KOLEJ WIT IPOH

(TECHNORATI CONSULTANCY (M)SDN.BHD.)


NO.8,JALAN CHARLETON,
OFF JALAN TUN ABDUL RAZAK,
30100 IPOH,PERAK DARUL RIDZUAN.

INFORMATION SHEET
EE-320-3 : 2012 THREE PHASE ELECTRICAL INSTALLATION &
PROGRAM’S CODE & NAME MAINTENANCE

LEVEL L3

COMPETENCY UNIT NO. AND


COCU 5 : THREE PHASE ELECTRICAL APPLIANCES MAINTENANCE
TITLE

1 IDENTIFY ELECTRICAL APPLIANCES MAINTENANCE


REQUIREMENT, SPECIFICATION AND MANUALS
WORK ACTIVITIES NO. AND 2 PREPARE THREE PHASE ELECTRICAL APPLIANCES
STATEMENT MAINTENANCE TOOLS, EQUIPMENT AND MATERIALS
3 CARRY OUT ELECTRICAL APPLIANCES INSPECTION
4 CARRY OUT ELECTRICAL APPLIANCES MAINTENANCE

Page : 1
CODE NO. EE-320 - 3 : 2012 - C05 / P(1/1)
Of :4

TITLE RUN MAINTENANCE ELECTRICAL APPLIANCES

OBJECTIVE: To ensure the equipment is safe to use after refurbishment work


                   or ongoing maintenance of electrical equipment
Page : 2
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

DESCRIPTION

The purpose of inspection and testing carried out on the installation manual or electrical devices is
to ensure the safety of an installation has been fulfilled in accordance with IEE regulations, TNB
Energy Commission (EC) in order to work properly and safely used.

Inspection and testing must be conducted on the following:

i. Equipment and electrical installations.


ii. Existing installations for the purpose of the addition or modification.
iii. The existing electrical installation on a regular basis according to plan or planning for
maintenance purposes.
iv. Tests on consumer demand or direction. This is usually when there is damage to the
installation.

VISION INSPECTION

 Review the proposed vision is carried out before any testing that is conducted by means of view,
Page : 3
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

the goal is as follows:

i. To ensure that the devices are installed in accordance with British Standard (BS), Standards
Malaysia (MS) approved by the Chairman of the Energy Commission (EC) and SIRIM. If the tools
are not there any sign of approval, then the contractor must submit a letter of approval in respect.
ii. To ensure that the entire installation is carried out in accordance with IEE regulations, TNB,
PWD, ST and other regulatory requirements.
iii. To ensure that no real or apparent damage to the installation or electrical devices connected to
it.

 During these tests do not need to be removed from the lamp holders and light switches should
be in Konkan.
 Meter shows the reading of the charges.

Continuity test circuit ring.

This test was done to ensure continuity along each conductor has a ring circuit. There are two
methods of testing the circuit continuity of the proposed ring. The tools used are a tester
Page : 4
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

multimeter (ohm meter) and bell tester (dc)

The first method of testing procedures.

1. Test the continuity between the end of each conductor ring circuit, connect the lead tester as
shown below:

1. Repeat the procedure as above for the continuity test phase and neutral conductors.
2. Meter will show a reading of less than one ohm must show continuity is good conductor.
Page : 5
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

The second method of testing procedures.

1. Test the continuity between the end of each conductor ring circuit, connect plambam testers like
the figure below. The conductor used for circuit the three conductors of the earth, neutral and live.
2. Meter will show a reading of less than one ohm must show continuity is good conductor.
3. The test is carried out with continuity conductor of the N - L, L - E and N - E

Protection conductor continuity test

The purpose of protection conductor continuity test is to make sure it is connected properly and
effectively. Tester is used for ohmic. There are two types of methods for testing the continuity of
protection conductors.

Procedure for testing the continuity of protection conductors of the first method.

1. The main supply disconnected if necessary.


Page : 6
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

2. To test the continuity of protection conductors connected plambam tester according to the
diagram below.
3. Meter readings will be shown less than one ohm shows good continuity of protection
conductors.

METHOD 1

Conductor continuity test procedures cover both methods


Page : 7
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

1. The main supply disconnected if necessary


2. To test the continuity of the protective conductor of additional conductors required for the
protection conductor circuit the phase or neutral conductor as the conductor guide.
3. The meter should show a reading of less than one ohm to show good continuity of protection
conductors.
Page : 8
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

QUESTION:

1. What is the purpose of inspection and testing carried out on the installation manual or tool-
      power tools?

2. What is the purpose of the continuity test circuit bracelet?

3. Name the test equipment is used to test the continuity of protection conductors.

4. Explain the procedure for carrying out the first method of protection conductor continuity test.
Page : 9
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis
Page : 10
CODE NO. EE-320-3 : 2012 - C05 / P(1/1)
Of :4

LUKISAN, DATA & JADUAL:

-TIADA-

ARAHAN UMUM:
Anda diminta menyediakan skop kerja anda dan senaraikan kemahiran dan pengetahuan yang perlu dimiliki
bagi melaksanakan tugas tersebut.

PERALATAN, KELENGKAPAN & BAHAN-BAHAN :


1. Kertas
2. Peralatan menulis

Reference
1. Teori Pemasangan Elektrik
ISRIHERWAN BIN SENAIN

2. ABD SAMAD HANIF


Pemasangan Dan Penyelenggaraan Elektrik EDISI KEDUA, DBP 2000