Professional Documents
Culture Documents
S M C - A A I B: Implified Odel For Omputer Ided Nalysis of Ntegral Ridges by Murat Dicleli
S M C - A A I B: Implified Odel For Omputer Ided Nalysis of Ntegral Ridges by Murat Dicleli
INTEGRAL BRIDGES
By Murat Dicleli1
ABSTRACT: This paper presents a computer-aided approach for the design of integral-abutment bridges. An
analysis procedure and a simplified structure model are proposed for the design of integral-abutment bridges
considering their actual behavior and load distribution among their various components. A computer program,
for the analysis of integral-abutment bridges, has been developed using the proposed analysis procedure and
structure model. The program is capable of analyzing an integral-abutment bridge for each construction stage
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.
and carrying the effects of applied loads on the structure members from a previous construction stage to the
next. The proposed analysis methods and structure models are compared with the conventional analysis method
and structure model currently used by many structural engineers for the design of integral-abutment bridges.
The benefits of using the proposed analysis method and simplified structure model for the design of integral-
abutment bridges are discussed. It was concluded that it may be possible to obtain more sound and economical
designs for integral-abutment bridges using the proposed analysis method and structure model.
1
Asst. Prof., Dept. of Civ. Engrg. and Constr., Bradley Univ., 1501 W.
Bradley Ave., Peoria, IL 61625. E-mail: mdicleli@usa.net
Note. Discussion open until January 1, 2001. To extend the closing
date one month, a written request must be filed with the ASCE Manager
of Journals. The manuscript for this paper was submitted for review and
possible publication on July 17, 1998. This paper is part of the Journal
of Bridge Engineering, Vol. 5, No. 3, August, 2000. 䉷ASCE, ISSN
1084-0702/00/0003-0240–0248/$8.00 ⫹ $$.50 per page. Paper No.
18806. FIG. 1. Typical Two-Span Integral-Abutment Bridge
Abendroth et al. 1989; Abendroth and Greimann 1989; Girton girders, and abutments. The effects of temperature variation,
et al. 1991). It may be speculated that the repetitive variation soil pressure, and live load are considered in this final stage.
of temperature and the effect of live load may cause low cycle
fatigue in the piles (Burke 1988). A hinge connection detail Soil-Structure Interaction
between the piles and the abutment may prevent such a po-
tentially destructive problem. The earth pressure coefficient is a function of the displace-
ment or rotation of the earth retaining structure. An integral-
PROPOSED ANALYSIS METHOD abutment bridge will experience elongation and contraction
due to temperature variations during its service life. Thus, the
Construction Stages and Loads earth pressure at the abutments should be considered in cor-
relation with temperature variation. A very small displacement
The construction of an integral-abutment bridge is done in
of the bridge away from the backfill soil can cause the devel-
stages. Therefore, it must be analyzed for each construction
opment of active earth pressure conditions (Barker et al. 1991;
stage to ensure that the structure has adequate capacity to sus-
Ministry 1991). Therefore, when the bridge contracts due to a
tain the applied loads particular to the stage under considera-
decrease in temperature, active earth pressure will be devel-
tion.
oped behind the abutment. At rest earth pressure behind the
Two stages are considered for the design of slab-on-pre-
abutment is assumed when there is no thermal movement.
stressed-concrete-girder integral-abutment bridges. The loads
When the bridge elongates due to an increase in temperature,
applied at each stage are listed in Table 1. In the first stage
the intensity of the earth pressure behind the abutment depends
the slab concrete is assumed to be wet. Accordingly, the pre-
on the magnitude of the bridge displacement toward the back-
stressed-concrete girders alone resist the applied loads. The
fill soil. The actual earth pressure coefficient K may change
structure is analyzed for the effects of prestressing force, dead
between at rest Ko and passive Kp earth pressure coefficients
weight of the girders, weight of wet concrete slab, and weight
depending on the amount of displacement. Past researchers
of the diaphragms. In the second stage the bridge is assumed
obtained the variation of earth pressure coefficient as a func-
to be in service. Full composite action is considered between
tion of structure displacement from experimental data and fi-
the slab, girders, and abutments. The effects of superimposed
nite-element analyses (Barker et al. 1991; Clough and Duncan
dead loads, asphalt weight, temperature variation, soil pres-
1991). For practical purposes, this variation is assumed to be
sure, and live load are considered in this stage.
