Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

SIMPLIFIED MODEL FOR COMPUTER-AIDED ANALYSIS OF

INTEGRAL BRIDGES
By Murat Dicleli1

ABSTRACT: This paper presents a computer-aided approach for the design of integral-abutment bridges. An
analysis procedure and a simplified structure model are proposed for the design of integral-abutment bridges
considering their actual behavior and load distribution among their various components. A computer program,
for the analysis of integral-abutment bridges, has been developed using the proposed analysis procedure and
structure model. The program is capable of analyzing an integral-abutment bridge for each construction stage
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

and carrying the effects of applied loads on the structure members from a previous construction stage to the
next. The proposed analysis methods and structure models are compared with the conventional analysis method
and structure model currently used by many structural engineers for the design of integral-abutment bridges.
The benefits of using the proposed analysis method and simplified structure model for the design of integral-
abutment bridges are discussed. It was concluded that it may be possible to obtain more sound and economical
designs for integral-abutment bridges using the proposed analysis method and structure model.

INTRODUCTION piers are usually idealized as simple roller supports in most


cases. The bridge is designed considering the effect of the
In the past, the construction of rigid-frame bridges, which loads at the final stage assuming a completed structure. The
could be categorized as a class of integral-abutment bridges, effect of seismic forces is usually neglected assuming that this
was accompanied by the construction of multiple-span bridges type of structures are not prone to such forces because of their
with discontinuous decks or movable joints. Expansion or continuity (Burke 1993a,b). A more detailed description of this
movable joints on bridges have provided considerable main- conventional design procedure, which is used by many bridge
tenance problems for transportation agencies (Burke 1988, engineers in North America and Europe, will be reported in
1990a; Wolde et al. 1988a,b; Steiger 1993). Consequently, the upcoming sections.
bridge engineers have been trying to design bridges as jointless The above approach uses simple structure models for the
structures to minimize the cost of maintenance. Recently, in analysis of integral-abutment bridges. Hence, its application is
many parts of North America, the overall economy of contin- easier and less time consuming when conducted manually.
uous construction is made applicable to bridges with multiple Consequently, it has been exercised by many structural engi-
spans (Wolde et al. 1988a,b; Burke 1990a,b, 1994; Soltani and neers to design integral-abutment bridges for the effects of
Kukreti 1992). Multiple-span bridges with short abutments gravitational loads. However, the procedure contains unnec-
that are cast integral with the deck and supported on a single essary assumptions, and the structure model fails to reflect the
row of flexible piles are now considered as an alternative to actual behavior of the bridge and the effects of several loading
traditional multiple-span bridges with separate heavy abut- conditions. Considering these limitations, an analysis proce-
ments. dure and a structure model that realistically represent the ac-
Although arch bridges, rigid-frame bridges, and culverts can tual behavior of integral-abutment bridges and load distribu-
be classified as integral-abutment bridges, the types of inte- tion among their various components are proposed. The
gral-abutment bridges considered in this paper, as shown in proposed analysis method and structure model are imple-
Fig. 1, are the ones that resemble the conventional jointed mented in a computer program developed for the analysis of
bridges. In these types of bridges, the road surfaces are con- integral-abutment bridges.
tinuous from one approach embankment to the other, and the In the subsequent sections, the types of integral-abutment
abutments are cast integral with the deck. They differ from bridges studied in this paper are first described. Then, the cur-
rigid-frame bridges in the manner of distribution of stresses rently used conventional analysis methods and structure mod-
due to temperature change, prestressing, creep, shrinkage, and els are defined concisely. The behavior of and design consid-
restraints provided by abutment foundation and backfill. The erations for integral-abutment bridges are also briefly
effect of forces parallel to the longitudinal direction of the discussed. Next, the proposed analysis method is introduced.
bridge is minimized basically by designing the abutments and Following this, a structure model for the analysis of integral-
their foundations less resistant to longitudinal movements of abutment bridges under gravity loading is introduced. Then,
the structure.
Conventionally, for the design of the bridge deck, integral-
abutment bridges are idealized as a continuous beam with sim-
ply supported ends (Hambly and Nicholson 1990; Hayward
1992; Soltani and Kukreti 1992; Burke 1993a,b; Husain and
Bagnariol 1996). They are modeled as a continuous frame only
for the design of deck-abutment joints. But, in the model, the

1
Asst. Prof., Dept. of Civ. Engrg. and Constr., Bradley Univ., 1501 W.
Bradley Ave., Peoria, IL 61625. E-mail: mdicleli@usa.net
Note. Discussion open until January 1, 2001. To extend the closing
date one month, a written request must be filed with the ASCE Manager
of Journals. The manuscript for this paper was submitted for review and
possible publication on July 17, 1998. This paper is part of the Journal
of Bridge Engineering, Vol. 5, No. 3, August, 2000. 䉷ASCE, ISSN
1084-0702/00/0003-0240–0248/$8.00 ⫹ $$.50 per page. Paper No.
18806. FIG. 1. Typical Two-Span Integral-Abutment Bridge

240 / JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000

J. Bridge Eng. 2000.5:240-248.


the developed computer program for the analysis of integral-
abutment bridges is defined. Subsequently, the analysis results
obtained from the proposed analysis procedure are compared
with those obtained from the conventional analysis method.
Finally, the benefits of using the proposed analysis procedure
and structure model for the design of integral-abutment
bridges are discussed in the conclusions.

