Professional Documents
Culture Documents
Pow - Street Light (Crossing-Tago)
Pow - Street Light (Crossing-Tago)
Project Title :
BACK-UP ESTIMATE
Concrete Works
Footing = 0.80 x 0.80 x 0.20 x 40 = 5.12
Pedistal = 0.38 x 0.38 x 1.08 x 40 = 6.16
1,825 x 0.10 x 0.50 = 91.25 plant box base
1,825 x 0.07 x 0.60 x 2 = 153.30 plant box
Center Island =
1,825 x 0.07 x 0.15 x 2 = 38.33 plant box
0.32 x 0.10 x 0.60 x 18 = 0.35 upper plant box
294.50 cu.m
RSB
use 1pc 16mmØ x 6m for 1 Footing
1 x 40 = 40 pcs (16mmØ x 6m)
Center Island
1,825 / 0.6 = 3,042
3,042 x 0.7 = 2,129
2,129 / 6 = 355
355 x 2 = 710 pcs (9mmØ x 6m) Vertical Bars
156
1,945.45
PROPOSED CENTER ISLAND WITH STREET LIGHT FROM TAGO TO LAPAZ
Project Title :
BACK-UP ESTIMATE
Center Island
1,795.45 / 0.6 = 2,992
2,992 x 0.7 = 2,095
2,095 / 6 = 349
349 x 2 = 698 pcs (9mmØ x 6m) Vertical Bars
140.19075
7
REPUBLIC OF THE PHILIPPINES
MUNICIPALITY OF TAGO
PROVINCE OF SURIGAO DEL SUR
PROGRAM OF WORK
(5) Name/(6)Location of Project: (7) Source of Funds : (8) Issued (9) Released
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA
TO PURISIMA ROAD SECTION W/ CENTER ISLAND
GENERAL FUNDS
I. GENERAL REQUIREMENTS
A.1.1(7) Temporary Facility 0.67% month 5.00 5,124.00 25,620.00
B.5 Project Billboard / Signboard 0.14% sq.ft. 32.00 162.65 5,204.66
B.9 Mobilization / Demobilization 0.71% ls 1.00 26,877.18 26,877.18
SUB TOTAL I 57,701.84
II. EARTHWORKS/SITE WORKS
101(3) Removal Of Existing Pavement 2.45% ls 1.00 93,106.59 93,106.59
103(1)a Structure Excavation (Common Soil) 0.27% cu.m 6.48 659.67 4,274.67
SUB TOTAL II 97,381.26
III. CONCRETE WORKS
900(1)c1 Structural Concrete (Class "B", 28 days) 41.78% cu.m. 289.92 5,476.04 1,587,592.66
SUB TOTAL III 1,587,592.66
IV. REINFORCING STEEL BAR
902 (1)a1 Reinforcing Steel (Deformed) Grade 40 11.60% kgs 5,362.36 82.18 440,682.98
SUB TOTAL IV 440,682.98
V FORMS & FALSEWORKS
903(1) Formworks 0.52% ls 1.00 19,916.05 19,916.05
SUB TOTAL V 19,916.05
VI ELECTRICAL WORKS
1100 Conduits, Boxes and Fittings 8.07% lot 1.00 306,781.89 306,781.89
1101(1) Wires and Cables 5.38% lot 1.00 204,553.28 204,553.28
1101(2) Switches and Convenience Outlets 0.72% lot 1.00 27,210.26 27,210.26
1101(3) Lighting Fixtures and Lamps 14.03% ls 1.00 533,036.76 533,036.76
624 Street Light Post Double Arm Galvanized 13.82% ls 1.00 525,143.02 525,143.02
SUB TOTAL VI 1,596,725.21
PROGRAM OF WORK
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD
SECTION W/ CENTER ISLAND
2. L a b o r 14.04% 533,573.81
2.1 Direct Cost
2.2 Leaves
2.3 Medicare
2.4 State Insurance
3. Equipment Expenses 6.11% 232,168.76
C. INDIRECT COST:
1. Overhead Expenses, Contingency, Miscellaneous (12%) 9.23% 350,566.57
2. Profit (10%) 7.69% 292,138.81
3 Value Added Tax (VAT, 5% of (EDC+Mark-up)) 4.69% 178,204.67
CONTRACT COST 100.00% 3,800,000.00
(16) II. ESTIMATED EXPENSES
1. POW/Site Acquisition
2. Soil Exploration
-
-
-
-
SUB-TOTAL (A) -
QUANTITY
B. LABOR COST Hourly Rate Total Cost
No. Personnel Total Hours
SUB-TOTAL ( C ) 22,592.00
D. TOTAL DIRECT COST (A + B + C) 25,597.31
E. ADD: INDIRECT COST
OCM ( 0% ) -
Contractors Profit ( 0% ) -
VAT ( 5% ) 1,279.87
TOTAL INDIRECT COST 1,279.87
TOTAL COST ( D + E ) 26,877.18
SUB-TOTAL (A) -
QUANTITY
B. LABOR COST Hourly Rate Total Cost
No. Personnel Total Hours
SUB-TOTAL ( C ) 1,339.04
D. TOTAL DIRECT COST (A + B + C) 3,336.98
SUB-TOTAL ( C ) 46,440.00
D. TOTAL DIRECT COST (A + B + C) 1,239,338.53
5,362.36
SUB-TOTAL (A) 248,919.56
QUANTITY
B. LABOR COST Hourly Rate Total Cost
No. Personnel Total Hours
SUB-TOTAL ( C ) 21,975.00
D. TOTAL DIRECT COST (A + B + C) 344,014.82
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 15,547.27
182.00
SUB-TOTAL (A) 237,689.76
QUANTITY Hourly Rate Total Cost
B. LABOR COST
No. Personnel Total Hours
SUB-TOTAL ( C ) 100,638.72
D. TOTAL DIRECT COST (A + B + C) 409,947.71
NOTE:
Updated labor rates provided by DOLE region with fringe benefits and additional COLA effective October 2016.
L03 Heavy Equipment Operator 1.73 484.40 12,594.40 201.83 1,049.53 822.70 100.00 137.50 10.00 14,915.97 573.69 71.71
Monthly wages based on 313.25 days per year at 8 hours per day
Leave (vacation and sick) = Basic Daily Wage x 5 /12
HOURLY DAILY
BARE OPERATED
EQUIPMENT DESCRIPTION
RENTAL RENTAL
(Pesos) (Pesos)
w/Fuel +
Operator&h
I. EARTHWORKS elper @ 8-
hrs.
BULLDOZER Komatsu D65E-8/155 Hp. 3,379.00 27,032.00
ROAD ROLLER,VIBRATOR Bomag BW 151AC-2 1,846.00 14,768.00
ROAD ROLLER,PNEUMATIC TIRE/STATIC W251D 553.00 4,424.00
PAYLOADER (Wheel-type) TCM/Clark 835-2 1,733.00 13,864.00
ROAD GRADER 140Hp/G710A 2,173.00 17,384.00
BACKHOE SE 130 LC-2,0.28 cu.m. 1,537.00 12,296.00
BACKHOE , WHEEL TYPE PW60N-1,0.28 cu.m. 922.00 7,376.00
BACKHOE (Breaker) Catterpilar (all model) 1,998.10 15,984.00
DUMPTRUCK (All Model) Japan 10-11 cu.m. 1,420.00 11,360.00
PLATE COMPACTOR(W=500mm) Single Smooth rum,SD 100dc 10 123.00 984.00
WATER TRUCKS 16000L 2,450.00 19,600.00
Crawler Crane 36-40T 1,902.00 15,216.00
II. CONCRETE STRUCTURES
TRANSIT MIXER Japan 5-6 cu.m.(All Model) 1,318.00 10,544.00
CONC. BATCHING PLANT 30.60cu.m./hr with SILO 1,759.50 14,076.00
CONC. SCREEDER 610-762mm;4 blades 545.00 4,360.00
CONC. SAW/CUTTER Cut depth 6-3/4"W/BLADE 14" 167.38 1,339.00
III. STRUCTURES
1 BAGGER-CONC. MIXER 25-36cu.ft./min 172.00 1,376.00
1.5-2 BAGGER-CONC. MIXER 190.00 1,520.00
CONC. VIBRATOR 5 hp Gasoline Drive Unit w/2" Shaft 91.25 730.00
A. Speed of Dumptruck
a. When empty = 55.00 kph
b. When loaded = 35.00 kph
c. Empty running time = 76.36 mins
d. Loaded running time = 120.00 mins
e. Loading & unloading time = 15.00 mins
f. Delay Allowance = 21.14 mins
B. Total Time/Trip = 232.50 mins
C. No. of Trips/Day = 2.06 trips
D. Capacity of Dumptruck = 10.00 cu.m.
E. Output of Dumptruck/Day = 20.65 cu.m.
F. No of Days for 1 Dumptruck = 601.76 say 602.00 days
Balance Fleet
1.00 Unit Payloader
2.00 Units Dumptruck
I. DIRECT COST
A.) Materials Cost
12423.38 cu.m. Coarse Aggregates @ P 140.00 = P 1,739,273.38
Total Materials Cost = P 1,739,273.38
A. Speed of Dumptruck
a. When empty = 55.00 kph
b. When loaded = 35.00 kph
c. Empty running time = 76.36 mins
d. Loaded running time = 120.00 mins
e. Loading & unloading time = 15.00 mins
f. Delay Allowance = 21.14 mins
B. Total Time/Trip = 232.50 mins
C. No. of Trips/Day = 2.06 trips
D. Capacity of Dumptruck = 10.00 cu.m.
E. Output of Dumptruck/Day = 20.65 cu.m.
F. No of Days for 1 Dumptruck = 350.59 say 351.00 days
Balance Fleet
1.00 Unit Payloader
2.00 Units Dumptruck
I. DIRECT COST
A.) Materials Cost
7237.98 cu.m. Fine Aggregates @ P 120.00 = P 868,558.09
Total Materials Cost = P 868,558.09
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 97,402.00
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 298,188.82
PERT-CPM
= CRITICAL PATH
Electrical = PATH
Plumbing Works 45 = DUMMY
Works
Concrete 45 Carpentry & joinery
Works Works
Floor 10
start 24 Finishes end
7
Earth Reinforcing Steel Roofing Painting 10
1 works
2 Steel bars 3 4 Works
5 Works
6 7 works
7 14 10
14 7
Formwork & Masonry Ceiling & Wall
Falseworks works Finishes
20 14
15
ITEM DISCRIPTION OF WORKS MATERIAL COST LABOR COST EQUIPMENT COST OCM & PROFIT VAT PROJECT COST W% 1st MONTH 2nd MONTH 3rd MONTH
I. GENERAL REQUIREMENTS Err:509 747.97 0.00 - - Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
II. EARTHWORKS/SITE WORKS Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
III. CONCRETE WORKS 919,741.88 273,156.65 46,440.00 272,654.48 75,599.65 1,587,592.66 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
IV. REINFORCING STEEL BAR 248,919.56 73,120.26 21,975.00 75,683.26 20,984.90 440,682.98 Err:509 Err:509 Err:509 Err:509 Err:509
V FORMS & FALSEWORKS 12,053.39 3,493.88 0.00 3,420.40 948.38 19,916.05 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
VI Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
VII Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
VIII Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
IX Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509
X Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### Err:509
A Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
B Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
### Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509 Err:509
Structural Steel Framing including cross bracings, purlins, kg 1.000 52.00 52.00
anchorbolts, and incidentals to complete
consumables (5% of material cost)
SUB-TOTAL A 52.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 782.00
D. TOTAL D (B + C) 983.99
E. Output per hour 69.360 kgs/hr
F. UNIT COST ( B + C)/E 14.19
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,066.19
H. OCM ( 9%) 5.96
I. Contractors Profit (8%) 5.29
J. 5%VAT 3.87
K. TOTAL INDIRECT COST 15.12
L. TOTAL UNIT COST Php 0,081.31
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 1,486.65
D. TOTAL D (B + C) 1,688.64
E. Output per hour 137.500 kgs/hr
F. UNIT COST ( B + C)/E 12.28