linear, as shown in Fig. 4. This linear relationship is expressed
Three stages are considered for the design of slab-on-steel-
as
girder integral-abutment bridges. The loads applied at each
stage are listed in Table 2. In the first stage, the naked steel K = Ko ⫹ d ⱕ Kp (1)
girders are assumed to be fully assembled and supported on
the abutments and piers, but the slab concrete is assumed to where d = displacement of the integral-abutment bridge toward
the backfill soil; and = slope of the earth pressure variation
TABLE 1. Summary of Stage Loading for Slab-on-Pre- depicted in Fig. 4. The value of varies as a function of the
stressed-Concrete-Girder Deck Integral-Abutment Bridges backfill soil type. Typical values of for various soil types
are provided elsewhere (Barker et al. 1991).
Stage Stage name Load Load description
The soil-structure interaction as a result of positive temper-
(1) (2) (3) (4)
ature variation is illustrated in Fig. 5, which consists of three
1 Simply supported beams 1 Self-weight of girder separate sketches. The sketch at the top illustrates the structure
2 Pretensioning
3 Weight of wet concrete slab, dia-
model used to formulate the effect of positive temperature var-
phragms, and abutment iation on the magnitude of earth pressure coefficient. The
2 Composite structure 4 Superimposed dead load (e.g., structure model is obtained by conservatively neglecting the
in sidewalks, curbs, medians)
5 Asphalt weight
6 Long-term prestress losses
7 Highway live loading and side-
walk load, or pedestrian loads
at fatigue limit state
8 As load 7 but at serviceability
limit state
9 As load 7 but at ULS
10 Thermal load due to longitudi-
nal expansion
11 Thermal load due to longitudi-
nal contraction
12 Passive earth pressure
13 At rest earth pressure
14 Active earth pressure FIG. 4. Variation of Passive Earth Pressure Coefficient as
Function of Structure Displacement toward Backfill
Ld
Substituting (7) into (1) and simplifying, the earth pressure
FIG. 5. Soil-Structure Interaction at Abutment
coefficient K for the backfill soil is expressed as follows:
resistance of the piers, abutments, and piles to the longitudinal 2Ko ⫹ ␣␦TLd
movement of the structure. In the top sketch, Ld is the span K= ⱕ Kp (8)
Ld h2we␥s
length of the bridge, and kd is the axial stiffness of the modeled 2⫹
2Eg(Ag ⫹ nAs)
bridge deck. The model is considered to have an effective
width we equal to the spacing of girders. The middle sketch
shows the free displacement do of the bridge deck due to a PROPOSED STRUCTURE MODEL
positive temperature variation neglecting the restraint provided For the computer-aided analysis of integral-abutment
by the soil. The sketch at the bottom illustrates the final dis- bridges subjected to gravitational loads, a separate structure
placement d of the bridge deck considering the combined ef- model is proposed for each construction stage. The proposed
fects of positive temperature variation and the earth pressure structure models are subject to the following assumptions:
force Fs behind the abutment.
The axial stiffness of the modeled bridge deck is expressed • The analysis of bridges having slab-on-girder-type deck
as follows: is reduced to the consideration of one beam and an effec-
2Eg(Ag ⫹ nAs) tive width of the slab for the purpose of gravity load anal-
kd = (2) ysis. Accordingly, the abutments are idealized to have a
Ld
tributary width equal to that of the slab. Similarly, the
where Eg = modulus of elasticity of the girder material; Ag = number of piers and piles per tributary width is calculated,
cross-sectional area of the girder; As = cross-sectional area of and their stiffness is lumped to obtain a single pier or pile
the portion of the deck slab with an effective width equal to element for analysis purposes.
the spacing of girders; and n = modular ratio defined as the • The effect of frictional forces between the approach slab
ratio of the elastic modulus of slab material to that of girder and soil as well as between the wing-walls and soil, re-
material. sulting from movements due to temperature variations, is
Assuming nearly identical abutment configurations at both ignored.
