Testing and Commissioning For Cooling Tower
Testing and Commissioning For Cooling Tower
COOLING TOWERS
The scope of this method statement is to determine the thermal capability of water cooling towers. Its main
purpose is to describe instrumentation and procedures for the testing and performance evaluation of water
cooling towers.
It is recognized that the data limitations specified throughout this Testing & Commissioning Procedure
represent desired conditions which may not exist at the time the test is performed.
In such cases, existing conditions may be used if mutually agreed upon prior to test by client authorized
representative, contractor, sub-contractor & third party personnel.
Before commencement of Testing & Commissioning activity, the supervisor/ engineer must ensure that:
All Installations & Pressure Testing of Pipe? Duct works have been completed & approved by the client.
Determine whether the units occurs damages during the storage, installation & shifting of units into its site
location.
Permission to start or Civil Clearances prior to testing & commissioning has been given by the main
contractor.
All relevant Approved Shop drawings, manufacturer’s recommendations, specifications etc. for the testing &
commissioning of the system shall be available & approved by the client.
Testing & Commissioning activities shall only commence when all associated works by the civil contractor
has been completed, Installation activities & all associated works intended & connected to the Cooling
Towers has been completed & approved by the client.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the Safety in
charge at site.
Ensure that at the time of test the tower shall be in good operating condition.
Water distribution system shall be essentially clear and free of foreign materials which may impede the
normal water flow.
Mechanical equipment if involved, shall be in good working order Fans shall be rotating in the correct
direction, with proper orientation of leading and trailing edges. Fan blades shall be at uniform angle that will
yield within +1- 10 % of the specified horsepower loading. In addition, centrifugal fans shall be free of
foreign material and properly secured to the shafts.
Drift eliminators shall be essentially clear and free of algae and other deposits which may impede normal air
flow.
Fill shall be essentially free of foreign materials such as oil, tar, scale or algae.
Water level in cold water basin shall be at normal operating elevation and shall be maintained substantially
constant during the test in order to provide proper airflow to the fill.
Make-up and or blow down streams may be stopped during the test if other test condition requirements are not
adversely affected.
The wet-bulb and dry-bulb temperatures shall be the inlet values, measured in accordance to this test
procedure.
The water shall be distributed to all operating cells and/ or parts of the tower.
The total dissolved solid in the circulating water, as determined by evaporation, shall not exceed the greater of
the following:
5,500 ppm
1 times the design concentration.
For a valid test, variations in test conditions shall be within the following limits:
Readings shall be taken at regular intervals and recorded for future reference.
Measurement Procedures
Water flow measurements may be made by means of pitot tube, orifice, venture, volumetric, weir,
flow nozzle & turbine meter.
The accuracy of any of the above shall be presumed to be within ± 1.25%. The selection of location of
measurement will be dependent upon the nature of the installation to be tested.
The water quantities shall be measured in terms of, Circulating water flow to the tower If required,
consider make-up water flow & blow-down flow.
If circulating water flow to the tower is measured by pitot tube traverse, an air-over-water (inverted
type) manometer shall be used unless otherwise agreed or instructed. One full traverse (along two
axes at 900 to each other) shall be made immediately preceding the test, and a minimum of three
center point readings shall be taken during the test.
Water temperature measurements shall be made by any of the instruments such as resistance
thermometers or mercury-in-glass thermometers. Instruments shall be designated to indicate or record
in 0.2°F graduations. Temperature sensitive elements shall be carefully located where the water will
be thoroughly mixed.
Hot water circulating water temperature measurement shall be made in tower risers or at the discharge
of the inlet riser into the flume or distribution system or, for a multi-cell tower, in the supply header
just upstream of the first riser, If the source ¡s a mixture of two or more streams of different
temperatures, complete mixing must be assured at the point of measurement or sufficient flow rate
and temperature measurements shall be made to ensure an accurate weighted average water
temperature.
Cold Circulating water temperature measurements should preferably be made in a full flowing bleed
stream at the circulating pump discharge, and the average corrected for heat added by the pump. If the
measurement the measurement is made at a location where temperatures and velocities are not
uniform over the stream cross section, sufficient flow rate and temperature measurements shall be
made to ensure an accurate weighted average water temperature.
Make-up water temperature measurement (if applicable), shall be made at the point the make-up water
enters the system.
Blow-down temperature measurement (if applicable), shall be made at the point the blow-down leaves
the system.
The wind velocity measurement shall be made with an anemometer of the rotating cup type. Measurement
shall be made in an open and unobstructed location within 100 feet of and to windward of the tower at a point
5 feet above basin curb elevation.
Cleaning
Inspection
Conduct external inspection of the equipment. Check for leaks, corrosion and any structural damage.
Conduct internal inspection of the equipment. Check for anything unusual such as structural or
mechanical component damage.
Inspect piping connections.
Thoroughly inspect the fan for any damage.
Verify proper fan tip clearance.
At seasonal start-up or after prolonged shutdown, check the motor insulation with an insulation tester
prior to motor start-up.
Check & adjust the belt tension or check gear drive oil levels.
Check that the float operated make-up valve is operating freely.
Start-Up
Prior to start-up, lubricate the motor base adjusting screw and the fan shaft bearings at initial start-up,
bearings are factory lubricated prior to shipment. However if the unit has been idle for more than
three months, re-lubricate the bearings.
Fill the cold water basin with fresh water to the overflow level via the make- up valve,
Set the make-up valve float so the water shuts off at the operating level.
Verify the drain plug ¡s installed.
Check that the float operated make up valve is operating freely. Closely monitor the water level and
adjust as necessary during the first 24 hours of operation.
For the top inlets only, adjust the flow balancing valves to equalize flow to the hot water basins.
For multi- cell arrangements, balance the flow between the cells to obtain even water distribution.
Check to ensure the controls for the fan motor are set to allow maximum of six on-off cycles per hour
to prevent motor overload.
Adjust the valve in the tower bleed line to achieve the desired bleed rate by closing or opening the
valve.
Inspect the nozzles heat transfer section.
Execute one of the following biocide treatment programs while operating the circulating pump and
prior to operating the units fans:
Resume treatment with biocide (or as recommended by water treatment supplier) that was used prior
to shut-down. Operate the pump only while maintaining the maximum recommended biocide residual
for a sufficient duration as recommended by water treatment supplier. Start fan only after this
treatment period is completed.
Check the pH of the circulating water and, if necessary, adjust it to 7.0-7.6 pH. Then, running the
pump only, treat the system with sodium hypochlorite (or as recommended by water treatment
supplier) to maintain a level of 4 to 5 mg/I (ppm) free chlorine (as CI2) over a six hour period. Start
the fan only after this treatment period is completed.
For initial start-up, briefly energize the fan motors and note the direction of rotation. The fan should
rotate in the direction indicated by the arrow on the fan cowl.
Run the fan in manual mode for several minutes to check for any unusual noise or vibrations.
Check that the starter incorporates a 15 second time delay when switching from high to low speed.
Check the operation of the vibration cut-out switch.
Once the cooling tower is operating, check the current and voltage of all three phases of the fan motor
with a heat load on the tower under warm ambient conditions. The current must not exceed the motor
nameplate rating.