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,012.28
H. OCM ( 9%) 1.11
I. Contractors Profit (8%) 0.98
J. 5%VAT 0.72
K. TOTAL INDIRECT COST 2.81
L. TOTAL UNIT COST Php 0,015.09
SUMMARY OF QUANTITIES & SCOPE OF WORK
III. EARTHWORKS
A. Concrete:
1. Footings/Columns/Beams/Suspended Slabs
Structural Concrete (Class "A", 28 days) m3 500.81
3. 2.4 Formworks ls 1
VII. CARPENTRY & JOINERY WORKS'!D4:E4 ls 1
A. Floor Finishes
1. (FL-1) 600 x 600mm Unpolished Synthetic Granite Tile Floor Fin. m2 795
2. (FL-2): 600 x 600mm Textured Ceramic Tile m2 120
3. (FL-3): Wood Parquet Floor Fin. m2 126
4. (FL-4): 200 200mm Vitrified Unglazed Tiles Floor m2 54
5. (FL-5): 300 x 300mm Vinyl Tiles Floor Fin. m2 33
6. (FL-6): Non-Skid Cement Floor Fin. With 6mm wide Groove Lines m2 8
7. (FL-7): Plain Cement Floor Fin. m2 29
(Provide Water Base Waterproofing)
B. Wall/Column Finishes:
1. 200 x 300mm Vitrified Glazed Tiles Wall Fin. m2 58
2. Plain Cement Plaster Fin. m2 3,106
3. Aluminum Metal Cladding m2 1,060
C. Ceiling Finishes:
1. (CL-1): 4.50mm THK. Fiber Cement Ceiling Board with Drop Ceiling m2 1040
2. (CL-2): 4.50mm THK. Fiber Cement Ceiling Board with 150mm Wide Reces m2 692
3. (CL-2A): 4.50mm THK. Fiber Cement Ceiling Board m2 171
4. (CL-3): Exposed R.C Under slabs with Plain cement Plaster Fin. m2 45
5. (CL-4): Aluminum Metal Cladding m2 155
6. (CL-4A): Aluminum Metal Cladding/Ceiling Panels On Metal Furrings m2 26
D. Miscellaneous:
1. Steel Pipes 150mmØ x 7.30m (Including Bolts & Steel Plates anchorage) set 96
2. Fire Escape set 2.1
3. Tubular Horizontal Grilles at Accu Ledge set 4
4. Stair Nosing, 6mm thk. Non-skid Metal Nosing Strip l.m. 75
5. Stainless Railing at Ramp l.m. 36
6. Stair Railing, 50mmØ G.I. Pipe Handrail & 19mm Square Bar Railing (0.90 l.m. 36
7. 38mmØ Stainless Steel L-Type Fixed Grab Rail (at toilet) pcs 2
8. 38mmØ Stainless Steel Movable Grab Bar (at toilet) pcs 2
9. 12 mm thk. Laminated Compact Board Urinal Partition 400 x 900 mm pcs 6
10. Tilted Facial Mirror (at toilet for PWD) pcs
11. Facial Mirror 1400 x 600 mm (at toilet for women) sq.m. 1.54
12. 12 mm thk. Laminated Compact Bd./Phenolic Cubicle Partition sq.m. 1.6
13. RC Counter with Polished Pure/Natural Granite Slab Counter Top Finish pcs 4
14. 50 x 100 mm Decorative Tubular Steel Horizontal Grilles l.m. 90
B. Water Lines
1. 50 mm Ø PPRC Pipe pcs 26
2. 32 mm Ø PPRC Pipe pcs 16
3. 20 mm Ø PPRC Pipe pcs 18
4. 20 mm 90° Elbow pcs 24
5. 32 mm 90° Elbow pcs 18
6. 50 mm 90° Elbow pcs 10
7. 20 mm x 32 mm Reducer Elbow pcs 5
8. 32 mm x 50 mm Reducer Elbow pcs 3
9. 20 mm Female Elbow pcs 40
10. 20 mm Plain Tee pcs 11
11. 50 mm Plain Tee pcs 5
12. 50 mm x 32 mm x 50 mm Tee Reducer pcs 3
13. 50 mm x 20 mm x 50 mm Tee Reducer pcs 5
14. 32 mm x 50 mm x 32 mm Tee Reducer pcs 4
15. 32 mm x 20 mm x 32 mm Tee Reducer pcs 28
16. 20 mm x 50 mm x 20 mm Tee Reducer pcs 3
17. 50 mm Coupling pcs 19
18. 32 mm Coupling pcs 4
19. 20 mm Coupling pcs 3
20. 20 mm x 32 mm Coupling Reducer pcs 4
E. Catch Basin
1. CB-1 unit 13
2. CB-2 unit 2
XIV. ELECTRICAL WORKS
E. PANELBOARDS
1. MAIN DISTRIBUTION PANELBOARD "MDP"
Main Circuit Breaker Rating: set 1
800 Af, 800at, 3p, 240v Bolt-On Type Circuit Breaker In
Nema-1 Enclosure
BRANCHES:
2- 100 AF, 100 AT, 3P, 240 V
2- 225 AF, 150 AT, 3P, 240V
2- 400 AF, 250 AT, 3P, 240 V
BRANCHES:
21- 50 AF, 20 AT, 2P, 240 V
3 - 50 AF, 30 AT, 2P, 240V
BRANCHES:
21- 50 AF, 20 AT, 2P, 240 V
3 - 50 AF, 30 AT, 2P, 240V
BRANCHES:
1- 50 AF, 20 AT, 2P, 240 V
5 - 50 AF, 30 AT, 2P, 240V
3 - 100 AF, 60 AT, 2P, 240V
BRANCHES:
6- 50 AF, 30 AT, 2P, 240 V
2 -100 AF, 100 AT, 3P, 240V
2 - 225 AF,125 AT, 3P, 240V
BRANCHES:
3- 50 AF, 30 AT, 2P, 240 V
3 -100 AF, 60 AT, 2P, 240V
7. POWER PANELBOARD - DATA CENTER "DPS" (SECOND FLOOR)
Main Circuit Breaker Rating: set 1
400 AF, 250AT, 3P, 240V Bolt-On Type Circuit Breaker In
Nema-1 Enclosure
BRANCHES:
6- 100 AF, 60 AT, 2P, 240 V
1 -100 AF, 70 AT, 2P, 240V
1 -100 AF, 100 AT, 2P, 240V
A. Airconditioning System
1. FCU-5 Fan coil Unit (FM), 14KW (47,782Btu/hr.)Indoor unit, unit 4
5 Hp. 230V, 1Ø 60 Hz. with remote control.
2. FCU-4 Fan coil Unit (FM),11.2KW (38,226 Btu/hr.) Indoor unit, unit 5
4 Hp. 230V, 1Ø 60 Hz,with remote control.
3. FCU-4 Fan coil Unit (CS) 11.2KW (38,728Btu/hr) Indoor Unit, unit 1
4 Hp. 230 v,1Ø,60Hz. with remote control.
4. FCU-3 Fan coil Unit (CS) with a capacity not less than 9Kw unit 1
(30,717Btu3Hp, 230V,1Ø,60hz.
with remote control
5. FCU-3 Fan coil Unit (FM), 8KW (27,304 Btu/hr) Indoor Unit, unit 7
3 Hp. 230V, !Ø 60 Hz,with remote control.
6. FCU-2 Fan coil Unit (WM) 4.5KW (19,113 Btu/hr.) Indoor unit, unit 2
2Hp, 230V,1Ø,60hz. with remote control
7. FCU-1.7 Fan coil Unit (WM) 4.5KW (15,358 Btu/hr.) Indoor unit unit 1
1.7Hp, 230V,1Ø,60hz.with remote control
B. Miscellaneous
1. Other complete all accessories needed for installation lot 1
includes fittings,insulation,drain pipe lines,platform
brackets/hangers,refrigerant (freon 410A) and elec-
trcal wires and conduits and etc. to make the
system operational ready for service.
2. SP-3 Split type Package unit complete with Air condensing unit 1
cooling unit (ACCU), (36,000 Btu/hr./37,980Kj/hr.)220V,
1Ø,60Hz.and all other accessories needed for installation
includes copper tubing, fittings,installation,drain pipe
line,platform,brackets/hangers,refrigerant and electrical
wires and etc. to make the system operational ready
for service.
Approved:
Err:509
Volume = 423.32 - 172.43 = 250.89
Embankment
Volume = 0.40 15.00 35.00 = 210.00 cu.m.
Soil Poisoning
Volume = 15.00 35.00 = 525.00 sq.m.
Gravel fill
Slab
(ground)
Volume = 0.10 15.00 35.00 = 52.50 cu.m.
Tie beam Volume = 0.10 0.50 260.00 = 13.00 cu.m.
Footing Volume = 0.10 177.12 = 17.71 cu.m.
Ports,
Ramp,
Corridor Volume = 0.10 3.00 35.00 = 10.50 cu.m.
(front &
Back)
93.71 cu.m.
Grade 60 33,323.55
Grade 40 24,071.08
CONCRETE RSB 16mm
Total Total
Footing length # of bar
length
unit wt.
weigth
Ties
F-1 Volume = 2.20 2.20 0.35 = 10.00 set = 16.94 2.20 448.00 28.00 = 1,064.0 1.58 1,679.35
F-2 Volume = 2.40 2.40 0.40 = 18.00 set = 41.47 2.40 604.80 34.00 = 2,073.6 1.58 3,272.83
F-2a Volume = 2.40 2.40 0.40 = 2.00 set = 4.61 2.40 67.20 34.00 230.4 1.58 363.65
F-3 Volume = 2.60 2.60 0.40 = 2.00 set = 5.41 2.60 44.80 36.00 232.0 1.58 366.17
16mm = 5,682.00
RSB
Total Total
length 2nd floor Splice # of bar unit wt.
Column length weigth
C-1 Volume = 0.45 0.45 9.50 = 18.00 set = 34.63 cu.m. 9.90 8.00 8.00 2,577.60 2.47 6,358.08
C-2 Volume = 0.45 0.45 9.50 = 2.00 set = 3.85 cu.m. 9.90 8.00 8.00 286.40 2.47 706.45
C-3 Volume = 0.50 0.75 9.50 = 2.00 set = 7.13 cu.m. 4.20 3.50 26.00 14.00 12.00 506.80 2.47 1,250.11
C-4 Volume = 0.45 0.45 9.50 = 10.00 set = 19.24 cu.m. 9.90 8.00 8.00 1,432.00 2.47 3,532.27
64.84 cu.m. Main bar 20mm = 11,846.91
Ties 10mm = 7,057.75
Total Total
length Splice # of bar unit wt. Ties
Beam 2nd length weigth
2B-1 Volume = 0.25 0.40 70.00 = 7.00 cu.m. 70.00 11.00 7.00 567.00 2.47 1,398.60 691.65
2B-2 Volume = 0.25 0.40 70.00 = 7.00 cu.m. 70.00 11.00 6.00 486.00 2.47 1,198.80 691.65
2B-3 Volume = 0.25 0.40 100.00 = 10.00 cu.m. 100.00 16.00 12.00 1,392.00 2.47 3,433.60 987.65
2B-4 Volume = 0.25 0.40 30.00 = 3.00 cu.m. 30.00 4.00 6.00 204.00 2.47 503.20 296.99
2B-5 Volume = 0.20 0.35 6.25 = 0.44 cu.m. 6.25 0.00 5.00 31.25 2.47 77.08 62.65
2B-6 Volume = 0.15 0.35 2.35 = 0.12 cu.m. 2.35 0.00 5.00 11.75 2.47 28.98 24.17
2B-7 Volume = 0.25 0.40 6.20 = 0.62 cu.m. 6.20 0.00 5.00 31.00 2.47 76.47 62.16
EB-1 Volume = 0.15 0.35 6.50 = 0.34 cu.m. 6.50 0.00 5.00 32.50 2.47 160.33 130.24
EB-2 Volume = 0.15 0.35 17.20 = 0.90 cu.m. 17.20 2.00 6.00 115.20 2.47 568.32 341.39
2CB-1 Volume = 0.25 0.40 10.65 = 1.07 cu.m. 10.65 1.00 7.00 81.55 2.47 402.31 212.13
2CB-2 Volume = 0.25 0.40 15.40 = 1.54 cu.m. 15.40 2.00 8.00 139.20 2.47 686.72 305.87
28.52 cu.m. Main bar 20mm = 8,534.42
Slab 2nd Ties 10mm = 3,806.56
Volume = 0.14 15.00 35.00 = 70.88 cu.m. 2S-1 12.00 unit
Total
unit wt.
L W Total weigth weigth
6.25 5.00
128.00 102.00 = 2,760.00 0.89 2,451.80
2S-2 7.00 unit
2.50 5.00
52.00 102.00 = 1,078.00 0.89 957.62
2S-3 4.00 unit
2.00 5.00
42.00 102.00 = 576.00 0.89 511.68
2S-4 6.00 unit
2.80 1.70
29.00 18.00 = 282.00 0.89 250.51
2S-5 2.00 unit
0.85 6.80
10.00 69.00 = 158.00 0.89 140.36
12mm bar 4,311.97
Total Total
unit wt.
L W weigth weigth
Slab on fill 15.00 35.00
Volume = 0.10 15.00 35.00 = 52.50 cu.m. 44.00 351.00 = 395.00 0.62 243.58
Volume = 0.10 4.35 4.60 = 2.00 cu.m. 4.35 4.60
Volume = 0.10 1.20 6.45 = 0.77 cu.m. 13.00 47.00 = 60.00 0.62 37.00
Volume = 0.10 1.50 4.60 = 0.69 cu.m. 1.20 6.45
55.97 cu.m. 4.00 66.00 = 70.00 0.62 43.17
1.50 4.60
5.00 47.00 = 52.00 0.62 32.07
Ties 10mm = 355.82
Total Total
unit wt.
Stair L W weigth weigth
Volume = 0.15 2.50 7.70 = 2.89 cu.m. 2.50 7.70
Volume = 0.15 1.40 5.00 = 1.05 cu.m. 16.00 156.00 = 172.00 0.89 152.79
3.94 cu.m. 1.40 5.00
Parapet & Conc. Gutter 10.00 102.00 = 112.00 0.89 99.49
Volume = 0.15 1.20 100.00 = 18.00 cu.m.