sides of the bridge and neglecting the translational stiffness of • An equivalent pile length is assumed in the structural
the piles in the longitudinal direction, the earth pressure force model.
acting on the abutment is assumed to be completely transferred • The live load applied on the structure is proportioned to
to the bridge deck. Then, assuming a triangular earth pressure
distribution behind the abutment, the earth pressure force Fs
is expressed as
1 2
Fs = h we␥s K (3)
2
2Eg(Ag ⫹ nAs)
Fd = (do ⫺ d ) (5)
Ld
Connection Elements
Connection elements are used to define the rotational and/
or translational stiffness of the joints at various parts of an
integral-abutment bridge. These elements have an infinitesimal
length of 10 mm.
The connection element at the deck-abutment joint, shown
in Fig. 10, is used to idealize the rotational stiffness of the
connection between the deck and the abutment. Normally, if
adequate continuity is provided between the slab, girders, and
abutment using a proper reinforcement detailing, connection
FIG. 9. Models for Pile Element elements are assumed as rigid. Otherwise, the joint may be
idealized as hinge or semirigid by adjusting the stiffness of
fixed support condition at its base as illustrated in Figs. 7 and the connection element. For hinge idealization, the connection
9. element is assigned a very small flexural stiffness to permit
If the soil-spring model shown in Fig. 9 is preferred to ide- free rotation of the deck (1/1,000 of the abutment stiffness).
alize the pile, the actual pile length must be used in the model. For semirigid idealization, the connection element is assigned
The pile element must be divied into a number of equal seg- a flexural stiffness smaller than that of the abutment to allow
ments. Then, using the coefficient of subgrade reaction for the some relative rotation of joint elements. If the piles are rigidly
foundation soil, the lateral stiffness of the soil must be cal- fixed to the abutment, the connection element at the abutment-
culated at each node level along the pile member. Then, spring pile joint, shown in Fig. 10, is assigned stiffness properties
elements with the calculated lateral soil stiffness are attached equal to those of the idealized pile element. For a pin con-
to each node. The base of the pile is assumed to have a roller nection at the piles’ ends, the connection element is assigned
pin support. In the case of friction piles, the roller in the model a stiffness equal to 1/1,000 of that of the idealized pile ele-
shown in Fig. 9 must be replaced with a vertical spring with ment.
a stiffness representing the relationship between the displace- If the deck is isolated by a set of bearings from the pier,
ment and frictional resistance of the pile. then the connection element at the deck-pier joint, shown in
Fig. 10, is used to idealize the stiffness of the bearings. The
Joint Elements connection element is assumed as rigid if the pier is mono-
lithically connected to the bridge deck. For piers fixed to a
The joint elements shown in Figs. 7 and 10 are used to rigid foundation, the connection element at the idealized pier
idealize the geometry and stiffness of the bridge components base, shown in Fig. 10, is assigned stiffness properties equal
within the joints. Element 1 in Fig. 10 is used to idealize the to those of the idealized pier element. For a pin connection at
stiffness of the deck within the joint. Its length extends from the pier base, the connection element is assigned a stiffness
the geometric centerline of the abutment element to the face equal to 1/1,000 of that of the idealized pier element. The
of the abutment. Obviously, the moment of inertia of the deck rotational stiffness of the foundation can also be modeled us-
element within the joint is very high as any cross section taken ing the connection element at the pier base.
at that location has a vertical dimension equal to the sum of
the deck depth and the abutment height up to the soffit. There- COMPUTER-AIDED ANALYSIS OF
fore, the part of the deck within the joint is modeled as a rigid INTEGRAL-ABUTMENT BRIDGES
element. Similarly, element 2 in Fig. 10 is used to model the
part of the abutment within the joint as a rigid element. Ele- A computer program is developed for the analysis of inte-
ment 3 is also modeled as a rigid member. Nonetheless, it does gral-abutment bridges using the proposed analysis method and
not have any structural significance. It is used to enable the structure model. The developed computer program uses an in-
JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000 / 245
COMPARATIVE STUDY
The relative stiffness of horizontal and vertical components
in a rigid frame dictates the distribution of forces and mo-
ments. Accordingly, the ratio of deck bending stiffness to
equivalent abutment stiffness is an important characteristic of
an integral-abutment bridge. The equivalent abutment stiffness
is the stiffness of a single member that represents the com-
bined performance of the abutment and piles. This ratio is
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.