DEFINITION OF INTEGRAL-ABUTMENT BRIDGE


TYPES CONSIDERED
The integral-abutment bridges considered in this paper are
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

assumed to have a slab-on-steel or prestressed-concrete girder


deck. In such bridges, only a single row of piles is used to
provide vertical support to abutments and modest lateral re-
sistance to longitudinal forces. The abutments are built shorter
to reduce the restraint provided by the backfill soil to the lon-
gitudinal movement of the bridge. The connection between the
bridge deck and the abutment can be rigid or semirigid de-
pending on the detailing of joint reinforcement. A typical two-
span integral-abutment bridge is illustrated in Fig. 1.
For multiple-span integral-abutment bridges, the columns
FIG. 2. Conventional Structure Model for Deck Design
may be reinforced concrete (RC) or steel. The RC columns
may be either free standing or rigidly connected to a cap-beam
supporting the superstructure. The steel columns may be either
rapidly connected to a steel superstructure or separated by
movable joints from the superstructure. The connections of the
columns to the foundations may have rigidity ranging between
zero (pin) and infinite (fixed). Most RC columns are designed
to develop full continuity with the foundation at their bases.
Therefore, the fixed support condition may be suitable for such
cases. However, the connection of steel columns to the RC
footing is usually designed as a pin to prevent any potential
damage to the foundation due to penetration of plastic hinging
at the column base.

CURRENT DESIGN PRACTICE AND STRUCTURE


MODELING TECHNIQUES FIG. 3. Conventional Structure Model for Deck-Abutment
Joint Design
Current design practice recommends that an integral-abut-
ment bridge is modeled as a continuous beam with simply
supported ends for gravity load analysis. A separate frame is neglected. The deck-abutment joints are designed assuming
model is only considered if the design of deck-abutment con- a maximum passive earth pressure condition at the abutments.
tinuity connection is specifically required (Hambly and Nich- In the current design practice, the detailing of abutment-
olson 1990; Burke 1993a,b; Husain and Bagnariol 1996). deck continuity connections are standardized for various range
A typical three-span, slab-on-steel-girder, integral-abutment of applications (Hamley 1992). Therefore, in most cases, the
bridge and its structure model are shown in Fig. 2. The struc- structure model shown in Fig. 3 is not considered in the anal-
ture model is used for the design of the bridge deck only. It ysis. The bridge is modeled as a simply supported continuous
is composed of only horizontal beam elements. Full composite beam, shown in Fig. 2, and the full design is completed based
action between the slab and the girders is assumed for the on that model. Nevertheless, the detailing may vary depending
beam elements. As shown in Fig. 2, the piers and abutments on the type of loads applied to the structure. For example,
in the actual structure are replaced with simple supports in the seismic design provisions for RC rigid-frame structures usu-
model. Thus, the continuity of the structure at the deck-pier ally require joint details that must have some level of rotational
and deck-abutment joints is totally neglected for the deck de- and/or translational ductility for energy dissipation purposes
sign. The structure is analyzed only for the final stage where (Federal 1987). Consequently, the standard reinforcement de-
the bridge is assumed to be completed. The weight of the tails for abutment-deck continuity connections may not be ap-
concrete slab, girders, diaphragm beams, and superimposed plicable if the structure is built in an area with high risk of
dead load and live load are considered in the analysis of the seismic activity. The joint details may also vary as a function
structure. of the structure geometry.
The structure model shown in Fig. 3 is used to analyze the In most cases, for the design of piers supporting the integral-
same three-span integral-abutment bridge for the design of abutment bridge decks, the unbalanced horizontal soil pressure
deck-abutment joints assuming full composite action between forces resulting from unsymmetrical abutment configurations
the slab, girders, and the abutments only. The deck-pier joints are assumed to be transferred directly to the approach em-
are modeled as simple roller supports (Burke 1993a,b; Husain bankments with no effect on piers. Accordingly, the piers are
and Bagnariol 1996). The weight of the concrete slab, girders, designed for vertical reaction loads transferred from the su-
diaphragm beams, superimposed dead loads, live load, earth perstructure and for lateral loads directly applied on the piers.
pressure, and effect of temperature variation are considered in Obviously, this design approach is limited to some simple
the analysis of the structure. However, the correlation between cases where the structure is fully symmetrical and the soil
the temperature variation and the magnitude of earth pressure pressures at both sides of the bridge are in equilibrium.
JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000 / 241

J. Bridge Eng. 2000.5:240-248.


The effect of axial force in the deck, resulting from earth be wet. Therefore, the steel girders alone resist the applied
pressure loads at both sides of the structure, is also neglected loads. The loads due to the wet concrete slab, diaphragms, and
in the current design approach. This axial force may cause self-weight of the steel girders are considered in this stage. In
extra shortening of the prestress concrete girders due to elastic the second stage, the steel girders are assumed to be composite
deformation and creep, which may lead to a reduction in the with the concrete slab. However, the modulus of elasticity of
effective prestressing force in the girders. the concrete slab is assumed as one-third of its actual final
The current design practice allows for the design of pile- value to consider the effect of creep due to superimposed dead
abutment connection joints to develop full continuity. Conse- loads (Ministry 1991). In addition to the loads applied in the
quently, bending moments at pile ends are produced due to first stage, asphalt load and superimposed dead loads due to
temperature variations and vehicular traffic. These bending sidewalks, curbs, barrier walls, and median are considered in
moments could be high enough to initiate plastic yielding of this stage. In the final stage, the bridge is assumed to be in
steel piles (Emanual et al. 1973; Loveall 1985; Burke 1988; service. Full composite action is assumed between the slab,
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