Volume = 0.10 0.60 70.00 = 4.20 cu.m. 1.20 100.00
22.20 cu.m. 4.00 1,001.00 = 1,005.00 0.89 892.78
Ties
3,996.00
444.00
397.75
2,220.00
Legend Description QUANTITY Dimension
Excavation 803(1)a
Beams 2 1 0.25
SF Slab on Fill 1 35 15
1 5 4.1
1 2.775 2.3
1 2.45 1.7
2S1 RC Slab 12 6.25 5
2S2 RC Slab 7 5 2.5
2S3 RC Slab 2 3.5 2
RC Slab 2 1.775 1.425
2S4 RC Slab 2 2.8 1.2
RC Slab 1 4.375 2.45
RC Slab 1 2.125 1.2
RC Slab 2 1.4 2.8
2S5 RC Slab 1 4.025 1.25
RC Slab 1 3.875 1.375
RC Slab 1 5 1.25
Catch Basin 13
2
TOTAL 451.90
Backfill 804(1)a 804(4) Embankment Concrete 900(1)c1
mm dia
1.55 75.02 0.1 4.84 0.35 16.94 16
1.50 155.52 0.1 10.37 0.4 41.47 16
1.50 19.44 0.1 1.3 0.4 5.18 16
1.45 19.6 0.1 1.35 0.45 6.08 16
Height
9.25 33.72 20
Removal of Structures and Obstruction
Structure Excavation 9.2 3.73 20
Embankment ( from structure excavation)
Embankment (from borrow) 5.7 4.28 20
Gravel Fill
3.5 2.63 20
9.15 18.53 20
5.7 1.28 12
5.7 2.99 12
5.7 0.86 12
5.7 0.68 10
0.4 7.00 20
20
0.4 7.00 20
20
20
0.4 10.00 20
20
20
0.4 1.00 20
0.4 2.00 20
0.4 0.73 20
20
20
0.4 0.18 20
20
20
0.4 0.40 20
20
20
0.4 0.20 20
20
20
0.4 0.67 20
20
20
0.4 1.40 20
20
20
0.4 0.25 20
0.4 0.36 20
0.4 1.44 20
0.4 0.25 20
0.4 0.18 20
0.4 0.36 20
0.4 0.65 20
0.4 16.80 20
20
20
0.4 4.50 20
20
20
0.4 2.40 20
20
20
0.4 4.50 20
20
20
0.4 3.00 20
20
20
0.8 8.40 20
12
0.4 0.71 20
0.4 0.29 20
0.4 0.21 20
0.4 0.47 20
0.4 0.26 20
0.3 0.35 20
0.3 0.36 20
0.45 0.52 20
26.09
2.24
2.29
4.27
0.135 50.63 12
0.135 11.81 12
0.135 1.89 12
0.135 0.68 12
0.135 0.91 12
0.135 1.45 12
0.135 0.34 12
0.135 1.06 12
0.135 0.68 12
0.135 0.72 12
0.135 0.84 12
2.29
4.27
8.24
3.54
0.816
8 12 2 32
14 7.3 1.5 42
12 4.7 1 24
8 10.75 2 160
3 42 24 24
3 39.25 21 21
4 18.6 12 12
1499
350
56
21
27
43
11
32
21
22
25
Ties
GF = 7.5 m
SF = 5.54 m
10 1.8 1 -50; 6-100; 5 - 150 rest @ 250 1332 3
10 1.27 1 -50; 6-100; 5 - 150 rest @ 250 1332 4
10 1.8 1 -50; 6-100; 5 - 150 rest @ 250 148 3
10 1.2 1 -50; 6-100; 5 - 150 rest @ 250 296 5
10 2.5 1 -50; 6-100; 5 - 150 rest @ 250 78 2
10 1.75 1 -50; 6-100; 5 - 150 rest @ 250 78 3
10 2 1 -50; 6-100; 5 - 150 rest @ 250 78 3
10 2.5 1 -50; 6-100; 5 - 150 rest @ 250 58 2
10 1.75 1 -50; 6-100; 5 - 150 rest @ 250 58 3
10 2 1 -50; 6-100; 5 - 150 rest @ 250 58 3
10 1.8 1 -50; 6-100; 5 - 150 rest @ 250 740 3
10 1.27 1 -50; 6-100; 5 - 150 rest @ 250 740 4
27 16.8 27
75 56 75
10 24 10
9 21 9
7 12 7
129.5 84 129.5
24
129.5 56 129.5
24
14
180 128 180
64
38.4
20 10.8 20
50 24 50
17 8 17
6
10
5 1.6 5
2
1
11 3.2 11
4
2
7 1.6 7
2
2
16 5.6 16
6
2
34 12 34
10
5
15 2 15
13 3 13
51 12 51
15 2 15
8 2 8
11 3 11
15 6 15
259 112 259
28
28
68 28.8 68
6
3.6
50 16 50
3.2
1.6
68 28.8 68
6
3.6
45 19.2 45
4
2.4
173 84 173
56
19 7.2 19
10 3.6 10
13 2.4 13
23 3.6 23
9 2.4 9
7 5.6 7
9 3.2 9
9 4.8 9
252 252
20 36
56 394.4
547 298.48 5837.12
22
8
6
1499
350
56
21
27
43
11
32
21
22
25
19 21
37 41
1499
350
56
21
27
43
11
32
21
22
25
19 21
37 41
85 10
110.5
22
31,802.69 Grade 60
41,813.03 Grade 40
737
2726.9
UNIT PRICE ANALYSIS
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD SECTION W/ CEN
JOB :
Item No. / Description : Err:509 Err:509
Quantity (exterior) 583.54 m2
Quantity(interior) : 3,595.47 m2
Total Area : 4,179.01 m2
A) MATERIALS: COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
Exterior
Concrete Neutralizer gal 28.00 740.00 20,720.00
Acrytext Primer gal 29.00 900.00 26,100.00
Acrytext Semi Gloss gal 58.00 980.00 56,840.00
Acrytext Reducer gal 15.00 600.00 9,000.00
Tinting Color can 15.00 200.00 3,000.00
Acrytex Cast gal. 15.00 750.00 11,250.00
Paint brush pc 10.00 65.00 650.00
Paint roller set 10.00 160.00 1,600.00
Sand Paper m 34.00 250.00 8,500.00
Interior
Concrete Neutralizer gal 171.00 740.00 126,540.00
Flat Latext gal 180.00 900.00 162,000.00
Semi Gloss Latex gal 360.00 980.00 352,800.00
Tinting Color can 90.00 120.00 10,800.00
Body Filler gal. 90.00 750.00 67,500.00
Paint brush pc 10.00 65.00 650.00
Paint roller set 10.00 160.00 1,600.00
Sand Paper m 34.00 250.00 8,500.00
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 1,140,504.00
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD SECTION W/ CENTER ISLAND
V STEEL WORKS
As Evaluated
902 (1)a1 Reinforcing Steel (Deformed) Grade 40
As Submitted 5,362.36 kg 344,014.82 12.0% 8.00% 20.00% 68,802.96 20,640.89 89,443.85 433,458.67 80.83
As Evaluated
TOTAL OF PART VI
As Submitted 344,014.82 68,802.96 20,640.89 89,443.85 433,458.67
VI FORMS AND FALSEWORKS
As Evaluated
903(1) Formworks
As Submitted 1.00 ls 15,547.27 12.0% 8.00% 20.00% 3,109.45 932.84 4,042.29 19,589.56 19,589.56
As Evaluated
TOTAL OF PART XII
As Submitted 15,547.27 3,109.45 932.84 4,042.29 19,589.56
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted 1.00 Err:509 274,441.50 12.0% 8.00% 20.00% 54,888.30 16,466.49 71,354.79 345,796.29 345,796.29
As Evaluated
TOTAL OF PART XII
As Submitted 274,441.50 54,888.30 16,466.49 71,354.79 345,796.29
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 298,188.82 12.0% 8.00% 20.00% 59,637.76 17,891.33 77,529.09 375,717.92 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 Err:509 12.0% 8.00% 20.00% Err:509 Err:509 Err:509 Err:509 Err:509
As Evaluated
TOTAL OF PART IV
As Submitted Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 #REF! 12.0% 8.00% 20.00% #REF! #REF! #REF! #REF! #REF!
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 #REF! 10.0% 8.00% 18.00% #REF! #REF! #REF! #REF! #REF!
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 #REF! 12.0% 8.00% 20.00% #REF! #REF! #REF! #REF! #REF!
As Evaluated
TOTAL OF PART VIII
As Submitted #REF! #REF! #REF! #REF! #REF!
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 280,989.04 12.0% 8.00% 20.00% 56,197.81 16,859.34 73,057.15 354,046.19 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 33,213.46 12.0% 8.00% 20.00% 6,642.69 1,992.81 8,635.50 41,848.96 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 Err:509 12.0% 8.00% 20.00% Err:509 Err:509 Err:509 Err:509 Err:509
As Evaluated
TOTAL OF PART VII As Submitted Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 18,350.01 12.0% 8.00% 20.00% 3,670.00 1,101.00 4,771.00 23,121.01 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 235,413.92 12.0% 8.00% 20.00% 47,082.78 14,124.84 61,207.62 296,621.54 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 9,030.08 12.0% 8.00% 20.00% 1,806.02 541.80 2,347.82 11,377.90 Err:509
As Evaluated
TOTAL OF PART IX
As Submitted 262,794.01 52,558.80 15,767.64 68,326.44 331,120.45
Err:509 Err:509
Err:509 Err:509
As Evaluated
Err:509 Err:509 As Submitted Err:509 m² 342,020.48 12.0% 8.00% 20.00% 68,404.10 20,521.23 88,925.32 430,945.80 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 m² Err:509 12.0% 8.00% 20.00% Err:509 Err:509 Err:509 Err:509 Err:509
As Evaluated
TOTAL OF PART X
As Submitted Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
As Evaluated
Err:509 Err:509 As Submitted Err:509 m² 189,070.00 12.0% 8.00% 20.00% 37,814.00 11,344.20 49,158.20 238,228.20 Err:509
As Evaluated
TOTAL OF PART X
As Submitted 189,070.00 37,814.00 11,344.20 49,158.20 238,228.20
Err:509 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 m² 1,140,504.00 12.0% 8.00% 20.00% 228,100.80 68,430.24 296,531.04 1,437,035.04 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 m² Err:509 12.0% 8.00% 20.00% Err:509 Err:509 Err:509 Err:509 Err:509
As Evaluated
TOTAL OF PART XI
As Submitted Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Err:509
As Evaluated
Err:509 Err:509 As Submitted Err:509 Err:509 97,402.00 12.0% 8.00% 20.00% 19,480.40 5,844.12 25,324.52 122,726.52 Err:509
As Evaluated
Err:509 Err:509 As Submitted Err:509 Err:509 763,994.50 12.0% 8.00% 20.00% 152,798.90 45,839.67 198,638.57 962,633.07 Err:509
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 9,738.40 12.0% 8.00% 20.00% 1,947.68 584.30 2,531.98 12,270.38 Err:509
As Evaluated
TOTAL OF PART XII
As Submitted 871,134.90 174,226.98 52,268.09 226,495.07 1,097,629.97
VI ELECTRICAL WORKS
As Evaluated
1100 Conduits, Boxes and Fittings
As Submitted 1.00 lot 3,620.21 12.0% 8.00% 20.00% 724.04 217.21 941.25 4,561.46 4,561.46
1101(1) As Evaluated
Wires and Cables
As Submitted 1.00 lot 6,309.48 12.0% 8.00% 20.00% 1,261.90 378.57 1,640.46 7,949.94 7,949.94
1101(3) As Evaluated
Lighting Fixtures and Lamps
As Submitted 1.00 ls 3,401.16 12.0% 8.00% 20.00% 680.23 204.07 884.30 4,285.46 4,285.46
As Evaluated
Err:509 Err:509
As Submitted Err:509 Err:509 3,151.16 12.0% 8.00% 20.00% 630.23 189.07 819.30 3,970.46 Err:509
As Evaluated
TOTAL OF PART XIII
As Submitted 16,482.01 3,296.40 988.92 4,285.32 20,767.33
Item No. / Description : 1003 (1)a1 Fiber Cement Board Ceiling on Metal Frame
Quantity : 1,262.18 sq.m
4.50mm THK. Fiber Cement Ceiling Board on Metal Furring Channel pc 439.00 420.00 184,380.00
12mm x 38mm x 5m x 0.8mm THK. Metal Double Furring Channel pc 38.00 200.00 7,600.00
12mm x 38mm x 5m x 0.8mm THK. Metal Carrying Channel pc 18.00 200.00 3,600.00
Bars/Rod Suspension Hanger pc 56.00 100.00 5,600.00
Performed Wire Clip pc 56.00 5.00 280.00
Pre-painted Spamdril eaves sq.m. 18.37 350.00 6,429.50
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 274,441.50
Item No. / Description : 1003 (1)a1 Fiber Cement Board Ceiling on Metal Frame
Quantity : Err:509 sq.m
4.50mm THK. Fiber Cement Ceiling Board on Metal Furring Channel pc Err:509 420.00 Err:509
12mm x 38mm x 5m x 0.8mm THK. Metal Double Furring Channel pc 38.00 200.00 7,600.00
12mm x 38mm x 5m x 0.8mm THK. Metal Carrying Channel pc 18.00 200.00 3,600.00
Bars/Rod Suspension Hanger pc 56.00 100.00 5,600.00
Performed Wire Clip pc 56.00 5.00 280.00
Pre-painted Spamdril eaves sq.m. 18.37 350.00 6,429.50
25 x 25 x 300mm Wood Slats from 25 x 75 x Wood Vent. Frame
( Provide Wire Mish Inside ) set 9.00 1,000.00 9,000.00
( Provide Wire Mesh Inside )
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
(DW-1): Tubular aluminum frame two-leaf swing Door w/ fixed sq.m. 9.49 3,500.00 33,215.00
tinted glass transom above (1-set) (3.65x2.6)
(SDW-1): Steel door frame two-leaf swing door w/ louvers panel &
w/ steel fixed window “z-type” louver on steel tubular frame (1- sq.m. 7.20 6,800.00 48,960.00
set)(1.25x1.2x2) (2x2.1)
(D-1): Tubular aluminum frame swing door with fixed clear glass
sq.m. 2.60 4,550.00 11,830.00
transom above (1-set) (1x2.6)
(D-2): Tubular aluminum framed swing door (3-sets)(0.9x2.1) sq.m. 5.67 4,550.00 25,798.50
(D-3): Hollow core flush type swing door with ordinary plywood sq.m. 3.78 1,900.00 7,182.00
facings on wooden jamb/frame (2-sets) (0.9x2.1)
(D-6): Prefab vinyl swing door with fixed louvers below (3-set)
sq.m. 3.78 2,300.00 8,694.00
(0.6x2.1)
(BD-1): Pressurized laminated wood particles (bar door type), (10- sq.m. 9.00 9,300.00 83,700.00
sets)
FED-1): Fire-rated fire exit steel door with fire rated glass view
sq.m. 1.89 10,200.00 19,278.00
panel & with panic hardware (1 set)(0.9x2.1)