used in the analysis of the bridge. For both bridges the gran- is also developed and implemented in the computer program.
ular backfill soil at the abutments has a unit weight of 20 kN/ The program is capable of analyzing integral-abutment bridges
m3 and an angle of internal friction of 30⬚. The slope of the for each construction stage and carrying the effects of applied
passive earth pressure variation is obtained as 24 m⫺1 for the loads on the structure members from a previous construction
backfill soil. The full passive earth pressure condition is as- stage to the next. The analysis method and structure model
sumed to develop at the abutments for the conventional employed in the developed computer program are compared
method. Accordingly, a passive earth pressure coefficient of with the conventional analysis method and structure model
3.0 is obtained. For the proposed method, the passive earth currently used by many structural engineers for the design of
pressure coefficient is calculated as 0.56 for the first bridge integral-abutment bridges in North America and Europe. The
and 0.68 for the second bridge using (8). The bridges are an- following are observed:
alyzed considering all possible load combinations at the ulti-
mate limit states (ULS). The optimum responses obtained from • The conventional analysis method neglects the continuity
both design methods are then compared. of the structure at the deck-pier and deck-abutment joints
Analysis results for the first bridge demonstrated that at the for the deck design. The proposed structure model used
ULS the maximum span moment obtained from the conven- in the program reflects the effect of the continuity at such
tional method (10,543 kN ⭈ m) is 25% larger than that obtained joints on the performance of the bridge deck.
from the proposed method (8,471 kN ⭈ m). This discrepancy is • The effect of axial load in the deck due to earth pressure
a result of the assumptions made in the conventional method, forces at the abutments is neglected in the conventional
where the beneficial effects of continuity at the joints and earth analysis method. Such effects are fully considered in the
pressure forces applied at the abutments, in reducing the span proposed analysis method and structure model.
moment, are neglected. It is noteworthy that the maximum • The conventional analysis method recommends the use of
span moment obtained from the proposed method is due to full passive pressure for the design of deck-abutment
the combined effects of dead load, live load, temperature de- joints. The proposed soil-structure interaction model may
crease, and active earth pressure. The conventional design result in smaller earth pressure forces, which may lead to
method also yields much larger forces at the deck-abutment a more economical deck-abutment joint design.
joints. The maximum deck moment obtained at the deck-abut- • For single-span bridges, the conventional analysis method
ment joint is 7,691 kN ⭈ m for the conventional method and does not consider the beneficial effect of earth pressure
2,716 kN ⭈ m for the proposed method. Similar differences also forces applied at abutments when calculating the maxi-
are obtained for the forces in the abutments and piles. The mum span moment for the deck design. The proposed
maximum moment at the abutment top is 1,142 kN ⭈ m/m for structure model considers such beneficial effects in the
the conventional method and 587 kN ⭈ m/m for the proposed design of the deck.
method. This discrepancy is mainly due to the differences in • The comparison of analysis results from the conventional
the magnitude of the passive earth pressure forces used by the and proposed analysis methods demonstrated that it may
conventional and proposed methods. The conventional method be possible to obtain more economical designs using the
considers a full passive earth pressure at the abutments, proposed analysis method and structure model.
whereas the proposed method considers only a partial passive
earth pressure as a function of structure movement and soil APPENDIX. REFERENCES
properties. The moment at the abutment bottom and pile top AASHTO. (1994). AASHTO LRFD bridge design specifications, 1st Ed.,
is obtained as zero because a hinge connection at the pile- Washington, D.C.
abutment joint was assumed in the analysis. It is noteworthy Abendroth, R. E., and Greimann, L. F. (1989). ‘‘A rational design ap-
that the ultimate resistance of the piles exceeds the maximum proach for integral-abutment bridge piles.’’ Transp. Res. Rec. 1233,
Transportation Research Board, Washington, D.C., 12–23.