Abendroth et al. 1989; Abendroth and Greimann 1989; Girton girders, and abutments. The effects of temperature variation,
et al. 1991). It may be speculated that the repetitive variation soil pressure, and live load are considered in this final stage.
of temperature and the effect of live load may cause low cycle
fatigue in the piles (Burke 1988). A hinge connection detail Soil-Structure Interaction
between the piles and the abutment may prevent such a po-
tentially destructive problem. The earth pressure coefficient is a function of the displace-
ment or rotation of the earth retaining structure. An integral-
PROPOSED ANALYSIS METHOD abutment bridge will experience elongation and contraction
due to temperature variations during its service life. Thus, the
Construction Stages and Loads earth pressure at the abutments should be considered in cor-
relation with temperature variation. A very small displacement
The construction of an integral-abutment bridge is done in
of the bridge away from the backfill soil can cause the devel-
stages. Therefore, it must be analyzed for each construction
opment of active earth pressure conditions (Barker et al. 1991;
stage to ensure that the structure has adequate capacity to sus-
Ministry 1991). Therefore, when the bridge contracts due to a
tain the applied loads particular to the stage under considera-
decrease in temperature, active earth pressure will be devel-
tion.
oped behind the abutment. At rest earth pressure behind the
Two stages are considered for the design of slab-on-pre-
abutment is assumed when there is no thermal movement.
stressed-concrete-girder integral-abutment bridges. The loads
When the bridge elongates due to an increase in temperature,
applied at each stage are listed in Table 1. In the first stage
the intensity of the earth pressure behind the abutment depends
the slab concrete is assumed to be wet. Accordingly, the pre-
on the magnitude of the bridge displacement toward the back-
stressed-concrete girders alone resist the applied loads. The
fill soil. The actual earth pressure coefficient K may change
structure is analyzed for the effects of prestressing force, dead
between at rest Ko and passive Kp earth pressure coefficients
weight of the girders, weight of wet concrete slab, and weight
depending on the amount of displacement. Past researchers
of the diaphragms. In the second stage the bridge is assumed
obtained the variation of earth pressure coefficient as a func-
to be in service. Full composite action is considered between
tion of structure displacement from experimental data and fi-
the slab, girders, and abutments. The effects of superimposed
nite-element analyses (Barker et al. 1991; Clough and Duncan
dead loads, asphalt weight, temperature variation, soil pres-
1991). For practical purposes, this variation is assumed to be
sure, and live load are considered in this stage.
linear, as shown in Fig. 4. This linear relationship is expressed
Three stages are considered for the design of slab-on-steel-
as
girder integral-abutment bridges. The loads applied at each
stage are listed in Table 2. In the first stage, the naked steel K = Ko ⫹ ␸d ⱕ Kp (1)
girders are assumed to be fully assembled and supported on
the abutments and piers, but the slab concrete is assumed to where d = displacement of the integral-abutment bridge toward
the backfill soil; and ␸ = slope of the earth pressure variation
TABLE 1. Summary of Stage Loading for Slab-on-Pre- depicted in Fig. 4. The value of ␸ varies as a function of the
stressed-Concrete-Girder Deck Integral-Abutment Bridges backfill soil type. Typical values of ␸ for various soil types
are provided elsewhere (Barker et al. 1991).
Stage Stage name Load Load description
The soil-structure interaction as a result of positive temper-
(1) (2) (3) (4)
ature variation is illustrated in Fig. 5, which consists of three
1 Simply supported beams 1 Self-weight of girder separate sketches. The sketch at the top illustrates the structure
2 Pretensioning
3 Weight of wet concrete slab, dia-
model used to formulate the effect of positive temperature var-
phragms, and abutment iation on the magnitude of earth pressure coefficient. The
2 Composite structure 4 Superimposed dead load (e.g., structure model is obtained by conservatively neglecting the
in sidewalks, curbs, medians)
5 Asphalt weight
6 Long-term prestress losses
7 Highway live loading and side-
walk load, or pedestrian loads
at fatigue limit state
8 As load 7 but at serviceability
limit state
9 As load 7 but at ULS
10 Thermal load due to longitudi-
nal expansion
11 Thermal load due to longitudi-
nal contraction
12 Passive earth pressure
13 At rest earth pressure
14 Active earth pressure FIG. 4. Variation of Passive Earth Pressure Coefficient as
Function of Structure Displacement toward Backfill

242 / JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000

J. Bridge Eng. 2000.5:240-248.


where ␣ = coefficient of thermal expansion for the deck ma-
terial; and ␦T = differential temperature variation.
To satisfy the equilibrium of forces in the longitudinal di-
rection of the bridge, the axial force Fd in the deck must be
equal to the earth pressure force Fs. By first substituting (6)
into (5) and then setting (4) equal to (5) and simplifying, the
final displacement of the bridge deck at abutment location,
considering the combined effects of positive temperature var-
iation and the earth pressure force, is obtained as
2␣␦TEg(Ag ⫹ nAs) ⫺ h2we␥s Ko
d= (7)
4Eg(Ag ⫹ nAs)
⫹ h2we␥s␸
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

