Professional Documents
Culture Documents
1 Chairman
1 Chairman
1 Chairman
Opening of Session
Danie Badenhorst
ICOLD 25th Congress Question 99
25ème congrès de la CIGB Upgrading and Re-Engineering of Existing Dams
17 – 19 June 2015 Réhabilitation et ré-ingénierie des barrages existants
Question 99
Upgrading and Re-Engineering of
Existing Dams
3
Introduction
Themes
– Session D: Upgrading/decommissioning to
meet new operational and environmental
conditions (5)
4
ICOLD 25th Congress Question 99
25ème congrès de la CIGB Upgrading and Re-Engineering of Existing Dams
17 – 19 June 2015 Réhabilitation et ré-ingénierie des barrages existants
Change of programme:
6
Introduction
• Speaker will be notified when 1 minute is left
7
Programme
Programme: ICOLD 2015 Q99
14:30-
18 JUNE - Room Lysefjorden A/B 18:00
11
Summary: Session A: Increase
storage capacity
Three Papers
• Fuse plugs been used for raising
• Single concrete arch raised and changed to double curvature
concrete arch. Demolish top part of existing dam
• Concrete gravity Dam 70m high raised 30m by providing CFRD on
downstream side: Problem with side valley movement
12
Summary: Session B: Maintain
Reservoir Active Storage
Five papers
• Sediment bypass Tunnels
• Vertical Multi Hole Suction Pipe
• Install casing Pipe under dam fro dredging discharge
• Retrofitting and change in operation of cascade dams
• Case studies showing each site and each sediment fraction
requires a specific treatment and regular monitoring and
upgrading when necessary
13
Summary: Session C: Upgrading
of monitoring systems and re-
instrumentation
Six Papers
• Thermal monitoring of seepage and erosion. Upgrading thermal
cables and sensors
• 185m high Arch Emosson Dam: Upgrading of thermal monitoring
system.
• New seepage detection techniques
• New method of continuous monitoring of vertical concrete joint
movement in concrete arch dams: fibre optic cables
• Various applications to instrumentation improvements on dams:
risk analysis for identifying needs , Piezometers, concrete
expansion stresses, etc.
• Planning, stakeholder involvement, project specific applications of
new technologies.
14
Summary: Session D:
Three Papers
• Upgrading in Spain addressing various safety issues: Foundation
leakage, floods issues, lowering of spillway crest level.
• R19: Risks of incomplete dam addressed: Marmarik Dam Armenia
settlement of 13,5m just after construction: Various unsafe issues
and upgrades
• R23: Norway: Rehabilitation of the five Dams: Five Dams became
1 lake by construction of two new dams.
15
Summary
Heightening: Consider the full extend of the foundation – not
just the dam. No real recipe for dam heightening specific..