(SD-3): Steel door frame swing door with fixed “z-type” louvers (1-
sq.m. 1.68 6,800.00 11,424.00
set) (0.8x2.1)
SUB-TOTAL A 786,991.50
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 0.003 sq.m./hr
F. UNIT COST ( B + C)/E 158,570.00
G. TOTAL DIRECT UNIT COST ( A + F ) Php 945,561.50
H. OCM ( 9%) 85,100.54
I. Contractors Profit (8%) 75,644.92
J. 5%VAT 55,315.35
K. TOTAL INDIRECT COST 216,060.80
L. TOTAL UNIT COST Php 1,161,622.30
DETAILED
INSTALLATION OF STREET UNIT
LIGHT FROM PRICEVICTORIA
CROSSING ANALYSIS
TO PURISIMA ROAD SECTION W/ CENTER ISLAND
Job :
Item No./ Description : Windows
Unit of Measurement : lot Output/Manhour : 0.64 sq.m./hr
Output per hour : 0.005 lot
(W-1): Tubular aluminum casement type window frame with sq.m. 55.85 3,500.00 195,475.00
tinted glass panel & with fixed tinted glass transom above (9-sets)
(3.65x1.7)
(W-2):Tubular aluminum casement type window frame with tinted sq.m. 33.32 3,500.00 116,620.00
glass panel & with fixed tinted glass transom above (8-sets)
(2.45x1.7)
(W-3): Tubular aluminum casement type window frame with sq.m. 13.60 3,500.00 47,600.00
tinted glass panel & with fixed tinted glass transom above (4-sets)
(2x1.7)
(W-3A): Tubular aluminum casement type window frame with sq.m. 2.90 3,500.00 10,150.00
tinted glass panel & with fixed tinted glass transom above (1-set)
(W-4): Tubular aluminum window frame with fixed tinted glass sq.m. 20.74 3,500.00 72,590.00
panels & sliding window & w/ fixed tinted glass transom above (4-
sets) (1.65x1.7) (1.4x1.7)
(W-5): Tubular aluminum casement type window frame with sq.m. 13.20 3,500.00 46,200.00
tinted glass panel & with fixed tinted glass transom above(4-sets)
(3x1.1)
(W-6): Tubular aluminum casement type window frame with sq.m. 5.72 3,500.00 20,020.00
tinted glass panel & with fixed tinted glass transom above (2-sets)
(2.6x1.1)
(W-7): Tubular aluminum projected type window frame with tinted sq.m. 9.49 3,500.00 33,215.00
glass panels & with fixed tinted glass transom above (1-set)
(3.65x2.6)
(W-8): Tubular aluminum projected type window frame with tinted sq.m. 6.00 3,500.00 21,000.00
glass panels & with fixed tinted glass transom above (1-set)
(2.4x2.5)
(W-9): Tubular aluminum fixed glass window frame with clear glass sq.m. 2.88 3,500.00 10,080.00
panels (1-set) (1.2x1.35) (1.2x1.05)
SUB-TOTAL A 572,950.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 0.01 lot/hr
GD01 - Swing Door with fixed glass both side w/ 12mm thk
sq.m. 17.24 3,200.00 55,168.00
tempered glass (4.06m x 3.95m)
GD02 - Fixed glass w/ 12mm thk tempered glass sq.m. 11.76 3,200.00
(4.06m x 3.95m) 37,632.00
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 247,555.48
600 x 600mm Unpolished Synthetic Granite Tile pcs 2,546.00 320.00 814,720.00
Cement bags 207.00 260.00 53,820.00
Sand cu.m. 17.00 650.00 11,050.00
White Cement kgs. 24.00 45.00 1,080.00
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 1,068,774.32
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 189,070.00
4.5 mm 4' X 8' THICK FIBER CEMENT BOARD pcs Err:509 600.00 Err:509
Metal Furring pcs 590.00 150.00 88,500.00
CARRYING CHANNELS pcs Err:509 180.00 Err:509
HANGER BARS/ROD pcs Err:509 100.00 Err:509
Channel Clip pcs Err:509 35.00 Err:509
Corner bid pcs Err:509 150.00 Err:509
Rivets pcs Err:509 2.00 Err:509
1" concrete nail kgs Err:509 150.00 Err:509
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
Err:509
8.00 20.00
Err:509
12%
8%
5%
TION W/ CENTER ISLAND
8 3
Err:509
10.00%
8.00%
5.00%
UNIT PRICE ANALYSIS
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 30,551.88
JOB : #REF!
Item No. / Description : Err:509 Err:509
Quantity : Err:509 Err:509
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
JOB : #REF!
Item No. / Description : Err:509 Err:509
Quantity : Err:509 Err:509
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
JOB : #REF!
Item No. / Description : Err:509 Err:509
Quantity : Err:509 Err:509
Stair Nosing, 6mm thk. Non-skid Metal Nosing Strip pcs Err:509 580.00 Err:509
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) Err:509
6 8 #REF!
29%
10%
8%
5%
8 1.5
Err:509
12.00%
8.00%
5.00%
Err:509 8 2.25
12.00%
8.00%
5.00%
8 2.25
Err:509
12.00%
8.00%
5.00%
UNIT PRICE ANALYSIS
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD SECTION W/ C
JOB :
Item No. / Description : SPL-15 Multi-Co Polymerized Resin Based Waterproofing (at Parapet/Gutter)
Quantity : 73.09 sq.m.
Output/ hour : 1.50 sq.m.
A) MATERIALS: COST/UNIT UNIT QUANTITY UNIT RATE TOTAL COST
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 57,965.70
0.60mm Thk. Pre-painted G.I. Roofing Sheet Long Span l.m. 429.66 494.00 212,252.04
Tekscrew pcs 2,578.00 1.50 3,867.00
Blind Revits box 1.00 250.00 250.00
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 280,989.04
-
1. MAIN PANELBOARD set 1.00 2,450.00 2,450.00
Circuit Breaker, 60amp, 30 amps, 20 amp, & 15 amps -
-
-
-
SUB-TOTAL (A) 2,450.00
QUANTITY
B. LABOR COST Hourly Rate Total Cost
No. Personnel Total Hours
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 3,151.16
FCU-4 Fan coil Unit (FM),11.2KW (38,226 Btu/hr.) unit 5.00 41,995.00 209,975.00
Indoor unit, 4 Hp. 230V, 1Ø 60 Hz,with remote control.
FCU-4 Fan coil Unit (CS) 11.2KW (38,728Btu/hr) Indoor unit 1.00 37,995.00 37,995.00
Unit, 4 Hp. 230 v,1Ø,60Hz. with remote control.
FCU-3 Fan coil Unit (CS) with a capacity not less than unit 1.00 36,495.00 36,495.00
9Kw (30,717Btu/hr) Indoor Unit, with remote control
FCU-3 Fan coil Unit (FM), 8KW (27,304 Btu/hr) Indoor unit 7.00 34,500.00 241,500.00
Unit, 3 Hp. 230V, !Ø 60 Hz,with remote control.
FCU-2 Fan coil Unit (WM) 4.5KW (19,113 Btu/hr.) unit 2.00 16,295.00 32,590.00
Indoor unit, 2Hp, 230V,1Ø,60hz. with remote control
FCU-1.7 Fan coil Unit (WM) 4.5KW (15,358 Btu/hr.) unit 1.00 16,295.00 16,295.00
Indoor unit 1.7Hp, 230V,1Ø,60hz.with remote control
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 3,167,311.16
b
UNIT PRICE ANALYSIS
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD SECTION W/ CE
JOB :
Item No. / Description : Err:509 Err:509
Quantity : 18.00 set
-
-
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 53,664.32
-
FE-2 Dry Chemical ( Mono Ammonium Phosphate) (9kg/20 set 2.00 3,100.00 6,200.00
lbs) and with Trolley as shown on the plan
- -
- -
SUB-TOTAL ( C ) -
D. TOTAL DIRECT COST (A + B + C) 7,016.08
2 #REF!
#REF!
373750
6
921,020.15
3,800,000.00
2,878,979.85
80.00 8.00
62 8
18%
12%
8%
5%
2,677,098.26
ON W/ CENTER ISLAND
=
4 8
12%
8%
5%
ON W/ CENTER ISLAND
8 1
12.00%
8.00%
5.00%
= 3.50
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1200(1) Airconditioning System
Unit of Measurement : lot Output/Manhour : kg/hr
Output per hour : 0.004 lot
FCU-5 Fan coil Unit (FM), 14KW (47,782Btu/hr.)Indoor unit, 5 Hp. 230V, 1 unit 4.00 45,195.00 180,780.00
FCU-4 Fan coil Unit (FM),11.2KW (38,226 Btu/hr.) Indoor unit, 4 Hp. 230 unit 5.00 41,995.00 209,975.00
FCU-4 Fan coil Unit (CS) 11.2KW (38,728Btu/hr) Indoor Unit, 4 Hp. 230 unit 1.00 37,995.00 37,995.00
FCU-3 Fan coil Unit (CS) with a capacity not less than 9Kw (30,717Btu/hr) unit 1.00 36,495.00 36,495.00
FCU-3 Fan coil Unit (FM), 8KW (27,304 Btu/hr) Indoor Unit, 3 Hp. 230V, ! unit 7.00 34,500.00 241,500.00
FCU-2 Fan coil Unit (WM) 4.5KW (19,113 Btu/hr.) Indoor unit, 2Hp, 230 unit 2.00 16,295.00 32,590.00
FCU-1.7 Fan coil Unit (WM) 4.5KW (15,358 Btu/hr.) Indoor unit 1.7Hp, unit 1.00 16,295.00 16,295.00
ACCU-18 Air Condensing cooling Unit,22.4KW(76,451 Btu/hr) 8 Hp.DC Inv unit 2.00 317,500.00 635,000.00
ACCU-18 Air Condensing cooling Unit,22.4KW(76,451 Btu/hr) 8 Hp.DC Inv unit 2.00 330,000.00 660,000.00
SUB-TOTAL A 2,545,425.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 5.00 1.00 51.51 257.55
Laborers 10.00 1.00 39.73 397.30
SUB-TOTAL B 725.87
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 725.87
E. Output per hou 0.004 lot/hr
F. UNIT COST ( B + C)/E 181,467.50
G. TOTAL DIRECT UNIT COST ( A + FPhp 2,726,892.50
H. OCM ( 9%) 245,420.33
I. Contractors Profit (8%) 218,151.40
J. 5%VAT 159,523.21
K. TOTAL INDIRECT COST 623,094.94
L. TOTAL UNIT COST Php 3,349,987.44
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1200(2) Airconditioning System (Miscelaneous)
Unit of Measurement : lot
Output per hour : 0.085 lot
Miscellaneous
Split type Package unit complete with Air condensing cooling unit unit 1.00 59,059.00 59,059.00
(ACCU), (36,000 Btu/hr./37,980Kj/hr.)220V, 1Ø,60Hz.and all other
accessories needed for installation includes copper tubing,
fittings,installation,drain pipe line,platform,brackets/hangers,refrigerant
and electrical wires and etc. to make the system operational ready for
service.
Window type air conditioner having a capacity of not less than (18,000 Bt unit 1.00 20,199.00 20,199.00
SUB-TOTAL A 79,258.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 8.00 1.00 39.73 317.84
-
-
SUB-TOTAL B 594.90
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 594.90
E. Output per hour 0.085 lot/hr
F. UNIT COST ( B + C)/E 6,998.82
G. TOTAL DIRECT UNIT COST ( A + F ) Php 86,256.82
H. OCM ( 9%) 7,763.11
I. Contractors Profit (8%) 6,900.55
J. 5%VAT 5,046.02
K. TOTAL INDIRECT COST 19,709.68
L. TOTAL UNIT COST Php 105,966.51
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-19 Ventilation System
Unit of Measurement : lot
Output per hour : 0.170 lot
EF-1 Exhaust ceiling cassette type with complete all necessary accessori unit 10.00 4,300.00 43,000.00
EF-2 Exhaust wall mounted type with complete all necessary accessories , unit 2.00 8,400.00 16,800.00
EF-2 Exhaust wall mounted type with complete all necessary accessories , unit 1.00 1,950.00 1,950.00
SUB-TOTAL A 61,750.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 3.00 1.00 51.51 154.53
Laborers 6.00 1.00 39.73 238.38
-
-
SUB-TOTAL B 463.93
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 463.93
E. Output per hour 0.170 lot/hr
F. UNIT COST ( B + C)/E 2,729.00
G. TOTAL DIRECT UNIT COST ( A + F ) Php 64,479.00
H. OCM ( 9%) 5,803.11
I. Contractors Profit (8%) 5,158.32
J. 5%VAT 3,772.02
K. TOTAL INDIRECT COST 14,733.45
L. TOTAL UNIT COST Php 79,212.45
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-20 Fire Protection System
Unit of Measurement : lot
Output per hour : 0.021 lot
FE-1 Dry Chemical (Mono Ammonium Phosphate) (4.5kg/10lbs) mounted o unit 18.00
FE-2 Dry Chemical ( Mono Ammonium Phosphate) (9kg/20 lbs) and with unit 2.00
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
-
-
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.021 sq.m./hr
F. UNIT COST ( B + C)/E 9,618.57
G. TOTAL DIRECT UNIT COST ( A + F ) Php 9,618.57
H. OCM ( 9%) 865.67
I. Contractors Profit (8%) 769.49
J. 5%VAT 562.69
K. TOTAL INDIRECT COST 2,197.84
L. TOTAL UNIT COST Php 11,816.42
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 506(2)b Masonry Works (150 mm thk CHB Wall)
Unit of Measurement : sq.m. Output/Manhour : 0.531 sq.m./hr
Output per hour : 5.313 sq.m.