Ld
Substituting (7) into (1) and simplifying, the earth pressure
FIG. 5. Soil-Structure Interaction at Abutment
coefficient K for the backfill soil is expressed as follows:
resistance of the piers, abutments, and piles to the longitudinal 2Ko ⫹ ␣␦TLd␸
movement of the structure. In the top sketch, Ld is the span K= ⱕ Kp (8)
Ld h2we␥s␸
length of the bridge, and kd is the axial stiffness of the modeled 2⫹
2Eg(Ag ⫹ nAs)
bridge deck. The model is considered to have an effective
width we equal to the spacing of girders. The middle sketch
shows the free displacement do of the bridge deck due to a PROPOSED STRUCTURE MODEL
positive temperature variation neglecting the restraint provided For the computer-aided analysis of integral-abutment
by the soil. The sketch at the bottom illustrates the final dis- bridges subjected to gravitational loads, a separate structure
placement d of the bridge deck considering the combined ef- model is proposed for each construction stage. The proposed
fects of positive temperature variation and the earth pressure structure models are subject to the following assumptions:
force Fs behind the abutment.
The axial stiffness of the modeled bridge deck is expressed • The analysis of bridges having slab-on-girder-type deck
as follows: is reduced to the consideration of one beam and an effec-
2Eg(Ag ⫹ nAs) tive width of the slab for the purpose of gravity load anal-
kd = (2) ysis. Accordingly, the abutments are idealized to have a
Ld
tributary width equal to that of the slab. Similarly, the
where Eg = modulus of elasticity of the girder material; Ag = number of piers and piles per tributary width is calculated,
cross-sectional area of the girder; As = cross-sectional area of and their stiffness is lumped to obtain a single pier or pile
the portion of the deck slab with an effective width equal to element for analysis purposes.
the spacing of girders; and n = modular ratio defined as the • The effect of frictional forces between the approach slab
ratio of the elastic modulus of slab material to that of girder and soil as well as between the wing-walls and soil, re-
material. sulting from movements due to temperature variations, is
Assuming nearly identical abutment configurations at both ignored.
sides of the bridge and neglecting the translational stiffness of • An equivalent pile length is assumed in the structural
the piles in the longitudinal direction, the earth pressure force model.
acting on the abutment is assumed to be completely transferred • The live load applied on the structure is proportioned to
to the bridge deck. Then, assuming a triangular earth pressure
distribution behind the abutment, the earth pressure force Fs
is expressed as
1 2
Fs = h we␥s K (3)
2

where h = abutment height; we = tributary width of the ide-


alized bridge model; and ␥s = unit weight of backfill soil.
Substituting (1) into (3), the earth pressure force is expressed
as
1 2
Fs = h we␥s(Ko ⫹ ␸d ) (4)
2

In Fig. 5, the axial force Fd in the deck is expressed as

2Eg(Ag ⫹ nAs)
Fd = (do ⫺ d ) (5)
Ld

The free longitudinal displacement do of the bridge deck due


to a positive temperature variation is expressed as follows
(Roeder and Moorty 1990):
1
do = ␣␦TLd (6) FIG. 6. Actual Structure and Proposed Model for Construc-
2 tion Stage 1

JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000 / 243

J. Bridge Eng. 2000.5:240-248.


one girder considering the transverse distribution of the
live load effects.

Fig. 6 illustrates a typical two-span, prestressed-concrete-


girder integral-abutment bridge and its 2D structure model for
construction stage 1. The naked girder alone is considered in
the structure model assuming that the concrete is not hardened.
Accordingly, the composite action between the girder and slab
and the continuity between the girders of adjacent spans and
at the deck-abutment joints are ignored. The bridge is modeled
considering each span as a simply supported beam. The struc-
ture is analyzed for stage 1 loads tabulated in Table 1. The
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

resulting internal stresses are stored and are then superimposed


to the internal stresses resulting from the loads that are applied
in stage 2.
For slab-on-steel-girder integral-abutment bridges, the steel
beams are fully assembled to form a continuous beam before
the slab is cast in construction stage 1. Therefore, the hinge
shown at the middle support of the structure model depicted
in Fig. 6 is removed for this type of integral-abutment bridges.
Furthermore, if steel columns are rigidly connected to the steel
girders, the middle simple support shown in Fig. 6 is replaced
by a column element rigidly connected to the beam. Each span
is idealized using 2D beam elements. The structure is then
analyzed for stage 1 loads tabulated in Table 2. The resulting
internal stresses are stored and are then superimposed to the
internal stresses resulting from the loads that are applied in
subsequent stages.
Fig. 7 illustrates the structure model for the rest of the con-
struction stages for the same bridge shown in Fig. 6. The struc-
ture model can be used for the analysis of steel and prestressed
concrete, slab-on-girder, integral-abutment bridges. The bridge
is idealized as a plane frame considering only one girder and
FIG. 7. Actual Structure and Proposed Model for Final Con-
an effective width of slab. Full continuity at the intermediate
struction Stage
supports and at the abutment-deck connection joints is consid-
ered assuming that the concrete is fully hardened. The ideal-
ized abutment and pier members are connected to the deck Deck, Abutment, and Pile Elements
nodes by abutment-deck or pier-deck connection elements.
The pile member is connected to the abutment member by a The stiffness of the deck element is calculated assuming a
pile-abutment connection element. The components used in full composite action between the slab and girder. An effective
the structure idealization of integral-abutment bridges are de- width we, as shown in Fig. 8, is used for the slab. Note that
scribed in the following subsections. the contribution of the slab to the stiffness of the deck element
may not be significant in negative moment regions where the
slab is in tension. However, for the purpose of practicality, an
TABLE 2. Summary of Stage Loading for Slab-on-Steel-Girder effective slab width, obtained for the cases where the slab is
Deck Integral-Abutment Bridges in full compression, is used along the total length of the deck.
Stage Stage name Load Load description The procedures defined in various design codes (Ministry
(1) (2) (3) (4) 1991; AASHTO 1994) may be used to determine the effective
1 Naked steel beam 1 Self-weight of steel beam and
slab width. In the idealized structure model, the deck element
diaphragms must pass through the centroid of the composite section. The
2 Weight of wet concrete slab, vertical coordinates of other elements are determined accord-
diaphragms, and abutment ingly.
2 Composite structure (3n)- 3 Superimposed dead load (e.g., The abutment element is assumed to have a rectangular
superstructure only in sidewalks, curbs, medians) cross section with a thickness t and an effective width we equal
4 Asphalt weight
3 Composite structure (n) 5 As load 3
to that of the slab and is divided into five segments, as shown
6 As load 4 in Fig. 8. Node 5 is located at 0.9 times the abutment thickness
7 Highway live loading and side- for shear resistance check.
walk load, or pedestrian loads To model the piles, the number of piles per effective abut-
at fatigue limit state ment width is first calculated. Then, the area and moment of
8 As load 7 but at serviceability inertia of a single pile is multiplied by the number of piles per
limit state
9 As load 7 but at ULS
effective abutment width to obtain the properties of the ide-
10 Thermal load due to longitudi- alized pile element. The length of the idealized pile element
nal expansion is calculated using the equivalent cantilever method (Greimann
11 Thermal load due to longitudi- et al. 1987; Abendroth and Greimann 1989; Girton et al. 1989)
nal contraction as shown in Fig. 9. The equivalent pile length is a function of
12 Passive earth pressure the pile stiffness, its actual length, and the soil type. The pile
13 At rest earth pressure
14 Active earth pressure
displacements beyond this equivalent length are negligible.
Therefore, the idealized pile element is assumed to have a
244 / JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000

