Professional Documents
Culture Documents
Construction Contracts
Construction Contracts
net/publication/320282946
CITATIONS READS
0 13,448
1 author:
Mohamed Darwish
Ahram Canadian University
70 PUBLICATIONS 103 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Mohamed Darwish on 09 October 2017.
Construction Contracts
By:
Dr. Mohamed Darwish
1
10/9/2017
2
10/9/2017
3
10/9/2017
Disadvantages
1. The risk that the owner takes in this
contracting method is that the contract is
only as good as the accuracy of the contract
documents - if the scope of the project
changes or if errors exist in the
documentation, the contract will need to be
renegotiated, possibly exposing the owner to
increased financial risk.
Disadvantages
2. To allow a fixed price contract to be
negotiated, a complete set of contract
documents must be prepared.
4
10/9/2017
In summary,
•This contracting method combined with a
traditional delivery method allows the owner to
define and commit to an agreed-upon project
description and dollar amount before the work
begins.
•For owners who want to minimize risk on a project
that can be clearly defined (i.e., that has minimal
unforeseen conditions), this type of contracting
method works well.
•The owner must understand that the process will
take longer and that changes caused by mistakes,
unknowns, or changes in owner requirements will
jeopardize the agreement.
5
10/9/2017
Advantages
1. In many projects (heavy engineering projects
being a perfect example), it is difficult to
accurately quantify the work necessary.
–In excavation work it is often difficult to accurately
quantify the actual amount of rock versus soil that must
be excavated.
–To eliminate risk to both the owner and the bidders, the
designers will estimate quantities and then ask the
bidders to provide a unit price for each type of
excavation and bid the job.
–Actual payments will be made on the basis of
multiplying the actual quantities excavated by the unit
price provided.
6
10/9/2017
Advantages
2. Provides the owner with a competitive bid
situation, allowing for a fair price for the
work.
3. It eliminates the risk of getting a fixed price
and then having to renegotiate because of
differing site conditions, as explained before.
4. Work can also begin before the design is
completed, speeding up the completion of
the project.
Disadvantages
7
10/9/2017
Disadvantages
8
10/9/2017
In summary
In summary
•An owner presence in the field must also exist
to verify quantities and authorize payments.
9
10/9/2017
10
10/9/2017
Advantages
11
10/9/2017
Disadvantages
1. The risk to the owner in using this type of contract is
that, even with a GMP, the project is started with
considerable unknowns.
2. By using a GMP the project costs may be capped, but
the quality and scope may become sacrificed at the
expense of the GMP.
– If a GMP is not used, the scope and quality of the project
may be solid, but the cost and schedule may increase.
3. This type of contract requires a reputable contractor
or construction manager, since tremendous trust
needs to be placed with this participant.
Example:
12
10/9/2017
c
Final Price
$ 10,300 b
a
Contractor
Final Cost Profit %
Profit
$ 9,500 a = $ 800 8.42%
$ 10,500
$ 9,500
Final Cost
Lump-Sum Contract
13
10/9/2017
$ 10,500 c
Final Price
$ 10,000 b
Contractor
a Final Cost Profit %
Profit
$ 9,500 a = $ 500 5.26%
$ 10,500
$ 9,500
Final Cost
Guaranteed-Maximum-Price Contract
c
$ 10,500
Final Price
b
$ 9,975
Contractor
Final Cost Profit %
a Profit
$ 9,500 a = $ 475 5.00%
$ 10,500
$ 9,500
Final Cost
Time-and-Materials Contract
14
10/9/2017
In summary,
15
10/9/2017
Contract Changes
Contract changes occur for three main reasons:
16
10/9/2017
17
10/9/2017