Transformer Faults

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

UNCLASSIFIED - OPEN SOURCE

Accountability and Evaluation of Aggregate Effects of Through Faults


On Power Transformers
By Kipp Yule, Duane Brock, and Jim Purdy

Keywords – Electrical, Operability, Fault, A root cause evaluation was conducted and the
Transformer most significant contributor to the fault was
believed to be the aggregate effects of through
Abstract – This paper examines proposed fault events since the transformer had undergone
methodologies and recommendations to prevent internal inspection and repair in 1996. Due to
failures of power transformers due to the the mechanical and electrical stresses and
aggregate affects of through faults on physical shock imparted on transformers upon
transformers. exposure to each through fault, it is theorized
that these aggregate effects caused by forces over
A 1000MVA Three Phase Generator Step-UP time manifested in looseness of the low voltage
(GSU) Transformer at a Generating Station bus bar supports enabling the bus bars of two of
suffered a catastrophic electrical fault in October the low voltage phases to migrate towards each
2005. This resulted in a significant impact to the other to the degree that the dielectric properties
Operating Companies revenue stream as this of the oil alone could not preclude a phase to
base-loaded facility, minus a functional GSU phase fault from propagating.
Transformer could not export Power for 17 days
until a temporary (De-rated Output) Transformer A broadness review was instituted as a
was installed. Another full rated spare component of the root-cause evaluation and it
transformer was installed in early 2006 during was discovered that there are recent documented
the scheduled plant shutdown to replace the instances where cumulative through faults have
smaller unit. The new replacement Transformer led to comparable transformer faults.
(with an up-rated power rating) is scheduled for
installation in early 2008. As a corrective action for the event, the existing
maintenance program has been improved by
requiring consideration of the frequency, the
1. INTRODUCTION magnitude, and the duration of through faults
experienced when evaluating maintenance
Power transformers are designed and built by indicators that would lead to more detailed
manufacturers to withstand the large mechanical inspections and repair actions for transformers.
and electrical stresses imparted on the
transformer due to the maximum electrical fault 3. EXTENT OF THIS PROBLEM
energy postulated for that transformer.
Secondary side transformer faults also expose As an extension of the aforementioned root cause
the transformer to elevated mechanical and evaluation, additional searches were conducted
electrical stresses that are functions of; a) the to ascertain failure correlations within the
nature of the fault (3 phase fault, ground fault nuclear industry. There were several instances
etc.), b) the magnitude of the fault (function of where it was suspected that a power transformer
the equivalent system reactance where the fault failure was attributed to aggregate through faults.
occurs), and c) the time necessary for a One utility transformer maintenance group has
protective device to clear the fault. observed a pattern of transformer failures
Consequently, the challenge is to identify all following ice storms that is believed to be highly
transformer through faults, capture the energy correlated to an accumulation of through fault
profile of each individual through fault, and events on the failing transformers.
ascertain the consequences of the aggregate A review of IEEE papers revealed some potential
effects to the transformer. correlations with this phenomenon, however for
the sake of brevity, the following case study
2. ANATOMY OF THE POWER entitled ‘Analysis of a Generator Step-Up
TRANSFORMER FAILURE Transformer Failure Following a Faulty
Synchronization’ is offered to emphasize the