SUB-TOTAL A 787.19
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 5.313 sq.m./hr
F. UNIT COST ( B + C)/E 89.54
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,876.73
H. OCM ( 9%) 78.91
I. Contractors Profit (8%) 70.14
J. 5%VAT 51.29
K. TOTAL INDIRECT COST 200.33
L. TOTAL UNIT COST Php 1,077.06
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 506(1)a Masonry Works (100 mm thk CHB Wall)
Unit of Measurement : sq.m. Output/Manhour : 0.638 sq.m./hr
Output per hour : 6.375 sq.m.
SUB-TOTAL A 422.47
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 6.375 sq.m./hr
F. UNIT COST ( B + C)/E 74.62
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,497.09
H. OCM ( 9%) 44.74
I. Contractors Profit (8%) 39.77
J. 5%VAT 29.08
K. TOTAL INDIRECT COST 113.59
L. TOTAL UNIT COST Php 0,610.68
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 900(1)a1 Concrete (21 Mpa)
Unit of Measurement : cu.m. Output/Manhour : 0.41 cu.m./MHr
Quantity : 289.916 cu.m.
SUB-TOTAL A 990,090.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 10.00 1.00 39.73 397.30
-
-
-
SUB-TOTAL B 674.36
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 91.25
D. TOTAL D (B + C) 765.61
E. Output per hour 289.92 cu.m./hr
F. UNIT COST ( B + C)/E 2.64
G. TOTAL DIRECT UNIT COST ( A + F ) Php 990,092.64
H. OCM ( 9%) 89,108.34
I. Contractors Profit (8%) 79,207.41
J. 5%VAT 57,920.42
K. TOTAL INDIRECT COST 226,236.17
L. TOTAL UNIT COST Php 1,216,328.81
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 900(1)b2 Concrete (17 Mpa)
Unit of Measurement : cu.m. Output/Manhour : 0.41 cu.m./MHr
Output per hour : 6.195 cu.m.
Ready Mixed Concrete (2500 psi @ 28days) cu.m. 1.00 4,200.00 4,200.00
SUB-TOTAL A 4,200.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 10.00 1.00 39.73 397.30
-
-
-
SUB-TOTAL B 674.36
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 1,227.01
D. TOTAL D (B + C) 1,901.37
E. Output per hour 6.20 cu.m./hr
F. UNIT COST ( B + C)/E 306.92
G. TOTAL DIRECT UNIT COST ( A + F ) Php 4,506.92
H. OCM ( 9%) 405.62
I. Contractors Profit (8%) 360.55
J. 5%VAT 263.65
K. TOTAL INDIRECT COST 1,029.83
L. TOTAL UNIT COST Php 5,536.75
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 900(2)a Reinforcing Bars Grade 40
Unit of Measurement : kg Output/Manhour : 12.80 kgs/hr
Output per hour : 192.000 kg
SUB-TOTAL A 46.30
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 9.00 1.00 51.51 463.59
Laborers 5.00 1.00 39.73 198.65
-
-
-
-
SUB-TOTAL B 733.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 285.63
D. TOTAL D (B + C) 1,018.89
E. Output per hour 192.00 kgs/hr
F. UNIT COST ( B + C)/E 5.31
G. TOTAL DIRECT UNIT COST ( A + F ) Php 51.61
H. OCM ( 9%) 4.64
I. Contractors Profit (8%) 4.13
J. 5%VAT 3.02
K. TOTAL INDIRECT COST 11.79
L. TOTAL UNIT COST Php 0,063.40
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 900(2)b Reinforcing Bars Grade 33
Unit of Measurement : kg Output/Manhour : 12.80 kgs/hr
Output per hour : 192.000 kg
SUB-TOTAL A 46.30
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 9.00 1.00 51.51 463.59
Laborers 5.00 1.00 39.73 198.65
-
-
-
-
SUB-TOTAL B 733.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 285.63
D. TOTAL D (B + C) 1,018.89
E. Output per hour 192.00 kgs/hr
F. UNIT COST ( B + C)/E 5.31
G. TOTAL DIRECT UNIT COST ( A + F ) Php 51.61
H. OCM ( 9%) 4.64
I. Contractors Profit (8%) 4.13
J. 5%VAT 3.02
K. TOTAL INDIRECT COST 11.79
L. TOTAL UNIT COST Php 0,063.40
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 900(3) Formworks
Unit of Measurement : sq. m. Output/Manhour : 0.54 sq.m./hr
Output per hour : 8.115 sq.m.
SUB-TOTAL A 632.16
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 10.00 1.00 39.73 397.30
-
-
-
SUB-TOTAL B 674.36
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 674.36
E. Output per hour 8.12 sq.m./hr
F. UNIT COST ( B + C)/E 83.10
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,715.26
H. OCM ( 9%) 64.37
I. Contractors Profit (8%) 57.22
J. 5%VAT 41.84
K. TOTAL INDIRECT COST 163.44
L. TOTAL UNIT COST Php 0,878.70
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 803(1) Structure Excavation (With Equipment)
Unit of Measurement : cu.m. Output/Manhour : 6.667 cu.m.
Output per hour : 20.000 cu.m.*
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 3.00 1.00 39.73 119.19
-
-
-
-
SUB-TOTAL B 190.21
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 4,241.00
D. TOTAL D (B + C) 4,431.21
E. Output per hour 20.000 cu.m./hr
F. UNIT COST ( B + C)/E 221.56
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,221.56
H. OCM ( 9%) 19.94
I. Contractors Profit (8%) 17.72
J. 5%VAT 12.96
K. TOTAL INDIRECT COST 50.63
L. TOTAL UNIT COST Php 0,272.19
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 269.67
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 105.13
D. TOTAL D (B + C) 374.80
E. Output per hour 1.865 cu.m./hr
F. UNIT COST ( B + C)/E 200.96
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,200.96
H. OCM ( 9%) 18.09
I. Contractors Profit (8%) 16.08
J. 5%VAT 11.76
K. TOTAL INDIRECT COST 45.92
L. TOTAL UNIT COST Php 0,246.88
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 804(2) Embankment
Unit of Measurement : cu.m.
Output per hour : 1.865 cu.m.
SUB-TOTAL A 437.50
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 269.67
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 105.13
D. TOTAL D (B + C) 374.80
E. Output per hour 1.865 cu.m./hr
F. UNIT COST ( B + C)/E 200.96
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,638.46
H. OCM ( 9%) 57.46
I. Contractors Profit (8%) 51.08
J. 5%VAT 37.35
K. TOTAL INDIRECT COST 145.89
L. TOTAL UNIT COST Php 0,784.35
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 804(3) Gravel Bedding
Unit of Measurement : cu.m. Output/Manhour : 0.335 cu.m.
Output per hour : 2.010 cu.m.
SUB-TOTAL A 630.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 269.67
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 70.09
D. TOTAL D (B + C) 339.76
E. Output per hour 2.010 cu.m./hr
F. UNIT COST ( B + C)/E 169.03
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,799.03
H. OCM ( 9%) 71.91
I. Contractors Profit (8%) 63.92
J. 5%VAT 46.74
K. TOTAL INDIRECT COST 182.58
L. TOTAL UNIT COST Php 0,981.61
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL Dampproofing
Unit of Measurement : sq.m. Output/Manhour : 0.335 cu.m.
Output per hour : 19.828 sq.m.
SUB-TOTAL A 42.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 150.48
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 150.48
E. Output per hour 19.828 sq.m./hr
F. UNIT COST ( B + C)/E 7.59
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,049.59
H. OCM ( 9%) 4.46
I. Contractors Profit (8%) 3.97
J. 5%VAT 2.90
K. TOTAL INDIRECT COST 11.33
L. TOTAL UNIT COST Php 0,060.92
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1000(1) Soil Poisoning
Unit of Measurement : lit
Output per hour : 3.000 lit
SUB-TOTAL A 441.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 150.48
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 150.48
E. Output per hour 3.000 sq.m./hr
F. UNIT COST ( B + C)/E 50.16
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,491.16
H. OCM ( 9%) 44.20
I. Contractors Profit (8%) 39.29
J. 5%VAT 28.73
K. TOTAL INDIRECT COST 112.23
L. TOTAL UNIT COST Php 0,603.39
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 801(1) Removal of Structures and Obstruction
Unit of Measurement : lot
Output per hour : 1.000 lot
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 160.00 71.02 11,363.20
Laborers 20.00 160.00 39.73 127,136.00
-
-
-
SUB-TOTAL B 138,499.20
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 138,499.20
E. Output per hour 1.000 sq.m./hr
F. UNIT COST ( B + C)/E 138499.2
G. TOTAL DIRECT UNIT COST ( A + F ) Php 138,499.20
H. OCM ( 9%) 12,464.93
I. Contractors Profit (8%) 11,079.94
J. 5%VAT 8,102.20
K. TOTAL INDIRECT COST 31,647.07
L. TOTAL UNIT COST Php 170,146.27
DETAILED UNIT PRICE ANALYSIS
Job : One (1) Storey School Building and Similar Building Structures
Item No./ Description : Item 900(1)d Concrete Works (Slab on Grade)
Unit of Measurement : cu.m. Output/Manhour : 0.413 cu.m./MHr
Output per hour : 0.357 cu.m.
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour 0.357 cu.m./hr
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 6%7%9%12%)
I. Contractors Profit (8%10%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
Note: The presented DUPA was based on a one gang(1) of labor and equipment with specified output of 1.5 cu.m.
accomplished at 2.710 hrs. To increase the output, additional equipment and labor may be added.
DETAILED UNIT PRICE ANALYSIS
Job : One (1) Storey School Building and Similar Building Structures
Item No./ Description : Item 900(1)c Concrete Works (R.C. Beam)
Unit of Measurement : cu.m. Output/Manhour : 0.413 cu.m./MHr
Output per hour : 0.276 cu.m.
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour 0.276 cu.m./hr
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 6%7%9%12%)
I. Contractors Profit (8%10%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
Note: The presented DUPA was based on a one gang(1) of labor and equipment with specified output of 2.56 cu.m.
accomplished at 9.266 hrs. To increase the output, additional equipment and labor may be added.
DETAILED UNIT PRICE ANALYSIS
Job : One (1) Storey School Building and Similar Building Structures
Item No./ Description : Item 900(1)b Concrete Works (R.C. Column)
Unit of Measurement : cu.m. Output/Manhour : 0.413 cu.m./MHr
Output per hour : 0.294 cu.m.
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour 0.294 cu.m./hr
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 6%7%9%12%)
I. Contractors Profit (8%10%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
Note: The presented DUPA was based on a one gang(1) of labor and equipment with specified output of 1.92 cu.m.
accomplished at 6.533 hrs. To increase the output, additional equipment and labor may be added.
DETAILED UNIT PRICE ANALYSIS
Job : One (1) Storey School Building and Similar Building Structures
Item No./ Description : Item 900(1)a Concrete Works (R.C. Column Footing and Wall Footing)
Unit of Measurement : cu.m. Output/Manhour : 0.413 cu.m./MHr
Output per hour : 0.357 cu.m.
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour 0.357 cu.m./hr
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 6%7%9%12%)
I. Contractors Profit (8%10%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
Note: The presented DUPA was based on a one gang(1) of labor and equipment with specified output of 0.96 cu.m.
accomplished at 2.683 hrs. To increase the output, additional equipment and labor may be added.
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description
I. : Mobilization and Demobilization
Unit of Measurement : lot Output/Manhour : kg/hr
Output per hour : 1.000 lot
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. PersonnelTotal Hours Rate Cost
-
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.Total Hours Rate Cost
Mobilization and Demobilization (0.50 % of civil works) #REF!
-
-
-
-
-
SUB-TOTAL C #REF!
D. TOTAL D (B + C) #REF!
E. Output per hour 1.000 lot/hr
F. UNIT COST ( B + C)/E #REF!
G. TOTAL DIRECT UNIT COST ( A + F ) #REF!
H.
I.
J. 5%VAT #REF!
K. TOTAL INDIRECT COST #REF!
L. TOTAL UNIT COST #REF!
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : II.a Temporary Facilities
Unit of Measurement : month Output/Manhour : kg/hr
Output per hour : 1.000 month
Rental for 2 Units 40 footer van with ACU, furniture and maintenance 1.00 1.00 26,000.00 26,000.00
SUB-TOTAL A 26,000.00
B. LABOR COST QUANTITY Monthly Total
No. of Equipt.TotalMonths Rate Cost
-
-
SUB-TOTAL B -
C. EQUIPMENT COST QUANTITY Monthly Total
No. of Equipt.TotalMonths Rate Cost
-
-
-
-
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) -
E. Output per hour 1.000 lot/hr
F. UNIT COST ( B + C)/E -
G. TOTAL DIRECT UNIT COST ( A + F ) Php 26,000.00
H.
I. Contractors Profit (8%) 2,080.00
J. 5%VAT 1,404.00
K. TOTAL INDIRECT COST 3,484.00
L. TOTAL UNIT COST Php 29,484.00
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : II.b Safety and Health
Unit of Measurement : lot
Output per hour : 1.000 lot
SUB-TOTAL A #REF!
B. LABOR COST QUANTITY Hourly Total
No. of Equipt.Totalhours Rate Cost
-
-
SUB-TOTAL B 10,000.00
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.TotalHours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 10,000.00
E. Output per hour 1.000 lot
F. UNIT COST ( B + C)/E 10,000.00
G. TOTAL DIRECT UNIT COST ( A + F ) #REF!
H.