responses for all load cases. Abendroth, R. E., Greimann, L. F., and Ebner, P. B. (1989). ‘‘Abutment
Analysis results for the second bridge demonstrated that at pile design for jointless bridges.’’ J. Struct. Engrg., ASCE, 115(11),
the ULS comparable span moments are obtained from both 2914–2929.
methods (the maximum moments for the side and center spans Barker, R. M., Duncan, J. M. K., Rojiani, K. B., Ooi, P. S. K., and Kim,
are, respectively, 1,272 and 1,950 kN ⭈ m for the conventional S. G. (1991). ‘‘Manuals for the design of bridge foundations.’’ NCHRP
and 1,244 and 1,953 kN ⭈ m for the proposed methods). How- Rep. 343, Transportation Research Board, National Research Council,
Washington, D.C.
ever, the maximum moment at the inner supports obtained Burke, M. P., Jr. (1988). ‘‘Bridge deck joints.’’ NCHRP Synthesis of Hwy.
from the conventional method (993 kN ⭈ m) is 17% larger than Pract., No. 141, Transportation Research Board, National Research
that obtained from the proposed method (848 kN ⭈ m). The Council, Washington, D.C.
above results demonstrate that for continuous bridges, the con- Burke, M. P., Jr. (1990a). ‘‘Integral bridge design is on the rise.’’ AISC
tinuity at the deck-abutment joints and the earth pressure Modern Steel Constr., 30(4), 9–11.
Burke, M. P., Jr. (1990b). ‘‘Integral bridges.’’ Transp. Res. Rec. 1275,
forces applied at the abutments may not have a major impact
Transportation Research Board, Washington, D.C.
on the span moments but may influence the inner support mo- Burke, M. P., Jr. (1993a). ‘‘Integral bridges: Attributes and limitations.’’
ments. The conventional method still yields much larger forces Transp. Res. Rec. 1393, Transportation Research Board, Washington,
at the deck-abutment joints. The deck moment obtained at the D.C., 1–8.
Girton, D. D., Hawkinson, T. R., and Greimann, L. F. (1991). ‘‘Validation search Board, Washington, D.C., 17–25.
of design recommendations for integral-abutment piles.’’ J. Struct. Steiger, D. J. (1993). ‘‘Jointless bridges provide fuel for controversy.’’
Engrg., ASCE, 117(7), 2117–2134. Roads and Bridges, 31(11), 48–54.
Girton, D. D., Hawkinson, T. R., Greimann, L. F., Bergenson, K., Ndon, Thippeswamy, H. K., Raju, P. R., and Gangarao, H. V. S. (1994).
U., and Abendorth, R. E. (1989). ‘‘Validation of design recommenda- ‘‘Parametric study of single-span jointless steel bridges.’’ Transp. Res.
tions for integral-abutment piles.’’ Proj. HR-292, Iowa Department of Rec. 1460, Transportation Research Board, Washington, D.C.
Transportation, Ames, Iowa. Wilson, E. L., and Habibullah, A. (1990). SAP 90, computer software for
Greimann, L. F., Abendtroth, R. E., Johnson, D. E., and Ebner, P. B. structural and earthquake engineering, Computers and Structures Inc.,
(1987). ‘‘Pile design and tests for integral-abutment bridges.’’ Final Berkeley, Calif.
Rep., Proj. HR-273, Iowa Department of Transportation, Ames, Iowa. Wolde-Tinsae, A. M., Klinger, J. E., and Mullangi, R. (1988a). ‘‘Bridge
Hambly, E. C., and Nicholson, B. A. (1990). ‘‘Prestressed beam integral deck joint rehabilitation or retrofitting.’’ Final Rep., Dept. of Civ.
bridges.’’ The Struct. Engr., London, 68(23), 474–481. Engrg., University of Maryland, College Park, Md.
Hamley, E. C. (1992). ‘‘Integral bridge abutment details in practice and Wolde-Tinsae, A. M., Klinger, J. E., and White, E. (1988b). ‘‘Performance
theory.’’ Transp. Res. Lab. Rec. 19, Crowthorne, U.K. of jointless bridges.’’ J. Perf. Constr. Fac., ASCE, 2(2), 111–125.