1 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

cumulative effects of through faults. See Three Phase Generator Step-Up (GSU)
Reference 1 Transformer, which suffered a catastrophic
electrical fault in October 2005, prompting this
Abstract - This paper presents the details of an in-depth paper.
analysis carried out: to investigate an out-of-phase
synchronizing condition which resulted in the failure of a
725 MVA GSU transformer. Using a technique described in 4. SYSTEM CONFIGURATION
this paper, the circuit breaker closing angle was estimated AND FAULT TYPES
from oscillograph traces. This information was used with the
Electromagnetic Transients Program (EMTP) to simulate the
disturbance events and thereby produce a complete set of
A commonly used station one-line configuration
probable synchronizing currents and generator electrical is shown in Figure 12, where the generator and
torques experienced during the disturbance. The analysis of the step-up transformer have essentially the same
the simulation results, and further, the analysis of the failure rating. This is from Reference 3. We should
of the GSU transformer have been viewed in light of the large
number of prior system faults in the vicinity of the
recall that the location of a fault will determine
transformer. A brief review of the ANSI/IEEE standards on the severity or level of fault current. With a fault
transformer fault withstand capabilities as related to this postulated at C1, the fault current through the
type of analysis is also presented. Step-up transformer is mostly due to the
generator contribution with auxiliary system
Essentially the authors indicated that in this case contribution (generally negligible). In the case of
there were 42 faults below the current rating on a fault assumed at B1, the fault current through
phase 2 for the Muskingum River # 5 GSU and the Step-up transformer is mostly due to the
37 prior through faults above the 1.0 per unit system contribution but also has additional short
value that individually should not cause a circuit contribution from the auxiliary system.
transformer failure; however the cumulative Yet, the highest available fault current tends to
effect may have been sufficient to loosen the be at the Auxiliary system transformer due to the
windings and mechanical blocking to the extent contribution of both the System via the Step-Up
that the through fault capability had been Transformer and the direct connected generator.
reduced prior to the out of phase It is noted that the auxiliary system fault will
synchronization. subject the Auxiliary system transformer to a few
While the out of phase event in this case resulted cycles of short circuit forces, while limiting the
in winding failure, we must also include the longer term thermal input associated with
winding to bushing cabling, busses and flexible generator coast down, even when the Generator
and solid connectors, as components that are breaker is included in the system configuration.
repeatedly subject to severe mechanical stress as
was the case with the failure of the 1000MVA

2 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

From Reference 3 - IEEE C37-013


being evenly distributed events where one out of
We also want to briefly consider the possibility every three (or two out of every six) occurs
that faults may not be randomly distributed evenly or randomly across the phases. In the real
across the three phases. In the one case study, it world case it was observed through the historic
is believed that the area of failure was related to records that the failed phase had been subjected
one individual phase, which was subjected to to multiple faults that involved downed lines and
higher faults and / or experienced the initial a high voltage breaker failure. One may postulate
asymmetrical component of the fault. While the that if the fault current with a high degree of
IEEE C57.12.90 states: asymmetry occurs repeatedly, or consecutively,
12.3.4 Number of tests - Each phase of the on the same phase; then a close inspection and
transformer shall be subjected to a total of six verification of fitness for service is warranted.
tests satisfying the symmetrical current Reference 3 the figures of IEEE C37.013 that
requirement specified in 12.3.1 or 12.3.2, as provide good visual references of how the high
applicable. Two of these tests on each phase
shall also satisfy the asymmetrical current
mechanical stresses are imposed on the phase
requirements specified in 12.3.3. that receives the maximum asymmetrical
The real world has shown that the asymmetrical component of a through fault.
current does not always follow the pattern of

3 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

Figure 7— Asymmetrical system-source short-circuit current


From Reference 3 - IEEE C37-013

From Reference 3 - IEEE C37-013

5. INDUSTRY GUIDANCE established rule that is universally adopted by


REGARDING THROUGH transformer manufacturers regarding thresholds
FAULTS for evaluating the accumulative effects of less
than maximum through faults. There are some
Although there is specific industry guidance recommendations recently offered by some
established in IEEE C57.12.00 with respect to manufacturers as outlined in Section 10 to
the number and magnitude of maximum support this paper.
calculated faults that a power transformer must
be designed to withstand, there is no well

4 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

6. FAULT TRACKING through fault event and over time help to validate
PROGRAM ATTRIBUTES recommendations for continued operation.