I. Contractors Profit (8%) #REF!
J. 5%VAT #REF!
K. TOTAL INDIRECT COST #REF!
L. TOTAL UNIT COST #REF!
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : II.c.1 Project Bill Board
Unit of Measurement : set
Output per hour : 0.250 set
SUB-TOTAL A 2,565.00
B. LABOR COST QUANTITY Hourly Total
No. of Equipt.TotalMonths Rate Cost
-
-
SUB-TOTAL B 91.24
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.TotalHours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 91.24
E. Output per hour 0.250 lot
F. UNIT COST ( B + C)/E 364.96
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,929.96
H. OCM ( 9%) 263.70
I. Contractors Profit (8%) 234.40
J. 5%VAT 171.40
K. TOTAL INDIRECT COST 669.50
L. TOTAL UNIT COST Php 3,599.46
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : II.c.2 COA Bill Board
Unit of Measurement : set
Output per hour : 0.187 set
SUB-TOTAL A 4,710.00
B. LABOR COST QUANTITY Hourly Total
No. of Equipt.TotalMonths Rate Cost
-
-
SUB-TOTAL B 91.24
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt.TotalHours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 91.24
E. Output per hour 0.187 lot
F. UNIT COST ( B + C)/E 487.91
G. TOTAL DIRECT UNIT COST ( A + F ) Php 5,197.91
H. OCM ( 9%) 467.81
I. Contractors Profit (8%) 415.83
J. 5%VAT 304.08
K. TOTAL INDIRECT COST 1,187.72
L. TOTAL UNIT COST Php 6,385.64
DETAILED UNIT PRICE ANALYSIS
Job Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : II.d General Scafolding
Unit of Measurement : lot
Output per hour : 1.000 lot
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. of Equipt.TotalMonths Rate Cost
-
-
SUB-TOTAL B 10,888.05
C. EQUIPMENT COST QUANTITY Daily Total
No. of Equipt. TotalDays Rate Cost
Rental Basis
Shoring Jack, 3m 69.00 30.00 5.20 10,764.00
Shoring Jack, 4.5 m 69.00 30.00 5.90 12,213.00
Adjustable Base Jack, 1-1/4 x 600 mm 137.00 30.00 1.38 5,671.80
U-jack, 1-1/4 x 600 mm 137.00 30.00 1.45 5,959.50
1-1/2" G.I. Pipe x 20 ft 152.00 30.00 4.77 21,751.20
A- Frame and Accessories 137.00 30.00 10.51 43,196.10
SUB-TOTAL C 99,555.60
D. TOTAL D (B + C) 110,443.65
E. Output per hour 1.000 lot
F. UNIT COST ( B + C)/E 110,443.65
G. TOTAL DIRECT UNIT COST ( A + F ) Php 110,443.65
H. OCM ( 9%) 9,939.93
I. Contractors Profit (8%) 8,835.49
J. 5%VAT 6,460.95
K. TOTAL INDIRECT COST 25,236.37
L. TOTAL UNIT COST Php 135,680.02
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)a (FL-1) 600 x 600mm Unpolished Synthetic Granite Tile Floor Fin.
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 1.950 sq.m.
SUB-TOTAL A
B. LABOR COST QUANTITY
No. Personnel Total Hours
SUB-TOTAL B
C. EQUIPMENT COST QUANTITY
No. of Equipt. Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)b (FL-2): 600 x 600mm Textured Ceramic Tile
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 1.950 sq.m.
SUB-TOTAL A
B. LABOR COST QUANTITY
No. Personnel Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1019 (FL-3): Wood Parquet Floor Fin.
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 1.150 sq.m.
SUB-TOTAL B
C. EQUIPMENT COST QUANTITY
No. of Equipt. Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)c (FL-4): 200mm x 200mm Vitrified Unglazed Tiles Floor (provide water proofing)
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 1.150 sq.m.
SUB-TOTAL A
B. LABOR COST QUANTITY
No. Personnel Total Hours
SUB-TOTAL B
C. EQUIPMENT COST QUANTITY
No. of Equipt. Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1020 (FL-5): 300 x 300mm Vinyl Tiles Floor Fin.
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 2.250 sq.m.
SUB-TOTAL B
C. EQUIPMENT COST QUANTITY
No. of Equipt. Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1021(2) (FL-6): Non-Skid Cement Floor Fin. With 6mm wide Groove Lines
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 1.95 sq.m.
SUB-TOTAL A
B. LABOR COST QUANTITY
No. Personnel Total Hours
SUB-TOTAL B
C. EQUIPMENT COST QUANTITY
No. of Equipt. Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1021(1) Plain Cement Floor Fin. (provide water proofing)
Unit of Measurement : sq.m. Output/Manhour :
Output per hour : 2.50 sq.m.
SUB-TOTAL A
B. LABOR COST QUANTITY
No. Personnel Total Hours
SUB-TOTAL C
D. TOTAL D (B + C)
E. Output per hour
F. UNIT COST ( B + C)/E
G. TOTAL DIRECT UNIT COST ( A + F )
H. OCM ( 9%)
I. Contractors Profit (8%)
J. 5%VAT
K. TOTAL INDIRECT COST
L. TOTAL UNIT COST
LYSIS
Granite Tile Floor Fin.
0.195 sq.m./hr
0.195 10.00
671.31
Hourly Total
Rate Cost
-
71.02 71.02 8.5
51.51 206.04 12.8
39.73 198.65
-
-
-
475.71
Hourly Total
Rate Cost
-
475.71
1.950 sq.m./hr
243.95 0.363398
Php 0,915.27
82.37
73.22
53.54
209.14
Php 1,124.40
LYSIS
0.195 sq.m./hr
0.195 10.00
671.31
Hourly Total
Rate Cost
-
71.02 71.02 8.5
51.51 206.04 12.8
39.73 198.65
-
-
-
475.71
Hourly Total
Rate Cost
-
475.71
1.950 sq.m./hr
243.95 0.363398
Php 0,915.27
82.37
73.22
53.54
209.14
Php 1,124.40
LYSIS
0.000 sq.m./hr
830.00 871.50
43.58
915.08
Hourly Total
Rate Cost
-
71.02 71.02
51.51 103.02
39.73 79.46
-
-
-
253.50
Hourly Total
Rate Cost
-
253.50
1.150 sq.m./hr
220.43
Php 1,135.51
102.20
90.84
66.43
259.46
Php 1,394.97
LYSIS
Tiles Floor (provide water proofing)
0.000 sq.m./hr
500.00 525.00
250.00 81.25
2,400.00 63.00
16.50 2.06
550.00 550.00
1,221.31
Hourly Total
Rate Cost
-
71.02 71.02
51.51 206.04
39.73 198.65
-
-
-
475.71
Hourly Total
Rate Cost
-
475.71
1.150 sq.m./hr
413.66
Php 1,634.97
147.15
130.80
95.65
373.59
Php 2,008.56
LYSIS
0.000 sq.m./hr
250.00 262.50
13.13
275.63
Hourly Total
Rate Cost
-
71.02 71.02
51.51 103.02
39.73 79.46
-
-
-
253.50
Hourly Total
Rate Cost
-
253.50
2.250 sq.m./hr
112.67
Php 0,388.29
34.95
31.06
22.72
88.72
Php 0,477.02
LYSIS
m wide Groove Lines
1.190 sq.m./hr
-
Hourly Total
Rate Cost
-
71.02 71.02
51.51 51.51
39.73 119.19
-
-
-
241.72
Hourly Total
Rate Cost
-
241.72
1.950 sq.m./hr
123.96
Php 0,123.96
11.16
9.92
7.25
28.32
Php 0,152.28
LYSIS
1.190 sq.m./hr
260.00 177.45
600.00 31.80
550.00 550.00
759.25
Hourly Total
Rate Cost
-
71.02 71.02
51.51 51.51
39.73 119.19
-
-
-
241.72
Hourly Total
Rate Cost
-
241.72
2.500 sq.m./hr
96.69
Php 0,855.94
77.03
68.48
50.07
195.58
Php 1,051.52
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018(2) 200 x 300mm Vitrified Glazed Tiles Wall Fin.
Unit of Measurement : sq.m. Output/Manhour : 0.280 sq.m./hr
Output per hour : 1.120 sq.m.
SUB-TOTAL A 621.43
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 1.120 sq.m./hr
F. UNIT COST ( B + C)/E 180.35
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,801.77
H. OCM ( 9%) 72.16
I. Contractors Profit (8%) 64.14
J. 5%VAT 46.90
K. TOTAL INDIRECT COST 183.21
L. TOTAL UNIT COST Php 0,984.98
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 1027 Cement Plaster Finish
Unit of Measurement : sq.m. Output/Manhour : 1.188 sq.m./hr
Output per hour : 11.875 sq.m.
SUB-TOTAL A 101.70
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 11.875 sq.m./hr
F. UNIT COST ( B + C)/E 40.06
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,141.76
H. OCM ( 9%) 12.76
I. Contractors Profit (8%) 11.34
J. 5%VAT 8.29
K. TOTAL INDIRECT COST 32.39
L. TOTAL UNIT COST Php 0,174.15
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1039 Aluminum cladding
Unit of Measurement : sq.m. Output/Manhour : 0.280 sq.m./hr
Output per hour : 0.950 sq.m.
SUB-TOTAL A 2,150.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 2.00 1.00 51.51 103.02
Laborers 4.00 1.00 39.73 158.92
-
-
-
SUB-TOTAL B 332.96
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 332.96
E. Output per hour 0.950 sq.m./hr
F. UNIT COST ( B + C)/E 350.48
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,500.48
H. OCM ( 9%) 225.04
I. Contractors Profit (8%) 200.04
J. 5%VAT 146.28
K. TOTAL INDIRECT COST 571.36
L. TOTAL UNIT COST Php 3,071.84
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)a (FL-1) 600 x 600mm Unpolished Synthetic Granite Tile Floor Fin.
Unit of Measurement : sq.m. Output/Manhour : 0.195 sq.m./hr
Output per hour : 1.950 sq.m.
600 x 600mm Unpolished Synthetic Granite Tile sq.m. 1.050 500.00 525.00
Cement bags 0.325 250.00 81.25
Sand cu.m. 0.026 2,400.00 63.00
White Cement bags 0.125 16.50 2.06
SUB-TOTAL A 671.31
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 1.950 sq.m./hr
F. UNIT COST ( B + C)/E 243.95
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,915.27
H. OCM ( 9%) 82.37
I. Contractors Profit (8%) 73.22
J. 5%VAT 53.54
K. TOTAL INDIRECT COST 209.14
L. TOTAL UNIT COST Php 1,124.40
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)b (FL-2): 600 x 600mm Textured Ceramic Tile
Unit of Measurement : sq.m. Output/Manhour : 0.195 sq.m./hr
Output per hour : 1.950 sq.m.
SUB-TOTAL A 671.31
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 1.950 sq.m./hr
F. UNIT COST ( B + C)/E 243.95
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,915.27
H. OCM ( 9%) 82.37
I. Contractors Profit (8%) 73.22
J. 5%VAT 53.54
K. TOTAL INDIRECT COST 209.14
L. TOTAL UNIT COST Php 1,124.40
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1019 (FL-3): Wood Parquet Floor Fin.
Unit of Measurement : sq.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 1.150 sq.m.
SUB-TOTAL A 915.08
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 2.00 1.00 51.51 103.02
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 253.50
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 253.50
E. Output per hour 1.150 sq.m./hr
F. UNIT COST ( B + C)/E 220.43
G. TOTAL DIRECT UNIT COST ( A + F ) Php 1,135.51
H. OCM ( 9%) 102.20
I. Contractors Profit (8%) 90.84
J. 5%VAT 66.43
K. TOTAL INDIRECT COST 259.46
L. TOTAL UNIT COST Php 1,394.97
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1018 (1)c (FL-4): 200mm x 200mm Vitrified Unglazed Tiles Floor (provide water proofing)
Unit of Measurement : sq.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 1.150 sq.m.
200mm x 200mm Vitrified Unglazed Tiles Floor sq.m. 1.050 500.00 525.00
Cement bags 0.325 250.00 81.25
Sand cu.m. 0.026 2,400.00 63.00
White Cement bags 0.125 16.50 2.06
Cement based water proofing sq.m. 1.00 550.00 550.00
SUB-TOTAL A 1,221.31
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 1.150 sq.m./hr
F. UNIT COST ( B + C)/E 413.66
G. TOTAL DIRECT UNIT COST ( A + F ) Php 1,634.97
H. OCM ( 9%) 147.15
I. Contractors Profit (8%) 130.80
J. 5%VAT 95.65
K. TOTAL INDIRECT COST 373.59
L. TOTAL UNIT COST Php 2,008.56
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1020 (FL-5): 300 x 300mm Vinyl Tiles Floor Fin.
Unit of Measurement : sq.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 2.250 sq.m.
SUB-TOTAL A 275.63
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 2.00 1.00 51.51 103.02
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 253.50
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 253.50
E. Output per hour 2.250 sq.m./hr
F. UNIT COST ( B + C)/E 112.67
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,388.29
H. OCM ( 9%) 34.95
I. Contractors Profit (8%) 31.06
J. 5%VAT 22.72
K. TOTAL INDIRECT COST 88.72
L. TOTAL UNIT COST Php 0,477.02
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1021(2) (FL-6): Non-Skid Cement Floor Fin. With 6mm wide Groove Lines
Unit of Measurement : sq.m. Output/Manhour : 1.190 sq.m./hr
Output per hour : 1.95 sq.m.