J. Bridge Eng. 2000.5:240-248.


Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

FIG. 8. Details of Abutment and Deck Elements


FIG. 10. Rigid and Connection Elements’ Details at Joints

application of earth pressure or other types of loading above


the geometric centerline of the deck. Element 4 is modeled as
a rigid member to idealize the depth of the deck measured
from its geometric centerline to the top of the bearing or pier.

Connection Elements
Connection elements are used to define the rotational and/
or translational stiffness of the joints at various parts of an
integral-abutment bridge. These elements have an infinitesimal
length of 10 mm.
The connection element at the deck-abutment joint, shown
in Fig. 10, is used to idealize the rotational stiffness of the
connection between the deck and the abutment. Normally, if
adequate continuity is provided between the slab, girders, and
abutment using a proper reinforcement detailing, connection
FIG. 9. Models for Pile Element elements are assumed as rigid. Otherwise, the joint may be
idealized as hinge or semirigid by adjusting the stiffness of
fixed support condition at its base as illustrated in Figs. 7 and the connection element. For hinge idealization, the connection
9. element is assigned a very small flexural stiffness to permit
If the soil-spring model shown in Fig. 9 is preferred to ide- free rotation of the deck (1/1,000 of the abutment stiffness).
alize the pile, the actual pile length must be used in the model. For semirigid idealization, the connection element is assigned
The pile element must be divied into a number of equal seg- a flexural stiffness smaller than that of the abutment to allow
ments. Then, using the coefficient of subgrade reaction for the some relative rotation of joint elements. If the piles are rigidly
foundation soil, the lateral stiffness of the soil must be cal- fixed to the abutment, the connection element at the abutment-
culated at each node level along the pile member. Then, spring pile joint, shown in Fig. 10, is assigned stiffness properties
elements with the calculated lateral soil stiffness are attached equal to those of the idealized pile element. For a pin con-
to each node. The base of the pile is assumed to have a roller nection at the piles’ ends, the connection element is assigned
pin support. In the case of friction piles, the roller in the model a stiffness equal to 1/1,000 of that of the idealized pile ele-
shown in Fig. 9 must be replaced with a vertical spring with ment.
a stiffness representing the relationship between the displace- If the deck is isolated by a set of bearings from the pier,
ment and frictional resistance of the pile. then the connection element at the deck-pier joint, shown in
Fig. 10, is used to idealize the stiffness of the bearings. The
Joint Elements connection element is assumed as rigid if the pier is mono-
lithically connected to the bridge deck. For piers fixed to a
The joint elements shown in Figs. 7 and 10 are used to rigid foundation, the connection element at the idealized pier
idealize the geometry and stiffness of the bridge components base, shown in Fig. 10, is assigned stiffness properties equal
within the joints. Element 1 in Fig. 10 is used to idealize the to those of the idealized pier element. For a pin connection at
stiffness of the deck within the joint. Its length extends from the pier base, the connection element is assigned a stiffness
the geometric centerline of the abutment element to the face equal to 1/1,000 of that of the idealized pier element. The
of the abutment. Obviously, the moment of inertia of the deck rotational stiffness of the foundation can also be modeled us-
element within the joint is very high as any cross section taken ing the connection element at the pier base.
at that location has a vertical dimension equal to the sum of
the deck depth and the abutment height up to the soffit. There- COMPUTER-AIDED ANALYSIS OF
fore, the part of the deck within the joint is modeled as a rigid INTEGRAL-ABUTMENT BRIDGES
element. Similarly, element 2 in Fig. 10 is used to model the
part of the abutment within the joint as a rigid element. Ele- A computer program is developed for the analysis of inte-
ment 3 is also modeled as a rigid member. Nonetheless, it does gral-abutment bridges using the proposed analysis method and
not have any structural significance. It is used to enable the structure model. The developed computer program uses an in-
JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000 / 245

J. Bridge Eng. 2000.5:240-248.


preceding stages are then superimposed manually to obtain the
cumulative responses.