The increased sensitivity to the effects of through There are numerous inputs, which need to be
fault currents on large transformers has considered when performing the post through
motivated some individual plant sites as well as fault event analysis of transformer health.
the organizations responsible for the utility Transformer age, electrical loading, any
distribution system to evaluate the effectiveness movement due to physical relocation, physical
of their maintenance programs. A major design, OE, maintenance and inspection history,
contributor to an effective program for inclusion as well as the through fault event data and results
of through fault tracking and analysis is to of subsequent testing are a few considerations.
identify and obtain the base-line data needed for The physical design of the transformer will help
future analysis. It is most desirable of course to to determine the failure modes that might be
obtain this data while the transformer is in a possible. Differences between transformer
healthy state. Preferably this will be performed designs may necessitate the use of different
in the manufacturers shop prior to delivery. It strategies in the specifics of post event testing
can also be established after a transformer has and analysis. While comparison of testing
undergone major refurbishment or maintenance. results taken after a through fault event to the
Another major aspect of a through fault base-line data can show potential movement or
monitoring program is the identification of the shifting of the coils, it may not show movement
through fault event and the capturing of the data of bus bars or other internal components, which
necessary to support the analysis. There can be can eventually cause failure of the transformer.
two parts to capturing this data. The primary OE has shown that oil sampling and DGA will
source for a power plant is the protective not always detect transformer degradation of this
relaying and on-site Fault Recorder data type either. OE has also shown that some
acquisition system. It should be verified that the transformer designs are physically more robust
Fault Recorder data acquisition system is set up than others and alternatively others are more
to be triggered (start the data acquisition) at the sensitive and as such are more likely to
proper level of fault current (recommendations experience these failure modes. This will
may be as low as 0.25 per unit, or at a threshold introduce an additional degree of subjectivity
level commensurate with the transformer design into the engineering analysis and weight the
margin) and that adequate voltage and current decision for instituting an internal inspection.
readings will be taken for the three phases at the
appropriate locations. A secondary source of 6.1 Preparation Prior To Fault
valuable data can be secured from the
transmission system group. Operational Some of the actions which should be
Experience (OE) has documented cases where incorporated into a transformer fault tracking
events on the grid, which happened away from program are as follows:
the plant site, contributed to transformer failure
at the site. Formal communication with the 6.1.1. Identify the responsible department and
appropriate contacts within the transmission individual(s) for implementing a
system group could provide information about strategic program designed to foster
grid events where the magnitude of the event as long term operation of Power
seen at the site of the transformer is under the Transformers as described below to
threshold for triggering the data acquisition ensure focus and accountability.
system, but which would be useful in analyzing 6.1.2. Determine what testing has been
the accumulated effects of through fault events performed on the existing transformers
on a transformer. and initiate actions to fill any gaps to
ensure a compliment of test results are
Supplemental data necessary for the analysis of secured as outlined in 6.1.9 below.
the transformer health is the result of periodic oil 6.1.3. Verify the base-line data that is
samples, Dissolved Gas Analysis (DGA), power available for the existing transformers
factor testing, Frequency Response Analysis and determine what actions can be
(FRA) testing, and infrared imaging thermograph taken to fill any gaps to ensure a
readings. Proper trending of this data should compliment of test results are secured
support the analysis performed in response to a as outlined in 6.1.9 below.