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 3.00 1.00 39.73 119.19
-
-
-
SUB-TOTAL B 241.72
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 241.72
E. Output per hour 1.950 sq.m./hr
F. UNIT COST ( B + C)/E 123.96
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,123.96
H. OCM ( 9%) 11.16
I. Contractors Profit (8%) 9.92
J. 5%VAT 7.25
K. TOTAL INDIRECT COST 28.32
L. TOTAL UNIT COST Php 0,152.28
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1021(1) Plain Cement Floor Fin. (provide water proofing)
Unit of Measurement : sq.m. Output/Manhour : 1.190 sq.m./hr
Output per hour : 2.50 sq.m.
SUB-TOTAL A 759.25
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 3.00 1.00 39.73 119.19
-
-
-
SUB-TOTAL B 241.72
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 241.72
E. Output per hour 2.500 sq.m./hr
F. UNIT COST ( B + C)/E 96.69
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,855.94
H. OCM ( 9%) 77.03
I. Contractors Profit (8%) 68.48
J. 5%VAT 50.07
K. TOTAL INDIRECT COST 195.58
L. TOTAL UNIT COST Php 1,051.52
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1003(2)c (CL-2A): 4.50mm THK. Fiber Cement Ceiling Board
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 1.090 sq.m./hr
F. UNIT COST ( B + C)/E 185.31
G. TOTAL DIRECT UNIT COST ( A + F ) Php 506.77
H. OCM ( 9%) 45.61
I. Contractors Profit (8%) 40.54
J. 5%VAT 29.65
K. TOTAL INDIRECT COST 115.80
L. TOTAL UNIT COST Php 622.57
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.950 sq.m./hr
F. UNIT COST ( B + C)/E 212.62
G. TOTAL DIRECT UNIT COST ( A + F ) Php 534.08
H. OCM ( 9%) 48.07
I. Contractors Profit (8%) 42.73
J. 5%VAT 31.24
K. TOTAL INDIRECT COST 122.04
L. TOTAL UNIT COST Php 656.12
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1003(2)b (CL-2): 4.50mm THK. Fiber Cement Ceiling Board with 150mm Wide Recessed Corners
Unit of Measurement : sq.m. Output/Manhour : 0.273 sq.m./hr
Output per hour : 0.950 sq.m.
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.950 sq.m./hr
F. UNIT COST ( B + C)/E 212.62
G. TOTAL DIRECT UNIT COST ( A + F ) Php 534.08
H. OCM ( 9%) 48.07
I. Contractors Profit (8%) 42.73
J. 5%VAT 31.24
K. TOTAL INDIRECT COST 122.04
L. TOTAL UNIT COST Php 656.12
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : Item 1027(2) (CL-3): Exposed R.C Under slabs with Plain cement Plaster Fin.
Unit of Measurement : sq.m. Output/Manhour : 1.188 sq.m./hr
Output per hour : 11.875 sq.m.
SUB-TOTAL A 146.10
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 475.71
E. Output per hour 11.875 sq.m./hr
F. UNIT COST ( B + C)/E 40.06
G. TOTAL DIRECT UNIT COST ( A + F ) Php 0,186.16
H. OCM ( 9%) 16.75
I. Contractors Profit (8%) 14.89
J. 5%VAT 10.89
K. TOTAL INDIRECT COST 42.54
L. TOTAL UNIT COST Php 0,228.70
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1039 (CL-4): Aluminum Metal Cladding
Unit of Measurement : sq.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.875 sq.m.
SUB-TOTAL A 2,150.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 2.00 1.00 51.51 103.02
Laborers 4.00 1.00 39.73 158.92
-
-
-
SUB-TOTAL B 332.96
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 332.96
E. Output per hour 0.875 sq.m./hr
F. UNIT COST ( B + C)/E 380.53
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,530.53
H. OCM ( 9%) 227.75
I. Contractors Profit (8%) 202.44
J. 5%VAT 148.04
K. TOTAL INDIRECT COST 578.23
L. TOTAL UNIT COST Php 3,108.75
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1039(1) (CL-4A): Aluminum Metal Cladding/Ceiling Panels On Metal Furrings
Unit of Measurement : sq.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.875 sq.m.
Aluminum Metal Cladding/Ceiling Panels On Metal Furrings sq.m. 1.000 2,150.00 2,150.00
SUB-TOTAL A 2,150.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 2.00 1.00 51.51 103.02
Laborers 4.00 1.00 39.73 158.92
-
-
-
SUB-TOTAL B 332.96
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 332.96
E. Output per hour 0.875 sq.m./hr
F. UNIT COST ( B + C)/E 380.53
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,530.53
H. OCM ( 9%) 227.75
I. Contractors Profit (8%) 202.44
J. 5%VAT 148.04
K. TOTAL INDIRECT COST 578.23
L. TOTAL UNIT COST Php 3,108.75
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-1 Steel Pipes 150mmØ x 7.30m (Including Bolts & Steel Plates anchorage)
Unit of Measurement : set Output/Manhour : 0.273 sq.m./hr
Output per hour : 0.123 set
SUB-TOTAL A 17,892.63
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
Welding Machine 1.00 1.00 391.00 391.00
SUB-TOTAL C 391.00
D. TOTAL D (B + C) 592.99
E. Output per hour 0.123 l.m./hr
F. UNIT COST ( B + C)/E 4,821.06
G. TOTAL DIRECT UNIT COST ( A + F ) 22,713.69
H. OCM ( 9%) 2,044.23
I. Contractors Profit (8%) 1,817.09
J. 5%VAT 1,328.75
K. TOTAL INDIRECT COST 5,190.08
L. TOTAL UNIT COST Php 27,903.76
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-2 Fire Escape
Unit of Measurement : set Output/Manhour : 0.273 sq.m./hr
Output per hour : 0.170 set
-
-
SUB-TOTAL A 4,300.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.170 sq.m./hr
F. UNIT COST ( B + C)/E 1,188.18
G. TOTAL DIRECT UNIT COST ( A + F ) Php 5488.18
H. OCM ( 9%) 493.94
I. Contractors Profit (8%) 439.05
J. 5%VAT 321.06
K. TOTAL INDIRECT COST 1,254.05
L. TOTAL UNIT COST Php 6742.22
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-3 Tubular Horizontal Grilles at ACU Ledge
Unit of Measurement : set Output/Manhour : 1.188 sq.m./hr
Output per hour : 0.244 set
SUB-TOTAL A 12,854.40
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 4.00 1.00 51.51 206.04
Laborers 5.00 1.00 39.73 198.65
-
-
-
SUB-TOTAL B 475.71
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
Welding Machine 1.00 1.00 391.00 391.00
SUB-TOTAL C 391.00
D. TOTAL D (B + C) 866.71
E. Output per hour 0.244 sq.m./hr
F. UNIT COST ( B + C)/E 3,552.09
G. TOTAL DIRECT UNIT COST ( A + F ) Php 16,406.49
H. OCM ( 9%) 1,476.58
I. Contractors Profit (8%) 1,312.52
J. 5%VAT 959.78
K. TOTAL INDIRECT COST 3,748.88
L. TOTAL UNIT COST Php 20,155.37
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-5 Stainless Railing at Ramp
Unit of Measurement : l.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.190 l.m.
SUB-TOTAL A 2,310.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
Welding Machine 1.00 1.00 391.00 391.00
SUB-TOTAL C 391.00
D. TOTAL D (B + C) 553.26
E. Output per hour 0.190 l.m./hr
F. UNIT COST ( B + C)/E 2,911.89
G. TOTAL DIRECT UNIT COST ( A + F ) Php 5,221.89
H. OCM ( 9%) 469.97
I. Contractors Profit (8%) 417.75
J. 5%VAT 305.48
K. TOTAL INDIRECT COST 1,193.20
L. TOTAL UNIT COST Php 6,415.10
DETAILED UNIT PRICE ANALYSIS
Job : Standard
SPL-6 DistrictStair
Engineering Office Building
Railing, 50mmØ Surigao
G.I. Pipe del&Sur
Handrail 1st DEO
19mm
Item No./ Description : Square Bar Railing (0.90 m high)
Unit of Measurement : l.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 1.000 l.m.
SUB-TOTAL A 1,564.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
Welding Machine 1.00 1.00 391.00 391.00
SUB-TOTAL C 391.00
D. TOTAL D (B + C) 553.26
E. Output per hour 1.000 l.m./hr
F. UNIT COST ( B + C)/E 553.26
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,117.26
H. OCM ( 9%) 190.55
I. Contractors Profit (8%) 169.38
J. 5%VAT 123.86
K. TOTAL INDIRECT COST 483.79
L. TOTAL UNIT COST Php 2,601.05
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-4 Stair Nosing, 6mm thk. Non-skid Metal Nosing Strip
Unit of Measurement : l.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 1.500 l.m.
Stair Nosing, 6mm thk. Non-skid Metal Nosing Strip l.m. 1.000 250.00 250.00
SUB-TOTAL A 250.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 1.500 sq.m./hr
F. UNIT COST ( B + C)/E 108.17
G. TOTAL DIRECT UNIT COST ( A + F ) 358.17
H. OCM ( 9%) 32.24
I. Contractors Profit (8%) 28.65
J. 5%VAT 20.95
K. TOTAL INDIRECT COST 81.84
L. TOTAL UNIT COST 440.02
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-7 38mmØ Stainless Steel L-Type Fixed Grab Rail (at toilet)
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.222 pcs
38mmØ Stainless Steel L-Type Fixed Grab Rail (at toilet) including
accessories and incidentals to complete l.m. 1.000 3,400.00 3,400.00
SUB-TOTAL A 3,400.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.222 sq.m./hr
F. UNIT COST ( B + C)/E 730.90
G. TOTAL DIRECT UNIT COST ( A + F ) Php 4,130.90
H. OCM ( 9%) 371.78
I. Contractors Profit (8%) 330.47
J. 5%VAT 241.66
K. TOTAL INDIRECT COST 943.91
L. TOTAL UNIT COST Php 5,074.81
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-8 38mmØ Stainless Steel Movable Grab Bar (at toilet)
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.353 pcs
SUB-TOTAL A 2,125.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.353 sq.m./hr
F. UNIT COST ( B + C)/E 459.66
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,584.66
H. OCM ( 9%) 232.62
I. Contractors Profit (8%) 206.77
J. 5%VAT 151.20
K. TOTAL INDIRECT COST 590.59
L. TOTAL UNIT COST Php 3,175.25
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-9 12 mm thk. Laminated Compact Board Urinal Partition 400 x 900 mm
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.333 pcs
SUB-TOTAL A 1,512.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.333 sq.m./hr
F. UNIT COST ( B + C)/E 486.78
G. TOTAL DIRECT UNIT COST ( A + F ) Php 1,998.78
H. OCM ( 9%) 179.89
I. Contractors Profit (8%) 159.90
J. 5%VAT 116.93
K. TOTAL INDIRECT COST 456.72
L. TOTAL UNIT COST Php 2,455.50
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-10 Tilted Facial Mirror (at toilet for PWD)
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.500 pcs
Tilted Facial Mirror (at toilet for PWD) pcs 1.000 2,000.00 2,000.00
SUB-TOTAL A 2,000.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.500 sq.m./hr
F. UNIT COST ( B + C)/E 324.52
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,324.52
H. OCM ( 9%) 209.21
I. Contractors Profit (8%) 185.96
J. 5%VAT 135.98
K. TOTAL INDIRECT COST 531.15
L. TOTAL UNIT COST Php 2,855.67
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-11 Facial Mirror 1400 x 600 mm (at toilet for women)
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.400 pcs
Facial Mirror 1400 x 600 mm (at toilet for women) sq.m. 0.840 2,700.00 2,268.00
SUB-TOTAL A 2,268.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.400 sq.m./hr
F. UNIT COST ( B + C)/E 405.65
G. TOTAL DIRECT UNIT COST ( A + F ) Php 2,673.65
H. OCM ( 9%) 240.63
I. Contractors Profit (8%) 213.89
J. 5%VAT 156.41
K. TOTAL INDIRECT COST 610.93
L. TOTAL UNIT COST Php 3,284.58
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-12 12 mm thk. Laminated Compact Bd./Phenolic Cubicle Pa
Unit of Measurement : lot Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.167 lot
12 mm thk. Laminated Compact Bd./Phenolic Cubicle Partition sq.m. 0.840 4,270.00 3,586.80
SUB-TOTAL A 3,586.80
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.167 sq.m./hr
F. UNIT COST ( B + C)/E 971.62
G. TOTAL DIRECT UNIT COST ( A + F ) Php 4,558.42
H. OCM ( 9%) 410.26
I. Contractors Profit (8%) 364.67
J. 5%VAT 266.67
K. TOTAL INDIRECT COST 1,041.60
L. TOTAL UNIT COST Php 5,600.01
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-13 RC Counter with Polished Pure/Natural Granite Slab Counter Top Finish
Unit of Measurement : pcs Output/Manhour : 0.000 sq.m./hr
Output per hour : 0.150 pcs
SUB-TOTAL A 4,200.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 0.150 sq.m./hr
F. UNIT COST ( B + C)/E 1,081.73
G. TOTAL DIRECT UNIT COST ( A + F ) Php 5,281.73
H. OCM ( 9%) 475.36
I. Contractors Profit (8%) 422.54
J. 5%VAT 308.98
K. TOTAL INDIRECT COST 1,206.88
L. TOTAL UNIT COST Php 6,488.61
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-14 50 x 100 mm Decorative Tubular Steel Horizontal Grilles
Unit of Measurement : l.m. Output/Manhour : 0.000 sq.m./hr
Output per hour : 19.000 l.m.