COMPARATIVE STUDY
The relative stiffness of horizontal and vertical components
in a rigid frame dictates the distribution of forces and mo-
ments. Accordingly, the ratio of deck bending stiffness to
equivalent abutment stiffness is an important characteristic of
an integral-abutment bridge. The equivalent abutment stiffness
is the stiffness of a single member that represents the com-
bined performance of the abutment and piles. This ratio is
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

lower for integral-abutment bridges with longer spans. The


effect of continuous frame action is more pronounced in such
structures, whereas integral-abutment bridges with shorter
spans and/or flexible abutments and piles have a higher deck
bending stiffness to equivalent abutment stiffness ratio. Such
structures may behave like a continuous beam with simply
supported ends when subjected to vertical loading.
Numerous symmetrical, single-span, integral-abutment
bridges with various deck bending stiffness to equivalent abut-
FIG. 11. Operation of Developed Computer Program
ment stiffness ratios are analyzed using the developed com-
puter program, which is based on the proposed analysis
house structural analysis program (SAP) as the main tool for method and structure model. The same integral-abutment
the analysis of integral-abutment bridges. A graphical user in- bridges also are analyzed using the conventional analysis pro-
terface (GUI) is developed to define the geometric and struc- cedure and structure model. The results obtained from both
tural properties of, and the loads acting on, integral-abutment analyses are compared in Fig. 12. In the figure, the vertical
bridges. Several postprocessor programs are coded for proc- axis is the ratio RM of the maximum live load span moment
essing the user-input data and intermediate output results. The obtained using the proposed method to that obtained using the
processed data is used as input for the subsequent operations conventional method. The horizontal axis is the ratio Rs of
of SAP for stage-by-stage analysis of the structure. Addition- deck bending stiffness to equivalent abutment stiffness.
ally, programs are developed for calculating the resistance ca- In the conventional analysis method, the structure is mod-
pacity of the structural components. A control program man- eled as a simply supported beam for the design of the deck.
ages the database and execution sequence of the postprocessor Single-span integral-abutment bridges with larger ratios of
programs based on the type of integral-abutment bridge. deck bending stiffness to equivalent abutment stiffness behave
Fig. 11 shows the operation of the system for a prestressed more like a simply supported bridge when subjected to vertical
concrete girder integral-abutment bridge. In the figure, the files loading. Consequently, as shown in Fig. 12, the ratio of the
denoted with OP are output and those denoted with IN are maximum live load span moments approaches unity for such
input files. The numbers preceded by a # are file numbers used bridges. However, larger differences between the maximum
in the system. The files denoted with the same numbers are live load span moments are observed for integral-abutment
identical regardless of whether they are input or output files. bridges with smaller ratios of deck bending stiffness to equiv-
The control program first allows the user to define the gen- alent abutment stiffness. This basically demonstrates that more
eral properties of the bridge using a GUI as shown in Fig. 11. economical deck designs may be obtained when full frame
The GUI then produces a structured data file denoted as OP action is considered for the analysis of such structures. Pre-
#1 in the figure. The file contains information about the prop- vious studies also demonstrated that the maximum live load
erties of the integral-abutment bridge defined by the user. The span moment in an integral-abutment bridge may be as little
control program then initiates processor program P1 which as 50% of that in a simply supported bridge (Thippeswamy et
uses the file generated by the GUI as input (IN #1). Program al. 1994).
P1 then outputs file OP #2. This file is used by SAP for stage To study the impact of the conventional and proposed meth-
1 analysis of the bridge. The results generated by SAP for
stage 1 analysis are stored in file OP #3. The control program
then initiates processor program P2. The program uses the files
IN #1 and IN #3 as input data that are generated by the GUI
and SAP, respectively. Program P2 generates file OP #4. This
file is used by SAP for stage 2 analysis of the bridge. The
results generated by SAP for stage 2 are stored in OP #5.
Finally, resistance module P3 is invoked by the control pro-
gram to calculate the member resistances at each construction
stage. The resistance and responses for the bridge components
are printed in file OP #6.
The above procedure may be followed to analyze integral-
abutment bridges using any conventional structural analysis
program such as SAP 90 (Wilson and Habibullah 1990). The
functions of the GUI and control program may be passed to a
user. The user has to prepare the input data for the conven-
tional structural analysis program for the analysis of the bridge
using an appropriate structure model and loads for stage 1. FIG. 12. Comparison of Live Load Span Moments Obtained
The same procedure is repeated using the appropriate structure Using Developed Computer Program and Conventional Analy-
model and loads for the subsequent stages. The responses from sis Method