5 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

6.1.4. Review the existing maintenance occurs, a recommended course of action would
procedures to insure that the desired oil be as follows:
analysis, DGA, thermal readings, are
being taken in accordance with 6.2.1. Determine what relay actuations were
manufacturers recommendations and/or received on protection systems.
governing IEEE recommendations. 6.2.2. Obtain the data from the Fault Recorder
6.1.5. Verify that the onsite Fault Recording data acquisition system.
data acquisition system is capable of 6.2.3. Obtain data from any other data
securing all of the necessary data acquisition system available.
required to facilitate a complete 6.2.4. Obtain the operational history for the
evaluation. transformer, including through fault
6.1.6. Establish a communication protocol legacy information.
with the proper individual(s) that 6.2.5. Contact the appropriate transmission
triggers communication between group to determine what other transients
transmission and the designated plant may have been experienced on the grid
representative(s) for incidents that could at that time.
adversely influence the health of the 6.2.6. To the degree possible, determine the
transformer. initiating event, the location, and the
6.1.7. Implement procedural requirements to magnitude of the fault as seen by the
track faults on the system, identifying transformer.
the location, magnitude, etc. 6.2.7. Pull maintenance history and trending
6.1.8. Review the maintenance history and analysis for the transformer.
through fault events experienced by the 6.2.8. Secure vendor information for the
existing transformers and initiate transformer.
actions to perform any future testing or 6.2.9. If the protective relaying isolated the
inspections as necessary. transformer from the system, perform
6.1.9. For new transformers, ensure that the the following tests as dictated by the
procurement specifications include analysis of the event data:
requirements for execution of relevant • DGA
baseline testing such as, Insulation • Oil Power Factor
Resistance, Winding Resistance, 10kV • Insulation Resistance
single phase excitation (Doble), Induced • Insulation Power Factor
Voltage, Turns Ratio, Frequency • FRA
Response Analysis (FRA), and • Winding Resistance
Insulation Power Factor, to be
• Turns Ratio
conducted in the manufacturer’s shop.
6.2.10. If the transformer remained in service,
6.1.10. Once the new transformer is received,
review the data secured in step 1
perform a 10kV single phase excitation
through 8 above to determine if the Unit
(Doble)test, Ratio test, and FRA test.
should be removed from operation and
Also, if there is any indication based on
the above testing performed.
external testing, conduct an internal
6.2.11. Perform an engineering analysis using
visual inspection or when assembling
the specific transformer design and
bushings or other components removed
considering the data obtained in the
for shipment.. If the transformer is
steps above. This analysis may
stored and subsequently moved again to
recommend continued operation as is,
another location, the appropriate subset
more testing, or an internal inspection
of these tests and internal inspection
of the transformer.
should be repeated depending on the
6.2.12. Consult with the transformer
details of the move.
manufacturer if available and
communicate the findings and
6.2 Post Fault Actions
recommendations to gain a consensus
opinion.
All of the above recommendations of course are
just the preparation for dealing with a
transformer through fault event. Once one

6 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

7. CURRENT TECHNOLOGIES TO could be reasonably long periods of time


SUPPORT COMPREHENSIVE between faults, say five to ten years, or more,
THROUGH FAULT PROGRAM without significantly consuming the original
manufactured ability to withstand through faults.
There are many relay platforms that are capable This requires a transformer lifetime commitment
of waveform capture of system faults on both the by the end user to record and track significant
high and low side of large power transformers. events from the perspective of the transformer.
There is increasing use of digital fault recording In the world of analogies, this is the equivalent
on the transmission side as well as the generation of our own lifetime medical records whereby the
side. However, one key aspect of all the data input of multiple care givers, doctors, parents,
collection available from the various data spouses and children are involved across
acquisitions and event capture equipment is the generations to maintain an accurate historic
organizational and management structures that record of the significant events in our lives.
are required to be present to analyze and act on Similarly, the health of the transformer should be
the collective aspect of information that is recorded and reviewed to allow for preventative
derived from the analyzed data. measures and to assess the projected remaining
life. The second obstacle is the multiple parties,
7.1. Data Management over Lifecycle groups, or even companies that may be involved
in providing data to a possibly virtual data
The first obstacle to overcome is the long life Owner. Refer to Figure 7A depicting an
spans that many large power transformers are organizational arrangement of data collection
capable of achieving. Many in service units in groups that may be typical due to the specialized
North America are twenty, thirty and in some functions of these groups and their inherent
well established infrastructures even forty years charter. There is a distinct possibility that no one
old. Considering the IEEE C57.12.00 standard individual, group, or assigned entity is required
(Reference 2) regarding short circuit capability, a to compile and analyze the collective data,
new transformer is expected to be able to although that should be the objective to ensure
withstand at least six (6) through faults. So there program accountability.

