precaution;
Permits; Communication requirements; Reference
documents; Work measurement; Procurement etc.

Coordination
 Consists of the logistical efforts of assembling all necessary
resources so the job is ready to be scheduled.
 It is accomplished in harmony with Purchasing, Receiving, and
Stores.

© Dwi Priyanta Page 3 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

 Operations, Engineering, and Maintenance then review all jobs


ready to be executed and agree upon which are the most
important jobs to be performed the coming week – given the
limitation of available resources and feasibility of releasing
involved assets to maintenance.

Scheduling
 Scheduling is the written process whereby labor resources and
support equipment are allocated to specific jobs at a fixed time
when Operations can make the associated equipment or job
site accessible.
 Scheduling is the marketing arm of a successful maintenance
management installation because it yields the earliest benefits
visible to internal customers.

3. Planning and Scheduling : The Key Steps


 Effective maintenance work comes down to six key steps.
 The process starts with identifying what has to be done and
ends with analyzing why we had to do it in the first place.

© Dwi Priyanta Page 4 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

 Identify
Identify potential problems through regular inspection, FLM, and
routine checks.
 Plan
Ensure that all resources necessary to do the job are accounted for.
The most obvious planning tasks are to determine what has to be
done, in what sequence, and with what skills.
 Schedule
Scheduling is a matter of availability. When can you coordinate
with the people who have the needed skills? Do you have the
parts? Do you have agreement of production department to
release the equipment?
 Assign
The assignment of the job depend on the organization
arrangements in place.
 Execute
This is where ‘the rubber hits the road.’ Cost-effective maintenance
management can be measured from the execution of maintenance
planning.
 Analyze
Thoughtful analysis of the failure, and your respond to it, will
lessen the chance of repeating the same mistakes.

4. Palnning Horizon
 All types of fixed assets require at least three kinds of planning:
 Life cycle and long range plans
 Annual plan and budget
 Work orders and projects

© Dwi Priyanta Page 5 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

Life-Cycle and Long Range Plan


This type of planning is closely associated with strategic planning for
maintenance. The planning process involves creating a VISION of
future performance, including human financial, and physical
resources. It also includes action plans to achieve the vision.

Annual Plan and Budget


What’s needed in the annual maintenance budget and plan is clear-cut
– accurate equipment histories, periodic inspection, condition based
monitoring, and emphasis on continuous improvement. Plant
shutdowns, equipment overhauls, and major inspections should be
forecast by month, priced, and incorporated.

Work Order and Project


The use of work order:
1. Planning and scheduling mechanism for complex jobs.
2. Cost collection mechanism
3. Way to capture delays and measure productivity
4. Tool to determine and manage work backlogs
5. Means of saving equipment histories to analyze failure

© Dwi Priyanta Page 6 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

5. Planning and Scheduling Tools


Tools for planning and scheduling:
 The Gantt Chart
 The Critical Path Method
 The Pareto Diagram

6. Planning and Scheduling Sequence

© Dwi Priyanta Page 7 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

7. Backlog Management Model

Backlog
 The net workload, measured in labor hours, requested but not
yet completed.
Ready Backlog
 Jobs that are ready to go.
 All tools, parts, materials, drawings, and authorizations are in
hand.
Total backlog
 Includes ready backlog plus all other open work orders for
which something is missing.
 The job could be missing parts, authorization, budget, or
some element.

© Dwi Priyanta Page 8 of 10


EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

Discuss with your group following cases.


 1. What happened if maintenance workload is less than
maintenance resources?
2. What happened if maintenance workload is greater than
 maintenance resources?
3. What happened if maintenance workload is equal to
maintenance resources?

8. Case Study : Development of Maintenance Work


Program
The objective of maintenance work program development is to
reduce or to eliminate backlog that might be happened when an
organization managed its maintenance program.

To understand how to develop maintenance work program, you


and your group are required to solve the following case study.

A maintenance superintendent of a company has identified that the


backlog of his department is 4800 man-hours where 3200 hours of the
total backlog can be categorized as a ready backlog. You and your
team are assigned to develop “Maintenance Work Program” with the
objective to relieve the backlog. Based on the current situation, the
available man-hours per week for doing maintenance task is 800 man
hours.

Maintenance work program is usually documented in a spreadsheet.


To develop a maintenance work program spreadsheet model, the
following information should be taken into account.
a. Available resources (in man hours) that must be considered
such as straight time man-hour available per week, planned
overtime per week, man-hour contracted or borrowed per
week.
© Dwi Priyanta Page 9 of 10
EDUCATE – ENHANCE – EMPOWER Rev. Dec. 2015
ME091325 Work Book :8
Maintenance Management Planning and Scheduling

b. Less indirect commitment of maintenance personnel that may


reduce the maintenance activities such as lunch (if paid),
personnel in vacation, absence, training, meetings, special
assignments, Average Man-Hours Loaned to Other Areas, etc.
c. There is a possibility that the maintenance personnel must do
routine preventive or predictive maintenance, unscheduled /
emergency maintenance or other routine maintenance.
d. Other activities that might reduce man-hour other than
maintenance activities could be included in the models.

Now you and your team shall develop the maintenance work program.

© Dwi Priyanta Page 10 of 10