50 x 100 mm Decorative Tubular Steel Horizontal Grilles l.m. 1.050 30.00 31.50
SUB-TOTAL A 31.50
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
Welding Machine 1.00 1.00 391.00 391.00
SUB-TOTAL C 391.00
D. TOTAL D (B + C) 553.26
E. Output per hour 19.000 l.m./hr
F. UNIT COST ( B + C)/E 29.12
G. TOTAL DIRECT UNIT COST ( A + F ) 60.62
H. OCM ( 9%) 5.46
I. Contractors Profit (8%) 4.85
J. 5%VAT 3.55
K. TOTAL INDIRECT COST 13.85
L. TOTAL UNIT COST 74.47
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1003(3) Cabinet, Table, Chair and Cubicle
Unit of Measurement : lot Output/Manhour : 0.000 sq.m./hr
Output per hour : 1.000 lot
-
-
-
SUB-TOTAL B 61,852.80
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 61,852.80
E. Output per hour 1.000 l.m./hr
F. UNIT COST ( B + C)/E 61,852.80
G. TOTAL DIRECT UNIT COST ( A + F ) 1747238.06
H. OCM ( 9%) 157,251.43
I. Contractors Profit (8%) 139,779.04
J. 5%VAT 102,213.43
K. TOTAL INDIRECT COST 399,243.90
L. TOTAL UNIT COST 2,146,481.96
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 403(1)a Steel Framing (Fabrication)
Unit of Measurement : kgs Output/Manhour : kg/hr
Output per hour : 69.360 kgs
Structural Steel Framing including cross bracings, purlins, kg 1.000 47.00 47.00
anchorbolts, and incidentals to complete
consumables (5% of material cost)
SUB-TOTAL A 47.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 782.00
D. TOTAL D (B + C) 983.99
E. Output per hour 69.360 kgs/hr
F. UNIT COST ( B + C)/E 14.19
G. TOTAL DIRECT UNIT COST ( A + F ) 61.19
H. OCM ( 9%) 5.51
I. Contractors Profit (8%) 4.89
J. 5%VAT 3.58
K. TOTAL INDIRECT COST 13.98
L. TOTAL UNIT COST 75.17
SUB-TOTAL A -
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C 1,486.65
D. TOTAL D (B + C) 1,688.64
E. Output per hour 137.500 kgs/hr
F. UNIT COST ( B + C)/E 12.28
G. TOTAL DIRECT UNIT COST ( A + F ) 12.28
H. OCM ( 9%) 1.11
I. Contractors Profit (8%) 0.98
J. 5%VAT 0.72
K. TOTAL INDIRECT COST 2.81
L. TOTAL UNIT COST 15.09
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1014 Pre-painted G.I. Roofing Sheet Long Span
Unit of Measurement : sq.m. Output/Manhour : 1.04 sq.m.
Output per hour : 2.769 sq.m.
Pre-painted G.I. Roofing Sheet Long Span sq.m. 1.000 560.00 560.00
Teckscrew pcs 9.000 2.00 18.00
Sealant qrt 0.019 160.00 3.04
SUB-TOTAL A 581.04
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
-
-
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 2.77
F. UNIT COST ( B + C)/E 72.95
G. TOTAL DIRECT UNIT COST ( A + F ) Php 653.99
H. OCM ( 9%) 58.86
I. Contractors Profit (8%) 52.32
J. 5%VAT 38.26
K. TOTAL INDIRECT COST 149.44
L. TOTAL UNIT COST Php 803.42
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1013(2)b End Wall Flashing, 0.60mm THK. Pre-formed Pre-Painted
Unit of Measurement : l.m. Output/Manhour : 5.31 l.m./Mhr
Output per hour : 10.600 l.m.
End Wall Flashing, 0.60mm THK. Pre-formed Pre-Painted l.m. 1.00 396.00 396.00
teckscrew pcs 10.00 2.00 20.00
blind rivets pcs 2.00 1.50 3.00
SUB-TOTAL A 419.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
-
-
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 10.60 l.m./hr
F. UNIT COST ( B + C)/E 19.06
G. TOTAL DIRECT UNIT COST ( A + F ) Php 438.06
H. OCM ( 9%) 46.10
I. Contractors Profit (8%) 40.98
J. 5%VAT 29.97
K. TOTAL INDIRECT COST 117.04
L. TOTAL UNIT COST Php 629.28
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1013(2)a Ridge Roll, 0.60mm THK., Pre-formed Pre-Painted
Unit of Measurement : l.m. Output/Manhour : 5.31 l.m.
Output per hour : 10.600 l.m.
Ridge Roll, 0.60mm THK., Pre-formed Pre-Painted l.m. 1.00 250.00 250.00
teckscrew pcs 10.00 2.00 20.00
blind rivets pcs 2.00 1.50 3.00
SUB-TOTAL A 273.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 1.00 1.00 39.73 39.73
-
-
-
-
-
-
-
-
SUB-TOTAL B 162.26
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 162.26
E. Output per hour 10.60 l.m./hr
F. UNIT COST ( B + C)/E 15.31
G. TOTAL DIRECT UNIT COST ( A + F ) Php 288.31
H. OCM ( 9%) 25.95
I. Contractors Profit (8%) 23.06
J. 5%VAT 16.87
K. TOTAL INDIRECT COST 65.88
L. TOTAL UNIT COST Php 354.19
UNIT PRICE ANALYSIS
INSTALLATION OF STREET LIGHT FROM CROSSING VICTORIA TO PURISIMA ROAD SECTIO
JOB :
Item No. / Description : Err:509 Err:509
Quantity : 196.00 sq.m.
SUB-TOTAL (A)
QUANTITY
B. LABOR COST Hourly Rate
No. Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
C. EQUIPMENT COST Hourly Rate
No. of Equipt. Total Hours
SUB-TOTAL ( C )
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
UNIT PRICE ANALYSIS
JOB :
Item No. / Description : 900(1)b2 Concrete ( 17Mpa)
Quantity : #NAME? cu.m.
SUB-TOTAL (A)
QUANTITY
B. LABOR COST Hourly Rate
No. Personnel Total Hours
SUB-TOTAL (B)
QUANTITY
C. EQUIPMENT COST Hourly Rate
No. of Equipt. Total Hours
SUB-TOTAL ( C )
D. TOTAL DIRECT COST (A + B + C)
UNIT COST
CTORIA TO PURISIMA ROAD SECTION W/ CENTER ISLAND
TOTAL COST
225,400.00
-
-
225,400.00
Total Cost
4.00
2,344.96 6
3,914.24 5%
5,228.80
11,488.00
Total Cost
-
-
-
236,888.00
28,426.56 12%
18,951.04 8%
14,213.28 5%
61,590.88
298,478.88
1,522.85
TOTAL COST
#NAME?
#NAME?
#NAME?
#NAME?
Total Cost
2,344.96
3,914.24
10,457.60 4 8
16,716.80
Total Cost
-
-
-
#NAME?
12%
8%
#NAME? 5%
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?
= 3.50
8.00
8
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : SPL-15 Multi-Co Polymerized Resin Based Waterproofing (at Parapet/Gutter)
Unit of Measurement : sq.m. Output/Manhour : kg/hr
Output per hour : 1.500 sq.m.
SUB-TOTAL A 1,150.00
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
-
-
-
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 1.500 sq.m./hr
F. UNIT COST ( B + C)/E 134.66
G. TOTAL DIRECT UNIT COST ( A + F ) Php 1,284.66
H. OCM ( 9%) 115.62
I. Contractors Profit (8%) 102.77
J. 5%VAT 75.15
K. TOTAL INDIRECT COST 293.54
L. TOTAL UNIT COST Php 1,578.20
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1032 (1)a Painting on Concrete
Unit of Measurement : sq.m. Output/Manhour : 2.09 sq.m./hr
Output per hour : 4.183 sq.m.
SUB-TOTAL A 140.40
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 3.00 1.00 51.51 154.53
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 305.01
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 305.01
E. Output per hour 4.18 sq.m./hr
F. UNIT COST ( B + C)/E 72.92
G. TOTAL DIRECT UNIT COST ( A + F ) 213.32
H. OCM ( 9%) 19.20
I. Contractors Profit (8%) 17.07
J. 5%VAT 12.48
K. TOTAL INDIRECT COST 48.74
L. TOTAL UNIT COST 262.07
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1032(1)b Painting on Metal
Unit of Measurement : sq.m. Output/Manhour : 1.05 sq.m./hr
Output per hour : 2.100 sq.m.
SUB-TOTAL A 157.34
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 2.10 sq.m./hr
F. UNIT COST ( B + C)/E 96.19
G. TOTAL DIRECT UNIT COST ( A + F ) 253.53
H. OCM ( 9%) 22.82
I. Contractors Profit (8%) 20.28
J. 5%VAT 14.83
K. TOTAL INDIRECT COST 57.93
L. TOTAL UNIT COST 311.46
SUB-TOTAL A 147.42
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 3.00 1.00 51.51 154.53
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 305.01
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 305.01
E. Output per hour 4.18 sq.m./hr
F. UNIT COST ( B + C)/E 72.92
G. TOTAL DIRECT UNIT COST ( A + F ) 220.34
H. OCM ( 9%) 19.83
I. Contractors Profit (8%) 17.63
J. 5%VAT 12.89
K. TOTAL INDIRECT COST 50.35
L. TOTAL UNIT COST 270.69
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1032(1)c Wood Painting
Unit of Measurement : sq.m. Output/Manhour : 0.95 sq.m./hr
Output per hour : 1.890 sq.m.
SUB-TOTAL A 103.13
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Foreman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 1.89 sq.m./hr
F. UNIT COST ( B + C)/E 106.87
G. TOTAL DIRECT UNIT COST ( A + F ) 210.00
H. OCM ( 9%) 18.90
I. Contractors Profit (8%) 16.80
J. 5%VAT 12.29
K. TOTAL INDIRECT COST 47.99
L. TOTAL UNIT COST 257.99
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(1) Sewer and Drainange Lines
Unit of Measurement : lot Output/Manhour : kg/hr
Output per hour : 0.003 lot
-
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
-
-
-
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.003 lot/hr
F. UNIT COST ( B + C)/E 67,330.00
G. TOTAL DIRECT UNIT COST ( A + F ) Php 427,843.00
H. OCM ( 9%) 38,505.87
I. Contractors Profit (8%) 34,227.44
J. 5%VAT 25,028.82
K. TOTAL INDIRECT COST 97,762.13
L. TOTAL UNIT COST Php 525,605.13
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(2) Waterlines
Unit of Measurement : lot Output/Manhour : kg/hr
Output per hour : 0.015 lot
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.015 lot/hr
F. UNIT COST ( B + C)/E 13,466.00
G. TOTAL DIRECT UNIT COST ( A + F ) Php 98,573.60
H. OCM ( 9%) 8,871.62
I. Contractors Profit (8%) 7,885.89
J. 5%VAT 5,766.56
K. TOTAL INDIRECT COST 22,524.07
L. TOTAL UNIT COST Php 121,097.67
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(3) Sanitary Fixtures and Accessories
Unit of Measurement : lot Output/Manhour : kg/hr
Output per hour : 0.012 lot
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.012 lot/hr
F. UNIT COST ( B + C)/E 16,832.50
G. TOTAL DIRECT UNIT COST ( A + F ) Php 309,592.50
H. OCM ( 9%) 27,863.33
I. Contractors Profit (8%) 24,767.40
J. 5%VAT 18,111.16
K. TOTAL INDIRECT COST 70,741.89
L. TOTAL UNIT COST Php 380,334.39
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(4) Septic Vault (Type E)
Unit of Measurement : set Output/Manhour : kg/hr
Output per hour : 0.005 set
SUB-TOTAL A 170,963.80
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.005 lot/hr
F. UNIT COST ( B + C)/E 40,398.00
G. TOTAL DIRECT UNIT COST ( A + F ) Php 211,361.80
H. OCM ( 9%) 19,022.56
I. Contractors Profit (8%) 16,908.94
J. 5%VAT 12,364.67
K. TOTAL INDIRECT COST 48,296.17
L. TOTAL UNIT COST Php 259,657.97
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(5)a Catch Basin 1
Unit of Measurement : set Output/Manhour : kg/hr
Output per hour : 0.375 set
SUB-TOTAL A 2,700.78
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.375 lot/hr
F. UNIT COST ( B + C)/E 538.64
G. TOTAL DIRECT UNIT COST ( A + F ) Php 3,239.42
H. OCM ( 9%) 291.55
I. Contractors Profit (8%) 259.15
J. 5%VAT 189.51
K. TOTAL INDIRECT COST 740.21
L. TOTAL UNIT COST Php 3,979.63
DETAILED UNIT PRICE ANALYSIS
Job : Standard District Engineering Office Building Surigao del Sur 1st DEO
Item No./ Description : 1002(5)b Catch Basin 2
Unit of Measurement : set Output/Manhour : kg/hr
Output per hour : 0.300 set
SUB-TOTAL A 3,451.50
B. LABOR COST QUANTITY Hourly Total
No. Personnel Total Hours Rate Cost
-
Construction Leadman 1.00 1.00 71.02 71.02
Skilled Laborers 1.00 1.00 51.51 51.51
Laborers 2.00 1.00 39.73 79.46
-
-
-
SUB-TOTAL B 201.99
C. EQUIPMENT COST QUANTITY Hourly Total
No. of Equipt. Total Hours Rate Cost
-
-
SUB-TOTAL C -
D. TOTAL D (B + C) 201.99
E. Output per hour 0.300 lot/hr
F. UNIT COST ( B + C)/E 673.30
G. TOTAL DIRECT UNIT COST ( A + F ) Php 4,124.80
H. OCM ( 9%) 371.23
I. Contractors Profit (8%) 329.98
J. 5%VAT 241.30
K. TOTAL INDIRECT COST 942.52
L. TOTAL UNIT COST Php 5,067.32