7 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

High Voltage Side

Grid faults monitored by


Transmission Group or
wheeling utility.

GSU XFMR

HV -- Grid
LV – Generator
Plant loads via Isophase
Bus to Aux Xfmr

Generator AUX XFMR(s)


Plant auxiliary load faults,
Generator & Iso Phase Bus
including Auxiliary
faults monitored by
Transformers monitored
Generator Group
by Plant Electrical Group.

Figure 7A -- Radial
The ability of the transformer to fully withstand Figure 7B. Asset managers and those that may
the next through fault is clearly dependant on the require external companies, or even outsourced
history and present health of the transformer. services, should ensure that the data is collected,
While the technology to capture and accumulate analyzed and actions implemented to maintain or
data may best be served by the radial functional restore the power transformers ability to
groups that interface with a power transformer, withstand the next and the requisite accumulated
the ownership and guardianship must also be a through faults.
circular one of empowerment as shown in

8 of 11

UNCLASSIFIED - OPEN SOURCE


UNCLASSIFIED - OPEN SOURCE

Generator GSU XFMR

Generator & Iso Phase HV -- Grid


Bus faults monitored by LV – Generator
Generator Group Plant loads via Isophase
Bus to Aux Xfmr

MULTIPLE GROUP
INTERFACE
REQUIRED FOR
CUMULATIVE
FAULT TRACKING

AUX XFMR(s) High Voltage Side

Plant auxiliary load faults, Grid faults are monitored


including Auxiliary by Transmission Group
Transformers monitored or wheeling utility.
by Plant Electrical Group.

Figure 7B – Circular

7.2. Fault Levels and Remnant Fault levels to just be a percentage of full fault level,
Capacity say three quarters (75%), half (50%) and one
fourth (25 %). The question or expectation that is
When attempting to find concise and / or attempting to be confirmed is: Assuming that
consensus type guidelines in the industry and via short circuit forces are basically a squared
the standards regarding the degree of effect of function of the current, then can one postulate
accumulated faults ranging from a full design that the transformer can be reasonably expected
basis or type test fault, several manufactures to successfully endure a numerous
provided helpful guidance, design practice and mathematically proportional number of lesser
their experience based on end user feedback. For faults that would constitute a full design basis
the purposes of this paper we considered or fault level. In a more classical mathematical
defined a full design basis or type test fault as the relationship, if the transformer could accept one
one hundred percent fault (100%) level located at 100% through fault, then could it be expected to
the transformer terminals and the lesser fault