246 / JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000

J. Bridge Eng. 2000.5:240-248.


ods on the design, two existing integral-abutment bridges in deck-abutment joint is 1,802 kN ⭈ m for the conventional
Ontario, Canada, are analyzed using both methods. The first method and 856 kN ⭈ m for the proposed method. Similar dif-
one is a single-span prestressed concrete bridge. It has a span ferences are also obtained for the forces in the abutments and
length of 30 m and an abutment height of 5 m. The steel H piles.
piles at the abutments are detailed to have hinge connections
at their tops by cutting the flanges along the embedded portion CONCLUSIONS
of the piles within the abutment. Effective design temperature A computer program for the analysis and design of integral-
variations of ⫺38 and 18⬚C were used in the analysis of the abutment bridges has been developed. The developed program
bridge. The second one is a symmetrical, three-span, contin- uses a simplified, but realistic, structure model to idealize the
uous, steel bridge. The length of the side and center spans are behavior of integral-abutment bridges and load distribution
12 and 18 m, respectively, and the abutment height is 4 m. among their various components. A soil-structure interaction
Effective design temperature variations of ⫺52 and 30⬚C were model to calculate the passive earth pressure at the abutments
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

used in the analysis of the bridge. For both bridges the gran- is also developed and implemented in the computer program.
ular backfill soil at the abutments has a unit weight of 20 kN/ The program is capable of analyzing integral-abutment bridges
m3 and an angle of internal friction of 30⬚. The slope ␸ of the for each construction stage and carrying the effects of applied
passive earth pressure variation is obtained as 24 m⫺1 for the loads on the structure members from a previous construction
backfill soil. The full passive earth pressure condition is as- stage to the next. The analysis method and structure model
sumed to develop at the abutments for the conventional employed in the developed computer program are compared
method. Accordingly, a passive earth pressure coefficient of with the conventional analysis method and structure model
3.0 is obtained. For the proposed method, the passive earth currently used by many structural engineers for the design of
pressure coefficient is calculated as 0.56 for the first bridge integral-abutment bridges in North America and Europe. The
and 0.68 for the second bridge using (8). The bridges are an- following are observed:
alyzed considering all possible load combinations at the ulti-
mate limit states (ULS). The optimum responses obtained from • The conventional analysis method neglects the continuity
both design methods are then compared. of the structure at the deck-pier and deck-abutment joints
Analysis results for the first bridge demonstrated that at the for the deck design. The proposed structure model used
ULS the maximum span moment obtained from the conven- in the program reflects the effect of the continuity at such
tional method (10,543 kN ⭈ m) is 25% larger than that obtained joints on the performance of the bridge deck.
from the proposed method (8,471 kN ⭈ m). This discrepancy is • The effect of axial load in the deck due to earth pressure
a result of the assumptions made in the conventional method, forces at the abutments is neglected in the conventional
where the beneficial effects of continuity at the joints and earth analysis method. Such effects are fully considered in the
pressure forces applied at the abutments, in reducing the span proposed analysis method and structure model.
moment, are neglected. It is noteworthy that the maximum • The conventional analysis method recommends the use of
span moment obtained from the proposed method is due to full passive pressure for the design of deck-abutment
the combined effects of dead load, live load, temperature de- joints. The proposed soil-structure interaction model may
crease, and active earth pressure. The conventional design result in smaller earth pressure forces, which may lead to
method also yields much larger forces at the deck-abutment a more economical deck-abutment joint design.
joints. The maximum deck moment obtained at the deck-abut- • For single-span bridges, the conventional analysis method
ment joint is 7,691 kN ⭈ m for the conventional method and does not consider the beneficial effect of earth pressure
2,716 kN ⭈ m for the proposed method. Similar differences also forces applied at abutments when calculating the maxi-
are obtained for the forces in the abutments and piles. The mum span moment for the deck design. The proposed
maximum moment at the abutment top is 1,142 kN ⭈ m/m for structure model considers such beneficial effects in the
the conventional method and 587 kN ⭈ m/m for the proposed design of the deck.
method. This discrepancy is mainly due to the differences in • The comparison of analysis results from the conventional
the magnitude of the passive earth pressure forces used by the and proposed analysis methods demonstrated that it may
conventional and proposed methods. The conventional method be possible to obtain more economical designs using the
considers a full passive earth pressure at the abutments, proposed analysis method and structure model.
whereas the proposed method considers only a partial passive
earth pressure as a function of structure movement and soil APPENDIX. REFERENCES
properties. The moment at the abutment bottom and pile top AASHTO. (1994). AASHTO LRFD bridge design specifications, 1st Ed.,
is obtained as zero because a hinge connection at the pile- Washington, D.C.
abutment joint was assumed in the analysis. It is noteworthy Abendroth, R. E., and Greimann, L. F. (1989). ‘‘A rational design ap-
that the ultimate resistance of the piles exceeds the maximum proach for integral-abutment bridge piles.’’ Transp. Res. Rec. 1233,
Transportation Research Board, Washington, D.C., 12–23.
responses for all load cases. Abendroth, R. E., Greimann, L. F., and Ebner, P. B. (1989). ‘‘Abutment
Analysis results for the second bridge demonstrated that at pile design for jointless bridges.’’ J. Struct. Engrg., ASCE, 115(11),
the ULS comparable span moments are obtained from both 2914–2929.
methods (the maximum moments for the side and center spans Barker, R. M., Duncan, J. M. K., Rojiani, K. B., Ooi, P. S. K., and Kim,
are, respectively, 1,272 and 1,950 kN ⭈ m for the conventional S. G. (1991). ‘‘Manuals for the design of bridge foundations.’’ NCHRP
and 1,244 and 1,953 kN ⭈ m for the proposed methods). How- Rep. 343, Transportation Research Board, National Research Council,
Washington, D.C.
ever, the maximum moment at the inner supports obtained Burke, M. P., Jr. (1988). ‘‘Bridge deck joints.’’ NCHRP Synthesis of Hwy.
from the conventional method (993 kN ⭈ m) is 17% larger than Pract., No. 141, Transportation Research Board, National Research
that obtained from the proposed method (848 kN ⭈ m). The Council, Washington, D.C.
above results demonstrate that for continuous bridges, the con- Burke, M. P., Jr. (1990a). ‘‘Integral bridge design is on the rise.’’ AISC
tinuity at the deck-abutment joints and the earth pressure Modern Steel Constr., 30(4), 9–11.
Burke, M. P., Jr. (1990b). ‘‘Integral bridges.’’ Transp. Res. Rec. 1275,
forces applied at the abutments may not have a major impact
Transportation Research Board, Washington, D.C.
on the span moments but may influence the inner support mo- Burke, M. P., Jr. (1993a). ‘‘Integral bridges: Attributes and limitations.’’
ments. The conventional method still yields much larger forces Transp. Res. Rec. 1393, Transportation Research Board, Washington,
at the deck-abutment joints. The deck moment obtained at the D.C., 1–8.

JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000 / 247

J. Bridge Eng. 2000.5:240-248.


Burke, M. P., Jr. (1993b). ‘‘The design of concrete integral bridges.’’ Hayward, A. (1992). ‘‘Continuous and jointless steel bridges.’’ Transp.
Concrete Int., June, 37–42. Res. Lab. Rec. 19, Crowthorne, U.K., 83–90.
Burke, M. P., Jr. (1994). ‘‘Semi-integral bridges: Movements and forces.’’ Husain, I., and Bagnariol, D. (1996). ‘‘Integral-abutment bridges.’’ Rep.
Transp. Res. Rec. 1460, Transportation Research Board, Washington, SO-96-01, Ontario Ministry of Transportation, St. Catharines, Ont.,
D.C., 1–7. Canada.
Clough, G. M., and Duncan, J. M. (1991). Foundation engineering hand- Loveall, C. L. (1985). ‘‘Jointless bridge decks.’’ Civ. Engrg., ASCE,
book, 2nd Ed., H. Y. Fang, ed., Van Nostrand Reinhold, New York. 55(11), 64–67.
Emanual, J. H., Hulsey, J. L., Best, J. L., Senne, J. H., and Thompson, Ministry of Transportation. (1991). Ontario highway bridge design code,
L. E. (1973). ‘‘Current design practice for bridge superstructures con- 3rd Ed., Quality and Standards Division, Downsview, Ont., Canada.
nected to flexible substructures.’’ Civil Engrg. Study 73-3, University Roeder, C. W., and Moorty, S. (1990). ‘‘Thermal movements in bridges.’’
of Missouri at Rolla, Rolla, Mo. Transp. Res. Rec. 1290, Transportation Research Board, Washington,
Federal Highway Administration. (1987). ‘‘Seismic design and retrofit D.C., 135–143.
manual for highway bridges.’’ FHWA-IP-87-6, U.S. Department of Soltani, A. A., and Kukreti, A. R. (1992). ‘‘Performance evaluation of
Transportation, Washington, D.C. integral-abutment bridges.’’ Transp. Res. Rec. 1371, Transportation Re-
Downloaded from ascelibrary.org by MISSOURI, UNIV OF/COLUMBIA on 08/29/14. Copyright ASCE. For personal use only; all rights reserved.

Girton, D. D., Hawkinson, T. R., and Greimann, L. F. (1991). ‘‘Validation search Board, Washington, D.C., 17–25.
of design recommendations for integral-abutment piles.’’ J. Struct. Steiger, D. J. (1993). ‘‘Jointless bridges provide fuel for controversy.’’
Engrg., ASCE, 117(7), 2117–2134. Roads and Bridges, 31(11), 48–54.
Girton, D. D., Hawkinson, T. R., Greimann, L. F., Bergenson, K., Ndon, Thippeswamy, H. K., Raju, P. R., and Gangarao, H. V. S. (1994).
U., and Abendorth, R. E. (1989). ‘‘Validation of design recommenda- ‘‘Parametric study of single-span jointless steel bridges.’’ Transp. Res.
tions for integral-abutment piles.’’ Proj. HR-292, Iowa Department of Rec. 1460, Transportation Research Board, Washington, D.C.
Transportation, Ames, Iowa. Wilson, E. L., and Habibullah, A. (1990). SAP 90, computer software for
Greimann, L. F., Abendtroth, R. E., Johnson, D. E., and Ebner, P. B. structural and earthquake engineering, Computers and Structures Inc.,
(1987). ‘‘Pile design and tests for integral-abutment bridges.’’ Final Berkeley, Calif.
Rep., Proj. HR-273, Iowa Department of Transportation, Ames, Iowa. Wolde-Tinsae, A. M., Klinger, J. E., and Mullangi, R. (1988a). ‘‘Bridge
Hambly, E. C., and Nicholson, B. A. (1990). ‘‘Prestressed beam integral deck joint rehabilitation or retrofitting.’’ Final Rep., Dept. of Civ.
bridges.’’ The Struct. Engr., London, 68(23), 474–481. Engrg., University of Maryland, College Park, Md.
Hamley, E. C. (1992). ‘‘Integral bridge abutment details in practice and Wolde-Tinsae, A. M., Klinger, J. E., and White, E. (1988b). ‘‘Performance
theory.’’ Transp. Res. Lab. Rec. 19, Crowthorne, U.K. of jointless bridges.’’ J. Perf. Constr. Fac., ASCE, 2(2), 111–125.

248 / JOURNAL OF BRIDGE ENGINEERING / AUGUST 2000

J. Bridge Eng. 2000.5:240-248.

You might also like