9 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

accept a mathematically equivalent number of basis event as the inverse of the percentage
lesser through fault events as shown in Table 1? squared of full fault current levels, it must be
emphasized that the manufacturer included a
Table 1 minimal time interval between repetitive through
Fault Fault Square Inverse Postulated faults at higher levels. The recommendation is
level level of per of per mathematical for through faults at levels of 50% and above
(%) at unit unit capability of there should be at least 15 live relaxation days
per value value equivalent between events. While there must be a time
unit squared through fault constant for a deformable but resilient
value events component to return to a point of mechanical
100 1 1 1 1 stress equilibrium after having a force exerted
75 ¾ .5625 1.7777 ~2 upon it, it is reassuring to know that some
50 ½ .25 4 4 manufacturers are able to quantify such
25 ¼ .0625 16 16 relaxation or recovery time between higher level
through fault events. This relaxation time is most
After performing some research of various likely obvious for the manufacturers and industry
standards, reviewing various operating and consultants, and does make good practical sense.
maintenance manuals, and discussing the topic The question that users should ask is: Is the
with a consultant, we believed there was a basis relaxation time between events, appropriate due
to expect the assumption to have some validity. to higher through fault level accounted for in
operating procedures? We know there are
Upon contacting several manufacturers, one thermal time constants (recover time) associated
strong point of consensus offered was that the with numerous hot starts of large motors, and
winding clamping force, and the original (as that some of the intelligent relays have
manufactured) condition of the windings, algorithms that will block the next restart based
insulation, key spacers, blocking, and other on the thermal characteristics and recent
cellulose products that are subject to short circuit operating history of a motor. For some specific
forces during a through fault must be within the situations, should a user similarly consider
design margin values for the specific design for operating procedures that recommend a minimal
any transformer to successfully withstand a relaxation time prior to re-energizing a unit that
through fault event. There are services such as has had a severe fault, or numerous consecutive
the Mature Transformer Management Program in lesser faults? This question can only be answered
Reference 5 and in conjunction with Advanced by the responsible entity in charge based on a
Diagnostic Testing Services offered by multitude of considerations. The question is only
Reference 5 that can provide unit specific asked to: a) provide a possible mechanism to
transformer design and condition assessment for reduce operating risk by adopting conservative
shell and core form transformers. The short operating practices, b) to further illustrate the
circuit strength analysis would consider the possible adverse consequences of not factoring
various stresses such as, buckling, crushing, this variable into the decision making process,
hoop, and tipping, acting on the radial and axial and c) to highlight that there are service life
directions of the winding for a specific design in reductions that might be accompanied with
combination with the historical loading, immediate attempts to re-energize a recent
operational history and diagnostic data and faulted unit.
would assign a relative risk category
proportional to the design margin. 7.3. ECONOMIC CONSIDERATIONS
One major manufacturer confirmed that their
design rules for short circuit withstand have a Considering the current robustness of the Power
section relating to this matter, and based on these Industry, typical quotes for new large power
rules the following number of short circuits per transformers are in the range of 15 to 18 months
year would be acceptable for one of their designs (and for some specific large capacity and high
from a specific manufacturing location: voltage, or special application factories, the lead
100% level - 1 per year; or at the 75% level - 5 times are over 22 months) for GSU Transformers
per year; or at the 50% level - 20 per year; or at and 12 to 15 months for auxiliary and station
the 25% level - 100 per year. While this supports service transformers. Some larger base load
the postulated mathematical relationship of the Units are subject to revenue losses of
probable number events at less than a full design approximately 1 million dollars a day after a

10 of 11
UNCLASSIFIED - OPEN SOURCE
UNCLASSIFIED - OPEN SOURCE

transformer failure. Consequently, if the Utility


does not have a spare power transformer readily
available, the economic consequences are
substantial.

7.4. CONCLUSIONS

Based on a review of industry data, it is apparent


that there are opportunities for original
equipment manufactures and industry
organizations to establish a formal program to
better predict when a Power Transformer is at
risk. This paper illustrates the salient attributes
of such a dedicated and structured program to
assist the operating and maintenance departments
in protecting themselves from significant
economic risks due to failed power transformers
as a consequence of the accumulative affects of
through faults.
In other words, instead of implementing a plan to
ensure operability and reliability of the power
transformers, one could find themselves working
a plan for an unplanned outage.

7.5. REFERENCES
1. Analysis of a Generator Step-Up
Transformer Failure Following a Faulty
Synchronization by B.M. Bernard, J. H.
Provanzana, and L. B. Wagenaar – IEEE
Transactions on Power Delivery, Volume 3,
No 3, July 1988
2. IEEE Std C57.12.00 -- IEEE Standard
General Requirements for Liquid-Immersed
Distribution, Power, and Regulating
Transformers
3. IEEE Std C37.013 - IEEE Standard for AC
High-Voltage Generator Circuit Breakers
Rated on a Symmetrical Current Basis
4. ABB Service Handbook for Transformers
5. ABB Mature Transformer Management
Program (MTMProgram™)

7.6. ACKNOWLEDGEMENTS
We wish to acknowledge the contributions,
opinions, and guidance provided by the
following companies and their technical experts
with respect to this paper:
1. ABB
2. AREVA
3. Hyundai
4. Southern Nuclear Company
5. Bechtel Power Corporation

11 of 11
UNCLASSIFIED - OPEN SOURCE

You might also like